Bluepoint Property Pty Ltd & Anor v Zuri Properties Pty Ltd [2018] QSC 86
SUPREME COURT OF QUEENSLAND
CITATION: Bluepoint Property Pty Ltd & Anor v Zuri Properties Pty Ltd
[2018] QSC 86
PARTIES: BLUEPOINT PROPERTY PTY LTD ACN 160 455 578
(first plaintiff/first applicant)
BLUEPOINT HENDRA PTY LTD ACN 622 756 389 AS
TRUSTEE FOR THE WHITCOMBE HENDRA TRUST,
DORE HENDRA TRUST AND LINDSAY HENDRA
TRUST
(second plaintiff/second applicant)
v
ZURI PROPERTIES PTY LTD ACN 615 214 910 AS
TRUSTEE FOR THE HENDRA ARTERIAL UNIT
TRUST
(defendant/respondent)
FILE NO/S: No 12390 of 2017
DIVISION: Trial Division
PROCEEDING: Application
DELIVERED ON: 19 April 2018, ex tempore
DELIVERED AT: Brisbane
HEARING DATE: 6 April 2018
JUDGE: Davis J
ORDER: Apart from the orders made on 6 April 2018, application
dismissed.
CATCHWORDS: EQUITY – EQUITABLE REMEDIES – INJUNCTIONS –
INTERLOCUTORY INJUNCTIONS – INJUNCTIONS TO
PRESERVE STATUS QUO OR PROPERTY PENDING
DETERMINATION OF RIGHTS – OTHER CASES – where
the plaintiffs apply for interlocutory relief to preserve status
quo – whether the injunction should be ordered
EQUITY – EQUITABLE REMEDIES – INJUNCTIONS –
INTERLOCUTORY INJUNCTIONS – RELEVANT
CONSIDERATIONS – BALANCE OF CONVENIENCE
GENERALLY – where the plaintiffs apply for interlocutory
relief to preserve status quo
EQUITY – EQUITABLE REMEDIES – INJUNCTIONS –
INTERLOCUTORY INJUNCTIONS – SERIOUS
QUESTION TO BE TRIED – GENERALLY – where the
plaintiffs’ application for interlocutory relief is opposed –
-- 1 of 21 --
2
whether there is a serious question to be tried in the substantive
matter
Australian Broadcasting Corporation v O’Neill (2006) 227
CLR 57, applied
Koppamurra Wines Pty Ltd v Mildara Blass Ltd (1998) 41
IPR 154, distinguished
Rapid Metal Developments (Australia) Proprietary Limited v
Anderson Formrite Proprietary Limited & Anor [2005]
WASC 255, cited
COUNSEL: D Cooper QC and C L Francis for the plaintiffs
J W Peden QC and L Sheptooha for the defendant and
Boardwalk Marine Investments Pty Ltd
SOLICITORS: Steindls Lawyers for the plaintiffs
Nicholsons for the defendant and Boardwalk Marine
Investments Pty Ltd
[1] HIS HONOUR: On 6 April 2018 I heard the Plaintiffs’ application. Upon the giving
of the usual undertakings as to damages by the Plaintiffs and various undertakings by the
Defendant designed to maintain the status quo for a short period, I made an order joining
Boardwalk Marine Investments Proprietary Limited as a Defendant to the proceedings.
Such a course was not opposed by the Defendant. I further gave leave to the Plaintiffs to
file and serve further material on the issue of the value of the Plaintiffs’ undertaking as to
damages. I reserved the costs of the application and reserved judgment. There were
subsequent emails with my Associate, and arrangements were made for further
submissions to be filed on the question of the Plaintiffs’ undertakings as to damages.
[2] Pursuant to the leave given, an affidavit of the Plaintiffs’ solicitor, Mr Matthew John
Jones, was sworn and filed. Both parties delivered submissions in relation to that further
evidence.
[3] The dispute arises out of an agreement between the First Plaintiff and the Defendant
concerning land at Hendra in Brisbane’s inner northern suburbs. The Defendant owns
the property, which is Lot 20 on Survey Plan 236557. The Defendant proposes to
subdivide the land and in the process create Lot 1 as an individual lot, which I will refer
to as Proposed Lot 1. The dimensions and shape of Proposed Lot 1 have changed as
different proposals for the development of the parcel have been considered. It is Proposed
Lot 1 that is the subject of the Plaintiffs’ claim.
-- 2 of 21 --
3
[4] The further amended statement of claim alleges various pre-contractual events, including
the making of an offer by the First Plaintiff in a document entitled “Acquisition Proposal”,
the acceptance of that proposal and the sending of an email by the Defendant’s solicitors
to the Plaintiffs’ solicitors. The agreement, the subject of the dispute, is a deed entered
into on 5 January 2017, which I will call the “Option Deed”.
[5] The Plaintiffs allege that the Acquisition Proposal and the email mentioned above formed
part of the contract with, of course, the Option Deed. Perhaps unsurprisingly, the
Defendant, while admitting that it entered into the Option Deed denies that either the
Acquisition Proposal or the email have contractual force, and says that the Option Deed
is the entire agreement between the parties. That dispute need not be resolved in order to
determine the present applications.
[6] The Option Deed provided to the First Plaintiff an option to purchase Proposed Lot 1
either by itself or by its nominee. In due course, the Second Plaintiff, as nominee of the
First Plaintiff, purported to exercise the option given in favour of the First Plaintiff. If
that was a valid exercise of the option, then the Defendant as seller and the Second
Plaintiff as buyer would execute a form of contract attached to the Option Deed;. that
contract is referred to as the Settlement Contract. For the sake of convenience, although
it is not strictly accurate to do so, I do not intend to distinguish between the First Plaintiff
and the Second Plaintiff and where either the First Plaintiff or the Second Plaintiff has
done something or has some right I will simply refer to the Plaintiffs.
[7] The parties intended to develop the site as a service station then to be leased to the
petroleum company, Caltex. The Plaintiffs submit that they have subsisting rights under
the Option Deed. The Defendant submits that the Plaintiffs’ right under the Option Deed
was, critically, to exercise the option to purchase, and that option must have been, by the
terms of the deed, exercised by 5 pm on 17 October 2017. The Defendant says that the
Plaintiffs did not do so.
[8] It seems to be common ground that over the time that both the Plaintiffs and the Defendant
considered themselves bound by the Option Deed, they worked towards the development
of Proposed Lot 1 as a service station site for Caltex.
-- 3 of 21 --
4
[9] The Plaintiffs, by their application, seek orders in very specific terms, but which can be
broadly described as follows:
1. Interlocutory injunctions preventing the Defendant, until trial, from creating or
parting with any interest in Proposed Lot 1; and ancillary to that relief, to deliver to
the Plaintiffs documents relevant to the creation of any interest. I will refer to this
as the first category of relief.
2. Interlocutory injunctions preventing the Defendant from developing Proposed
Lot 1, including restraining the Defendant from having further communication with
proposed tenants for Proposed Lot 1, including Caltex and 7-Eleven. I will refer to
this as the second category of relief.
3. Orders requiring the delivery up of documents, produced by the Plaintiffs through
their consultants and others, relevant to the proposed development of the site as a
service station. These are called in the material “the relevant documents”. The
alleged basis for this claim for relief is that the relevant documents are confidential
to the Plaintiffs and were created or delivered to the Defendant only for a very
specific purpose, which can be described sufficiently as their joint development of
the site. The application seeks final relief in this respect by way of an order that the
documents be delivered up to the Plaintiffs or, alternatively, interlocutory relief
restraining the use of the relevant documents and information until trial. This I will
call the third category of relief.
4. An order joining Boardwalk Marine Investments Proprietary Limited as a
Defendant in the proceedings. It is alleged that Boardwalk has acquired some
interest or will acquire some interest in Proposed Lot 1 from the Defendant, and is
proposing to have dealings with Caltex. As already mentioned, the joinder of
Boardwalk was not contentious by the time I heard the application on 6 April 2018,
and I have already made an order making Boardwalk a Defendant in the
proceedings. This, though, I will call the fourth category of relief.
5. Orders restraining Boardwalk in terms consistent with the injunction sought against
the Defendant, namely, not to develop Proposed Lot 1, not to acquire an interest in
-- 4 of 21 --
5
Proposed Lot 1, not to use the relevant documents, delivery up of the relevant
documents, not to use confidential information, not to communicate with potential
tenants including Caltex and 7-Eleven. I’ll refer to this as the fifth category of
relief. Mr Peden QC with Mr Sheptooha appeared for the Defendant and for
Boardwalk and were content for me to hear the applicant against Boardwalk, even
though Boardwalk was not strictly a party until I made an order joining it.
[10] The first category of relief, the second category of relief and the fifth category of relief
all, one way or another, seek to prevent the Defendant and Boardwalk from dealing with
Proposed Lot 1. I will deal with the issues raised by those three categories of relief
together.
[11] As these categories of relief are all interlocutory, the guiding principles are as stated in
Australian Broadcasting Corporation v O’Neill (2006) 227 CLR 57. In that case, Chief
Justice Gleeson and Justice Crennan at paragraph 19 said:
“…in all applications for an interlocutory injunction, a court will ask whether
the plaintiff has shown that there is a serious question to be tried as to the
plaintiff's entitlement to relief, has shown that the plaintiff is likely to suffer
injury for which damages will not be an adequate remedy, and has shown that
the balance of convenience favours the granting of an injunction. These are
the organising principles, to be applied having regard to the nature and
circumstances of the case, under which issues of justice and convenience are
addressed. We agree with the explanation of these organising principles in
the reasons of Gummow and Hayne JJ, and their reiteration that the doctrine
of the Court established in Beecham Group Ltd v Bristol Laboratories Pty Ltd
[(1968) 118 CLR 618] should be followed.”
[12] In the same case, Justices Gummow and Hayne, at paragraph 65 said as follows:
“The relevant principles in Australia are those explained in Beecham Group
Ltd v Bristol Laboratories Pty Ltd. This Court (Kitto, Taylor, Menzies and
Owen JJ) said that on such applications the court addresses itself to two main
inquiries and continued:
“The first is whether the plaintiff has made out a prima facie case,
in the sense that if the evidence remains as it is there is a
probability that at the trial of the action the plaintiff will be held
entitled to relief ... The second inquiry is ... whether the
inconvenience or injury which the plaintiff would be likely to
suffer if an injunction were refused outweighs or is outweighed
by the injury which the defendant would suffer if an injunction
were granted.”
-- 5 of 21 --
6
By using the phrase "prima facie case", their Honours did not mean that the
plaintiff must show that it is more probable than not that at trial the plaintiff
will succeed; it is sufficient that the plaintiff show a sufficient likelihood of
success to justify in the circumstances the preservation of the status quo
pending the trial. That this was the sense in which the Court was referring to
the notion of a prima facie case is apparent from an observation to that effect
made by Kitto J in the course of argument. With reference to the first inquiry,
the Court continued, in a statement of central importance for this appeal:
“How strong the probability needs to be depends, no doubt, upon
the nature of the rights [the plaintiff] asserts and the practical
consequences likely to flow from the order he seeks.””
[13] So, importantly, the Plaintiffs must show:
1. A prima facie case, which might also be described as a serious question to be tried;
2. That the balance of convenience favours the giving of relief; and
3. Importantly, it is not the law that an interlocutory injunction is only given where
the Plaintiffs’ success at trial is considered to be more than likely than not. The
Plaintiffs’ case must be sufficiently strong to justify the preservation of the status
quo until final rights can be determined: Australian Broadcasting Corporation v
O’Neill at paragraph 65.
[14] I will turn now to whether the Plaintiffs have shown a serious question to be tried in
relation to the first, second and fifth categories of relief as I have defined them. In
essence, that boils down to one question. Have the Plaintiffs demonstrated a prima facie
case that the Option Deed is still on foot? If so, they may have rights under it which
might lead to them securing Proposed Lot 1 for their benefit. If not, they simply have no
claim to the land.
[15] The Option Deed, as already observed, was executed by the Defendant as the seller and
the First Plaintiff as the buyer. The Option Deed creates various rights. In particular,
there is both a call option and a put option. By the call option, the Plaintiffs as buyer may
elect to enter into a contract for the purchase by, in this case, the Second Plaintiff as
nominee of the First Plaintiff of Proposed Lot 1. By the put option, the Defendant has a
right to elect to enter into a contract to the sell the property to the Plaintiffs.
-- 6 of 21 --
7
[16] The Option Deed was made conditional on the Plaintiffs performing due diligence.
Clause 2 of the option deed provides as follows:
“2 Conditions Precedent
2.1 Due Diligence
(a) This deed is subject to and conditional on the Buyer being
satisfied in its absolute discretion with its Due Diligence
Investigations on or before the Due Diligence Date.
(b) On or before 5pm on the Due Diligence Date, the Buyer
must by notice in writing to the Seller advise the Seller
whether the Buyer:
(1) is satisfied with its Due Diligence
Investigations;
(2) is not satisfied with its Due Diligence
Investigations; or
(3) waives the benefit of this clause 2.1.
(c) If the Buyer gives a notice to the Seller pursuant to clauses
2.1(b)(1) or (3), then this clause 2.1 will be deemed to be
satisfied.
(d) If the Buyer:
(1) gives a notice to the Seller pursuant too clause
2.1(b)(2); or
(2) does not give a notice pursuant to clause 2.1(b),
by 5pm on the Due Diligence Date, then this clause
2.1 will be deemed to be not satisfied and this deed
will be deemed to be terminated from 5pm on the
earlier of:
A. the date the Buyer gives a notice to the
Seller pursuant to clause 2.1(b)(2); and
B. the Due Diligence Date.
(e) This clause 2.1 is for the benefit of the Buyer and only the
Buyer may waive it.
(f) For the purpose of clarity, if the Buyer gives notice that it
is satisfied with its Due Diligence Investigations then both
the Initial Security Deposit and the Second Security Deposit
will be released to the Seller.
2.2 Termination of this deed
If this deed is terminated under clause 2.1(d) then:
-- 7 of 21 --
8
(a) no party shall have any other Claim against another party
arising under or in respect of this deedl and
(b) each party retains the rights it has against the other in
respect of any:
(1) breach of this deed occurring before
termination; or
(2) obligations otherwise agreed under this deed to
remain in full force and effect after termination
of this deed.
(c) the Seller will immediately consent to the Stakeholder
refunding the Initial Security Deposit and Second Security
Deposit to the Buyer without deduction.
2.3 Instrument of Easement
(a) The Seller will prepare the Instrument of Easement and
submit a draft to the Buyer within forty five (45) days from
the date of this deed.
(b) The Buyer, acting reasonably, will have fourteen (14) days
to make any requests for amendments to that instrument.
(c) For the avoidance of doubt the agreed terms of the
Instrument of Easement will form part of the Due Diligence
Investigations.”
[17] The term “Due Diligence Date” is defined as “120 days from 22 December 2016”.
[18] In essence, clause 2 provides that the Option Deed is conditional upon the Plaintiffs
performing due diligence and advising of satisfaction of due diligence by the due
diligence date, failing which the Option Deed is at an end.
[19] Clause 4 provides that the seller, namely, the Defendant, must prepare and lodge a
development application. The term “development application” is defined as:
“Subdivision Application required to be lodged by the seller with the local
authority to create a separate Certificate of Title for the land.”
[20] The “land” is what I have called Proposed Lot 1. Clause 4 is as follows:
“4 Development Approval
(a) The Seller will at its own cost prepare and lodge the
Development Application and the Seller will use reasonable
endeavours to have the Development Application
processed and approved.
-- 8 of 21 --
9
(b) If the Seller gives a notice to the Buyer that the
Development Approval has taken effect pursuant to SPA
then the Buyer will pay the Second Security Deposit within
two (2) business days receiving of the notice referred to in
this clause.
(c) In the event that the Seller has acted diligently and due to
Local Authority delays beyond the control of the Seller, the
Development Approval has not issued and taken effect
pursuant to SPA by the Development Approval Date then
the Buyer may elect to extend that Development Approval
Date by a further period of up to three (3) months for the
Seller to obtain a satisfactory Development Approval or
terminate this Deed by giving written notice to the Seller in
which event the provisions of clauses 2.2(a) and 2.2(B)
apply.
(d) In the event the Development Approval has not issued and
taken effect pursuant to SPA by the extended Development
Approval Date, the Buyer may terminate this Deed in which
event the provisions of clauses 2.2(a) and 2.2(b) apply.
(e) After the Development Approval has issued and the Plan
has been sealed by the Local Authority the Seller will at its
cost lodge the Plan for registration with the Department.
The Seller will notify the Buyer in writing immediately
after the Plan has been registered in the Department and will
provide a copy of the Registration Confirmation
Statement.”
[21] Clause 5 provides for the Call Option, that is, the option in favour of the Plaintiffs and
clause 6 provides for the Put option, that is, the option in favour of the Defendant. It is
the call option which is important here, so clause 5 provides as follows:
“5 Call Option
5.1 Grant of Call Option
(a) In consideration of the payment of the Call Option Fee by
the Buyer to the Seller, the Seller grants to the Buyer a Call
Option for the Buyer or a Nominee to purchase the
Property.
(b) The Seller acknowledges receipt of the Call Option Fee.
(c) The Call Option Fee is non-refundable.
5.2 Exercise of Call Option
The Buyer or Nominee may exercise the Call Option at any time
during the Call Option Period and may do so only by giving to
the Seller or to the Seller’s Solicitor the following items:
-- 9 of 21 --
10
(a) a Call Option Notice duly completed and executed by the
Buyer or Nominee;
(b) the Contract signed by:
(1) if the Buyer does not make a nomination under
clause 8.1, the Buyer only; or
(2) if the Buyer does make a nomination under
clause 8.1, the Nominee (in its capacity as
buyer);
(c) a cheque for the Third Security Deposit payable to the
Stakeholder;
(d) the documents referred to in this clause may be given by
way of delivery, facsimile or electronic mail in accordance
with the provisions of clause 14.1.”
[22] Importantly, the Call Option may be exercised as provided by clause 5.2 at any time
during the “Call Option period”. The term “Call Option period” is defined as:
“The Period:
(1) Beginning at 9am on the day immediately after the Conditions
Precedent Date; and
(2) Ending at 5pm on the day being five business days after the Conditions
Precedent Date.”
[23] The term “Conditions Precedent Date” is defined as “that date being two business days
after the later of the Due Diligence Date and/or the Development Approval Date”. I have
already referred to the definition of the Due Diligence Date. The Development Approval
Date is defined as “that day being nine months from the Due Diligence Date subject to
the provisions of clause 4 and being the date when the Development Approval has been
obtained”. I have already mentioned clause 4 which contains various provisions
concerning the relevant approval.
[24] There is dispute as to the date which is the Development Approval Date, and I will return
to that issue later.
[25] There is dispute between the parties as to whether the Plaintiffs have advised of due
diligence within time and in accordance with the terms of the Option Deed. It is not
necessary to form a view about that because of the way in which Mr Peden QC, who led
for the Defendant, approached the defence of the application.
-- 10 of 21 --
11
[26] Mr Peden QC submitted that any factual disputes concerning the Plaintiffs’ satisfaction
of the due diligence condition were irrelevant, because the Plaintiffs did not exercise the
option within time. He relied upon two authorities, being Duncan Properties v Hunter
[1991] 1 Qd R 101 and Justice Mullins’ decision in JV Tub Group Pty Ltd v Red Carpet
Real Estate Pty Ltd [2014] QSC 232.
[27] Mr Peden’s submission was that, based on the authority of those two cases, if an option
is not exercised within the option period, then the rights under the agreement are
exhausted, although there might, of course, be rights to damages for breaches of the option
agreement which were committed before the expiry of the option period. If Mr Peden
made good his submission to the extent that there was no real question to be tried about
its correctness, then the Defendant must succeed in its defence of the application, at least
as it relates to the categories of relief that are presently being considered. Mr Peden
sensibly conceded that if I did not accept his submission on this point about the exercise
of the option, then the Plaintiffs have shown a prima facie case and the only remaining
issue is the balance of convenience. Mr Peden’s concession was properly made.
[28] What the Defendant pleads on this issue and presses on the current application is that the
Call Option Period commenced on 11 October 2017 and expired on 17 October 2017.
That date is identified because the Due Diligence Date on the Plaintiffs’ case is fixed at
6 October, being the date that the First Plaintiff purported to notify the Defendant that it
was satisfied with its Due Diligence Investigations. The Conditions Precedent date is,
therefore, two business days later, so the Call Option Period starts the next day, i.e., 11
October, and expired on 17 October.
[29] However, the Call Option period, as has already been set out, depends upon the
Conditions Precedent Date. The Conditions Precedent Date is set by reference to the later
of the Due Diligence Date and the Development Approval Date. The Defendant says that
the later of the Due Diligence Date and the Development Approval Date is the
Development Approval Date, not the Due Diligence Date.
[30] The Plaintiff and Defendant differ in their submissions as to the Development Approval
Date. The Defendant says that the Development Approval Date is 4 August 2017. That
-- 11 of 21 --
12
is based on a development approval for a plan lodged for approval in July. However,
there were various plans prepared and, in particular, one in September 2017.
[31] The Plaintiffs say the Defendant had abandoned the July 2017 plan and proceeded on the
basis of the September plan. Therefore, the relevant Development Approval Date will be
calculated by reference to a development approval consistently with the September 2017
plan, which was obtained on 6 November. Consequently, so submit the plaintiffs,
exercise of the Call Option in November 2017 was within time.
[32] I can see some potential difficulties with the Plaintiffs’ submission in this respect;
however, the submission clearly raises legal issues as to the proper construction of the
Option Deed and raises factual issues concerning the preparation of the various plans, the
communications between the parties and, ultimately, a determination of what was the
Development Approval Date for the purposes of the Option Deed. It seems to me that a
prima facie case is shown that the option was exercised within time. Therefore, the
plaintiffs have made out a prima facie case to support the injunctive relief sought in
category 1, category 2 and category 5 relief.
[33] Turning, then, to the question of the balance of convenience; the Plaintiffs, on the
question of the balance of convenience, submit as follows:
(i) The Option Deed and the Settlement Contract, which is the agreement which will
be entered into if the Call Option has been properly exercised, are a set of
contractual obligations which are capable of being specifically performed. That
can be accepted.
(ii) If the injunction is not granted, then the Plaintiffs could lose their interest in
Proposed Lot 1, and damages is not an adequate remedy. Certainly, given that the
Defendant is intent on developing the land, the refusal of interlocutory relief will
undoubtedly lead to the practical loss of the Plaintiffs’ interests. As to damages not
being an adequate remedy, I shall return to that issue later.
(iii) The Defendant intends to register a plan created in March 2018. It is submitted by
the Plaintiffs that such registration would frustrate the completion of the Settlement
-- 12 of 21 --
13
Contract because Proposed Lot 1, as contemplated by that proposed contract, would
never come into existence. That is no doubt true but probably adds little to the
balance of convenience argument beyond consideration (ii) above.
(iv) If the Defendant and/or Boardwalk entered into agreements with Caltex or other
tenants, then third-party interests may frustrate the interests of the Plaintiffs. That
is no doubt true, but, again, it probably adds little to considerations (ii) and (iii)
above.
(v) The Plaintiffs say that there would be various consequential effects of the practical
termination of the deed such that damages would not adequately compensate the
Plaintiffs. As already indicated, I will say more about damages being an adequate
remedy later.
(vi) The Plaintiffs submit that they do not seek to restrain the Defendant from
developing the remainder of the Hendra site. The Plaintiffs are only concerned with
Proposed Lot 1. That is true to a point; however, as I will explain, the area and
boundaries of Proposed Lot 1 impact the configuration of other proposed
subdivided lots in the parcel. While the Plaintiffs are only interested in Proposed
Lot 1, it is an interest in Proposed Lot 1 as then configured. That configuration is
not consistent with the Defendant’s present plans, so an injunction would, in
practical terms, be likely to affect the development of the balance of the land.
(vii) The Plaintiffs submit that there is no real evidence of prejudice or hardship to the
Defendant if injunctions are granted. I do not accept that submission and will return
to that issue.
(viii) The Plaintiffs submit that any damage which the Defendant may suffer as a result
of dealings it has had since the dispute with the Plaintiffs began are troubles of their
own making, and the Plaintiffs particularly rely upon the judgment of Justice von
Doussa in Koppamurra Wines Pty Ltd v Mildara Blass Ltd (1998) 41 IPR 154. I
reject that submission but will return to it later.
-- 13 of 21 --
14
(ix) Any interlocutory injunction will be for a relatively short period because the matter
could be quickly made ready for trial. No doubt that is so to a point, and that is a
matter to take into account on the balance of convenience. However, damage would
still be suffered by the Defendant.
(x) By way of concluding submission, the Plaintiffs submit that the balance of
convenience favours the protection of the status quo.
[34] The Defendant, on the other hand, urges that the following factors be taken into account:
(i) The Plaintiffs have known of the Defendant’s position since 12 October 2017 and,
over the following months, was aware that the Defendant was taking steps to
develop the property but took no steps until recently to file an application for an
interlocutory injunction.
(ii) The Defendant has incurred costs in the further development of the site of about
$1,184,052.62.
(iii) It is no longer practical to convey Proposed Lot 1 in accordance with the Settlement
Contract, as a new development approval showing Proposed Lot 1 with different
boundaries has been lodged and is expected to be approved in June.
(iv) Third-party interests have since been created. These include:
(a) Negotiations (not concluded) with a proposed purchaser of Proposed Lot 2 on
the land. An offer of $4 million for Proposed Lot 2 has been received but is
dependent upon Lot 2 having access and easement arrangements in
accordance with the new proposed plan. An injunction would prevent the
Defendant from accepting the offer.
(b) The Council is developing a site adjoining the boundary of the land, and the
Defendant has agreed with the Council in principle to an access easement
over Council land, which satisfies the condition of the offer to purchase
Proposed Lot 2.
-- 14 of 21 --
15
(c) Heads of agreement have been entered into between Boardwalk and Caltex.
(d) The Defendant is a special purpose vehicle within the BMI Group. If the
Defendant was enjoined, then BMI would be in default of its lending
arrangements with the National Australia Bank, and the bank could either call
up loans or review its lending to the BMI Group.
(e) The financial impact of an injunction on the BMI Group’s business is
estimated to be at least $7 million and up to $9.4 million.
(f) The Defendant submits that damages are an adequate remedy for the
Plaintiffs.
[35] I have considered those submissions and the broad question of the balance of
convenience. Of significance is the acceptance or otherwise of the submission by the
Plaintiffs that damages would not be an adequate remedy. Often that is the case where
the subject matter of the dispute is land. Any parcel of land is, in some respects at least,
unique. On the other hand, there is no suggestion that the land here is to be used by the
Plaintiffs in their broader business. It is simply being developed for profit. It is not the
case, it seems, that the Defendant would not be able to meet any damages claim. It is
unlikely there will be difficulty in assessing damages.
[36] The loss to the Plaintiffs would be categorised as the loss of an opportunity to enter into
the contract contemplated by the Option Deed and then to secure and develop Proposed
Lot 1. It seems highly likely that the site will be developed and will be developed as a
service station, as was contemplated by the Plaintiffs. The resultant developed land could
then be easily valued. Therefore, I cannot see any obvious difficulties in the assessment
of the Plaintiffs’ damages if it comes to that.
[37] When the present application was filed, the Defendant, through its solicitors, raised
questions as to the value of the Plaintiffs’ undertaking as to damages. Mr Jones, the
Plaintiffs’ solicitor, swore an affidavit on 5 April 2018 whereby he exhibited a bank
statement of an account held in the name of the first plaintiff showing a credit balance of
$964,236.26. Of course, that, in itself, proves very little. Depending upon its financial
-- 15 of 21 --
16
commitments, the first Plaintiff may very well have that credit balance of almost $1
million, but may still be completely insolvent.
[38] Mr Jones swore another affidavit pursuant to the leave I gave on 6 April. To that affidavit,
Mr Jones exhibited a letter from Cordner Advisory, the controller of which is Mr Jason
Cordner, a certified practising accountant, and who is the accountant of the first Plaintiff
and its related companies.
[39] Mr Cordner’s letter attaches financial statements of the first plaintiff. Unfortunately, the
evidence of Mr Cordner, which comes in through Mr Jones, somewhat raises more
questions than it answers. The First Plaintiff is a property developer, and Mr Cordner
says the projects which it has completed have all been successful. Mr Cordner points to
the net assets of the company at $3,158,571. However, the assets of the First Plaintiff
largely comprise loans to related parties. Mr Cordner explains:
“Loans to related parties are either advances to various project entities to fund
their developments where these loans are repaid at completion or advances to
entities controlled by the directors Marcus Dore and Geordie Whitcombe
where those amounts are repayable at call.”
[40] Therefore, the business model seems to be a series of single project companies in a silo
structure. There is no suggestion of any real estate being held by the First Plaintiff or any
other commercially realisable assets such as shares or securities. There is no real evidence
as to the ability of the stand-alone companies to repay the loans.
[41] The Defendant has properly raised with the Plaintiffs the question of the worth of their
undertaking. While there is certainly cash at bank, there is no evidence to explain what
claims there are upon that cash and whether, in particular, the related entities may call
upon it.
[42] The Defendant very clearly raised with the Plaintiffs that it did not accept the value of
their undertaking as to damages. Despite that issue being raised, an undertaking on behalf
of the Second Plaintiff was only offered at the hearing before me. The only evidence at
the hearing before me on the topic was the evidence of Mr Jones exhibiting the bank
statement, and even after leave was given to the Plaintiffs to adduce further evidence on
-- 16 of 21 --
17
this issue, all that was produced was an affidavit of the Plaintiffs’ solicitors swearing
certain belief on information from the Plaintiffs’ financial adviser. In particular:
(i) There is no affidavit from the directors of the Plaintiffs verifying any of this.
Of course, if there had been such an affidavit, Mr Peden QC may have sought
to explore the position in cross-examination.
(ii) What evidence there is about the operation of the Plaintiffs’ group of
companies is scant.
(iii) Whilst there are broad statements in Mr Cordner’s letters about the
profitability of the group and its financial stability, there has been no attempt
to provide any real evidence which will give any faith that the intercompany
loans are sound.
(iv) While those standing behind the Plaintiffs urge me to accept the value of the
undertaking as sufficient protection for the Defendant, those persons are
apparently not prepared to stand behind the undertaking themselves by giving
their personal undertakings.
[43] I am not satisfied that the undertakings as to damages which are offered are of significant
value.
[44] There were objections taken to various parts of the Defendant’s material, which was relied
upon to prove the likely damage caused by any injunction. This is how the Defendant
seeks to establish a potential loss of between 7 million and 9 million dollars. I am not
prepared to find, even on an interlocutory basis, potential losses of that extent.
[45] It is not necessary to determine the objections to evidence one by one. Broad, clearly
admissible statements of the types of loss that may be suffered were made by the deponent
to the Defendant’s affidavits without challenge by way of cross-examination. While I’m
not prepared to find potential losses as between 7 and 9.4 million dollars, I draw the
inference that losses caused by the interlocutory injunction may be significant. In
particular:
-- 17 of 21 --
18
(i) The injunction will bring the whole project to a temporary halt.
(ii) The injunction will put in jeopardy the Defendant’s dealings with third
parties.
(iii) There will be holding costs.
(iv) There will, at least potentially, be an impact upon the broader BMI Group.
[46] I reject the Plaintiffs’ submissions that, in assessing the potential loss to the Defendant if
an injunction is granted, I can only look strictly at loss suffered by the single entity, being
the Defendant. The Defendant is part of a wider group, and I cannot see why I can’t take
into account the broader damage that the group of companies will suffer in considering
the balance of convenience. The granting of an injunction will prevent the development
continuing at least for a period and will frustrate third parties who have been dealing with
the Defendant.
[47] It is said that the matter can be readied for trial quickly. In practical terms, though, taking
into account preparing the case, listing the trial, the hearing itself, the judgment being
reserved for a period and any potential appeal, the proceedings are unlikely to be resolved
this year.
[48] The Plaintiffs submit, in effect, that I ought to ignore the fact that the Defendant might
suffer any inconvenience in undoing any steps that it has taken since October 2017 or any
inconvenience caused or exacerbated by steps taken by the Defendant since October
2017. The Plaintiffs say that the Defendant took those steps knowing that the Plaintiffs
asserted an interest in the land.
[49] In support of that submission, Mr Cooper QC in oral submissions cited the decision of
Justice von Doussa in Koppamurra Wines Pty Ltd and Mildara Blass Ltd (1998) 41 IPR
154, to which I have referred earlier. That case concerned a dispute about a trademark,
“Koppamurra”. Mildara Blass Ltd commenced a campaign to promote the name
“Koppamurra” as a regional geographic name describing a particular area. Knowing the
interests of Koppamurra Wines Pty Ltd in the trademark, Mildara Blass marketed
products utilising the name “Koppamurra” in a clear challenge to the trademark. When
-- 18 of 21 --
19
an application was made for an interlocutory injunction, Mildara Blass pointed to the
losses it would suffer if it had to withdraw the products from the market. In that context,
Justice von Doussa said, at page 160:
“I consider that many of the losses which the respondent says are likely to
flow from an injunction are losses that the respondent will encounter because
it chose to pursue a commercial solution to the problem and the risks that
were associated with it. It is in that sense, I think, that the High Court in the
Beecham case at 626 talks about someone going into a situation with their
eyes open.”
[50] It was that passage in particular that Mr Cooper QC sought to rely upon.
[51] There is no principle of law that a court considering whether to make an injunction to
enjoin a party cannot consider events subsequent to the events giving rise to the dispute
and consider the damage or impact upon the party being sought to be enjoined. Certainly,
Koppamurra Wines v Mildara Blass is not authority for such a proposition. It is simply
an example of a case where the respondent’s conduct after the dispute arose was looked
at when assessing where the justice of the case might lie; in particular when assessing,
in the exercise of discretion, any loss which might be suffered by the party sought to be
enjoined. That is made clear by Justice von Doussa at page 159 in the passage:
“The respondent has deliberately sought to resolve the dispute over the use of
the Koppamurra name by taking the matter into its own hands. In my view,
there were other courses that it could have taken, but it has chosen to take a
commercial risk in forcing the issue. The respondent is substantially the
stronger economic entity, and, in my view, it has played on that fact to try and
resolve the dispute in the marketplace rather than in the court.”
[52] His Honour then went on in a similar vein to consider other aspects of the specific conduct
of Mildara Blass in that case. This is a very different case. Here, the Defendant is the
registered proprietor of a valuable piece of land which is ripe for development. Third
parties with major commercial interests, such as the petroleum company, Caltex have
been attracted to the site. Once the Defendant’s view that the option had been lost by the
Plaintiffs had been clearly communicated to the Plaintiffs, the Plaintiffs commenced
action on 23 November 2017. There is no reason to think that it was reasonable for the
Plaintiffs to assume that the Defendant would simply sit on its hands and hold the land.
Frankly, the sensible thing to do was to put the land to its best use, which is as a
development site. The Plaintiffs have waited some time to seek interlocutory relief.
-- 19 of 21 --
20
[53] The balance of convenience in relation to the first, second and fifth categories of relief
favour the Defendant and I decline to enjoin the Defendant. The fourth category of relief
is the joinder of Boardwalk, which has been dealt with. The remaining relief under
category 3 concerns the confidential information. As previously observed, there are both
the relevant documents and other information.
[54] There were submissions made as to whether documents which came into existence could
be described as confidential and, similarly, whether the information was confidential.
There are obviously disputes about that which need to be tried.
[55] Therefore, I would refuse final relief in relation to delivery up of the relevant documents.
[56] The real issue is whether interlocutory relief should be given to enjoin the Defendant from
use of the relevant documents and information pending trial.
[57] I am prepared to accept that there is a prima facie case that at least some of the relevant
documents which came into existence and some of the information may be confidential
and that the Plaintiffs may have a claim in that respect. What is unclear to me at the
moment is the extent of that claim and the identification of particular documents and
information to which confidentiality may attach. This raises the considerations identified
in Rapid Metal Developments (Australia) Proprietary Limited v Anderson Formrite
Proprietary Limited & Anor [2005] WASC 255 at [81].
[58] There is no real prospect, in my assessment, that any of the documents might be destroyed
or corrupted and no suggestion that proper disclosure will not be made in the course of
the litigation. Any injunction may disrupt the Defendant’s continued development of the
land and, as I’ve already explained, on the balance of convenience, the Defendant’s
continued development of the land is to be preferred, with the Plaintiffs to pursue damages
claims if they choose to do so. The balance of convenience favours refusal of
interlocutory relief for the third category of relief. For those reasons, apart from the orders
I made on 6 April 2018, I dismiss the Plaintiffs’ application. I’ll hear the parties on costs.
...
-- 20 of 21 --
21
[59] HIS HONOUR: The Defendant, who was the respondent to the injunction, submits that
it should have its costs of the application for the injunction, and the basis upon which that
claim is made is basically that costs follow the event. They have been successful. There
is, of course, some justification for that under the Rules and some force in that argument.
[60] Mr Cooper, who leads for the Plaintiffs, on the other hand, points to the following factors.
Firstly, he says that there was an application to join Boardwalk as a party to the
proceedings. That was opposed until the actual hearing. So Mr Cooper can claim some
success in the application. It has to be said, of course, that has to be regarded as a minor
success in the overall scheme of things. Secondly, though, and to my mind more
importantly, Mr Cooper says that whilst he’s been unsuccessful in the application, he was
unsuccessful on discretionary grounds. I found that a prima facie case for the relief sought
was made out.
[61] The case is a complicated one. I think it’s fair to say, in a loose sense, that the case has
a long way to go. I have some sympathy for the fact that the plaintiffs only lost upon the
exercise of discretion, and that was by no means a clear-cut issue. Mr Cooper has
submitted that the costs ought to be costs in the cause; however, in my judgment, there
may be many factors which arise between now and final determination of the case which
might bear upon the reasonableness or otherwise of the position of both parties before me
on the application for the injunctions. Each parties’ costs of the application ought to be
reserved.
-- 21 of 21 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2018/086