Dickson v Mount Isa Mines Ltd [1990] QSC 399
IN
THE SUPREME
COURT
OF QUEENSLAND
No.
57
of
1988
Before
Mr.
Justice
Cooper
BETWEEN:
CATCHWORDS:
Counsel:
Solicitors:
DAVID DICKSON
MOUNT
ISA
MINES LIMITED
JUDGMENT
-
COOPER
J.
Delivered the
30th
day
of
November,
1990.
R.J.
Douglas
for
plaintiff
J.P.
Barbeler for defendant
Plaintiff
Defendant
V.R.
Moffatt
&
Associates for plaintiff
Conroy
&
Conroy as
town
agents for
Bowdens
for defendant
Hearing dates: 2, 3, 10,
11 and 18 May, 1990.
-- 1 of 17 --
IN
THE SUPREME
COURT
OF
QUEENSLAND
BETWEEN:
AND:
DAVID DICKSON
MOUNT
-ISA MINES LIMITED
JUDGMENT
-
COOPER
J.
No. 57
of
1988
Plaintiff
Defendant
Delivered the
30th
day
of
November,
1990.
The
plaintiff is
a
married
man
born
on
1
June,
1950.
On
8
April,
1987
he
was
an
employee
of the
defendant
working
at
its
Hilton
mine.
On
that
day he
was
engaged
in
working
as
a
pipe
layer.
Normally he
was
engaged
as
a
plate layer.
Whilst
engaged
in
lifting
a
piece of
drilling
equipment
described as
a
rising
feed,
he
stood
up
with
some
force
and
the
top
of his
head
came
into contact with
a
rock
bolt
he had
recently inserted into
the
roof of the tunnel. In
consequence, he
sustained
an
injury to
his
neck.
The
defendant has denied
liability
or,
alternatively,
says
that
the injury
was
contributed to
by
the negligence of the
plaintiff.
On 8
April,
1987
the
plaintiff
was
the leading
hand
in the
three
man
gang engaged
in the pipe laying
work. The
plaintiff
was
usually
employed
as
a
plate layer/timber
man
although pipe
laying
formed
part of the
works he had
contracted for.
The
plaintiff
had had considerable experience in drilling in
mine~
and using
a
rising feed. His experience,
I
find,
was
limited to
-- 2 of 17 --
2
drilling
and
placing
rock
bolts.
The
significant
difference
between
rock
bolting
and
placing
bolts
for
piping
lies
in
the
fact that
rock
bolts
stand out
from
the roof of the tunnel
approximately
five to six
inches
whereas
bolts
for
piping stand
out
approximately twelve
to
eighteen inches.
The
procedure
for
drilling
and
inserting
the
bolts
using
a
pneumatic
wrench
is
otherwise the
same.
The
placing of
bolts
for
piping
requires
that
the
bolts
be
aligned
and
that
the
hangers
to
carry the pipes
are
all
at
the
one
level.
This
requires the
use
of
a
string line
to
establish level
and
distance
between
bolts.
Rock
bolting
is
a
more random
procedure
to
secure the
rock
surface or
wire·mesh
to
retain
rock.
The
procedure
in
pipe laying
involves the fixing of
a
string
line
below
the roof of the tunnel
and
the
marking
off
of the
line
at
five to six
metre
intervals
with white
paint.
At
each
interval
two
holes are
drilled
and
two
bolts inserted
so as
to
allow
a
pipe hanger
to
be
attached
at
the
level
of the
string
line.
In order to
drill
into
the roof the
workman
works from
the
platform of
a
truck.
The
platform
may
be
raised or
lowered
to
enable the
workman
to
perform
his task
from
the correct height.
The
rising
feed weighs
about
45
kilograms.
It
can have
attached
to
it
drilling bits
of various length.
It
has
a
pin
in the base
plate
which
is
used
to pivot the
equipment
when
it
is
being
lifted
or
swung
into the
vertical position for use.
It
operates
by
air
pressure
and water and
air
are fed
to the
equipment by
way
of attached hoses.
The
procedure
is to
lift
the rising feed,
drill
two
holes to the requisite depth, place the rising feed oh
the platform, detach the hoses from-the rising feed and
attach
-- 3 of 17 --
3
them
to
the
pneumatic
wrench,
insert
glue
in
containers
into
the
drill
hole
and,
finally,
to
drive the
bolts into
the
holes
and
the glue using
the
pneumatic
wrench.
I
find
that
the
defendant
had
given
an
instruction to
its
employees
of
which
the
plaintiff
was
aware
that
after
insertion
of the
bolts
the platform
was
to
be lowered
to
its
normal
position
on
the truck.
The
obvious purpose
of
such
an
instruction
is
to
remove
the
workman away
from
the
exposed
bolt
lest
the
workman
strike
his
head
or
upper
body
against
it
as
he
moves
around
or
stands
up
if
he
is
obliged
to
reach
down
to
do
anything
at
the
level
of the platform.
The
plaintiff'
was
supplied
with
a
safety
helmet
to
protect his
head
against
striking
anything
protruding
from
the roof of the tunnel or
anything
that
may
fall
from
it.
The
only
light
available to the
plaintiff
was
that
provided
from
the
lamp on
his
helmet
and
such
lamp
light
as
came
from
the
helmets
of
two
other
employees
who
worked
with
him.
On
the
day
in
question the
plaintiff
was
the person
who
gave
the
instructions to raise
and lower
the platform
on
the truck.
The
truck did not
move
from one
location to
another without
an
instruction
from
the
plaintiff.
The
procedure adopted
by
the
plaintiff
was
to
complete
the fixing of the
two
bolts in
each
position
and
then
to
lift
the rising
feed
and
lay
it
against the
string line to establish his level
and,
whilst standing in that
position, to direct the truck to drive forward
to the next
work
location.
At
the next location
he would immediately
commence
to
drill.
I
find that the plaintiff
adopted
that practice because
he formed the view
that
it
was
quicker than lowering the
-- 4 of 17 --
4
platform,
directing
the truck
to
proceed
to
the
next
location,
and
then
raising
the platform
to
commence
drilling at
that
location.
I
find
that
the
plaintiff
was
concerned
to
get the
job
finished
as
quickly
as
possible
on
that
shift,
having
been
told
by
a
supervisor
that
the supervisor
wanted
the
job
finished for
the
next
shift.
There
is
nothing
in
the
evidence
which
persuades
me
that
the
time
available to
do
the
work was
insufficient to
allow
the
work
to
be
done
in safety.
If
the
plaintiff
had
followed
the
procedure
of
which he
was
aware and
lowered
the platform
and
not attempted
to
lift
the
rising
feed as
he
did
he
would
not,
on
balance,
have
suffered the
injury
which he
did.
To
the extent
that
he
was
working
in
a
static
location,
the
sequence
of
work would
not
have
required
him
to
lift
the
heavy
piece of
equipment
in
the forceful
manner
he
did
and he
would
not
have been
at risk
of
his
head
coming
into
contact
with the protruding
bolt
with considerable force.
As
the
plaintiff
was
equipped with
a
safety
helmet
to protect
him from
accidental
bumping
or
striking
of the
bolt in
the period
after
the
bolt
was
inserted
and
the platform
lowered,
it
was
not
incumbent upon
the defendant
to
give
an
instruction or
warning
to the
plaintiff
not to stand
up
under
protruding
bolts.
In
that
case,
such an
instruction
"was
a
basic counsel
or caution of
which he
was
or
must be aware".
(Raimondo
v. South
Australia
(1979)
23
A.L.R.
513
at
518-519.)
It
was
submitted
by
the
plaintiff that the defendant ought
to
have
directed the
plaintiff
not to
lift
the rising
feed
when
he was on
the raised platform in close proximity to the
projecting bolt or ought to have equipped the platform with
some
-- 5 of 17 --
5
stowage
device
which
would
enable the
rising
feed
to
be
secured
in
a
vertical
position
after
use.
This,
it
was
submitted,
would
eliminate the prospect of the
plaintiff lifting
the
equipment
in
close
proximity
to
the
bolt
and
injuring
himself as
he
did.
In
my
view
the
submission
is
misconceived because
it
attempts
to
build
into
the
procedure adopted
by
the
plaintiff
steps
which
would
have
avoided
or
minimised
risk
of
the
injury
which he
sustained.
The
system
of
work employed by
the defendant,
namely,
the
lowering
of the platform
and
the transporting of the
rising
feed
laying
horizontally
on
the
platform
to
the next
site
where
it
was
next
to
be
used,
would have
avoided
the
injury to
the
plaintiff.
In the
instant
case
the
plaintiff
was
injured
because
he
devised
a
system
to
do
the
work which
cut corners
in
the
interests
of
speed
and
efficiency.
The
fault
of the
defendant
lay in the
fact that
it
knew
or
ought
to
have
known
by
proper
supervision
that
its
employees were
in
the
habit of not lowering
the platform
and
moving from one
site
to
another with the
platform
up
with
a
workman
on
the platform
and
possibly holding
heavy equipment.
The
defendant
failed to stop the practice
and
direct
and
supervise
its
employees
in
such
a way
that
the proper,
safe
system
was
complied
with.
I
accept the evidence
of Just
(transcript
p.
80
11. 12-60) and
Wharemate
(transcript
p.
105
11. 14-32)
that
it
was a common
practice for persons
after
completion of the task at
one
location to
remain on
the raised
platform as the vehicle proceeded to the next
work
station.
I
find that
such behaviour
was known
to the supervisors of the
defendant or ought to have been
known
if
a
proper system of
-- 6 of 17 --
6
supervision
was
in
place
and
being
carried
out.
Mr.
Slater,
the
shaft
and
construction
foreman
of
the
defendant
at
the Hilton
mine, gave
the
following evidence
in relation to
the
movement
of
workmen
on
the platform:-
"We
are
talking
only
now
about
the
movement
from mark
A
to
mark
B - I
don't
meaning
(sic)
drumming
up
and
down
the
driver or
anything
like that,
but
if
you
have
got
that
machine
moving from where
you
have
installed
one
set
of
bolts to
where
you
are
going
to
install
thenext
set
of
bolts, in
those
circumstances,
would
the
crew
stay
on
-
would
a man
stay
on
the platform?--
I
have
no
objection to
them
staying
on
the platform
moving from
point
A
to
point
B.
Do
they
have
to
do
anything------?--
Normally
after
he
has
installed his bolts,
he
has
got
his
air
on
to
his
impact
gun.
When
he
is
moving,
you
are pulling·
hoses along behind
and
making
sure
that
those hoses
are
not
snagging
and
changing
his
hoses
on
to his
rising
feed ready
for
the next hole.
What
about
the height of the platform?--
The
platform
must be lowered
down.
Then
if
it's
lowered,
he
is
riding
on
it,
from
whatyou
have
told
us, doing
these things but the platform
must be
lowered?--
Yeah.
If
I
can
make a
point,
when
you
are
moving
this
machine,
you
have
got
your hoses
hung
behind
you,
your
machine
is
going
first.
Your
hoses
are
hanging
over the
back
of
your machine and
they should
be making
sure
that
they
don't
snag
on
anything as they
are pulling
them
along.
BY
MR. BARBELER:
to
be
lowered?--
You
say
that
you
expect the platform
Yes.
Why
do you
expect
that.
How
does
the
worker
know
that?--
You
can't ride
on
-
you
are not
supposed
to
ride
any
distance
on
the
back
of those
Comeng'
s.
When
you
are shifting
you
should lower
it
because
you
don't
know
what
height
you have
to
lift it
to
on your next
hole.
How
would
they
know
that?--
They
are told.
If
a
person does
stay
on between point
A
and
point
B
while
it's
moving, what should be the position of the
rising feed?-- Should be laying
on
the top of the
Comeng.
-- 7 of 17 --
7
What
do you
say
to
the proposition
that
a
person
might
hold
the
rising
feed
either
with
or
without
a
steel
upright preparatory
to
moving
or whilst
moving?--
I
would
be dead
against
that.
Why
is
that?--
you
had
a
lump
it
would
lurch
you
falling.
If
you
were
driving
along
a
drive
and
and
the
wheels
went
over
that
lump
and
the
platform
and
there
is
a
chance
of
Would
you
do
anything
about
that
if
you saw
that
happening?--
I
certainly
would."
From
the
evidence
of
Just,
Goedhart
and
Wharemate,
which
I
accept, other
than
the
instruction
to
lower
the platform
after
completion
of the
task
the
proper
instructions
which
Slater
correctly
identifies
as being necessary,
if
workmen
are
going
to
travel
on
platforms with
equipment,
were
not
at
the relevant
time
being given.
There
is
a
danger
that
if
the
employees
are
permitted
to
remain
on
the platform
after
the task
is
finished,
while being
transported to
the
next
site,
the
discreet
steps in
the
system
of
work
tend
to
break
down
and
the
end
of the
drilling
and
fix
task
at
one
site
merges
into preparation for
the
commencement
of
drilling at
the next
site.
That
is
what
occurred
in
this
case.
Although
the injury
occurred
in
a
static
location
and
the allowing
of
employees
to travel
on
the platform did not
directly
cause
the
plaintiff's
injury, the
plaintiff
was
commencing
his preparation for the next task
by
lifting
the
rising
feed
to align
it
with the
string line
before instructing
the driver to
proceed forward with the
plaintiff
standing
on
the
platform.
An
instruction to lay
down
the rising
feed
if
given
and
enforced,
where
the
employee was
to
remain on
the platform,
would have broken the sequence of steps taken
by
the plaintiff.
The
defendant's system of training is to place an employee
with an experienced
man
to receive instruction
on the job and to
-- 8 of 17 --
8
receive
instructions
from
supervisors
or
foremen.
There
is
no
specific training in
respect of
specific
tasks
e.g.
pipe
laying.
In
the case
of the
plaintiff,
I
find
that
there
was
no
specific
training or instruction in
respect of the
procedures
to
be
followed
in
pipe laying.
I
find
that
the
plaintiff
was
an
experienced
driller
and
rock
bolter
but
had had
little
actual
experience
in
laying
pipe
work.
I
find
that
the
plaintiff
developed
his
own
system
of
work,
relying, in
part,
on
his
observation of
what
others did
in
performing
such
a
task
and
with
a
view
to
speeding
up
the operation.
I
find
that
the defendant
failed to
make
any
proper enquiry as
to
the experience
of the
plaintiff
or
the
procedure
he
would
adopt
in
performing
the
task
before
he
was
allowed
to
undertake
it.
Any
such
enquiry
would
have
revealed
that
what
he.
intended
to
do
was
unsafe
and would,
I am
satisfied,
have
led
Mr.
Slater
to
give
appropriate
instructions.
I
find
that
the
defendant
was
negligent
in failing to
properly supervise
and
enforce
compliance with the
normal and
safe
system
of
work,
in particular, in failing to
ensure
that
the
platform
was
lowered
after
the
bolts
had been
secured
in
position.
I
find
that
the defendant
was
negligent in
failing to
properly
instruct
the
plaintiff
as
to the
sequence and manner
in
which
the tasks associated with the placing of bolts for piping
was
to
be undertaken
and
that,
if
he intended to travel
on
the
platform the rising
feed ought
to
be
laid
on
the lowered
platform.
I
find that
because
Mr.
Slater
knew
the
plaintiff
was
experienced in drilling
and
bolting
and had previously seen the
plaintiff
engaged in pipe laying he-assumed that the plaintiff
-- 9 of 17 --
9
had
greater
experience
in
pipe laying
than
he had
in
fact.
I
find
that
by
allowing
the
plaintiff
to
prepare
for the
next
work
function
in
proximity
to
the protruding
bolt,
it
was
foreseeable
that
the
plaintiff
would
stand
up
and
strike
the
bolt
injuring
himself
as,
in fact,
occurred.
It
was
submitted
by
the
plaintiff
that
the
work
was
repetitive
and
that
the
injury
occurred
as
an
act
of
inadvertence
or thoughtlessness
and
as
such
not
conduct
amounting
to
contributory
negligence
(Sungravure
Proprietary
Limited
v.
Merni
(1963-1964)
110
C.L.R.
24).
The
failure
of the
plaintiff
to
lower
the platform
was
a
conscious
act
which
the
plaintiff.knew
was
contrary
to
the
instructions
given
by
the defendant.
I
am
not
satisfied that
the decision
was
forced
upon
the
plaintiff
by
the pressure of the
work
to
be
undertaken
or
any
unreasonable
time
constraint.
The
decision
to
cut
this
corner
in
the
interest
of
speed
operated
directly
on
the
harm which
he
suffered.
This
is
notwithstanding
that
the actual
lifting
of the
equipment
and
the
striking
of the
bolt
occurred as
a
result
of his
not
ascertaining
where
the
bolt
was
before
he
undertook
the
lift,
which
failure,
I
accept,
was
an
inadvertent or thoughtless
ac~.
In the
result,
I
find
that
the
plaintiff
contributed
to
25
per
cent of the
harm which he
has
suffered.
Although
there
was no immediate
pain, the
plaintiff
experienced pain in his
neck and
right
upper
arm
the next day.
On 10
April,
1987 he
presented to the defendant's doctor
and was
X-rayed and
treated with physiotherapy
and
anti-inflammatory
drugs.
He was
treated
and reviewed in April and
May
1988.
By
-- 10 of 17 --
10
February 1988 the plaintiff's neck pain had deteriorated and he
had a decreased range of all neck movement due to pain.
On 8 March, 1988 a myelogram was performed by
Dr. R.G. Rossato, neurosurgeon. This indicated a broad
indentation at CS/6 on the right, consistent with a disc lesion.
On 17 March, 1988 a single level anterior interbody surgical
procedure was performed by Dr. Rossato. The plaintiff initially
recovered well from the operation and was returned to work by
Dr. Conway, the defendant's staff doctor, on 17 May, 1988 with
restrictions for heavy lifting and no overhead work.
On 30 May, 1988 the plaintiff presented to Dr. Conway with
neck pain and headaches at the end of the working day. The pain
was being brought on by the use of a hard hat and lamp
underground during the day. Notwithstanding a programme
developed by an occupational therapist to build up a graduated
programme aimed at achieving pain-free wearing of the hard hat
for the entire day, this has not proved successful.
Dr. Gavin Douglas, orthopaedic surgeon, reviewed the
plaintiff on 1 December, 1988. In his opinion, X-ray examination
revealed that the cervical fusion was then not yet sound and
recommended further physiotherapy to try and redevelop the neck
muscle tone. The plaintiff was further re-examined on
10 October, 1989 by Dr. Douglas. In a report dated 13 October,
1989 Dr. Douglas states:-
"On examination there was a normal range of rotation
and flexion of his neck with slight restriction of
extension and a complaint of discomfort with full neck
extension. There was tenderness of the muscles down
the left side of his neck. He had a tendency to hold
his head held forward which was apparently the most
comfortable position for him.
-- 11 of 17 --
11
I ref erred him for further x-rays of the cervical
spine which were taken on the 10th October 1989.
These x-rays showed the bodies of CS and C6 were now
soundly fused.
This man has residual symptoms of neck aching and
headaches following a CS/6 fusion but has little or no
discomfort in his arm. I think he is probably as good
as he is going to be and I would regard his present
level of disability as being permanent. I do not
think he will be able to wear a hard hat or carry a
light on his head for prolonged periods of time and
for this reason I would regard him as being unfit to
return to underground work."
The plaintiff is presently 40 years of age. He was 36 when
injured. He has been engaged in underground mining with the
defendant since 1981 . His previous work experience wa,s in
smaller underground mining and station work. He left school at
15 years of age and has no academic training or trade
qualifications.
The plaintiff, I find, has a permanent disability of the
neck which will preclude him from engaging in underground mining
with the defendant, or in any mine situation where the wearing
of a hard hat and lamp is necessary. I find that, on the balance
of probabilities, the plaintiff would have continued to work with
the defendant underground for as long as employment was available
and he was physically fit for the work. I do not accept as a
matter of probability that the plaintiff would have left the
employment of the defendant to return to the mining fields at
Cooper Pedy for any of the possible reasons contended for by the
defendant. The matrimonial problems of the defendant and his
former wife precluded his having sufficient capital to undertake
such a move to self-employed prospecting.
The plaintiff is still employed by the defendant
aboveground. He is now employed as a sampling supervisor. He
-- 12 of 17 --
12
took
up
that
position
on
28
November,
1989.
Prior to
that
he
was
employed
as
leading
hand
in
the
core
shed,
a
position
he had
held
for
18
months.
So
far
as
the
evidence
discloses,
the
plaintiff
is
secure
in his
present
employment
with
the
defendant.
I
find
that
if
the
plaintiff
were
forced onto
the
open
labour
market,
he
would
be
at
a
distinct
disadvantage
because
of
his
lack of
education
or trade
skills
and
his
inability
to
perform
heavy
lifting
or
manual work.
He
would be
reduced
to
light
unskilled
labouring
or supervising functions.
Evidence
was
given
by
Mr.
J.
Cox,
chartered
accountant,
in
relation
to
the
comparative
financial position of the
employee
who
took
the
plaintiff's
position
and
the
plaintiff
from
the date
of accident to
March
1990. Without
taking
overtime
into
consideration, the
plaintiff
was,
at
11
March,
1990,
$562.58
per
fortnight or
$281 . 29
per
week
worse
off.
On
the other
hand,
the
plaintiff
was
earning
more
overtime so
that
the
nett loss
was
approximately
$230.
00
per
week.
In order
to
earn
the extra
overtime
payments,
the
plaintiff
had
regularly
been working
six
or
seven
day weeks.
The
additional
money was
therefore
at
a
significant cost to the
plaintiff's
general
amenity
of
life.
The
extra
hours
were
necessarily
worked
because
of the position held.
They were
not
a
matter of conscious choice.
The
plaintiff, at
the time
of his injury, suffered
from
high
blood pressure
which
required
him
to take medication
daily.
He
had
suffered
a
number
of injuries
underground and, although they
resolved themselves and did not interfere
with his
work, some
of
the injuries
were
to the lower back.
He was
also losing his
hearing due to working with industrial
machines and on each
test
-- 13 of 17 --
13
every
two
years
his
hearing
was
markedly
worse.
From
working
with
vibrating
machinery he had
developed
carpal tunnels
which
resulted in
some
numbness
in
the
arms. Although
none
of
these
conditions
interfered
with
his
capacity
to
work,
they demonstrate
that
mining
is
a
hard
and
hazardous occupation
which
takes
its
toll
on
the
human
body.
There
may
be examples
of older
persons
continuing
in
such
work
underground,
however,
I
am
of the
opinion
that,
on
balance, the
plaintiff
would
have
ceased
heavy
underground mining
by
age
50
and,
more
probably than
not,
changed
to
light
duties
with the
defendant
or
some
other
employer
to
age
60.
The
present
value
of
$230.00
per
week
nett
on
the
5
per cent
tables for
10
years
is
$94,398.00.
The
plaintiff
has
some
prospects of
promotion
in his
present
employment
although
he
is
reluctant to
accept
positions of authority
and
this will
hold
him
back. His
present
base
salary
is
subject to
annual review
and
he
may move
upward
in the
range over
the
next
few
years,
depending
upon
satisfactory
performance. There
is
some
unquantified superannuation
benefit
advantage
in his
present
staff
position
over
working underground because each
is
computed
on
base
salary, his present
base
salary
being higher than
a
plate
layer
working underground. There
are other incidental benefits,
e.g.
commuting one week's holiday
and
contributions for
medical
services.
Taking account of the prospects of betterment because
of his present
staff position
and
the
normal
exigencies of
life,
and
recognising that
I
have reduced the working
life
to
10
years
because of the particular circumstances of the
plaintiff
and
the
particular occupation in which he was engaged,
I
consider that
-- 14 of 17 --
14
a sum
of
$80,000.00
is
an
appropriate figure
for future
economic
loss.
Mr. Cox
also
gave
evidence
that
as
at
11
March,
1990,
without
taking
overtime
into
consideration,
the
plaintiff
was
$24,726.95
worse
off
than
the
comparative
employee,
Mr.
Allen.
The
nett
weekly
disadvantage as
at
11
March, 1990 was
approximately
$230.00
per
week
after
taking the
overtime
of
both
the
plaintiff
and
Allen
into
account as appears
from
the evidence
of
Cox. From
March 1990
to
judgment
is
approximately
38
weeks.
The
additional past loss
is
therefore
approximately $8,700.00
nett.
Discounting
for
contingencies,
I
consider
$30,000.00
is
an
appropriate figure for past
economic
loss.
I
turn to
the
plaintiff's
claim
for loss
of amenities.
The
plaintiff
spent four
to five
days
in hospital
after
the
surgical
intervention to
fuse the
discs.
He
was
in
a
neck
brace
for
two
months
after
the operation.
The
plaintiff
gave
evidence
of
severe
debilitating
pain
and
headaches
prior to
the operation.
The
pain
radiated
from
the
neck
down
the
right
arm.
After the
operation the pain
down
the
arm
went away. However,
the
plaintiff
has continued
to suffer
from
neckaches
and
headaches
of varying degree
on
a
daily basis.
As was
apparent
from
watching
the
plaintiff
in court,
he
holds
his
head forward
all
the time. This,
he
says, helps his pain.
The
evidence
of the
physiotherapist,
Ms. Nye, was
to the effect that
the pain
was
muscular
or postural
and
that the
plaintiff
should have improved
more
than he has
after
the operation. There
is
no
suggestion in
the report of Dr. Douglas, the orthopaedic surgeon,
that the
plaintiff's condition is
caused by bad posture or is anything
-- 15 of 17 --
15
other
than
permanent.
I
accept
the
opinion
of
Dr. Douglas
in
preference
to
that
of the physiotherapist.
I
do
not accept the
suggestion
made
by
the
defence
that
the
pain
is
exaggerated
or
anything
other
than
intermittent
moderate
pain.
The
clear
impression
I
gained
listening
to
the
plaintiff is
that
he does
not
like
a
staff
position
aboveground
with
the
responsibility
that
the
position
entails.
· I
have
no
doubt
that
if
the
plaintiff
could
work
underground
with
a
moderate degree
of pain
he
would
do
so.
I am
satisfied that
the
headaches
and
pain
that
the
plaintiff
suffers
are
real
and
substantially interfere
with
his
amenity
of
life.
I
accept
his
evidence
that
his
ability
to
go
prospecting for
gems
or
gold,
which
was
a
hobby
he
previously
engaged
in,
has been impaired
to
a
significant
degree.
As I
indicated
above,
the
need
to
work
substantial
overtime,
while reducing
his
economic
loss,
has
in
the past
and
will in
the
future
reduce
the recreational
time
that
he
would
otherwise
have
had
available.
I am
of the opinion
that
an
appropriate figure
for past
and
future pain, suffering
and
loss of amenities
is
$30,000.00.
Interest
should
be awarded on
$10,000.00
of the
award
for past pain, suffering
and
loss
of amenities.
The
plaintiff
swore
that
he had
in the past,
and
at
the date of
trial,
used
a
pack
of
100
Panadene
tablets
each
fortnight.
No
evidence of cost
was
given.
I
will
allow
$500.00
for past
and
future medication.
The
special
damages
total
$6,057.12 and
the
plaintiff is
obliged to repay to the
Workers' Compensation Board $15,938.39.
Of
this
amount $5,922.53
was
paid as weekly
benefits (gross)
between
1 March, 1988 and 26 May, · 1989. Tax
in the
sum
of
-- 16 of 17 --
16
$1,626.81
was
deducted.
Additionally,
a
disability
settlement
of
$5,585.00
was
paid
on
a
date
not
disclosed
by
the
evidence.
In the
circumstances,
I
propose
to
allow
interest
on
$20,000.00
of the
past
economic
loss
at
6
per cent
from
the date of the
injury to
judgment.
The
plaintiff's
damages
ought
therefore
to
be
assessed as
follows:-
(a)
Pain,
suffering
and
loss
of
amenities
(b)
Interest
on
$10,000.00
of
(a)
above
at
6
per cent
for
3.5 years
(c)
Past
economic
loss
(d)
Interest
on
$20,000.00
of
(c)
above
at
6
per cent for
3.5 years
(e)
Impairment
of earning capacity
(f) Special
damages
(g)
Past
and
future
medication
Less
25
per cent contribution
Less workers' compensation refund
$
30,000.00
$
2,100.00
$
30,000.00
$
4,200.00
$
80,000.00
$
6,057.12
$
500.00
$152,857.12
$
38,214.28
$114,642.84
$
15,938.39
$
98,704.45
There
will
be judgment
for the
plaintiff
against the
defendant
in the
sum
of
$98,704.45 with
costs of
and
incidental
to the action, including reserved costs,
if
any,
to
be
taxed.
-- 17 of 17 --
Official source: https://www.sclqld.org.au/caselaw/QSC/1990/399