Creevey v Lyons [2014] QCAT 41
CITATION: Creevey v Lyons [2014] QCAT 41
PARTIES: Matthew Creevey
(Applicant)
v
Damien Lyons
(Respondent)
APPLICATION NUMBER: BDL279-13
MATTER TYPE: Building matters
HEARING DATE: 31 January 2014
HEARD AT: Brisbane
DECISION OF: Member Deane
DELIVERED ON: 3 February 2014
DELIVERED AT: Brisbane
ORDERS MADE: 1. Damien Lyons is to pay Matthew Creevey
the sum of $30 by 4.00pm 28 February
2014.
CATCHWORDS: DOMESTIC BUILDING DISPUTE – contract
partly in writing and partly oral – owner builder
claims for variations by omissions – whether the
reasonable costs of variations had been allowed
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Matthew Creevey, in person
RESPONDENT: Damien Lyons, in person
REASONS FOR DECISION
[1] Mr Creevey, as an owner builder, contracted with Mr Lyons to perform
building work on his house. The terms of the contract were partly in writing
and partly oral. Mr Creevey claims that variations by omissions have not
been properly reflected in the amount payable and paid and that a refund
is due.
-- 1 of 4 --
2
[2] It is not disputed that:
a) Mr Creevey provided to Mr Lyons a scope of work1. The scope of
work did not provide for painting;
b) Mr Lyons quoted for work in 2 stages2. The quote is dated 30 July
2013 and the quoted amount for stage 1 was originally $8,800 (incl
GST). In view of the dispute which arose in relation to the price to
be paid for stage 1 the parties agreed not to continue with stage 2;
c) Mr Creevey and Mr Lyons discussed that Mr Creevey intended to
supply some labour and if he was able to source materials at a
cheaper price he would supply those materials and the contract price
would be adjusted to reflect these omissions.
d) No hourly rate to be applied and no mechanism or methodology for
valuing Mr Creevey’s contribution in labour or materials was agreed
at the time that the contract was entered into. This is the source of
the dispute between the parties.
e) Mr Creevey supplied a laminated beam and supplied some labour on
the first day Mr Lyons was on site. There is a dispute as to whether
the first day on site was 7 August 2013 or earlier.
f) Mr Lyons offered to reduce the contract price to $7,700 (incl GST) to
reflect the supply of the beam and some labour. This offer was
made either on 6 August 2013 or before.3 There is a dispute as to
whether the offer was made before or after the first day on site.
g) The parties agreed to vary the scope of work to defer some work to
stage 2. On 6 August 2013 Mr Lyons offered to reduce the contract
price further to $6,600 (incl GST).
h) On 7 August 2013 Mr Creevey paid $6,600.
[3] Mr Creevey gave evidence that in addition to supplying the beam and
some labour on the first day he also supplied framing, which it is
conceded was not used by Mr Lyons and additional labour by an
associate and himself on other days. He contends that further deductions
to the contract price to reflect the omissions should be made and
challenges the value of the reductions offered by Mr Lyons.
[4] Mr Creevey as applicant bears the onus of satisfying the Tribunal that he
is entitled to his claim both as to entitlement and amount. Little evidence
was provided to the Tribunal to support the claim. No evidence of the
actual cost of the beam or the framing was put forward by Mr Creevey.
He concedes he still has the framing and he may yet have a use for it.
1 Appendix 1 to Application for domestic building disputes.
2 Appendix 2 to Application for domestic building disputes.
3 Appendix 5 to Application for domestic building disputes.
-- 2 of 4 --
3
[5] Mr Creevey accepted that Mr Lyons as a professional was likely to
perform tasks more quickly than he and his associate so that the labour
component would not be reflected in an hour for hour reduction but
contends that the hourly rate should reflect Mr Lyons’ charge out rate
because of the resulting saving in his time such work would entail.
[6] There is no evidence as to Mr Lyons’ charge out rate before the Tribunal
because Mr Lyons quoted a fixed price and no agreement was made
about how omissions should be valued. Mr Creevey gave oral evidence
that other carpenters he had used charged at the rate of about $60 per
hour.
[7] No evidence from another builder or carpenter was put forward as to the
reasonable costs of the work performed by Mr Creevey and his associate
or the materials supplied. In short there was no evidence of the
reasonable costs of the variations by omission other than the amounts Mr
Lyons offered during the course of the work.
[8] Mr Creevey did not provide to the Tribunal any evidence as to the
reasonable value of the deferred work. There is therefore no evidence
upon which I am able to find that the reasonable costs of the deferred
work were more than the amount offered by Mr Lyons.
[9] Mr Creevey gave evidence as to the nature of the work he and his
associate performed on other than the first day. He estimated that the
time spent was in the order of 9 man hours.
[10] Mr Lyons disputed that much of the work fell within the scope of works
because painting was not part of the scope of works and most of the work
performed was preparation of surfaces for painting and applying an
undercoat to external timber surfaces. No evidence from a builder or
carpenter was before the Tribunal as to whether it is industry practice to
include such preparation of timber where painting is excluded. There is
therefore no evidence upon which I can rely to find that such work was
within the scope of work where the written scope does not expressly
provide for it. I am not satisfied that it ought to be considered a variation
by omission.
[11] During the hearing Mr Lyons conceded that it is usual for a contractor to
include in its price for the removal of rubbish. Mr Lyons gave evidence
that the refuse tip fees which he would have incurred would have been in
the order of $30.
[12] Mr Creevey gave evidence that:
a) the round trip to the refuse tip is about 1½ hours and that he took
about the same to time to sort the rubbish into recyclable and non-
recyclable waste.
b) he used refuse vouchers so he did not pay tip fees.
-- 3 of 4 --
4
[13] Mr Lyons gave evidence that the cost of the beam would be in the order of
$450 - $500. Mr Lyons is an industry professional. In the absence of
evidence as to its actual cost I accept his evidence. On that basis an
amount of at least $600 had been allowed for labour savings. Mr Lyons
gave oral evidence that Mr Creevey assisted him on the first day on site
for about 3 – 4 hours. He had intended his offsider to assist but the
offsider was unable to work that day.
[14] On the basis of Mr Creevey’s oral evidence that carpenters’ charge about
$60/hour the amount allowed for labour by Mr Lyons is equivalent to at
least 10 hours. Even if all the work performed by Mr Creevey and his
associate is taken into account the evidence is that total man hours is no
more than 13. As stated earlier:
a) Mr Creevey conceded it would not be one for one in relation to
hours; and
b) I am not satisfied that some of the work was within the agreed scope
of work.
[15] There is no evidence before the Tribunal upon which I can rely to find that
the reasonable costs of the variations by omission in relation to labour and
the supply of the beam are more than the amount offered by Mr Lyons.
[16] I find that the value of the variation by omission in relation to fees for
removal of rubbish is $30.
-- 4 of 4 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2014/041