Bluefin Seafoods Pty Ltd v Fraser Coast Regional Council [2018] QSC 14
SUPREME COURT OF QUEENSLAND
CITATION: Bluefin Seafoods Pty Ltd v Fraser Coast Regional Council
[2018] QSC 14
PARTIES: BLUEFIN SEAFOODS PTY LTD ABN 90 063 023 807
(plaintiff)
v
FRASER COAST REGIONAL COUNCIL
(defendant)
FILE NO: SC No 5626 of 2016
DIVISION: Trial Division
PROCEEDING: Application
DELIVERED ON: 9 February 2018
DELIVERED AT: Brisbane
HEARING DATE: 6 February 2018
JUDGE: Bowskill J
ORDERS: 1. The further amended statement of claim filed on 1
December 2017 is struck out.
2. Judgment is entered for the defendant.
CATCHWORDS: LIMITATION OF ACTIONS – GENERAL MATTERS –
AMENDMENT OF ORIGINATING PROCESS AND
PLEADINGS OUTSIDE LIMITATION PERIOD –
AMENDMENTS INTRODUCING NEW CAUSE OF
ACTION OR PARTICULARISING CAUSE OF ACTION –
Where the defendant applies to strike out the statement of
claim in its entirety, on the basis that the plaintiff’s claims are
statute barred – where the plaintiff concedes that the causes of
action for which it commenced the proceedings on 8 June 2016
are statute barred – whether new allegations in the plaintiff’s
amended statement of claim filed in December 2017 constitute
new causes of action, in respect of which the limitation periods
have expired – whether the new causes of action arise out of
the same or substantially the same facts as the earlier causes of
action for which relief was claimed
Uniform Civil Procedure Rules 1999 (Qld), r 376(4)
Borsato v Campbell [2006] QSC 191
Draney v Barry [2002] 1 Qd R 145
Paul v Westpac Banking Corporation [2017] 2 Qd R 96
Thomas v Queensland [2001] QCA 336
-- 1 of 13 --
2
COUNSEL: K N Wilson QC for the defendant (applicant)
SOLICITORS: Barry Nilsson Lawyers for the defendant (applicant)
Ms T M Rimmer, a director of the plaintiff, appeared for the
plaintiff by leave
[1] On 8 June 2016 Bluefin Seafoods Pty Ltd commenced proceedings against the Fraser
Coast Regional Council seeking “damages including equitable damages”. Ms Rimmer
and Mr Meaclem, in their capacity as shareholders of Bluefin, were the second and third
plaintiffs, but their action has been discontinued. The cause(s) of action relied upon by
Bluefin are difficult to elucidate from the original statement of claim, but appear to
comprise claims for damages for misleading and deceptive conduct, on the basis of
representations by representatives of the Council, which Bluefin relied upon in making
certain decisions in relation to a sea cucumber aquaculture hatchery operated by it at
Urangan, to its financial detriment; as well as related claims for damages for neglige nce
and breach of contract (in relation to what is described as a Development Agreement
entered into in October 2006).
[2] At no stage since this proceeding was commenced has Bluefin been legally represented.
Ms Rimmer, as a director of Bluefin, was given leave to appear for Bluefin at the hearing
of this application, there being no objection to that course from the Council.1
[3] The original statement of claim is poorly drafted and difficult to comprehend, but
relevantly for present purposes Bluefin alleged that:
(a) On or about 13 October 2006 Bluefin and the Council entered into an agreement
under which in consideration of the Council providing the necessary infrastructure,
Bluefin would develop an aquaculture facility on certain land (paragraph [19]).
(b) Under the terms of this contract Bluefin spent $560,000 developing the land
(paragraph [21]).
(c) “But wrongfully and in breach of the express and implied terms. Council has not
provided or co-operated in the provision of the necessary infrastructure in
consequence whereof Bluefin has suffered loss and damage” (paragraph [22]).
(d) (After referring to various other things that happened, or were represented by the
Council, in the period from about March 2007 to about April 2009) “By December
2009, contrary to representations the Council has not built the infrastructure, which
had caused Bluefin to be financially strained” (paragraph [45]).
1 As to the need for leave, see s 90 of the Supreme Court of Queensland Act 1991 (formerly s 209 of the Supreme
Court Act 1995); see also Hubbard Association of Scientologists International v Anderson [1972] VR 340 at
341-344 and Simto Resource Ltd v Normandy Capital Ltd (1993) 10 ACSR 776 at 781-783, referred to by
Keane JA in ASIC v Neolido Holdings Pty Ltd [2006] QCA 266 at [59].
-- 2 of 13 --
3
(e) There was a meeting with the Council on 25 February 2010 to discuss the
development proposal (at paragraph [51]) and a further meeting on 1 March 2010
at which the Council confirmed it “will proceed with Stage 1 of the development
as discussed” (at paragraph [52]).
(f) “By October 2010, contrary to the representations the Council has not built the
infrastructure, which had caused Bluefin to be financially strained” (paragraph
[53]).
[4] The conclusions, in terms of a legal consequence, sought to be drawn from these, and the
other allegations in the pleading, are very broad, and purport to relate to all the
“representations” apparently pleaded. So, for example, in so far as Bluefin is concerned,
the pleading concludes with the following:
“61. The Council knew or ought reasonably to have known that Bluefin
would risk the incurring of economic loss if the representations or any
of them were not accurate.
62. The representations were incorrect and misleading.
63. As a result of Council’s negligence Bluefin, has suffered loss and
damage.”
[5] In its defence filed on 4 August 2016, among other matters, including objections to the
form of the pleading as improper and embarrassing, the Council pleaded that, in so far as
Bluefin’s action accrued prior to 8 June 2010 it is statute barred, and s 10 of the Limitation
of Actions Act 1974 was relied upon to defeat Bluefin’s claim.
[6] An amended statement of claim was filed on 26 August 2016. It did not fix the many
problems with the original statement of claim.
[7] An amended defence was filed on 2 September 2016, in which the limitations defence
remained unchanged.
[8] The proceeding was placed on the supervised case list in April 2017, and has been the
subject of review by Applegarth J on various occasions since then.
[9] A (second) amended statement of claim was filed on 12 June 2017. This version was not
an improvement on the original.
[10] On 7 July 2017 the defendant filed an application seeking that the claim filed 8 June 2016
and the amended statement of claim filed 12 June 2017 be struck out, or alternatively that
summary judgment be entered for the defendant. In addition to challenging the form
and substance of the pleading, it was also contended that Bluefin’s claims were statute
barred (see Council’s written submissions filed on 18 July 2017).
-- 3 of 13 --
4
[11] By orders made on 18 July 2017 by Martin J the amended statement of claim filed on 12
June 2017 was struck out, but the plaintiffs (at that time, still including Ms Rimmer and
Mr Meaclem) were given leave to re-plead. I infer from this that the limitation issue was
not a basis for striking out the pleading.
[12] A (third) amended statement of claim was then filed on 11 September 2017. Although
Bluefin was still unrepresented, from this version of its statement of claim it is apparent
that it had by this time received some legal assistance, from a barrister volunteering with
LawRight, whose name appears at the end of the document.
[13] In this version of the statement of claim, an effort has been made to categorise the
representations alleged to have been made at various times, and the steps taken in reliance
upon them. So, for example, representations alleged to have been made in October 2004,
which are said to have induced Bluefin to enter into the Development Agreement, are
referred to as the “First Representations” (see paragraphs [6]-[9]). Representatio ns
alleged to have been made in October 2006, about works the Council was then
undertaking, and which it is said were for the purpose of encouraging Bluefin to continue
spending money in complying with its obligations under the Development Agreement,
which it did, are referred to as the “Second Representations” (see paragraphs [25]-[29]).
[14] In addition, the alleged failure of the Council to complete construction of the “utilities ”
on the relevant land, by about December 2006, is alleged to be in breach of the Council’s
obligations under the Development Agreement, and is described as the “First Breach”,
as a result of which Bluefin suffered loss and damage (see paragraphs [30]-[38]). A
“Second Breach” of the Development Agreement is alleged, arising from the Council’s
refusal, in about March 2007, of Bluefin’s request to exercise an option under that
agreement to purchase the relevant land (see paragraphs [40]-[45]).
[15] This version of the statement of claim also alleges that on 1 March 2010 a “Third
Representation” was made, to the effect that the Council would proceed with stage 1 of
the development, which seems to relate to the construction by the Council of utilities on
the relevant land, which it is alleged was made for the purpose of encouraging Bluefin to
continue to comply with its obligations under the Development Agreement. It is not
expressly alleged that Bluefin relied on the Third Representation in that way. It is alleged
that, contrary to this representation, the Council did not carry out the construction of the
utilities within a reasonable time or at all (see paragraphs [50]-[54]).
[16] On 3 November 2017 Bluefin was ordered to file and serve a reply specifically addressing
the limitations defence pleaded by the Council.
[17] The reply filed by Bluefin on 1 December 2017 contains one paragraph, as follows:
“[Bluefin] Admits that if cause of action accrued prior to 8 June 2010 it would
be statute barred but denies the cause of action is statute barred for the reasons
-- 4 of 13 --
5
set out in paragraphs 50 to 80 of the Further Amended Statement of claim
filed and served with this Reply.”
[18] Also on 1 December 2017, Bluefin filed a (fourth) further amended statement of claim.
In contrast to the previous version, this document does not bear the name of any counsel,
voluntary or otherwise.
[19] The main changes in this version of the statement of claim are:
(a) The deletion of the concluding paragraphs pleading loss or damage suffered as a
result of the First Representation (paragraph [12]) and the Second Representatio n
(paragraph [28]). The equivalent concluding paragraphs in respect of the First
Breach (paragraph [38]) and the Second Breach (paragraph [45]) remain, but for
reasons explained below, this may have been an oversight.
(b) In relation to the Third Representation:
(i) Whilst in substance this remains an allegation that “the Council will proceed
with stage 1 of the development”, the pleading is amended to allege that this
was said in a meeting on 25 February 2010 and in an email dated 1 March
2010 (see paragraphs [52]-[54]).
(ii) It is alleged that by 25 February and/or 1 March 2010 the Council was liable
to Bluefin for damages for the First Breach and the Second Breach, and/or
the First Representation and the Second Representation (see paragraphs [50]
and [51]).
(iii) It is further alleged that in reliance upon the Third Representation, Bluefin
did not proceed against the Council with a claim for damages for the First
Breach, the Second Breach and/or the First Representation and the Second
Representation (see paragraph [55]).
(c) The addition of a new allegation that on or around 1 March 2010 the Council and
Bluefin agreed to vary the Development Agreement, to allow the Council to carry
out the construction of the utilities within a reasonable time of that date; that a
reasonable time was no later than 31 August 2010; that in breach of the
Development Agreement as varied, the Council failed to do that, as a result of
which Bluefin suffered loss and damage, comprising a combination of the losses
previously alleged to have flowed from the First Breach, Second Breach, First,
Representation and Second Representation (see paragraphs [59]-[61] and [77]-
[80]).
[20] On 22 December 2017 the Council filed the present application, seeking orders:
(a) firstly, that the amended statement of claim filed on 1 December 2017 be struck
out in its entirety;
-- 5 of 13 --
6
(b) alternatively, that almost all of it be struck out, apart from the new claim in relation
to variation of the Development Agreement;
(c) alternatively, for summary judgment in favour of the Council.
[21] The sole basis of the Council’s application on this occasion is that Bluefin’s claims are
statute barred.
[22] Bluefin has been able to receive some assistance from LawRight, including in the
preparation of a written outline for the purposes of this application.
[23] It is recorded in Bluefin’s written outline, filed in court on 6 February 2018, that Bluefin
“does not maintain a claim for damages for the first and second breaches of contract or
the first or second representations (the initial breaches). The causes of action based
upon the initial breaches are now statute barred” (see paragraph [8]).
[24] This is a fair and appropriate concession to have made given that, in order to have been
within the 6 year limitation period (assuming, favourably to Bluefin, that was the period
which applied to its misleading and deceptive conduct claims), the causes of action for
those “initial breaches” would have to have arisen no later than 8 June 2010. Having
regard to the facts alleged by Bluefin (see paragraphs [13] and [14] above) I accept the
Council’s submission that the claims based on the First and Second Breaches, and the
First and Second Representations, were unarguably brought outside the 6 year limita tio n
period.2 Accordingly, it is appropriate that they be struck out. As noted at paragraph
[19](a) above, it appears Bluefin may have attempted to do this, but perhaps not in a
complete or entirely satisfactory manner.
[25] The real issue is whether the same conclusion follows in respect of the causes of action
based on the Third Representation and the alleged variation of the Developme nt
Agreement.
[26] In both cases, taking the facts alleged in the amended statement of claim on their face,
and putting the case at the highest for Bluefin, each of these causes of action had accrued
by 31 August 2010, being the time by which, Bluefin alleges, it was reasonable for the
utilities to have been constructed by the Council, in accordance with the Third
Representation, and the terms of the varied Development Agreement. That is the position
of Bluefin, in its written submissions, where it is said:
“13. The loss suffered by the plaintiff arising out of the varied contract did
not accrue until the defendant was in breach of the contract as varied on
1 March 2010.
14. That breach of contract / loss occurred when the defendant did not carry
out the construction works by 31 August 2010.
2 See paragraphs [19] to [32] of the Council’s written submissions, filed in court on 6 February 2018.
-- 6 of 13 --
7
…
22. The loss suffered by the plaintiff as a consequence of the Third
Representations by the defendant occurred when the defendant failed to
complete the works within a reasonable time of that representation i.e.
31 August 2010.”
[27] Assuming the claims for damages by reference to the Third Representation and the
variation to the Development Agreement are new causes of action, proceedings in respect
of them would need to be commenced by 31 August 2016, in order to be within the
requisite 6 year time limitation. They were not pleaded until the further amended
statement of claim was filed on 1 December 2017.
[28] Bluefin contends that its causes of action based upon the Third Representation, and
breach of the varied Development Agreement, are not statute barred. Bluefin’s argument
in this regard seems to be on the basis that the proceedings otherwise were commenced
on 8 June 2016 (that is, before 31 August 2016).
[29] The issues to be determined therefore are:
1. Whether the pleading based on the Third Representation, as it appears in
paragraphs [50]-[58] and [62] of the further amended statement of claim filed 1
December 2017, and the pleading based on the breach of the varied Developme nt
Agreement, as it appears in paragraphs [59]-[62] of that document, are new causes
of action.
2. If so, whether they are statute barred.
3. If so, whether they can be permitted to be added to the proceedings, outside the
limitation period, under r 376(4) of the Uniform Civil Procedure Rules 1999.
New causes of action?
[30] In Borsato v Campbell [2006] QSC 191 McMurdo J (as his Honour then was) said this
in relation to the meaning of “cause of action” in r 376(4):
“[8] The term ‘cause of action’ was defined in Cooke v Gill as being ‘every
fact which is material to be proved to entitle the plaintiff to succeed’, a
definition which many judgments have employed in the context of this
rule or its equivalent: see eg Allonnor Pty Ltd v Doran per
McPherson JA. But it has not been applied literally, for otherwise any
new fact to be added to a plaintiff’s case would be treated as raising a
new cause of action which required leave in the context of a rule such
as r 376(4). So in Allonnor Pty Ltd v Doran for example, there is an
indication of what the Court of Appeal in Thomas v Queensland
subsequently endorsed as a ‘fairly broad brush comparison between the
-- 7 of 13 --
8
nature of the original claim and that to which it is sought to be
amended’. The dividing line is between the addition of facts which
involve a new cause of action and those which are simply furthe r
particulars of the cause already claimed, and its location involves a
question of degree which can be argued, one way or the other, by the
level of abstraction at which a plaintiff’s case is described. Some
illustrative guidance is provided by Allonnor Pty Ltd v Doran; Thomas
v Queensland and another judgment of the Court of Appeal, Central
Sawmilling No 1 Pty Ltd v Queensland.
[9] In Allonnor, the plaintiff was employed by the defendant as a deliver y
driver, and sued for an injury to his back and neck said to have been
suffered on a certain date making a certain delivery of furniture. He
sought to amend to add a claim for an injury to his shoulder, alleged ly
caused by another delivery made to a different address but on the same
day. McPherson JA ‘doubted whether what was sought to be added by
way of amendment really amounts to a new cause of action’ but in any
case held that the new cause of action (if any) arose out of substantia lly
the same facts and the amendment should be allowed. His Honour said:
On any view of what is pleaded, the plaintiff was, at the end of
the day in question, left with physical injury to his body, which
resulted from the same cause, which was lifting (whether on one
or more than one occasion) in the course of the same employme nt
with the same employer. It is not unreasonable to state it in this
way, although admittedly it is to some extent a matter of the level
of generality at which the proposition is expressed.
[10] In Thomas v Queensland, the Court of Appeal disallowed an
amendment of a case brought by an injured motorcyclist against the
State as the authority responsible for the highway on which he was
injured. His case was that there was a large amount of soil on the road
surface which caused his motorcycle to lose traction and collide with
another vehicle. His claim was pleaded originally on the basis that the
defendant had been undertaking road works at the scene which had
resulted in this soil on the road. He sought to amend to claim that the
soil was there because it had been washed from a nearby embankment
in a way which was attributable to poor construction of the highway in
the first place. The court held that this was a new cause of action, saying
in its joint judgment:
The essential elements in a claim for damages for negligence are
the duty of care, breach of that duty and injury caused by that
breach. Here, although only for one injury an incident is alleged,
different duties, different breaches and different causes of injury
-- 8 of 13 --
9
are now alleged. In our view the effect of the amendment is to
include new causes of action.
[11] In Central Sawmilling, the plaintiffs claimed damages for breach of
contract, saying that the defendant, the State of Queensland, by three
identified written agreements had promised to provide them with
certain quantities of timber. They then sought to amend to plead another
agreement made between various timber millers, including the
plaintiffs, and the defendant by which they were to receive those
amounts of timber. That was held to involve a new cause of action.”3
[31] Borsato was a medical negligence claim. As originally pleaded, the plaintiff alleged a
breach of duty on the part of two surgeons in the manner in which they performed surgery
on him. The amendments sought to plead a breach of the duty to warn about risks of the
surgery. McMurdo J found that:
“[14] Indisputably, the breach of duty now alleged is quite distinct from that
already alleged. In substance it is such a different case from an
allegation of negligent performance of the surgery that it cannot be
described as some further particularisation of the original claim of
breach of duty. It requires the plaintiff to prove a distinct fault,
necessarily prior in time to the alleged breach in the course of the
surgery, and then to prove the likelihood of some sequence of events in
response to a proper warning. I do not accept that it is appropriate for
present purposes to characterise the duty in this new case as the same
as in the existing case, but on any view the new case involves quite a
different breach.”
[32] McMurdo J’s approach has been adopted in a number of subsequent cases: see, for
example, Wolfe v State of Queensland [2009] 1 Qd R 97, Jetcrete Oz Pty Ltd v Conway
[2015] QCA 272 and the discussion in McQueen v Mount Isa Mines Ltd [2017] QCA 259
at [44]-[55].
[33] In this case, both the cause of action arising from the Third Representation, as it is
pleaded in the amended statement of claim filed on 1 December 2017, and the cause of
action for breach of the allegedly varied Development Agreement, are new causes of
action. Those were not causes of action sought to be raised by Bluefin prior to the
amendment. That is plainly the case in relation to the cause of action for breach of the
allegedly varied Development Agreement, because no such variation had previously been
pleaded. It is also the case in relation to the Third Representation because, although there
had been earlier references to a representation being made on 25 February and/or 1 March
2010 in the pleadings:
3 Emphasis added; references omitted.
-- 9 of 13 --
10
(a) prior to the (third) amended statement of claim filed on 11 September 2017, this
was simply part of a broader narrative – there was no pleading of anything being
done in reliance on what was said; and no cause of action pleaded arising from
what was said (cf paragraphs [3] and [4] above);
(b) in the (third) amended statement of claim filed on 11 September 2017, a statement
made on 1 March 2010 (that Council will proceed with stage 1 of the development
as previously discussed) is pleaded and defined as the Third Representation, but
there is still no pleading of anything done in reliance on it, and it is seemingly
incorporated into the First Representation and the Second Representation –
collectively the “misleading and deceptive conduct” – for the purposes of the
damages claimed (see [73] of this document);
(c) the first time it was alleged Bluefin relied upon the Third Representation in
deciding not to bring proceedings in relation to the “initial breaches” was in the
(fourth) amended statement of claim filed on 1 December 2017. This is a new case.
It is not a particularisation of the cause of action (arguably) previously pleaded; it
is a new cause of action.
[34] The mere presence in the earlier versions of the statement of claim of a reference to a
person on behalf of the Council saying, on 25 February or 1 March 2010, that Council
will proceed with stage 1 of the development as previously discussed, does not enable
the conclusion to be reached that the cause of action arising from the Third
Representation, as eventually pleaded on 1 December 2017, is not a new cause of action.
In this regard, the following observations of Pincus JA in Draney v Barry [2002] 1 Qd R
145 at [32] are apposite:
“… one cannot evade the plain intention of … r 376(4), by inserting in a
pleading a vague allegation raising no identifiable cause of action. Such an
allegation would be liable to be struck out as not setting out the materia l
facts… But the fact that [a paragraph containing such an allegation] was not
struck out does not oblige the Court to ignore its vacuous character, when
considering whether an amendment will if allowed add or substitute a ‘new
cause of action’… The spirit of the UCP Rules would not be respected if the
question whether what are in substance new causes of action should be
allowed to be added out of time is made to depend upon the presence or
absence in the existing pleading of an allegation of misconduct which is so
vague as to be devoid of any ascertainable meaning.”
Has the limitation period expired?
[35] As already discussed, the limitation period in respect of these two new causes of action
would have commenced to run from 30 October 2010, and therefore expired on 30
October 2016. They were not pleaded until 1 December 2017, after the limitation period
had expired.
-- 10 of 13 --
11
Can they be relied upon now?
[36] Bluefin has not made an application for leave to make the amendments which appear in
the pleading filed on 1 December 2017. Nevertheless, it is appropriate to consider
whether leave ought to be given under r 376(4), in determining this application.
[37] Relevantly, r 376(4) provides that the court may give leave to make an amendment to
include a new cause of action in respect of which the relevant period of limitation has
ended only if:
(a) the court considers it appropriate; and
(b) the new cause of action arises out of the same facts or substantially the same
facts as a cause of action for which relief has already been claimed in the
proceeding by the party applying for leave to make the amendment.
[38] In determining whether a new cause of action arises out of the same or substantially the
same facts, the relevant principles to be applied are as follows.
[39] In Draney v Barry [2002] 1 Qd R 145 at [57] Thomas JA said:
“[Rule 376(4)] allows a fairly wide discretion in that the court will not allow
such an amendment unless it considers it ‘appropriate’ to do so and also
considers that the new cause of action arises at least substantially out of the
same facts as the existing cause of action. I do not think that ‘substantia lly
the same facts’ should be read as tantamount to the same facts, and consider
that the need to prove some additional facts is not necessarily fatal to a
favourable exercise of discretion under r 376(4). If the necessary additiona l
facts to support the new cause of action arise out of substantially the same
story as that which would have to be told to support the original cause of
action, the fact that there is a changed focus with elicitation of additiona l
details should not of itself prevent a finding that the new cause of action arises
out of substantially the same facts. In short, this particular requirement should
not be seen as a straitjacket.”
[40] In Thomas v Queensland [2001] QCA 336 at [19] the Court of Appeal clarified, by
reference to this passage from Draney v Barry, that:
“Of course ‘the story’ is a shorthand reference to the matters that the plaintiff
has to prove.”4
[41] In Paul v Westpac Banking Corporation [2017] 2 Qd R 96 at [15] Fraser JA (with whom
Gotterson JA and Douglas J agreed) said:
4 See also Althaus v Australia Meat Holdings Pty Ltd [2007] 1 Qd R 493 at [33]-[36] per Keane JA.
-- 11 of 13 --
12
“In an appropriate case leave to amend to add a new cause of action which is
statute barred may be granted even though it involves reliance upon facts in
addition to those out of which a pleaded cause of action arises, provided that
those additional facts are substantially the same as facts already pleaded. The
question in each case is whether the facts out of which a new cause of action
arises are substantially the same as facts relied upon in a cause of action for
which relief has already been claimed in the proceeding. As has been
mentioned in other cases, this may involve questions of degree and fine
judgment, but the answer to that question should be informed by an
appreciation that the policies underlying the applicable statute of limitatio n
may be inappropriately undermined if the required analysis is conducted at
too high a level of generality...”5
[42] In so far as the claim based on the Third Representation is concerned, the new facts, out
of which this new cause of action arises, are that Bluefin did not proceed against the
Council with its claim for damages for the First Breach and the Second Breach, and the
First Representation and the Second Representation, because it relied upon the Third
Representation, made in February and March 2010 that the “Council will proceed with
Stage 1 of the development”, which it was apparent by 31 August 2010 would not occur.
[43] That new cause of action does not “arise out of” substantially the same facts as the causes
of action previously pleaded. It arises out of new facts that are not substantially the same
as the facts relied upon as giving rise to the previous causes of action; although those
facts would have to also be proved, in order to establish the loss which is claimed.
[44] The mere reference, in the pleading, at an early stage, to a representation of the kind now
said to comprise the Third Representation, is not sufficient to avoid this conclusion. At
no stage prior to the 11 September 2017 amendment (which in any event was outside the
limitation period) was the Third Representation clearly pleaded as such. At that stage,
no reliance on the Third Representation was pleaded. Prior to the 11 September 2017
amendment, the reference to a statement by a representative of the Council, on 25
February or 1 March 2010, to the effect of the later defined Third Representation, was
simply part of the narrative – it was not a fact that Bluefin had to prove, in order to
establish its previous claims for damages for the First Breach, Second Breach, First
Representation or Second Representation.
[45] In so far as the claim based on breach of the varied Development Agreement is
concerned, the new facts are that on or around 1 March 2010 the Council and Bluefin
agreed to vary the Development Agreement to allow the Council to carry out the
construction of the utilities within a reasonable time; a reasonable time was no later than
31 August 2010; that did not occur; that was a breach of the Development Agreement as
varied; Bluefin suffered loss and damage as a consequence of that breach.
5 References omitted.
-- 12 of 13 --
13
[46] It is even clearer, in the case of this new cause of action, that it does not arise out of
substantially the same facts as the causes of action previously pleaded. It arises out of
entirely new facts pleaded, which are not substantially the same as those previously
pleaded. In addition, although no distinction is presently drawn in the 1 December 2017
version of the pleading, the measure of damages will be different, from that said to flow
from the First Breach, the Second Breach, the First Representation and the Second
Representation. In so far as the alleged breach of the varied Development Agreement is
concerned, the measure of damages is that which would put Bluefin into the position it
would have been had the varied Development Agreement been performed. That would
necessarily be quite different to the damages which may have flowed, had Bluefin been
able to successfully maintain and prove its claims for damages as a result of the First
Breach, the Second Breach, the First Representation and the Second Representatio n.
This is a case where, as Keane JA said in Zonebar Pty Ltd v Global Management
Corporation Pty Ltd [2009] QCA 121 at [23]: “[t]he substance of the new cause of action
is different in terms of the acts or omissions which give rise to it, and the adverse
consequences for which damages are claimed”.6
[47] The new causes of action sought to be added by the amendment made on 1 December
2017 do not arise out of the same or substantially the same facts as the causes of action
previously pleaded. I would not, therefore, grant leave to make the amendments.
[48] It follows that it is appropriate to strike out the whole of the amended statement of claim
filed on 1 December 2017. Since this is on the basis that the causes of action pleaded in
it are all statute barred, it is appropriate, further, to give judgment for the Council, under
r 293 of the UCPR.
[49] I will hear the parties as to costs.
6 See also Borsato v Campbell [2006] QSC 191 at [15]-[16] per McMurdo J.
-- 13 of 13 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2018/014