Babooti Pty Ltd v Watson [1990] QSC 279
10
c 20
1
C'
30
C
40
C
·-·
-
••
----.
--
~.~_-!
-.-·
IN
THE SUPREME
COURT OF
QUEENSLAND
CIVIL
JURISDICTION
BEFORE
MR.
JUSTICE
COOPER
BRISBANE,
30
JULY
1990
--.-.--:--~,,
No.
6524
of
1982
REV!3ED COPIES .ISSUE
Court Rep0rting -Bureau
Date, a / 8
!C/0
----,,.-.....---.
...
.-
..
----+
(Copyright
in this transcript
is
vested
in
the
Crown.
Copies
thereof
must
not
be
made
or sold
without
the
written
authority
of the
Chief Court
Reporter,Court
Reporting
Bureau.)
BETWEEN:
BABOOTI PTY LIMITED
-and-
GRAHAM
GEORGE WATSON
JUDGMENT
Plaintiff
Defendant
HIS
HONOUR:
In
this
matter
I am
satisfied
that
the
defendant
Graham
George Watson
was
called
and
failed to
appear
and
-that the matter
is
one
to
which
0.39
r.31 of the
Rules
of
Court apply.
I am
satisfied,
having
regard
to
the contents of the
affidavit
of
Robert Bernard Davis,
that
the
plaintiff
has
made
out
its
cause of action
as pleaded
and
that
it
is
entitled to forfeit
a
deposit of
$19,000
paid
by
the
defendant under
a
contract for the sale
of
a
building
unit,
being Lot
74
on
registered plan
no.
5369, Vol.6393,
Folio
30.
The
relevant contract of sale
is
dated
23 November
1982. The
right to forfeiture
was
provided
by
clause
7
of
10
20
30
40
so so
that
agreement.
I am
also satisfied that the
plaintiff
was
entitled to
$98,044.77 for
damages,
including liquidated
damages
for
delays provided for
by clause
11
of the agreement for the
___:::_6""-0--+------------------------~-----------'
60
-Glovt. Printer, Qld. 1
-- 1 of 2 --
,,r--...
(
10
20
30
40
50
60
period 22 September .1982 until the date of resale of the
building unit on 16 September 1983 in accordance with the
exercise of the powers which the plaintiff had under the
said agreement. I am satisfied that for the purpose of
clause 11 of the agreement the l.iquidated damages for delay
applies for the period until payment, being a payment
received by the plaintiff from the new purchaser.
I have been asked to grant interest pursuant to s.72 of
the Common Law Practice Act in the sum of 18 per cent on the
basis that such was an agreed sum. I am not persuaded in
all the circumstances the sum of 18 per cent is an
appropriate sum. What I propose to do is grant interest at
the rate of 12 per cent for a period of three years. There
is no material before me to indicate who is responsible for
the apparent delay in this matter coming on-for trial;· The
writ action was commenced in 1982. The last interlocutory
step, other than entry for trial, appears to have taken
place in 1985, and so far as I can see from the file, the
matter was entered for trial in October last year. In the
absence of material explaining the delay, I think a period
of three years at 12 per cent on the sum of $75,444.67 is
fair and reasonable in all the circumstances.
I order that the defendant pay the plaintiff's costs of
and incidental to the action, including reserved costs, if
any, to be taxed, and I would ask counsel to have minutes of
order prepared and delivered to me which I will initial and
place with the file.
--vt. Printer, Qld. 2
10
30
0
40
0
so
60
-- 2 of 2 --
Official source: https://www.sclqld.org.au/caselaw/QSC/1990/279