Barry Pitt Constructions Pty Ltd v Smith & Anor [2014] QCAT 25
CITATION: Barry Pitt Constructions Pty Ltd v Smith & Anor
[2014] QCAT 025
PARTIES: Barry Pitt Constructions Pty Ltd
(Applicant)
v
Shane Harold Smith
Agnieszka Smith
(Respondents)
`
APPLICATION NUMBER: BDL037-13
MATTER TYPE: Building matters
HEARING DATE: 13 – 14 November 2013
HEARD AT: Mackay
DECISION OF: Member Dooley
DELIVERED ON: 23 January 2014
DELIVERED AT: Brisbane
ORDERS MADE: 1. Shane Smith and Agnieszka Smith pay to
Barry Pitt Constructions Pty Ltd the sum
of seventy four thousand, four hundred
and thirty one dollars and fifty cents
($74,431.50), by:
4:00pm on 14 February 2014
2. The claim for costs is refused.
CATCHWORDS: BUILDING DISPUTE – failing to follow Plan -
whether damages should be calculated as costs
of rectification or diminution of property‟s value
– whether rectification costs reasonable
Domestic Building Contracts Act 2000
Lida Build Pty Ltd v. Miller (2013) QCATA 139
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Barry Pitt Constructions Pty Ltd represented by
Mark Williams, Counsel instructed by Bill
Cooper & Associates
-- 1 of 9 --
2
RESPONDENTS: Shane Harold Smith
Agnieszka Smith
REASONS FOR DECISION
[1] The Applicant/Builder commenced an Application QCAT on 14 February
2013 claiming the sum of $74,431.50 pursuant to a Domestic Building
Services Authority Contract entered into with the Respondents in the
amount of $220,000.00 for the construction of a house at Lot 10, 94
Bedford Road, Andergrove in the State of Queensland.
[2] The Applicant calculated the claim as follows:-
Contract Price $220,000.00
Plus Contact PC approved items $ 4,431.50
$224,431.50
Less payments $150,000.00
Claim $ 74,431.50
[3] The Applicant‟s add on items of $4,431.50 were calculated as follows:-
a) Tiles and carpets – Contract allowed for a Prime Cost of $2,500.00.
Applicant claims the Respondents chose items costing an extra
$1,500.00
b) Cabinet making – Contract allowed for a Prime Cost of $9,900.00.
Applicant claims Respondents chose items costing an extra
$2,271.50.
c) Provision was not made in the Contract for the installation of air
conditioning. Applicant charged an extra $660.00.
[4] The Respondent filed a Response and Counter claim on 10 April 2013.
The Respondents refute the Applicant‟s claim for $4,431.50 and at the
hearing set out their counter-claim seeking the following:-
a) Jackhammering – seeking a refund of $1,500.00
b) $10,000.00 compensation for the house being sited in a position
some 34cm different to that shown on the plan
c) $10,000.00 compensation for the patio roof height shortfall
d) $20,000.00 compensation for the house eaves width
e) $5,280.00 compensation for scratches, dents and other deficiencies
regarding the roof
f) $500.00 compensation for damage to the water tank
g) $186,870.00 for rectification works to the residence to make the
residence comply with the original plans
-- 2 of 9 --
3
h) compensation for the use of chipped and cracked bricks in the
residence
i) $4,550.00 damages for delay including $500.00 per week loss of rent
[5] At the hearing the following list of issues was drawn up:-
1. Tiles/carpet
2. Cabinet making
3. Air-conditioning provision
4. Water tank
5. Roof
6. Bricks
7. Position of house
8. Patio height and supports
9. Jackhammering
10. Eaves
11. Contract delay and damages
12. Insulation and Vents
13. Rectification costs
(1) Tiles/Carpet
[6] Various Prime Cost items were listed in the Contract. Total tiles were listed
as $2,500.00. Evidence was given at the hearing by the Applicant Mr Pitt
that the Respondents selection of the tiles and carpets totalled $1,500.00
above the allowed P.C. cost. The Applicant stated in evidence that he
contacted the Respondent Mrs Smith prior to her boarding a plane to go
overseas. The Applicant said that he advised her of the extra costs and
she said to go ahead. The Respondents deny this.
(2) Cabinet Making
[7] A Prime Cost amount for cabinetry was allowed in the Contact for an
amount of $9,900.00. The Applicant gave evidence that the actual cost of
the cabinetry chosen by the Respondents was $12,171.50 adding an extra
$2,271.50 to the cost. Benjamin Sharpe, the Cabinet Maker gave
evidence confirming these extra costs. The Respondent in cross
examination put to the Cabinet Maker that the Respondents were only
there to choose colours. The Cabinet Maker denied this and stated that
they were there to design the kitchen. Respondents deny this.
(3) Air Conditioning Provision
[8] Applicant gave evidence that he advised the Respondent that providing for
the proposed air conditioning systems pipe–work was easier and cheaper
at this stage before the bricks were up.
-- 3 of 9 --
4
[9] The Respondent gave evidence that the Applicant said this would not cost
more than $500.00. The Applicant denied this and says that he quoted
$600.00 plus GST.
[10] With respect to items 1-3, the Applicant‟s account of events appears to be
the more reasonable and credible account. In the circumstances I find that
the Respondent is liable for the Applicant‟s additional Contract amount of
$4,431.50.
(4) Water Tank
[11] The Contract provided for the installation of a 5,000 litre Water Tank at a
cost of $1,600.00.
[12] Evidence was given by Neil Kelly at Woodman‟s Mitre 10. His evidence
was that the Tank was new and in an acceptable condition. He stated that
the Tank was in the same condition as other Tanks supplied at that time.
No evidence produced by the Respondent with respect to the alleged
decreased value of the Tank. Respondent is seeking $500.00
compensation but has failed to quantify this amount in any way. In the
circumstances I find that the Respondents claim for $500.00 fails.
(5) Roofing
[13] The Respondent alleges that the Bluescope steel roof has scratches and
rust spots on same. It is the Respondents submission that the roof is
defective and that the installation has invalidated the warranty for the
roofing product.
[14] Evidence was given by Alan Stevens of the Steeline Roofing Centre. Mr
Stevens gave evidence that he had been the Manager for Steeline
Roofing for 9 years. He stated that he carried out roofing inspections and
had observed scuff marks and scrapes on the top of the subject roof. He
stated that the marks were not visible from the ground and that the marks
were normal and did not alter performance.
[15] In cross examination the Respondent asked the witness if he was aware
of rust marks on the roof. The witness said he was and that they were
“squaffe” caused by fragments of steel filings after the screws were put in
place. He said they do not in any way hurt the roof.
[16] The Respondent put into evidence a quote from M.J. Brady to repair the
roof for $5,280.00. This witness was not made available for cross
examination. The quote was very brief and gave no detail or an expert
opinion as to the necessity to carry out repairs.
[17] In the circumstances I dismiss this claim.
(6) Bricks
[18] The Respondent is claiming compensation for badly cracked and chipped
bricks that he alleges were used in the house.
-- 4 of 9 --
5
[19] Evidence was given by Robert Ford who stated that he was the State
Sales Manager for PGH Bricks for 6 years and had been with Boral for 25
years. He gave evidence that the bricks were up to industry standard and
that the imperfections were not noticeable if viewed according to industry
standards ie at a distance of 4-6 metres.
[20] Respondent is claiming $1,000.00 for the bricks but has provided no
explanation of how this amount was calculated or any expert evidence to
support his claim.
(7) Position of the Residence 6.35m from the affronting road rather
than 6.4m as specified in the Plans
[21] Both parties agree upon the position of the house. The Respondent is
claiming $10,000.00 compensation but fails to quantify how this
compensation amount has been calculated or to produce expert evidence
as to the diminution of the property‟s value due to the house being
positioned slightly closer to the front road.
[22] The Respondent also claims that he is unable to access the property‟s
back area and that this affects its value. The Respondent‟s own material
contains a rental valuation from Red Pepper Realty in which the property
is described as “fully fenced with huge double bay shed located at the rear
with side access”.
[23] This defect is at most a defect in name only. There is no evidence of a
resulting decrease in the property‟s value. In the circumstances I dismiss
this claim.
(9) Jackhammering
[24] The Respondent disputes a payment of $2,000.00 for the hire of
Jackhammers during the footing stage. The Respondent in their counter
claim Application states that a bystander on the neighbouring property
stated that the work took approximately 1 hour. The Respondent seeks to
pay $500.00 only for this item.
[25] The Applicant gave evidence that the site was originally identified as a “S”
site. It was later identified as a “P” site (due to the discovery that it was an
uncontrolled fill site). Two previous existing pool walls had to be removed
and further piers had to be put into place. This required the wages of 5
men for 5 hours. Jackhammering, concrete, engineering costs and bobcat
hire was also required. The Applicant requested $2,500.00 plus GST but
reached an agreement to receive $2,000.00 cash from the Respondent.
The Respondent denies this but failed to produce the independent
witnesses referred to in the Respondent‟s Counter-claim.
[26] In the circumstances I dismiss this claim.
(8) Patio Height and Columns
[27] (to be considered together with issues 10, 12 and 13)
-- 5 of 9 --
6
[28] The Respondent is seeking compensation in the sum of $10,000.00 for
the Patio Height at 2.3m (it is marked on the plan at 2.4m) and the
residence was completed with two round columns instead of one square
post as set out in the plans. The Respondent claims that the reduction in
the patio ceiling height now means that it is no longer legally possible to
close in this patio area and use it as a livable space.
[29] In evidence the Applicant stated that he was unaware of the Respondent‟s
intention to close in the patio area in the future. Asked about the two
columns as opposed to the square post on the plan the Applicant states
that that Respondent was frequently on-site and in discussions advised
the builder that he wanted his house the same as other houses around the
corner completed by the Applicant. The Applicant states that he therefore
put in the same columns and made the soffiet level same all the way
through including the patio as he had in the other houses. The Applicant
states that the Respondent Mr Smith was on the site every day and
although the patio was constructed in October/November, did not make
complaint until late November when payment become due.
[30] The Respondent when cross examining the Applicant asked if these
alterations were a variation to the plan and the Applicant stated yes. The
Respondent asked the Applicant if he had drawn up a variation and had it
signed and the Applicant said no.
[31] The Applicant later gave evidence that the alterations did not result in any
claims for extra payment by the Applicant.
(10) Eaves
[32] Evidence was given regarding this issue from the Applicant, the
Respondent and Nathan Galea (a builder for the Respondent who
prepared a quote for the rectification of the house to accord with the
original plans).
[33] The Respondent is seeking the sum of $20,000.00 for a variation of the
width of the eaves to the width shorter than the 600mm required for the
overhang in the plans. The Respondent believes that this will have an
affect on the residences energy rating. The Respondent was unable to
quantify how the sum of $20,000.00 was calculated as the damages being
sought.
[34] The evidence provided, particularly that from the builder Nathan Galea
provided ample opinion that the eaves were shorter in overhang width
than that required by the plan. Michael Plunkett provided evidence for the
Respondent that the energy rating for the residence was 5.5. This was
however disputed by the Applicant.
(12) Insulation and Vents
[35] The Respondent‟s witness Michael Plunkett gave evidence that the
insulation in the roof of the residence was not installed in accordance with
-- 6 of 9 --
7
the code. He believed that there were some shortcomings. Applicant gave
evidence that the house was compliant and has no defects.
[36] Argument also included a discussion with respect to a vent in the kitchen.
Respondent gave evidence that there should have been a vent but that
workmen sheeted over the area. Applicant gave evidence that the house
was approved.
Discussion of issues 8, 10, 12 and 13
[37] To summarise the Respondent is seeking the following amounts of
compensation to be reduced from the Contract Price:-
a) for the patio height and columns $10,000.00
b) Eaves $20,000.00
c) Insulation and Vents – no amount
claimed
Total: $30,000.00
[38] The Respondent has not provided any method for the quantification of
these amounts. In other words as alleged by the Applicant these amounts
were chosen “as if plucked from the air” by the Respondent.
[39] The Respondent has provided an alternative method for compensation,
namely the sum of $186,870.00 plus GST as set out by the Builder Nathan
Galea in evidence. This amount is for the alteration of the house to
conform with the original house plans. It in effect requires the almost total
demolition and rebuilding of the house.
[40] The difficulty in this matter is that the evidence definitely indicates that the
residence does not conform to the original plans in the following areas:-
a) set back of the residence
b) Patio height and columns
c) Eaves
[41] The Applicant may argue that the Patio height and columns were by
verbal agreement with the Respondent and that the house has been
approved. This however does not alter the fact that written variations were
not provided to the Respondent and were not signed by the Respondent in
accordance with the Domestic Building Contracts Act 2000.
[42] I refer to Lida Build Pty Ltd v. Miller (2013) QCATA 139. The question in
this matter related to the roof pitch of the pool house which was to be 29
degrees so that it accorded with the roof pitch of the existing house. The
completed pool house had a pitch of 25 degrees which did not accord with
the plans. In failing to follow the plans it breached its contractual
obligations. In this decision it was considered whether the damages
should be calculated as costs of rectification or diminution of the property‟s
value.
-- 7 of 9 --
8
[43] Evidence was provided that the rectification cost would be $37,638.98.
[44] “The general rule for assessing damages for building work that is not in
conformance with the contact is that the building owner is entitled to the
difference between the contract price of the work and the costs of making
the work conform to the contact. There is of course a qualification to the
general rule that not only must the work undertaken be necessary to
produce conformity but that also it must be a reasonable course to adopt.”
[45] This was the approach adopted in D. Galambos & Son Pty Ltd v. McIntyre.
The correct approach appears to be to look at the value of the property
and to decide what amount, if any, that value would be reduced by the
defective work, where the cost of rectification would be unreasonable.
[46] In this particular matter I found that the cost of rectification, some
$186,870.00 plus GST, would be wholly unreasonable in the
circumstances as a method to compensate the Respondent for the
variations to the building plan.
[47] At the commencement of this matter I indicated my concerns regrading
this particular part of the evidence to the parties. I recognise that the
Respondent was self represented while the Applicant was legally
represented. I did however make my concerns known to the parties in a
very plain manner.
[48] The Respondent was also asked on several occasions during cross
examination to provide a quantification of the damage amounts claimed or
at least some insight into the rationale used to calculate these amounts.
The Respondent provided no insight into this issue at all during evidence.
[49] No expert evidence was provided by the Respondent at all with respect to
the possible diminution of the value of his property due to the Applicant‟s
non compliance with the plans. Also, no expert building evidence was
provided by the Respondent as to the variations affecting the habitability
of the residence or it‟s general compliance with the building code and thus
it‟s general approval.
[50] It is not possible for this Tribunal to make awards of damages without
evidence upon which to base these calculations.
[51] Awards must be transparent and reasonable in all the circumstances. No
evidence of loss has been shown by the Respondent. Direction hearings
were conducted prior to the hearing and both parties were made aware of
the importance of producing their best evidence at the hearing. Matters
cannot be delayed if parties after such a process fail to provide reasonable
evidence to prove their claims.
[52] It is procedurally unfair to the Applicant for the matter not be decided in a
timely fashion.
-- 8 of 9 --
9
[53] In all the circumstances I dismiss the Respondent‟s claim for damages
with respect to issues 8, 10, 12 and 13.
(11) Liquidated damages for Contract delay
[54] The Respondent is claiming liquidated damages for delay in the
completing of the residence in the sum of $4,500.00. The contract
provided for the completion of the residence by end of October. The
Applicant claims the property was completed by 12 December 2012 but
Respondent claims final completion by 11 February 2013.
[55] Either way I must refer to the provision of the Contract for “late
compensation damages”. The words „N/A‟ were inserted here in lieu of a
set amount per day. If there had been nothing stated in this section
damages would have been set at $50.00 per day. However this is not the
case. The parties both signed this Contract agreeing that there would be
no liquidated damages for late completion. In the circumstances I dismiss
this claim.
Summary
[56] In summary I find for the Applicant in the sum of $74,431.50.
[57] I dismiss the Applicant‟s claim for costs on the grounds that the
Respondents were able to prove their case at least in part, even though
this did not result in an award of damages in their favour.
-- 9 of 9 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2014/025