Albion Projects Pty Ltd v Simpson & Anor [2014] QCAT 73
CITATION: Albion Projects Pty Ltd v Simpson & Anor [2014]
QCAT 73
PARTIES: Albion Projects Pty Ltd
(Applicant)
v
Jonathon Simpson & Kim Simpson
(Respondents)
APPLICATION NUMBER: BDL104-13
MATTER TYPE: Building matters
HEARING DATE: 20 February 2014
HEARD AT: Brisbane
DECISION OF: Senior Member Oliver
DELIVERED ON: 25 February 2014
DELIVERED AT: Brisbane
ORDERS MADE: 1. The application filed on 12 February
2014 to transfer the proceeding to the
District Court of Queensland is
dismissed.
CATCHWORDS: Case Management – application to transfer the
proceeding to the District Court – where the
District Court proceeding seeks the same relief
that the Tribunal has jurisdiction to grant –
where proceeding is actively case managed –
where exercise of discretion does not favour a
transfer – where failure to comply with
directions.
Queensland Civil and Administrative Tribunal
Act 2009 (Qld) ss 3, 52
Queensland Building and Construction
Commission Act 1991 (Qld) s 77
AON Risk Services Australia Limited v Australia
National University [2009] HCA 27
-- 1 of 4 --
2
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Represented by Mr Feehely, solicitor Jim
Feehely Project Law.
RESPONDENT: Represented by Mr East, solicitor of Clarke and
Kann Lawyers.
REASONS FOR DECISION
[1] On 23 May 2013 the applicant commenced a proceeding in the building
jurisdiction of the Tribunal claiming $272,159.72 from the respondents for
the unpaid balance of monies owing under a cost plus building contract.
Interest is also claimed for the delay in payment as well as the return of a
bank guarantee in the sum of $47,845.00.
[2] A response and counter application was filed by the respondents on 23
May 2013. The counter claim is for $575,000.00 damages for the cost to
rectify defective building work less the amount of the bank guarantee.
[3] Both parties have filed extensive pleadings. The respondents now want
this proceeding transferred to the District Court of Queensland. The
Tribunal has power to transfer a proceeding to a court under s 52 of the
Act. A hearing of the application was conducted on 20 February and the
decision was reserved.
[4] In the usual way the parties were directed to file statements of evidence
and the proceeding progressed to a compulsory conference on 30 August
2013. The proceeding was not resolved. On 13 November 2013, at a
directions hearing, I made directions for the filing of further statements of
evidence by either party, including expert reports and listed the application
for an experts conclave on 28 February 2014. I also listed the matter for
hearing for two days commencing on 25 March 2014.
[5] The timetable put in place to progress this matter to a hearing and
finalisation at the earliest opportunity is consistent with the objects of the
QCAT Act to ensure that matters are dealt with in a way that is accessible,
fair, just, economical, informal and quick.1 Given the complexity of the
proceeding both parties were granted leave to be legally represented.
Because of recent events one could be forgiven for being sceptical as to
whether the granting of legal representation has assisted the timely
progress of this building dispute and to have it determined expeditiously at
a minimum cost to the parties.
[6] The applicant complied with the directions of 13 November 2013 and filed
its further material on 16 January 2014. The respondents however have
not complied with the direction to file their further material by 15 February
2014. Instead, on 12 February 2014 they filed an application to have this
1 QCAT Act s 3.
-- 2 of 4 --
3
whole proceeding transferred to the District Court of Queensland. This
application was listed for hearing on 20 February 2014. For some
unknown reason the respondents assumed that the filing of the application
for transfer relieved them of their responsibilities to comply with the
Tribunal’s directions of 13 November 2013. That is clearly not the case
and it is disturbing that the directions were not complied without the
Tribunal’s approval.
[7] The basis for the application for transfer, which is opposed by the
applicant, is that the relief sought in the District Court proceeding is for:-
“A declaration pursuant to section 23 of the Australian Consumer Law or
alternatively section 2 of Schedule 2 to the Trade Practices Act 1974 (Cth)
clauses 29.6(d) and 29.10 of the contract are void as unfair terms, or in the
alternative a declaration of clauses 29.6(d) and 29.10 of the contract are
void for uncertainty.”
[8] There is no doubt that the Tribunal has jurisdiction to decide whether a
term of a contract is void for uncertainty that is not challenged. What is
contended for by the respondents is that only the District Court has
jurisdiction to declare whether a term of a contract is unfair under section
51 of the Fair Trading Act, which Act supports the application of the
Australian Consumer Law as a law of Queensland. There is little doubt
that this must be right where that relief is sought as a cause of action.
[9] At the directions hearing held on 20 February 2014, at which time I also
heard the application for transfer; I gave leave to the respondents to file an
amended response and counterclaim. In the amended response they
allege, in paragraphs 13(g) and 16(d), that clauses 29.10 and 29.6 of the
cost plus building contract are void pursuant to section 23 of the Australian
Consumer Law. It may well be that, as a defence, the Tribunal has
jurisdiction to determine that issue although I need not decide the
application on point.
[10] The Tribunal’s jurisdiction to decide a domestic building dispute, which this
is, is conferred on it by section 77 of the Queensland Building and
Construction Commission Act 1991. Subsection (2)(e) confers the
following power on the Tribunal in deciding a building dispute:-
(e) declare any misleading, deceptive or otherwise unjust contractual term to
be of no effect, or otherwise vary a contract to avoid injustice.
[11] The power conferred by this section would permit the Tribunal to make a
finding that a specific clause in a contract is, in effect, unfair and void
which is the same relief provided by section 24 of the Australian
Consumer Law. This is also consistent with the general law where such a
defence is raised.
[12] For this reason alone I would not be prepared to order that this proceeding
be transferred to the District Court.
-- 3 of 4 --
4
[13] In addition, and as an exercise of discretion, I would refuse the application
because this proceeding is well advanced in the Tribunal providing of
course, the respondents comply with the directions that have been made.
The proceeding is listed for an expert’s conclave on 28 February 2014 and
then a hearing. The use of the expert’s conclave has proven to be highly
successful in resolving disputes or in the alternative narrowing issues that
go to hearing, which shortens the hearing time and saves the parties cost.
Upon provision of the joint experts report, in accordance with practice
direction 4 of 2009, the proceeding should be ready for hearing.
[14] The Tribunal engages in active case management of files to ensure that
the objects of the QCAT Act are achieved. This is also consistent with
ensuring that litigation of this kind does not get out of hand and is
unreasonably delayed.2 If this proceeding is transferred there will be,
undoubtedly, considerable delay. It is unlikely the proceeding will be case
managed and the parties will have to comply with the Uniform Civil
Procedures Rules both in respect of disclosure and pleadings to ensure
compliance with the Rules. Here, pleading rules do not apply, nor do the
strict rules of evidence. Also the Tribunal is a specialist tribunal for
deciding building cases with Members well versed in the building
jurisdiction.
[15] Therefore, because the Tribunal can give the same relief sought in the
District Court proceeding, and the matter is already listed for hearing,
there would be no advantage to the parties in having the matter
transferred. Also the exercise of discretion favours a refusal of the
application.
Order
[16] The application filed on 12 February 2014 to transfer the proceeding to the
District Court of Queensland is dismissed.
2 AON Risk Services Australia Limited v Australia National University [2009] HCA 27.
-- 4 of 4 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2014/073