Coro 1 Pty Ltd & Ors v Quality Build Pty Ltd [2014] QCAT 62
CITATION: Coro 1 Pty Ltd & Ors v Quality Build Pty Ltd
[2014] QCAT 62
PARTIES: Coro 1 Pty Ltd, Coro 2 Pty Ltd, Coro 3 Pty Ltd
and Coro 4 Pty Ltd t/as The Coronation
Partnership
(Applicant)
V
Quality Build Pty Ltd
(Respondent)
APPLICATION NUMBER: MCDO1662-13
MATTER TYPE: Other minor civil dispute matters
HEARING DATE: 27 November 2013
HEARD AT: Brisbane
DECISION OF: Adjudicator Bertelsen
DELIVERED ON: 17 February 2014
DELIVERED AT: Brisbane
ORDERS MADE: 1. The respondent pay to the applicants
the sum of $25,284.60.
CATCHWORDS: Contract – builder onsite – engagement of and
payment to subcontractors – builder’s
accountability for work completed in terms of
agreement and subcontractors paid – non
payment of subcontractors by builder.
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Coro 1 Pty Ltd, Coro 2 Pty Ltd, Coro 3 Pty Ltd
and Coro 4 Pty Ltd t/as The Coronation
Partnership represented by Robert Machin &
Coral Wilson, Directors
RESPONDENT: Quality Build Pty Ltd represented by John Gray,
Director
-- 1 of 8 --
2
REASONS FOR DECISION
Application
[1] The applicants Coro 1 Pty Ltd, Coro 2 Pty Ltd, Coro 3 Pty Ltd and Coro 4
Pty Ltd trading as the Coronation Partnership (Coro Partnership) claim
$25,000 as monies paid to the respondent Quality Build Pty Ltd (Quality
Build) the entity it asserts was contracted as a commercial builder in early
December 2012 to undertake renovations of 2 small blocks of units at 16-
18 Muraban Street, Mooloolaba and which were never paid to
subcontractors and suppliers by Quality Build but in fact retained by
Quality Build. The sum claimed includes registration and insurance
asserted as refundable. The sum of $25,000 only of $52,629.95 asserted
as unpaid to subcontractors and suppliers or otherwise refundable is
pursued to enable the claim to remain within the minor civil dispute
jurisdiction.
Background and evidence
[2] Coro Partnership and Quality Build entered into an agreement shortly
prior to or early in December 2012. There was no formal contract only
Coro Partnership’s confirmation letter of 14 December 2012 which
recorded that Quality Build would undertake renovations at $45 per hour
(at least initially) using its own tools and paying for its own fuel with
accommodation at no cost to be provided to Quality Build (for Mr Gray) in
one of the units being renovated. There was to be full disclosure in
respect of all rates and times worked by any person on site prior to
payment; contractors for plastering, balustrading and demolition were
listed. It was agreed that Coro Partnership would pay Quality Build’s
workcover at $2,250.00 and Master Builder’s registration and insurance of
$1,700.00. The confirmation records that Coro Partnership wanted full
disclosure of “everything in relation to building costs incurred at all times”
particularly as certain costs fell within repairs and maintenance and others
as capital improvements. Under the heading “progress payments” it was
clearly stated “we require full disclosure of all expenditure prior to any
further payment”. It was asserted by Coro Partnership that it would supply
quality materials and products from established sources wherever
possible with balance materials to come from Bunnings via Quality Build’s
credit card with that company.
[3] In the period early December 2012 through 18 April 2013 Quality Build
performed renovations initially estimated to take 3 - 4 months.
Pro rata refund
[4] Mr Gray of Quality Build stated that Quality Build was only ever employed
as a Foreman/Project Manager/Supervisor/Labour Hire Company.
However that Quality Build was a registered builder was not disputed nor
the placing of Quality Build’s container onsite, erection of a construction
fence and posting of safety signs. Due to monetary shortfalls on the part
of Quality Build apparent in early December 2012 Coro Partnership, upon
-- 2 of 8 --
3
production of an invoice from Quality Build, arranged to pay Quality
Build’s master builder’s registration and insurance $1,700.00 and
workcover $2,250.00 for the ensuing year to 28 December 2013. Quality
Build produced its invoice number 5 dated 15 December 2012 for
$3,950.00. It was paid to Quality Build which then rather than paying the
Master Builder’s registration and insurance and workcover annual fees
proceeded to pay these monthly thus delaying payment over time of a
considerable portion of that sum. Mr Machin of Coro Partnership asserted
those monies were only ever paid to Quality Build to enable it to start work
promptly and were repayable in any event. Mr Gray of Quality Build did
not raise any argument disputing or challenging that arrangement. Mr
Machin claimed pro rata refund for the period 18 April 2013 through 28
December 2013.
[5] Coro Partnership produced an affidavit of Abbey Rachel Benvegnu,
bookkeeper and registered BAS agent, sworn 26 November 2013. She
was retained by Coro Partnership to check and try to verify a number of
Quality Build’s invoices based on financial details supplied by Quality
Build. She says at no time during two site meetings at Mooloolaba did Mr
Gray indicate that works “were being undertaken by anyone other than the
respondent company in this action. If these works were being undertaken
by J Gray personally or by some other person or upon some other basis,
then this detail would certainly have been given to me by Mr Gray or some
explanation given, as there would be important ramifications such as
recording and claiming GST and collecting other financial data.” Ms
Benvegnu’s statements refer in particular to Quality Build’s invoices 5, 6
and 7 for $3,950.00, $10,000.00 and $30,000.00 respectively. All 3
invoices were paid in full by Coro Partnership. Invoice 6 included
electrical works at $7,277.89. Invoice 7 charged for a number of items
including “plasterboard” at $15,499.00.
Electrical reimbursement
[6] Mr Machin asserted that Gilletts Electrical Contractors invoice (Gilletts) for
$7,277.89, although included in and paid for as part of invoice 6 was
never credited by Quality Build to Gilletts. This is confirmed by Gilletts
letter of 15 October 2013 produced to the Tribunal. Subsequently this
invoice was paid directly by Coro Partnership to Gilletts as a component
of Gilletts later invoice of 7 March 2013. Mr Gray asserted Gilletts to be
Coro Partnerships contractor. Mr Machin stated he only ever arranged
Gilletts introduction to Mr Gray because it was a local business that could
be more readily accessed locally in the future.
[7] Apart from asserting general compliance with the Tribunal’s orders of 1
November 2013 which in essence required Mr Gray to provide receipts
and invoices for all building materials as well as a reconciliation of building
claims, no further evidence was forthcoming from Mr Gray.
-- 3 of 8 --
4
Gyprock plaster claims
[8] Mr Machin asserted payment of ATP Plastering Service Pty Ltd’s invoice
for $15,500.00 on 3 occasions and seeks reimbursement of two of those
payments at $15,499.00 and $15,500.00.
[9] Quality Build’s invoice number 7 of 23 January 2013 for $30,075.77
identifies “plasterboard - $15,499.00” as one of several components for
payment. This invoice was paid promptly on 24 January 2013.
[10] Quality Build’s invoice number 8 of 12 February 2013 for $30,000.00
identifies “plasterer - $15,500.00” as a component of that invoice. This
invoice was paid promptly in 3 part payments.
[11] Quality Build’s invoice numbers 9 and 10 of 27 February 2013 for
$45,479.01 identifies “plasterer (deleted $200 for extra work by painter
and clean up after all) - $15,300.00”. These two invoices were paid
promptly by the Coro Partnership.
[12] The sum of $15,300.00 was paid by Quality Build to the plasterer on 19
March 2013.
[13] Mr Gray stated that simply because he wrote the plaster’s cost on
invoices that did not mean that he did not require an additional $15,000.00
for plastering work. Mr Gray did not produce any evidence to indicate that
some other person or entity may have been paid for plastering.
Aluminium balustrading
[14] Mr Machin asserted Brockys Fabrication invoice of 18 March 2013 for
$4,793.80 was paid as part of Quality Build’s progress claim invoice
number 17 for $19,626.80 dated 11 April 2013. The handwritten detail
accompanying Quality Build’s invoice includes “Rob Brockhurst handrails -
$4,793.80”. The additions within the detail are mathematically correct. It
was not disputed that invoice 17 was paid in full immediately. Coro
Partnership subsequently paid Brocky Fabrication the same $4,793.80 on
23 April 2013 when it was discovered, according to Mr Machin that Quality
Build had not only failed to pay Brockys Fabrication’s invoice but that it
had been outstanding for some weeks.
[15] Mr Gray suggested that he was told not to pay invoices until the job was
finished but this begs the question why was this cost included in Quality
Build’s invoice number 17 dated 11 April 2013.
Bunnings expenses and recycled bins
[16] Mr Machin requested both these claims be withdrawn for the reason that
because of Quality Build’s non compliance with the Tribunal’s orders of 1
November 2013 it was impossible to properly or meaningfully traverse
these two issues. Mr Gray did not object.
[17] The Tribunal’s orders of 1 November 2013 were as follows:
-- 4 of 8 --
5
1. The respondent provide receipts and invoices for all building
materials and other items for all building and associated works at 16-
Muraban Street, Mooloolaba for the period 1 December 2012 to 18
April 2013, as invoiced to the applicant for building works during this
period. In particular, all invoices, receipts and statements from
Bunnings hardware.
2. The respondent to also provide a written reconciliation from the
respondent of all building claims made to and received from the
applicant for the period 1 December 2012 to 18 April 2013.
3. This is to be provided to the Tribunal the business day prior to the
scheduled hearing.
[18] What Mr Gray provided to Wilson Teis, Chartered Accountants for Coro
Partnership on Monday, 25 November 2013 (a few days prior to hearing)
were bank statements as well as Bunnings statements, invoice book and
some invoices. Wilson Teis provided a statement summarising what had
been provided in terms of the Tribunal’s order of 1 November 2013.
Wilson Teis was able to confirm that the reconciliation included all monies
raised by Quality Build Pty Ltd and all payments received by Quality Build.
Production of receipts and invoices as stated in the orders did not
eventuate. As far as Bunnings was concerned the “transactions for
account” pages 1 – 7 produced to Wilson Teis is simply a chronology of
expenditure by reference to coded items. Invoices and receipts were not
forthcoming. Nor did Quality Build provide any written reconciliation from
it of all building claims made to and received from Coro Partnership. In
the absence of not knowing what was being purchased by Quality Build
from Bunnings and in the absence of any properly detailed reconciliation
of Bunnings purchases it was impossible to take the Bunnings claim any
further.
[19] The same can be said for the recycled bins claim. All that was produced
by Quality Build in terms of Tribunal’s orders of 1 November 2013 were
three invoices from The Recycling Centre. In the context of provision of
bins for rubbish as well as recycling and the free bin(s) arrangement
apparently applicable to recycling all of which was discussed in some
detail at hearing it was impossible to take this claim any further.
[20] The Tribunal confirms the applicant as having been given leave to
withdraw these two claims due to non compliance with the Tribunal’s
orders of 1 November 2013 and on the basis the applicant should not be
precluded from pursuing these two claims in the future.
Witnesses
[21] Mr Gray called Mr Prichard, painting contractor, as a witness. In short it
seems he considered he was owed money by Coro Partnership.
[22] Mr Gray then called his brother Paul Gray, Plumber. He stated that he
was owed a sum of money for materials purchased by him before or other
-- 5 of 8 --
6
plumbers during his absence in the USA. He considered he was owed
money for materials directly by Coro Partnership.
[23] These two witnesses, as it transpired, were irrelevant but were allowed to
be called in the interests of fairness to Mr Gray.
Generally
[24] Cessation of the construction agreement subsisting between the parties
occurred on 18 April 2013. According to Mr Machin it was because Mr
Gray refused to accept that he had to provide substantiation of
expenditures; that people were ringing him direct saying that they had not
been paid. It appeared however that works were fairly much complete in
any event. Mr Machin stated the applicants did not have builder’s
licences; that they always used registered builders; that he went to the
site about once a week to keep abreast of progress.
[25] The summary of Quality Build invoices to the Coro Partnership (exhibit 3)
recording an overpayment of $7,840.99 was not challenged by Mr Gray.
It included Coro Partnership’s refusal to pay Quality Build’s final invoice
number 18 on 18 April 2013.
[26] Mr Gray asserted he had previously handed in receipts to Coro
Partnership posing such questions as “What more do you want from me”
and “What would you like me to do”. Mr Machin denied receiving any
such receipts; that if he had them at hand the present argument may well
have been very much diminished.
Conclusions
[27] Mr Gray failed to comply with the Tribunal’s orders of 1 November 2013.
Those orders were obviously designed to give Mr Gray the opportunity to
properly account for all monies paid to Quality Build which on the face of
it appeared either not properly accounted for or in respect of which there
was an absence of information. In fact the only summary/reconciliation of
any consequence was the material provided by Wilson Teis Chartered
Accountants dated 26 November 2013 on virtually 2 days notice. No
cogent rebuttal on the part of Mr Gray to Coro Partnership’s evidence in
support of its contentions was forthcoming. Exclamations such as “what
more do you want” do not constitute a rebuttal.
[28] Coro Partnership contracted with Quality Build, a registered builder (or at
least thought to be so), to carry out renovations and improvements. The
sums of money paid to Quality Build clearly indicate it to be the builder not
just a foreman/project manager/supervisor/labour hire company. Quality
Build’s onsite container, erection of a construction fence and posting of
safety signs are simple but compelling indicia of its builder’s role.
[29] Coro Partnership paid for Quality Build’s work cover $2,250.00 and
master builders registration and insurance at $1,700.00 for the year
through to 28 December 2013. Mr Gray did not deny payment by Coro
-- 6 of 8 --
7
Partnership to Quality Build. The Tribunal finds that it was never
envisaged that Coro Partnership pay for these particularly for any period
beyond that which was applicable to renovations at Muraban Street. The
sum of $2,633.00 is the portion of prepayment by Coro Partnership that is
repayable to it.
[30] It is clear from Quality Build’s invoice number 6 that Gilletts invoice formed
part of that invoice number 6. The Tribunal accepts Coro Partnership’s
evidence that despite being included in Quality Build’s invoice that Quality
Build never paid Gilletts and that Coro Partnership was subsequently
compelled to pay Gilletts direct. That was an overpayment to Quality
Build of $7,277.89.
[31] It is clear from Quality Build’s invoices numbers 7, 8, (9 and 10) that
plastering was charged for Quality Build on 3 occasions and paid only
once. The sums of $15,499.00 and $15,500.00 are repayable by Quality
Build to Coro Partnership.
[32] It is clear from Quality Build’s invoice number 17 that Brockeys
Fabrication invoice to Quality Build formed part of that invoice number 17.
Quality Build after being paid in full by Coro Partnership did not pay
Brockeys Fabrication. Coro Partnership was compelled at a later date to
pay Brockeys Fabrication the same $4,793.80. There was therefore an
over payment to Quality Build of $4,793.80 repayable to Coro Partnership.
[33] The Bunnings expenses and recycled bins claims were not pursued at
hearing for reasons already given.
[34] The overall summary of Quality Build’s invoices to Coro Partnership
prepared by Wilson Teis Chartered Accountants recording overpayment
of $7,840.99 were not challenged even though it included Coro
Partnership’s refusal to pay Quality Build’s final invoice. That is to say
that Quality Build did not bring any evidence to bear to refute that it had
already been overpaid despite non payment of its final invoice presented
to Coro Partnership.
[35] The claims proved on balance to the Tribunal’s satisfaction are pro rata
refund $2,633.00, electrical reimbursement $7,277.89, two gyprock
plaster claims $15,499.00 and $15,500.00 respectively and aluminium
balustrading at $4,793.80, a total of $45,703.69.
[36] Coro Partnership has capped its claim at $25,000.00 and therefore
forgoes any claim it may have for any balance in excess of $25,000.00
(except of course the Bunnings expenses and recycled bins claims) which
is the monetary limit for claim and interest in the minor civil dispute
jurisdiction.
[37] The Tribunal allows the filing fee of $284.60.
-- 7 of 8 --
8
Order
[38] The respondent pay to the applicants the sum of $25,284.60.
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2014/062