Brazil v The Commissioner of Main Roads [1990] QLC 31
"I •
,..
.. .. IN THE LAND COURT
OF QUEENSLAND
BETWEEN
H.A. and A.O. B. Brazil
and
The Commissioner of Main Roads
\ QBQER AMENDING CLERICAL ERROR IN JUDGMENT
'
(Claimants)
(Respondent)
On the 7th September, 1990, judgment determining compensation payable to the
claimants herein was handed down. The judgment inter alia reads:
II
Accordingly, compensation under all heads is determined at $207,550.
Advances against compensation were made in the sums of $40,000
on 9th January, 1989 ,. and $36,500 on 31st January, 1989. A stay of
interest was ordered by the Court during the period of an adjournment
between 5th March, 1990, and 29th July, 1990. Interest is therefore
ordered to be paid on the sum of $207,550 at the rate of 13
percentum per annum from and including the date of resumption up
to and including 9th January, 1989; thence on the sum of $167,550 up
to and including 29th January, 1989; and thereafter on the sum of
$131,050 up to and including the day immediately preceding the date
compensation is paid save that interest shall not be paid on the sum
during the period of the adjournment. "
The respondent has brought to my attention a clerical mistake in the judgment in
that the date 29th January, 1989, underlined in the above extract of the judgment
st10uld read "31st January, 1989".
To correct the mistake I order that the judgment of the 7th September, 1990, be
amended by deleting the words of the judgment set out above and substituting the
following words:-
II
Accordingly, compensation under all heads is determined at $207,550.
Advances against compensation were made in the sums of $40,000
on 9th January, 1989, and $36,500 on 31st January, 1989. A stay of
interest was ordered by the Court during the period of an adjournment
between 5th March, 1990, and 29th July, 1990. Interest is therefore
ordered to be paid on the sum of $207,550 at the rate of 13
percentum per annum from and including the date of resumption up
to and including 9th January, 1989; thence on the sum of $167,550 up
to and including 31st January, 1989; and thereafter on the sum of
$131,050 up to and including the day immediately preceding the date
compensation is paid save that interest shall not be paid on the sum
during the period of the adjournment. "
Dated this thirty-first day of Qctobe>r, 1990.
./4JtL!r,4--f1o,,J _,:::;i,e a,rr:f' /f/JA-/Jt:.
74c u.w,e.r 111~r do o~~
(D.M. White)
Meni5er of the Land Court
-- 1 of 17 --
LAND COURT,
BRISBANE
7th September, 1990
Re: Claim for Compensation -
Resumption for Purposes of a Transport Corridor.
A89-63.
H.A. and A.O.B. Brazil
v.
The Commissioner of Main Roads
J U D G M E N T
On and from 11th July, 1987, a strip of land was taken from the claimants' fee
simple parent parcel being Lot 2 on RP 205134 (original portions 40 and 41), County of
Stanley, Parish of Woogaroo, for the purpose of a Transport Corridor between the
Cunningham Arterial Road at Gailes and the Mount Lindesay Arterial Road at Browns Plains
and vested in the Commissioner of Main Roads. The land taken has an area of about 15.07
hectares (including about 1.82 hectares from Easement A on RP 127318). The land was
taken under the provisions of the Acquisition of Land Act 1967-1986 and the State
Development and Public Works Organization Act 1971-1981. The parent parcel prior to
the resumption had an area of 241.5 hectares. The parcel was generally of rectangular
shape with frontages of -
809.31 metres to Wadeville Street on the northern boundary;
2040.15 metres to Stapylton Road on the western boundary;
1457.62 metres to Johnson Road on the southern boundary;
2634.99 metres to the rear or eastern boundary.
[1990] QLC 31
-- 2 of 17 --
2
Between the rear boundary and Oxley Creek which generally parallels this
boundary is a strip of land a few hundred metres wide which was excised from the parent
parcel some years ago and sold to a company which intends to use it for extractive industry
purposes. This land is zoned for the purpose. Land on the east (right) bank of the creek is
used for this purpose by another company. At the date of resumption the parent parcel was
in an englobo state. It is situated within the area of the City of Brisbane and at the date of
resumption was zoned "Non-Urban". Under the Town Plan in force at that date it is clear
that land within this zone is intended to be retained in a semi-rural state, that no suburban
development of any kind will be allowed and that new allotments will be required to have a
minimum area of 4 hectares. The land is on the border of the City of Brisbane with the City
of Logan. The suburb in which the land is situated is predominantly a rural residential
suburb and is known as Heathwood. The area lies in a direct line about 19 kilometres south
of the Brisbane Central Business District. Town water, electricity and telephone services are
connected or are available to the property. Sewerage is not available. No public transport
system exists and the nearest primary school is in Ritchie Road which can be accessed from
Wadeville Street northerly. The nearest high school is about 5 kilometres away at Inala.
The nearest shopping centre is about 3 kilometres away at Browns Plains. The claimants live
on the property and part of it has been selectively cleared. The property before the
resumption could be described as being well elevated with gentle undulating falls from RL 65
metres to RL 25 metres in a general easterly direction towards Oxley Creek. The average
level is about RL 50 metres. Views of the high rise of the Central Business District can be
taken from parts of the property. Easement A is used for high voltage electricity transmission
lines.
What the resumption did was to take a funnel shaped parcel through the
central part of the property from west to east. The resumption follows and in part covers the
electricity easement. Three steel towers are located on the balance property. The peculiar
shape of the land taken comes about through the dual use which is to be made of it by the
-- 3 of 17 --
3
constructing authority. The land taken will house in part at the western end (the other part
being on the road reserve of Stapylton Road) a tollway whilst the narrow section will house a
toll road. The tollway consists of loops for entry to and exit from the toll road and the
structures necessary to collect toll fees. This picture may be completed by saying that to the
west of the subject land there lies an area of about 1,000 hectares or so of undeveloped land.
Wadeville Street northerly through to Ritchie Road is generally in rural residential subdivision
of about 1.6 hectare blocks whilst to the south-east (and south of Johnson Road) in the area of
Logan City is a subdivision known as Forestdale. This estate is also of rural residential sized
lots. Johnson Road is classified as a sub-arterial road whilst Stapylton Road is described as a
collector road. Johnson Road is a continuation of Browns Plains Road which connects
Browns Plains with Gailes in the west. Following the resumption the claimants
filed a claim on the respondent in the sum of $660,000. In the hearing of the matter leave
was granted to amend the claim for land, severance and injurious affection to $360,000 being
an assessment of compensation made by Mr G. Jorgensen, Dip.Bus., AAIV. Another valuer
called on behalf of the claimants (Mr G. de Bruyn AAIV) assessed compensation at $336,000.
Both considered that the parent parcel was ripe for subdivision at the date of resumption and
they made their assessments on the usual lines of a "before" and "after" valuation based on
hypothetical subdivision of the parcel into lots of a minimum of 4 hectares. On the plans
they followed 58 lots could have been achieved before the resumption and 54 lots after the
resumption. They had the benefit of an engineering assessment on costs and they both did
their final workings based on an interest factor of 13 percent (13%). On the other side the
assessment was made by Mr P.D. Grennan, a registered valuer in the employ of the
Department of Lands, Division of Valuations. He worked on similar lines and on the same
plans. His assessment of compensation is in the sum of $110,000. However, he made his
calculations (a) by providing reticulated water to all lots and (b) by providing reticulated
water to hypothetical lots 1 to 12 only. The latter exercise yielded a higher value for the land
in the hands of the owners and was accordingly adopted for the purpose of the assessment
although it actually brought up a lesser sum as compensation. Mr Jorgensen and Mr de
-- 4 of 17 --
4
Bruyn did their exercises on the basis that reticulated water would be provided to all lots. In
the pricing of the lots after the resumption, they performed two exercises - one on the
assumption that injurious affection arising from the use which would be made of the resumed
land was limited by law to that flowing from the toll road without regard being had to
injurious affection which may result from the use of the tollway in conjunction with the toll
road and the other from a combination of the total exercise. In the first exercise, injurious
affection is assessed in "ball park" terms of about 20% to 30% of the value of lots adjoining the
toll road; in the second, the expanse of injurious affection is taken along the frontage of
Stapylton Road into Wadeville Street on the north and southerly along Stapylton Road and
into and along the Johnson Road frontage - it being their opinion that traffic on these roads
which will become collector roads for the toll road will increase, will congest at the
intersections and consequently downgrade the value of frontage land after the resumption.
The range of depreciation in value to lots along these frontages is of the order of 4% to 6%.
There is a point of law here which needs to be addressed at this time. Counsel for the
respondent submits that the Court by law cannot address the matter to the extent it was
addressed by Mr Jorgensen and Mr de Bruyn on grounds that to do so would be offending the
principle of Edwards v. The Minister (1964) 2 QB 134 and would in effect be borrowing
from the scheme which is not permitted in law. Of recent years, Edwards case has received a
lot of consideration in this Court. The relevant cases are summarised succinctly in M.A. and
D.P. Syme v. The Commissioner for Railways (1988/89) 12 Q.L.C.R. 98. I see no point in
repeating them; save to say that the principle of Edwards case is applicable in the assessment
of compensation under s. 20 of the Acquisition of Land Act and secondly, that the words "the
exercise of any statutory powers by the constructing authority otherwise injuriously affecting
such other land" are not wide enough to embrace injurious affection flowing from the scheme
behind the resumption, except where and as discussed in the cases contained in the Syme case
a practical separation of damage cannot be made between the use which will be made of land
taken from the claimant and the use which will be made of the adjoining land. In this case,
counsel for the claimants submits that the question can be answered by going no further than
-- 5 of 17 --
5
considering the charter as laid down in s. 20. He says (and which was not sought to be
contested by counsel for the respondent) that the resumed land contains a toll way (in part
and the parts not separated) and a toll road and that it is therefore open to the Court as a
matter of law to consider the question of injurious affection arising directly from the
operation of these works as a whole. The only factual evidence I have is that part of the toll
way is upon the resumed land and the balance on the Stapylton Road reserve. In a plan
attached to the valuation of Mr de Bruyn, it appears that two leaves of the "four leaf clover"
are upon the resumed land and part of the toll "plaza" area. No attempt has been made to
separate the parts nor could they appear to be separated. I accordingly agree with the
submission of counsel for the claimant. However, as with the effects of the toll road, it must
be shown that the frontage land is damaged and that the damage is a direct and natural
consequence of such usage and that it be not too remote. See Harvey v. Crawley
Development Corporation (1957) 1 All. E.R. 504 C.A. and The Crown v. R.H. and J.M.
Corbould (1986/87) 11 Q.L.C.R. 50 L.A.C.
There is not a great deal of difference between the plan of the land before
resumption and the plan after the resumption. In the plan before the resumption there are
nine rectangular-shaped lots (Lots 1 to 9) fronting Wadeville Street. Coming into Stapylton
Road, there are then three lots (Lots 10 to 12) of similar shape and dimensions. Lot 12 will
border an internal cul-de-sac road which would run directly east and then swing to the
south-east towards the centre of the block. Opposite the southern (side) boundary of Lot 12,
there would be some five lots (Lots 22 - 26) fronting the internal road with the same
dimensions as Lot 12. There are then nine lots (Lots 13 - 21) which fan the internal road
with four lots sharing 180 degree frontage to the cul-de-sac. Of these lots, Lots 18, 19 and
20 would have the electricity easement well within the frontage area of the lots. The balance
of the Stapylton Road frontage would be taken up with ten lots (Lots 27 - 36) all of the same
shape and dimensions as Lot 12 except for Lots 34, 35 and 36 where they angle away slightly.
Lot 36 takes up the corner of Stapylton Road and Johnson Road. In Johnson Road, the
subdivision would comprise five lots (Lots 37 - 41) of near rectangular shape allowing for a
-- 6 of 17 --
6
slight curve in Johnson Road, then two square-type lots (Lots 42 and 43) which take up the
corner of Johnson Road and the internal road coming in in a north-easterly direction, then
northerly, ending in a cul-de-sac towards the centre of the block. Opposite would be Lots 57
and 58 taking up the frontage of Johnson Road. Beyond Lot 43 there are two lots of
rectangular shape (Lots 44 and 45) followed by four lots with frontage to the cul-de-sac (Lots
46 - 49) and then seven regular-shaped lots on the eastern side of the internal road (Lots 50 -
56). The higher contours on the land are found in a knoll which is at RL 65M and, together
with contour RL 60, swings in an arc through Lots 10, 11 and 12 and the frontage areas of
Lots 22 to 26. The contour in the area of Lots 1 to 9 is towards the north-east which is a
carry on of the slope from the knoll on Lots 10 to 12. The lowest point (RL35) of the area
intrudes into the frontage of the proposed Lot 2. In the area of Lots 13 to 21, slopes are
mixed, being in part to the north-east and part towards the south-east. In the southern area
of the block the contours are mixed and can best be described as sloping to the east from the
Stapylton Road frontage; to the north from midway on the Johnson Road frontage and falling
away from both sides of the proposed internal cul-de-sac road, more particularly with respect
of lots fronting the cul-de-sac. The view of the high-rise which the witnesses spoke about is
found in the area of Lots 10 and 12. It is accepted that the land is of fair average quality for
this locality. The design is one which is done on straightforward lines obtaining the
maximum permissible number of lots without providing any particular feature which would
isolate the design from the norm. Both Mr de Bruyn and Mr Jorgensen considered that it
would be prudent to provide water to all lots. They said that under this zoning the provision
of water is not mandatory but Mr de Bruyn is of the opinion that Council would prefer that
reticulated water be provided and that a development application would most likely meet
with approval more speedily if such was to be provided. On the other hand, Mr Grennan
said that the most likely usage of lots of this size will include the running of some stock. This
being so, he submits that dams would be provided. The likelihood of water rates would in his
opinion deter some purchasers. In order to compare the evidence on a common footing, I
propose to examine the hypothetical workings on the assumption that water is provided to all
-- 7 of 17 --
7
lots. In this light and in looking at the pricing structure on a broad base, there is a great deal
of unanimity between Mr Jorgensen and Mr Grennan. Overall, with water, Mr Grennan has
a gross realisation of $3,857,000 for 58 lots - an average of $66,500 per lot. Mr Jorgensen
has a gross realisation of $3,886,000 or $67,000 per lot but they do vary in their individual
pricing structure. This is evident in a consideration of the pricing of Lots 1 to 9 where Mr
Jorgensen has priced the lots at a uniform figure of $65,000. These lots fall in a
north-easterly direction from about RL 60 at the rear of Lot 9 down to RL 35 on the frontage
of Lot 2. Mr Grennan's pricing structure follows the contour - the better the contour the
higher the price - his pricing structure rises from $55,000 for Lots 2 and 3 up to $77,500 for
Lot 9. This line of pricing, he says, is supported by sales in the area. When I come then to
the pricing structure adopted by Mr de Bruyn, I find that his variation in pricing follows
generally that of Mr Grennan but he is on a considerably higher plane. He has Lot 2 at
$70,000 rising up to $80,000 (Lot 8) with a gross realisation for these lots of $695,000
compared with Mr Grennan's estimate of $577,500 and $585,000 (Mr Jorgensen). The key
to the approach taken by Mr de Bruyn is not found in the sales of land in the locality but in
the view taken by him that the estate could be marketed as an estate of some quality. In the
lands generally to the north in the suburb of Pallara subdivisions are of about 1.6 hectares
(some to 4 hectares) but there are no specific features which add to the area. On the other
hand, Forestdale which is situated within Logan City is an estate with curved internal roads
and with parkways meandering throughout. This estate is accepted by Mr de Bruyn as an
imaginative design. He uses Forestdale in the sense that the flavour of the estate could flow
over the subject estate. This is a proposition which I cannot accept. Nor does he accept it.
It is somewhat unfortunate because I was otherwise impressed with his evidence but in this
area of his evidence he admitted that if he were given a free hand in design, he would not
adopt the plan which has been adopted for the purposes of the assessment of compensation.
Prestigious estates, which Forestdale appears to be, require some sacrifices by the developer
and these are not present in the design plans in evidence. The general layout of the plan does
nothing to distinguish the proposed subdivision from subdivisions which exist to the north
-- 8 of 17 --
8
and hence, in my opinion, the market value of the lots would more likely tie in with the
market value of these lots than elsewhere. Sales in this part of the locality support the pricing
structure adopted by Mr Jorgensen and Mr Grennan. My only criticism of Mr Jorgensen's
approach is that his pricing structure is too general. If the market distinguishes between
elevation which is demonstrated in the sales attached to the valuation of Mr Grennan then I
would expect a developer to follow suit. In fact, to do otherwise could result in a fairly rapid
sale of the better blocks with little or no interest in the lower blocks. It follows that I take the
pricing structure and selling prices as advanced by Mr Grennan as the appropriate
commencing point. Not a whole lot needs to be said further. The development/engineering
costs which he has adopted are the lower of the estimates (by $30,000 in $1 million) and it is
agreed that the Court, acting on the well established principle of resolving doubts in favour of
the dispossessed owner adopt such costs. Mr Grennan has allowed for commission on sale at
rates recommended by the Institute. He has allowed for legal expenses in the sum of $300
per lot and advertising he has placed at $1,000 per lot. On the latter point, Mr Jorgensen
allowed $150 per lot. Mr de Bruyn would allow $2,000 per lot. He has, however,
endeavoured to market a prestigious estate on a standard design. The estimate of Mr
Jorgensen amounts to about $9,000 for the whole estate. Mr Grennan's estimate is $58,000.
Mr Jorgensen relied to some extent on the figures he obtained in respect of a completed estate
at Karama Outlook which was bought subsequent to the resumption date, subdivided and sold
in a market which it is agreed was more active than when the subject land was resumed.
The development was also a flow on from an existing development. Mr Grennan's estimate
envisaged signage on the property and newspaper advertisements. In the opinion of Mr de
Bruyn, if the lots were priced at the figures proposed by Mr Grennan and Mr Jorgensen, a
realistic estimate for advertising would be at the rate of $1,000 per lot. This estimate will
accordingly be adopted. It is agreed that it is reasonable to allow a period of six months to
obtain development approval. Mr Jorgensen and Mr de Bruyn postulated a selling rate of
about three lots per month. Mr Grennan has made his calculations on the basis that two lots
would be sold per month. It is agreed at the relevant date the market was static. Mr
-- 9 of 17 --
9
Grennan places a deal of reliance on statistics gathered by his employer. In the areas of
Pallara for the six month period - July/December, 1987 - two lots in excess of 4,000 square
metres were sold. In the ensuing six months, five lots were sold. In the area of Heathwood
and for the same periods, one lot and zero lots were sold. This form of evidence met with
some criticism on grounds that it could not be related to the number of lots on the market and
hence could not be directly related to the likely performance of a proposed development. Mr
Jorgensen placed some reliance on the sales of vacant lots in the areas which he used for
pricing the lots in subdivision and in the history of the Karana Outlook subdivision. The sales
attached to his valuation comprise three lots in Pallara which sold between June and October,
1987, three lots in Greenbank which sold between April, 1986, and July, 1987, two lots in
Park Ridge which sold between August and October, 1987, and two in Browns Plains which
sold in June, 1987. The exercise in respect of Karana Outlook showed that the land was
purchased, subdivided into 38 lots and sold between July, 1988 and May, 1990. The rate of
sale as worked out by Mr Jorgensen was 2.5 lots per month. Gross returns reflected an
average of $42,000 per lot. By comparison lots in the proposed subject subdivision are
priced at around $65,000. The market at the time of resumption was not active. The estate
would have been a new estate. The evidence suggests that a selling period based on 2 lots per
month is the more realistic. The allowance for risk and profit is the next matter in issue.
Here, Mr Jorgensen and Mr de Bruyn have allowed 30 percent. Mr Grennan has allowed 40
percent. Mr Jorgensen relies predominantly on the outcome of Karana Outlook. In
retrospect the development returned "as profit" about 30 percent. Mr de Bruyn relies on his
opinion and the opinion of another member of his firm taken from a settlement of
compensation with the constructing authority at Browns Plains. Mr Grennan relies on Court
determinations. The range of allowances appears to be between 30 percent to 40/50
percent. In L.M. Turner v. The Crown (1962) 29 C.L.L.R. 53, the Land Appeal Court at p. 62
said this:
"It is of course not possible to lay down a rigid standard to be applied in determining the risk of
realisation. The matter is one for determination in each case according to the
circumstances of each case. It seems clear to us that subdividers expect, quite
rightly in our opinion, a greater return on their outlay if areas are large,
subdivisional costs are likely to be high, if economic conditions point to delay in
-- 10 of 17 --
10
winding up an estate and if an estate is situated some distance from centres of
population and avenues of employment than they would if an estate is small,
costs are moderate, economic conditions favour quick sales and the land is close
to a metropolis. "
In the particular case a risk and profit factor of 35 percent was adopted for development
comprising 58 residential lots with an anticipated selling period of 12 to 15 months.
Towards the other end of the scale, the Land Appeal Court in J.A. and I.M. Schofield v. The
Crown (1968) 35 C.L.L.R. 233 determined a risk and profit factor of 45 percent in respect of
land having twice the number of lots involved in the Turner case and where it appeared that
a delay in obtaining approval was unavoidable. A consideration of the factors mentioned in
these judgments as being relevant for the purpose lead me to the conclusion that 40% should
be applied. It follows that the land may be valued before the resumption at the value
advanced by Mr Grennan, that is, $1,040,082 to which he would add the value of the
dwelling on the property at $70,000. The exercise reflects an englobo value of $4307 per
hectare excluding the dwelling.
The planning of the area after the resumption resulted in a loss of four lots. In
Stapylton Road south of the resumed area between what was to be Lot 26 in the "before" plan
and Johnson Road there were ten lots (Lots 27 to 36). After the resumption there will be
eight lots of similar dimensions to the former with the exception of Lot 24 where the northern
(side) boundary follows the funnel shape of the resumed land. The other alteration to the
design in the southern area is a reshaping of the lots at the end of the internal cul-de-sac road
which follows the conversion of the cul-de-sac into a T-type cul-de-sac whereby five lots are
obtained in lieu of four. On the northern side of the resumed land there were five lots
fronting the internal cul-de-sac road coming off Stapylton Road with northerly aspects.
These lots would have had the easement crossing them between the centre and the southern
boundary. In the "after" plan five lots remain - there being a widening of the frontage and a
shortening of the depth with the easement being placed on or near the rear boundary. In the
area of Lots 13 - 21 (9 lots) the redesign provides for six lots. In the "before" plan at least
-- 11 of 17 --
11
four were affected by the easement - three where the easement was quite near the frontage.
In the "after" design two lots are affected with the easement being towards the rear. Shape
and frontage has also changed. In the pricing of lots contained within the estate after the
resumption (and on the basis that water is provided to all lots), it is necessary to consider not
only the question of injurious affection but also the changes which have been made in design,
shape and frontage. According to Mr de Bruyn, the toll road presently has a traffic count of
about 8,000 vehicles per day. It is well lit, more so around the tollway. Lighting provides a
glow over the area which will, in his opinion, be within the view of those lots on the north
and south where the land slopes towards the east or to the point where the toll road leaves the
resumed land. Similarly he submits that the traffic drone will follow up the valleys, in
particular to those lots fronting the internal cul-de-sac road in the southern area. On the
assumption which seems reasonable that a purchaser would construct a home on a site so as
to gain the benefit of elevation and aspect, there is force in the submission put forward by Mr
de Bruyn. Conversely, in those areas where elevation and aspect is the opposite, the effect
must be much less if there is an effect at all. It is accepted that the lot which will be most
severely affected by the use made of the resumed land is Lot 24 as this lot borders the ramp of
the tollway and the toll road. Its counterpart on the north, Lot 23, has the tollway on the rear
boundary. Some idea of the measure of depreciation can be taken from the figures applied to
Lot 24 and those applied to Lot 27 on the plan before the resumption. Mr Grennan has the
relationship at $67,500 to $75,000; Mr de Bruyn $60,000 to $90,000; and Mr Jorgensen at $
52,500 to $65,000. Lots 22 to 26 on the "before" plan and which on the "after" plan with
redesign become Lots 19 to 23 have, according to Mr de Bruyn, been depreciated from about
$87,500 to $75,000. Mr Jorgensen's depreciation is from about $70,000 average to $52,500
whereas Mr Grennan has these lots reduced by the order of about 5 percent; that is, if Lot 20
is taken as a guide, from $75,000 to $71,000. In the southern area and in respect of lots
fronting the T-type cul-de-sac, Mr de Bruyn would reduce the value of lots by the order of
$65,000 down to $60,000 whilst Mr Jorgensen would appear to have depreciated these lots
from about $70,000 to $55,000. Mr Grennan sees little depreciation in this area in view of
-- 12 of 17 --
12
the fact that the logical homesites are near the road frontage. Both Mr Jorgensen and Mr de
Bruyn took their depreciation a little further away than Mr Grennan and generally followed
the valleys to lots at or near the end of the culs-de sac roads. Mr Grennan's approach is
based on reasoning that the depreciation would disperse after a couple of hundred metres and
hence would not affect the value of lots where the logical homesite was this distance or more
from the resumed land. The second part of this aspect of the case deals with the matter of
depreciation of lots fronting Wadeville Street, Stapylton Road and Johnson Road. On these
frontages the depreciation allowed by Mr Jorgensen and Mr de Bruyn is of the order of 4-6
percent. Mr de Bruyn who for several years was in the employ of the Department of Main
Roads describes Johnson Road as a sub-arterial road. He would describe Stapylton Road as a
collector road. He agrees that both are very busy roads. The purpose of the resumption was
to provide a corridor between the Cunningham Arterial Road at Gailes and the Mount
Lindesay Arterial Road at Browns Plains. In the absence of the corridor, access between the
two points was via Johnson Road-Browns Plains Road. This access remains. Stapylton Road
which he describes as a collector road takes traffic between Browns Plains and the industrial
areas to the north via Blunder Road. Wadeville Street carries only local suburban traffic. It
ceases just beyond the eastern boundary of the subject land. The toll road has been
constructed as a two-lane road. Mr de Bruyn said that when traffic flow gets to around
16,000 to 18,000 vehicles per day it is likely to be upgraded to a four-lane road. Mr
Grennan agrees with the description of Johnson Road as a sub-arterial road. He said that the
road carries a lot of truck traffic from the industrial areas to the west. He would describe
Stapylton Road as somewhere between a collector and sub-arterial road. He says that both
are very busy roads. He agrees that the construction of the toll road should increase the
traffic flow in the area around Johnson Road and Stapylton Road but, on the other hand, said
that an increase in traffic flow could be expected as the surrounding areas develop. The
greater part of the evidence on this issue is speculative. Mr de Bruyn's opinions came from
his deliberations on what might happen. There is no evidence of traffic counts on these roads
before and after the construction of the toll road. There is no evidence from a traffic
-- 13 of 17 --
13
engineer which the valuers could translate into their field of expertise. It is agreed that both
Johnson Road and Stapylton Road are at present very busy roads. It is reasonable to expect
that with development of the surrounding areas traffic would increase. Any increase above
that which may be directly related to the construction of the road on the subject land was not
quantified and in the absence of it being quantified in some reasonable form, no conclusions
can be drawn. This brings me back to the primary argument regarding depreciation. All
three valuers sought support in their opinions on depreciation by reference to sales of lots on
a freeway and off a freeway. Such exercises were relied on by Mr Grennan not only for the
purpose of obtaining some idea of the rate of depreciation but also of measuring the distance
over which the depreciation would flow. In the area of Browns Plains from sales of
residential lots situated on the toll road and those a few lots away, he came to the conclusion
that depreciation dissipated within a couple of hundred metres. He then applied this
reasoning to the subject land with the result that lots with homesites several hundred metres
away from the toll road were not depreciated by either visual or noise pollution. I am
influenced in this respect by the evidence of Mr de Bruyn which is to the effect that it is in
some way fallacious to compare depreciation of standard size residential lots on and off a toll
road with 4-hectare rural residential lots notwithstanding that logical homesites could be a
few hundred metres from the road. I have considered the evidence of the pricing of the lots
on the plan of the land after the resumption and set out my conclusions below. In doing so I
might say that I have leaned in favour of the relativity adopted by Mr Grennan and Mr de
Bruyn rather than the more general approach taken by Mr Jorgensen. Where individual
prices are not listed, the gross selling price is that estimated by Mr Grennan.
Wadeville Street Lots 1 - 9 $577,500
Stapylton Road Lots 10-12 $242,500
Cul-de-sac road -
-- 14 of 17 --
14
north Lots 13-15 $215,000
Lot 16 $ 60,000
Lot 17 $ 48,000
Lot 18 $ 55,000
Lot 19 $ 61,000
Lot 20 $ 64,000
Lot 21 $ 67,500
Lot 22 $ 67,500
Lot 23 $ 70,000 $493,000
Stapylton Road Lot 24 $60,000
Lots 25-31 $502,500
Johnson Road Lots 32-36 $322,500
Cul-de-sac road Lots 37-39 $194,000
Lot 40 $ 60,000
Lot 41 $ 52,500
Lot 42 $ 48,000
Lot 43 $ 48,000
Lot 44 $ 45,000
Lot 45 $ 50,000
Lot 46 $ 60,000 $363,500
Lots 47-53 $509,500
The gross realisation therefore becomes $3,480,000. This is $74,000 below Mr Grennan's
gross realisation of $3,554,000. His net value was $918964 or $4064 per hectare. By
comparison his exercises providing reticulated water to Lots 1 - 12 only yielded land values
with the residence at $1,305,312 before the resumption (about $5300 per hectare) and
$1,197,212 after the resumption (about $5300 per hectare).
He followed these exercises with an estimate of compensation based on a
-- 15 of 17 --
15
"piecemeal" valuation. The calculations were as follows:
Land taken 15.41 hectares
adopt englobo $ 5,500 per hectare = 84 755
Injurious affection, road noise,
1,050 metres long say 10% to
depth 200 metres each side i.e.
10% 1050 x 200 x 2 i.e. 42 hectares
@ 550 per hectare = 23 100
Severance - 300 metre extension over
corridor in Stapylton Street
Electricity 30% of 6000 = 1800
Telecom = 400 2 200
These items of severance
are not supported by the
subdivision exercise but
area practical allowance
for continued use as one
parcel
110 055
Mr de Bruyn did not attempt a similar exercise. Mr Jorgensen had some
regard to the englobo value of the land. His estimate of the value of the parcel before the
resumption is about $5,600 per hectare. Based on his hypothetical exercise, the value of the
area after the resumption is about $4,500 per hectare. If the exercise is pursued, it seems to
me that it would not be unreasonable to find that any injurious affection from the use of the
resumed land would be completely dissipated within 300 metres and that a factor of 15%
could be applied and so spread the depreciation over the whole of the lots within this ambit
notwithstanding that the impact on value would vary. The last item (severance) was not
covered in any detail. Mr Grennan admitted that in the subdivision of the land after the
resumption, development costs would be dearer. With 58 watered lots before the
resumption, development costs excluding interest are $768,900 or $13,257 per lot. With 54
watered lots after the resumption, development costs excluding interest are $760,100 or
$14,076 per lot. With reticulated water in part the costs are $7924 per lot before the
-- 16 of 17 --
16
resumption and $8237 per lot after the resumption. The differences need to be reflected in
the exercise. The exercise could take this form -
Land 15.41 ha @ $5,500 $84,755
Injurious Affection 63 ha @ $825 $51,975
Severance - higher development costs (say) $45,000
$181,730
At $5,500 per hectare, the parcel before the resumption is worth $1,328,250.
If the land is reduced in value by $181,730, the value of the parcel after the resumption
becomes $1,146,520 or $5,070 per hectare. With the hypothetical exercises and this
exercise, there is ever present an element of error which any prudent purchaser would
resolve in his favour. In my opinion, the sensible conclusion which would be reached by the
hypothetical prudent purchaser and vendor is that the land is worth $5,500 per hectare
before the resumption and $5,000 per hectare after the resumption.
Compensation for the taking of the land will therefore be determined in round
figures in the sum of $198,000.
Disturbance is agreed in the sum of $9,550.
Accordingly, compensation under all heads is determined at $207,550.
Advances against compensation were made in the sums of $40,000 on 9th January, 1989,
and $36,500 on 31st January, 1989. A stay of interest was ordered by the Court during the
period of an adjournment between 5th March, 1990, and 29th July, 1990. Interest is
therefore ordered to be paid on the sum of $207,550 at the rate of 13 percentum per annum
from and including the date of resumption up to and including 9th January, 1989; thence on
the sum of $167,550 up to and including 29th January, 1989; and thereafter on the sum of
$131,050 up to and including the day immediately preceding the date compensation is paid
save that interest shall not be paid on the sum during the period of the adjournment.
Acting President of the Land Court
-- 17 of 17 --
Official source: https://www.sclqld.org.au/caselaw/QLC/1990/031