Built Qld Pty Limited v Pro-Invest Australian Hospitality Opportunity (ST) Pty Limited as Trustee for the Pro-Invest Australian Hospitality Opportunity (BRF Springhill) Trust [2019] QSC 108
SUPREME COURT OF QUEENSLAND
CITATION: Built Qld Pty Limited v Pro-Invest Australian Hospitality
Opportunity (ST) Pty Limited as Trustee for the Pro-Invest
Australian Hospitality Opportunity (BRF Springhill) Trust
[2019] QSC 108
PARTIES: BUILT QLD PTY LIMITED
ACN 108 064 099
(applicant)
v
PRO-INVEST AUSTRALIAN HOSPITALITY
OPPORTUNITY (ST) PTY LIMITED AS TRUSTEE
FOR THE PRO-INVEST AUSTRALIAN HOSPITALITY
OPPORTUNITY (BRF SPRING HILL) TRUST
ACN 163 479 221
(respondent)
FILE NO: BS No 5426 of 2017
DIVISION: Trial Division
PROCEEDING: Interlocutory Application
ORIGINATING
COURT:
Supreme Court at Brisbane
DELIVERED ON: 9 May 2019
DELIVERED AT: Brisbane
HEARING DATE: 11, 12, 15 and 17 April 2019
JUDGE: Martin J
ORDER: The application is dismissed.
CATCHWORDS: PROCEDURE – CIVIL PROCEEDINGS IN STATE AND
TERRITORY COURTS – MOTIONS, INTERLOCUTORY
APPLICATIONS AND OTHER PRE-TRIAL MATTERS –
where the applicant is the contractor and the respondent is the
principal in a design and construct contract – where the
applicant arranged for a performance bond to be issued as part
of the requirements of the contract – where the respondent
alleges that the applicant has failed to rectify construction
defects exceeding the value of the bond – where the respondent
demanded payment of the bond – whether injunctive relief is
available to restrain the respondent from calling on, or
otherwise having recourse to, the bond – whether there is a
serious question to be tried and the balance of convenience
favours the granting of an injunction
-- 1 of 8 --
2
Queensland Building and Construction Commission Act 1991,
s 67J
Barclay Mowlem Construction Ltd v Simon Engineering (Aust)
Pty Ltd (1991) 23 NSWLR 451, cited
Castlemaine Tooheys Ltd v South Australia (1986) 161 CLR
148, cited
CBP Contractors Pty Ltd v JKC Australia LNG Pty Ltd (No 2)
[2017] WASCA 123, cited
Clough Engineering Ltd v Oil and Natural Gas Corporation
Ltd (2008) 249 ALR 458, cited
Queensland University of Technology v Project Constructions
(Aust) Pty Ltd [2003] 1 Qd R 259, cited
RCR O’Donnell Griffin Pty Ltd v Forge Group Power Pty Ltd
[2016] QCA 214, cited
Saipem Australia Pty Ltd v GLNG Operations Pty Ltd [2014]
QSC 310, cited
Saipem Australia Pty Ltd v GLNG Operations Pty Ltd [2017]
QSC 294, cited
Sugar Australia Pty Ltd v Lend Lease Services Pty Ltd (2015)
31 BCL 407, cited
COUNSEL: M Steele and B Reading for the applicant
S Webster for the respondent
SOLICITORS: Clayton Utz for the applicant
Thomson Geer for the respondent
[1] Built (the applicant) is the contractor and Pro-Invest (the respondent) is the principal in a
design and construct contract for the development of a Holiday Inn Express hotel in
Spring Hill.
[2] As part of the contractual requirements, Built arranged for Insurance Australia Limited
to issue a performance bond – referred to as the security sum in the contract.
[3] The works under the contract achieved practical completion in March 2017. Since then,
Built has commenced proceedings against Pro-Invest for money payable under the
contract or for damages as a result of variation and delay claims. Pro-Invest has
counterclaimed for, among other things, damages for Built’s failure to complete its defect
rectification obligation.
-- 2 of 8 --
3
[4] In February 2018, the contract Superintendent issued a direction to Built to rectify defects.
Built did not do that. Pro-Invest commissioned a report which concluded that the cost of
rectification exceeds the value of the security.
[5] On 11 April 2019, Pro-Invest:
(a) delivered a copy of a notice under s 67J of the Queensland Building and
Construction Commission Act 1991 to Built’s registered office, and
(b) delivered a demand to IAL for immediate payment of the security sum.
[6] IAL became aware of these proceedings and has not yet responded to the call made by
Pro-Invest.
[7] Built seeks an interlocutory injunction to prevent Pro-Invest from making a call on, or
otherwise having recourse to, the performance bond.
The test
[8] Built must demonstrate that there is a serious question to be tried and that the balance of
convenience favours the granting of an injunction.
Is there a serious question?
[9] Built identifies the serious question as being whether Pro-Invest was entitled to make the
call on the performance bond having regard to two matters:
(a) whether Pro-Invest complied with s 67J of the Queensland Building and
Construction Commission Act 1991, and
(b) whether Pro-Invest complied with the contractual requirements for calling on the
security.
Did Pro-Invest comply with s 67J of the Queensland Building and Construction
Commission Act 1991?
[10] Section 67J provides:
“(1) The contracting party for a building contract may use a security or
retention amount, in whole or in part, to obtain an amount owed under the
contract, only if the contracting party has given notice in writing to the
contracted party advising of the proposed use and of the amount owed.
(2) The notice must be given within 28 days after the contracting party
becomes aware, or ought reasonably to have become aware, of the contracting
party’s right to obtain the amount owed.
(3) If, because of subsections (1) and (2), the contracting party is stopped from
using a security or retention amount, the contracting party for the contract is
not stopped from recovering the amount owed in another way.
-- 3 of 8 --
4
(4) This section does not apply if, under the contract—
(a) work has been taken out of the hands of the contracted party or the
contract has been terminated; or
(b) the security or retention amount is to be used to make a payment
into court to satisfy a notice of claim of charge under the Building
Industry Fairness (Security of Payment) Act 2017.
(5) In this section—
amount owed, under a building contract, means an amount that, under the
contract, is a debt due from the contracted party for the contract to the
contracting party for the contract because of circumstances associated with
the contracted party’s performance of the contract.
use of security or retention amount includes the act of converting securities
into cash where the securities are held as negotiable instruments.”
[11] Thus, Pro-Invest had to give appropriate notice to Built before it could call on the
performance bond.
[12] The call on the CGU was made at about 10am on 11 April 2019. According to Built,
notice of intention to make the call did not arrive at its offices until about 11:33am on the
same day. This is disputed by Pro-Invest.
[13] Where there is a conflict in the evidence, then regard is to be had to the nature and quality
of the evidence. Whether a serious question is shown to exist is determined by asking: if
the evidence remains as it is, is there a probability that at the trial of the action the question
will be decided in the applicant’s favour?1
[14] The evidence from Pro-Invest on this point was precise. A solicitor employed by
Thomson Geer (Pro-Invest’s solicitors) deposes to delivering a copy of the s 67J notice
at 9.48am on 11 April to a receptionist at Built’s office. He knows that was the time
because he checked the time on his mobile phone. On his return to his office he called –
at 10.13am – another solicitor and told him that the notice had been delivered. At 10.15am
he prepared a file note recording those matters. He sent that file note to the other solicitor
at 10.42am.
[15] There is no affidavit from the receptionist. There is an affidavit from an in-house lawyer
at Built that he was told by a receptionist that: she did not record the time she received
the notice, she placed it on Built’s treasurer’s desk, she sent an email to Built’s treasurer
telling him that at 11.43am, and that those events occurred within “approximately 10
minutes of the notice having been served.”
[16] The lack of contemporaneity that pervades the hearsay account for the applicant compares
unfavourably to the account which is supported by file notes and reference to specifically
checking the time. If the evidence were to remain as it is, it is more likely than not that
the issue would be decided in favour of Pro-Invest.
1 Castlemaine Tooheys Ltd v South Australia (1986) 161 CLR 148 at 153.
-- 4 of 8 --
5
[17] Pro-Invest also argued that, for a number of reasons, it was not obliged to serve a notice
under s 67J. In the light of my decision that there is no serious question about service, I
need not consider those issues.
Did Pro-Invest comply with the contractual requirements for calling on the
security?
[18] This argument requires a consideration of a number of clauses from the relevant contract.
Built contends that the necessary pre-conditions did not exist for Pro-Invest to validly call
on the performance bond. It also involves the more general question of the construction
of the contract so far as the clause inhibiting an application of this kind is concerned.
[19] The relevant clauses are:
“Security Provision
5.1 Provision
Security shall be provided in accordance with Item 14 or 15 prior to the
commencement of WUC and maintained during the term of the Contract. All
delivered security shall be transferred in escrow.
Provision of security by the Contractor is a precondition to payment pursuant
to the Contract.
5.2 Recourse
The Principal may have recourse to security and may convert into money
security that does not consist of money where an entitlement exists pursuant
to subclause 37.6.
5.6 No entitlement to injunction
Except as provided in subclause 5.2, the Contractor shall have no entitlement
as a consequence of the conversion of a security into money.
The Contractor acknowledges that:
(a) the Principal has a right to convert security which does not consist of
money into money in accordance with subclause 5.2;
(b) the Contractor has no entitlement to obtain an injunction preventing the
Principal from converting security which does not consist of money into
money.
35 Defects liability
35.1 …
If the rectification is not commenced or completed by the stated dates, the
Principal may have the rectification carried out by others but without
prejudice to any other rights and remedies the Principal may have. The cost
thereby incurred shall be certified by the Superintendent as moneys due and
payable to the Principal.
37.6 Other moneys due
-- 5 of 8 --
6
Without limiting the Principal’s rights under any provision in the Contract,
the Principal may deduct from any moneys due to the Contractor pursuant to
the Contract, any amount which is payable by the Contractor to the Principal,
whether or not the Principal’s right to payment arises by way of damages
(whether liquidated or unliquidated), debt, restitution or otherwise.
If the moneys payable to the Contractor are insufficient to discharge the
liability of the Contractor to pay such sum to the Principal, the Principal may
have recourse to the security or any retention moneys. Nothing in this
subclause 37.6 shall affect the right of the Principal to recover from the
Contractor the whole of any such moneys or any balance that remains owing.”
[20] The gist of the argument for Built is that Pro-Invest was not entitled to call on the security
in this case because there is no amount presently payable to Pro-Invest, and there is no
basis to contend that any amount payable to Pro-Invest exceeds the amount payable to
Built. Built contends that cl 37.6 requires that an amount be “payable” by Built to Pro-
Invest and that under cl 35.1 an amount is only “payable” in respect of the rectification
of defects when the Superintendent has first “certified” that monies are due and payable.
[21] Pro-Invest contends that there are three reasons for rejecting the argument advanced by
Built:
(a) First, cl 35.1 expressly provides that the remedy available to Pro-Invest is “without
prejudice to any other rights and remedies”. Thus, Built has available to it a remedy
such as the pursuit of damages for breach of contract.
(b) Secondly, cl 37.6 expressly recognises a right to have resort to the security in
respect of payments for damages.
(c) Thirdly, the word “payable” does not require that Pro-Invest establish that Built is
obliged to pay damages. It is sufficient that a bona fide entitlement be asserted.
[22] The drafting of the clauses relevant to this application is not a fine example of that art.
Clause 5.6 commences: “Except as provided in subclause 5.2, the Contractor shall have
no entitlement as a consequence of the conversion of a security into money.” But, cl 5.2
does not afford the Contractor any entitlement – it provides the Principal with the ability
to have recourse to the security in certain circumstances. In any event, cl 5.2 only relates
to circumstances after the conversion of a security into money, not the circumstances
before such a conversion.
[23] Clause 5.2 defines when the Principal may have recourse to the security, namely, where
an entitlement exists pursuant to cl 37.6. The entitlements provided for in that clause are:
(a) The Principal may deduct, from any money due to the Contractor, any amount
which is payable by the Contractor to the Principal.
(b) If the monies payable to the Contractor are insufficient to discharge the liability of
the Contractor to pay that sum, then the Principal may have recourse to the security.
[24] A large part of the debate between the parties was about the meaning of the word
“payable”. Built argued that the position of Pro-Invest was a mere assertion as to the
amounts owing and so was insufficient to found an entitlement to call on the security. As
-- 6 of 8 --
7
there had been no certification by the Superintendent of any amount owing, there could
not be any “presently owing amount” under the contract. Built relied upon decisions
which support that stance including Queensland University of Technology v Project
Constructions (Aust) Pty Ltd2 and RCR O’Donnell Griffin Pty Ltd v Forge Group Power
Pty Ltd.3
[25] Pro-Invest relied upon a decision of the Court of Appeal of Western Australia in CBP
Contractors Pty Ltd v JKC Australia LNG Pty Ltd (No 2).4 In that case a similar clause
was considered. It permitted a party to have recourse to security “at any time in order to
recover any amounts that are payable … on demand.” The party seeking the injunction
contended that the word “payable” meant that the principal “may only make a demand
upon the bank guarantees where it is objectively established that the amount demanded is
due and payable.” The argument was rejected on the basis that the waiver of the right to
seek an injunction preventing recourse to the security makes “no sense and serves no
purpose” if the word “payable” requires an uncontested or uncontestable right to be paid.
The Court of Appeal concluded that the use of the word “payable” in that context did “not
signify only an admitted sum or a sum objectively or authoritatively established …”5
[26] I do not accept that the decision in CBP Contractors assists Pro-Invest. As with so many
of these clauses, minor changes can make a major difference. In cl 37.6 the reference to
“any amount which is payable by the contractor to the Principal” appears to then be
comprehended by the reference to “the Principal’s right to payment”. The reference to a
“right to payment” allows for an argument that the “amount which is payable” is
something which is more than a mere assertion of money owing. It is sufficient to raise a
serious question about the proper construction of the relevant agreement.
Balance of convenience
[27] Clause 5.6 creates a “substantial hurdle [for Built] to overcome when dealing with the
balance of convenience.”6 It has been said that the existence of such a clause “provides a
very strong argument that [a party] has given up any right to injunctive relief on that
ground, in a bargain which the Court should respect.”7
[28] In Clough Engineering Ltd v Oil and Natural Gas Corporation Ltd8 a Full Court of the
Federal Court of Australia considered issues of construction and the importance of
commercial practice in dealing with these types of clauses. They noted9 that a “court
ought not too readily favour a construction which is inconsistent with an agreed allocation
of risk as to who is to be out of pocket pending resolution of the dispute about breach.”
The court went on to say:
2 [2003] 1 Qd R 259.
3 [2016] QCA 214.
4 [2017] WASCA 123.
5 At [114].
6 Saipem Australia Pty Ltd v GLNG Operations Pty Ltd [2014] QSC 310 at [69].
7 Saipem Australia Pty Ltd v GLNG Operations Pty Ltd [2017] QSC 294 at [39].
8 (2008) 249 ALR 458.
9 At [82].
-- 7 of 8 --
8
“[83] It follows that clear words will be required to support a construction
which inhibits a beneficiary from calling on a performance guarantee where
a breach is alleged in good faith, that is, non-fraudulently.”
[29] Built submits that it will suffer significant reputational and other damage for which
damages will not be an adequate remedy if the call made by Pro-Invest is not restrained.
Evidence was led of the financial circumstances of Built and the manner in which it
conducts its business through the use of performance bonds which a financier can decline
to provide for any reason. Further, enquiries as to the financial status of Built would
necessarily disclose the fact that one of its bonds had been “cashed”. The damage that can
be caused to a builder’s reputation has been recognised in other decisions. See, for
example, Barclay Mowlem Construction Ltd v Simon Engineering (Aust) Pty Ltd.10
[30] The purpose of the performance bond in this contract falls into that category referred to
by Osborn and Ferguson JJA in Sugar Australia Pty Ltd v Lend Lease Services Pty Ltd11
where they said:
“[21] If a provision in a building contract requiring a performance bond is
intended to operate as a risk allocation device pending the final determination
of the dispute between the parties then that intention must be fundamental to
a consideration of the justice of an application made to restrain recourse to
such a bond pending final determination of the dispute.”
[31] That consideration was endorsed by McMurdo JA in RCR O’Donnell Griffin Pty Ltd
where his Honour said that a court hearing an interlocutory injunction must be: “alert to
the risk that if the Principal was to be enjoined from having recourse to the security,
pending resolution of the dispute as to whether it was entitled to do so, the benefit to the
Principal of the security could be substantially diminished.”12
[32] This case differs from many of those to which I was referred because the call has already
been made. What is sought is an order which would, in effect, prevent Pro-Invest from
receiving the money the subject of the bond. There is, of course, a way in which Built
might protect itself even though the call has been made and that is by paying the amount
the subject of the call to Pro-Invest and then to take such action as it may be advised in
the primary proceeding.
[33] I am not satisfied that the balance of convenience favours the making of the order sought
by Built, particularly because of the nature of the restraint to which Built subjected itself
by the terms of the contract. Built agreed to the allocation of risk which cl 5.6 entails and
should not be allowed to contradict that in these circumstances.
Conclusion
[34] The application is dismissed.
10 (1991) 23 NSWLR 451.
11 (2015) 31 BCL 407.
12 At [97].
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2019/108