Construction Management Associates Pty Ltd v Crawford-Fish & Ors [1990] QSC 334
IN
THE SUPREME
COURT
OF QUEENSLAND
No.
1041
of
1990
BETWEEN:
CONSTRUCTION
MANAGEMENT
ASSOCIATES PTY. LTD.
Plaintiff
GEOFFREY
NOEL
CRAWFORD-FISH
First
Defendant
PAC
PROP
DEVELOPMENTS
LIMITED
Second
Defendant
KABASKEL
PTY. LIMITED
Third
Defendant
EXTEMPORE
REASONS
- SENIOR
MASTER
HORTON
O.C.
Delivered the nineteenth
day
of
September,
1990
This
is
an
application for security for costs
by
the
defendant
against the
plaintiff
who
is
a
subcontractor with
respect to
a
large building project
on
the
North Coast. There
has been
a
number
of re-structurings in the organizations
which
stand behind the present defendants
and
these
all
go back
as
far
as indeed
Tricontinental
and
the State
Bank
of Victoria.
Everyone
in this
action therefore
seems
to
have had
some
degree
of financial
problems
in recent
months and
the present
state
of the
litigation
with
which
I am
concerned
is litigation
in
which
the
plaintiff
seeks to claim as against the receiver of
the present project manager/builder and one
of the original
owners
of the subject lands, monies due and owing
to the
subcontractor pursuant to certain subcontracts for the'supply of
carpentry work.
-- 1 of 3 --
~
The receiver/manager Mr. Crawford-Fish had a meeting with
the subcontractors on site in January this year and a transcript
of that meeting is annexed to the material. It may well be that
the respondent/plaintiff has been somewhat selective in the
passages which have been drawn from that transcript but it seems
to me arguable, at the very least, that the receiver adopted a
somewhat unusual course of conduct in order to induce
subcontractors (then on site and then unpaid) to continue
performance of their contractual obligations viz a viz Project
1 Pty. Ltd. which was then of course the project manager and
builder.
In February 1990 the receiver used his powers to terminate
the retainer of Project 1 and hence very correctly points out
that the receiver has no contractual obligations with the present
plaintiff or indeed in the other subcontractors.
The applicant has demonstrated that the present plaintiff
corporation is in a very delicate financial state. True it is,
that in recent months, the company has traded more successfully
than the previous twelve months, but I cannot close my eyes to
the fact that it is arguable that the plaintiff has acted to its
substantial detriment by completing its contractual obligations
viz a viz Project 1 as a result of the overtures made by the
receiver at the meeting in January 1990.
Hence, as I find the applicant has discharged the initial
obligation cast upon him to demonstrate that there is an
apprehension that in the event of a successful defence to this
action the plaintiff will be unable to pay the costs awarded
against it. However, when it comes to the further exercise of
the discretion I am satisfied that it is strongly arguable that
the respondents impecuniosity has arisen from the losses
sustained as result of the carrying out of its contractual
-- 2 of 3 --
l
obligations, the fruits of which the present applicant now
enjoys. That impecuniosi ty of course would be relieved by
satisfaction of the debts alleged to be owed to it with respect
to the construction work on the subject project and in my view
the justice would not be served in the circumstances of the
present case by shutting out the plaintiff from the prosecution
of its action and accordingly I decline to make an order for
security. The application is dismissed with costs to be taxed.
-- 3 of 3 --
Official source: https://www.sclqld.org.au/caselaw/QSC/1990/334