Antill v Estate of Parkinson [1990] QSCFC 91
IN THE SUPREME COURT
OF QUEENSLAND
FULL COURT
BETWEEN :
APPEAL 6 OF 1990
HARLEY JOHN ANTILL and
TONI MARGARET ANTILL
(Plaintiffs) Respondents
AND: JEFFREY ERVIN and MARGARET WEARNE
as Executors of the Estate of
KEITH PARKINSON Deceased
(Defendants) Appellants
CHIEF JUSTICE
DERRINGTON J
de JERSEY J
Reasons for Judgment delivered by de Jersey J on
21st November, 1990. The Chief Justice and Derrington J
agreeing with the reasons and concurring as to the order
"APPEAL DISMISSED WITH COSTS. ( I
[1990] QSCFC 91
-- 1 of 11 --
IN THE SUPREME COURT
OF QUEENSLAND
Appeal No. 6 of 1990
Before the Full Court
The Chief Justice
Mr. Justice Derrington
Mr. Justice de Jersey
BETWEEN:
HARLEY JOHN ANTILL and
TONI MARGARET ANTILL
(Plaintiffs) Respondents
AND:
JEFFREY ERVIN and WARREN WEARNE
as Executors of the Estate of
KEITH PARKINSON Deceased
(Defendants) Appellants
JUDGMENT - de JERSEY J.
Delivered the 21st day of November, 1990
CATCHWORDS:
Counsel: K.S. Howe for appellants
D.C. Andrews for respondents
Solicitors: Carberry and McQuire town agents for Greg Delaney
and Neil Hoore for appellants
Wilson and Copley for respondents
Hearing dates: 18th and 22nd October, 1990
-- 2 of 11 --
IN THE SUPREME COURT
OF QUEENSLAND
Appeal No. 6 of 1990
BETWEEN :
HARLEY JOHN ANTILL and
TONI MARGARET ANTILL
(Plaintiffs) Respondents
AND:
JEFFREY ERVIN and WARREN WEARNE
as Executors of the Estate of
KEITH PARKINSON Deceased
(Defendants) Appellants
JUDGMENT - de JERSEY J.
Delivered the 21st day of November, 1990
The appellants are the executors of the estate of the now
deceased lessor of premises at 129 Ferry Road, Southport. The
respondents were the lessees of the premises, of which they took
possession on 1st May, 1984 for a three year term. They left the
premises at the end of November, 1984, alleging that the lessor
was in serious breach of the lease. A learned District Court
Judge held that the respondents were entitled to terminate the
lease, and awarded them $4,222 damages. He dismissed the
counter-claim, by which the appellants had claimed $35,367 lost
rental, interest and re-leasing costs, on the basis that the
respondents had repudiated the lease.
Prior to entering into the lease, the respondents discovered
that the premises had a serious water leakage problem. During
an inspection on a rainy day, the male respondent (Mr. Antill)
saw that water was flowing through the premises, and that the
-- 3 of 11 --
2
walls were soaked. The respondents hoped to use the premises for
manufacturing purposes. Mr. Antill explained to the owner's
agent, one Chapman, that water leakage into the premises was not
acceptable, for safety reasons - the employees using electrical
equipment, to avoid electrical problems with the equipment, and
to avoid rusting of the product. Mr. Chapman, on behalf of the
now deceased owner Mr. Parkinson, agreed to have the problem
rectified. It was Mr. Parkinson's failure to rectify the
problem, despite efforts to do so from time to time, which led
to the respondents' leaving the premises seven months later.
The lease came about in this way. On 25th March, 1984,
Mr. Antill signed an offer to lease the premises. It set out all
material terms for a lease, and referred to the preparation of
a formal lease on those terms. The offer specified that
acceptance of it would create a binding lease on those terms.
The terms included this provision: "Owner to rectify leaks prior
to occupation". The parties signed a formal lease on 28th May,
1984.
That formal lease did not, however, refer to the lessor's
obligation to rectify the leaks, which had not been rectified
prior to the respondents' taking possession on 1st May, 1984.
Neither did the lease refer to the offer to lease dated
25th March, 1984 (which did refer to rectification of leaks prior
to occupation.). The Judge nevertheless held that the obligation
to rectify leaks had continuing contractual force. He held that
the offer to lease and the lease should be read together, as
constituting the true agreement between the parties, which
-- 4 of 11 --
3
therefore included the undertaking to rectify leaks prior to
occupation.
The appellants contended at the trial that the respondents
had waived the need for the lessor to comply with that
undertaking. The undertaking in terms obliged the lessor to
rectify the leaks prior to occupation . The respondents took
possession knowing that the rectification work had not been done
by then. Mr. Antill, whose evidence the Judge accepted, said
that when he entered into possession the weather was good, and
that he was "a trusting individual" and had confidence that
Mr. Parkinson would rectify the problem in accordance with his
word. The Judge pointed out that the entry into possession on
1st May, 1984 was to the advantage of both parties, and that
Mr. Parkinson's subsequent efforts to rectify the water problem,
taken with the respondents' persistent subsequent requests that
it be fixed, were inconsistent with a view by the parties that
Mr. Parkinson was no longer obliged to attend to the problem once
the respondents had gone into possession. The Judge held that
the need for rectification prior to occupation had been waived,
but not the need for rectification thereafter.
Over the next seven months, some rectification work was
done, but the problem was not removed. Two months after the
respondents took possession, there was substantial rain, which
led to Mr. Parkinson's men working on the roof and guttering, and
fixing the leakage into .the walls. But with subsequent rain,
flooding of the floor recurred. Cutting back of vegetation did
not solve the problem. Mr. Antill subsequently saw seepage
through cracks in the concrete slab, and notified Mr. Parkinson,
-- 5 of 11 --
4
who assured him that "everything would be fixed", but it was not.
Indeed, in September, Mr. Parkinson told Mr. Antill that a
seepage problem in the corridor "could not" be fixed, which
Mr. Antill did not accept. Then in a letter of 27th November,
1984, Mr. Parkinson's solicitors asserted that he "clearly (had)
no legal responsibility on the point of the flooding". They
asserted that it was "a problem affecting the general locality
and .. no fault of (their) client." The Judge saw this as an
indication that Mr. Parkinson "did not intend to take any further
steps to alleviate the problem".
The Judge held that the appellants had, in these
circumstances, breached what amounted to a condition of the
agreement between the parties. He also held that the undertaking
was of such crucial importance as to go to the root of the
contract. The Judge held the respondents entitled to terminate
the lease for the breach of that obligation. He noted that the
respondents' manufacturing process depended on dry working
conditions, especially for safety reasons; that Mr. Parkinson had
failed to rectify the water problem, despite repeated attempts,
over some seven months; and that with the forthcoming wet season,
the position in November, when the respondents terminated, was
critical .
The first major submission for the appellants was that,
accepting the Judge's characterisation of the obligation - as a
condition, or so important as to go to the root of the contract,
the respondents could not lawfully have terminated the lease
except for breach continuing after service of a notice making
time "of the essence" with respect to that obligation. The
-- 6 of 11 --
5
respondents did warn Mr. Parkinson, in advance of moving out, of
their intention to vacate the premises because of the water
problem, by letter dated 16th November, 1984, and orally (by
Mr. Antill) in early November. But they did not serve a notice
of the nature now claimed by the appellants to have been
necessary.
Such a notice was not necessary in this case. That is
because of the Judge's characterisation of the obligation, as
"essential" in the sense discussed in Associated Newspapers Ltd,
v. Bancks (1951) 83 C.L.R. 322, 337, and what amounted to his
conclusion that Mr. Parkinson repudiated that obligation.' The
repudiation of such a covenant entitles the innocent party to
rescind without giving a notice making time of the essence. See
Laurinda Ptv . Ltd, v. Capalaba Park Shopping Centre Ptv. Ltd.
(1988-9) 166 C.L.R. 623, 642-3.
The Judge directed his attention to whether the nature of
the obligation and the nature of the breach justified
termination. He did so against the background of a submission
by the appellants that they did not "repudiate the contract".
He described the obligation as a condition, of "crucial
importance", and as "going to the root of the contract". There
was ample basis for that characterisation. As the Judge said,
the business required dry working conditions, for safety reasons
especially; and Mr. Antill had emphasised the importance of that
consideration to Mr. Chapman, Mr. Parkinson's agent. As to the
nature of the breach, the Judge observed that the problem was not
resolved "despite repeated undertakings and attempts" by
Mr. Parkinson, over some seven months. The Judge had earlier
-- 7 of 11 --
6
referred to Mr. Parkinson's statement, concerning seepage in the
corridor, that that problem "could not be fixed". (That has
significance to an assessment of the owner's attitude to his
obligation, even though that area of seepage may have been of
little importance to the respondents, and in any case Mr. Antill
responded that "that wasn't good enough.") The Judge had also
referred to Mr. Parkinson's solicitors' statements in the letter
of 27th November, which he reasonably read as an indication that
Mr. Parkinson "did not intend to take any further steps to
alleviate the problem". In all these circumstances, the Judge
rejected the defence submission that Mr. Parkinson had not
"repudiated the contract", and went on to hold that the
respondents were entitled to terminate the lease. That must have
involved the conclusion that Mr. Parkinson had repudiated this
obligation to rectify the leaks. The giving of a notice making
time of the essence was therefore not a necessary pre-requisite
to termination.
Mr. Howe, who appeared for the appellants, conceded that the
Judge held that the lessor's breach of the essential obligation
to rectify was of a repudiatory character. He did however
challenge that characterisation. He referred especially to
Mr. Parkinson's efforts from time to time to repair the leaks,
and to Mr. Antill's agreement in his evidence that Mr. Parkinson
appeared to be willing to seek to rectify the leaks. Such
circumstances, he contended, meant that one could not reasonably
conclude that Mr. Parkinson, by the end of November, was
renouncing his obligation.
-- 8 of 11 --
7
The Judge clearly considered, however, that by the time of
the respondents' departure from the premises at the end of
November, assertions by Mr. Parkinson that "everything would be
fixed" and the like had become hollow. That explains the Judge's
reference to Mr. Parkinson's statement, with regard to the
leaking into the corridor, that it "couldn't be fixed", which had
potential significance even though that leakage produced no real
problem for the respondents. It is also consistent with the
Judge's reference to Mr. Parkinson's solicitors' letter of 17th
November, in which they denied that Mr. Parkinson was under any
legal obligation to rectify the flooding^' leading to the Judge’ s
conclusion that Mr. Parkinson did not intend to take any further
steps to alleviate that problem. From August, Mr. Parkinson's
response to complaints about leaking from Mr. Antill had become
sporadic. No further rectification work was carried out after
that. In response to Mr. Antill's statement that a complete re
construction of the floor was necessary, Mr. Parkinson responded
rather blandly that "everything can be fixed",. . It was not, .of
course, and when in early November, Mr. Antill told Mr. Parkinson
orally that he was sick of the problem and was going to move out,
in view of Mr. Parkinson's failure to rectify the problem over
a long time, Mr. Parkinson made no response at all, and that may
be thought somewhat inconsistent with a continuing willingness
or anxiety on his part to seek to resolve the problem.
Overall, therefore, the evidence of Mr. Parkinson's
willingness to rectify the problem, evident especially in the
early months of the tenancy, did not preclude the Judge's finding
-- 9 of 11 --
8
that the lessor's breach ultimately assumed a repudiatory
character.
The appellants also challenged the Judge's according
continuing contractual force to the obligation to "rectify leaks
prior to occupation" notwithstanding that it was not included
in the lease. The Judge did this by reading the lease and offer
to lease together, as constituting the true agreement. He might
also have regarded the offer to lease, accepted by the owner, as
a collateral contract. Either approach would have been
appropriate in view of the special importance to the respondents
of compliance with the undertaking, which Mr. Parkinson - through
Mr. Chapman - appreciated; the specific terms of the undertaking
in the offer to lease; and its provision that its terms would be
the terms of the formal lease.
A particular point taken by the appellants was suggested
inconsistency between that obligation and ell. 35 and 22 of the
lease. Clause 22 obliged the lessor "to keep the roof and
exterior walls ... weatherproof", "on written notice from the
lessee and within a reasonable time thereafter". Rectification
of leaks is different from keeping premises weatherproof, which
assumes that they are weatherproof to begin with. Clause 34 says
there is no warranty that the premises "are now or will remain
suitable or adequate for all or any of the purposes of the
lessee", and that all warranties "as to suitability and adequacy"
implied by law are negatived. There is no inconsistency between
that exclusion and this undertaking, which obliged the lessor to
rectify leaks (and thereby bring about that "adequacy") prior to
occupation, albeit that that time limitation was waived.
-- 10 of 11 --
9
The appellants also challenged the Judge's conclusion that
the "true agreement" covered both lease and offer to lease,
thereby including the obligation to rectify the leaks. While one
would ordinarily regard such a lease as an exclusive record of
the parties' obligations, this particular obligation need not
necessarily have been set out in the lease, and there are clear
indications that the parties meant it to survive the execution
of a lease. It was explicitly set out in the offer as a lease
condition, and the offer specified, as the terms of any lease,
those set out in the offer, should it be accepted. The conduct
of the parties subsequently, in requesting rectification of leaks
and attempting it, is consistent with there being a subsisting
obligation in that regard. Further, as the Judge mentioned,
where the lease and offer differed as to rental, the parties
chose to adopt the provisions of the latter. In summary, the
terms of the offer envisaged that it would have a continuing role
in defining the parties' obligations, the subsequent conduct of
the parties was consistent with its having that role, and it was
not necessary that a provision of this character find its way
into the formal lease document. The Judge's view as to the scope
of the agreement between the parties is sustainable.
It remains to mention that the Judge's conclusion as to the
extent of the waiver involved in the respondents' taking
possession notwithstanding that the leaks had not been rectified,
was one which was open on the evidence to which I earlier
referred .
I would dismiss the appeal with costs.
-- 11 of 11 --
Official source: https://www.sclqld.org.au/caselaw/QSCFC/1990/091