Cyclone Constructions Pty Ltd v Queensland Building and Construction Commission [2014] QCAT 3
CITATION: Cyclone Constructions Pty Ltd v Queensland
Building and Construction Commission [2014]
QCAT 003
PARTIES: Cyclone Constructions Pty Ltd
(Applicant)
v
Queensland Building and Construction
Commission
(Respondent)
APPLICATION NUMBER: GAR084-13
MATTER TYPE: General administrative review matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member Howe
DELIVERED ON: 7 January 2014
DELIVERED AT: Brisbane
ORDERS MADE: 1. The application for a stay of the operation
of the Scope of Works is refused
CATCHWORDS: Application for a stay – insurance claim already
processed and paid – grant of stay without
purpose or utility
Queensland Building and Construction
Commission Act 1991 s 86
Cyclone Constructions Pty Ltd v Queensland
Building Services Authority [2012] QCAT 621
Cyclone Constructions Pty Ltd v Queensland
Building Services Authority [2013] QCAT 484
APPEARANCES and REPRESENTATION (if any):
This matter was heard and determined on the papers pursuant to s 32 of the
Queensland Civil and Administrative Tribunal Act 2009 (QCAT Act).
REASONS FOR DECISION
Background
[1] By order made 12 September 2013 the Tribunal declared that Cyclone
Constructions Pty Ltd had made application for review of the decision of the
-- 1 of 2 --
2
Commission about the amended Scope of Works to be undertaken under the
statutory insurance scheme to rectify defective building work within the time
required by s 86 of the Queensland Building and Construction Commission
Act 1991.1
[2] Prior to that order being made, in March 2012 the Commission had sent a
Notice of Potential Debt to Cyclone advising that a claim under the statutory
insurance scheme had been approved and enclosing a Scope of Works
covering the remedial work.
[3] Cyclone applied to the Tribunal to both review that decision and to extend
time to enable it to make the application for review. Both applications were
dismissed2 on the basis the application was out of time.
[4] Subsequently the Commission concluded more extensive remedial work was
necessary to remedy the defective work than first estimated.
[5] A second Notice of Potential Debt with an amended Scope of Works was
issued. Cyclone applied for a review of the second Scope of Works and also
applied for a stay to the operation of that Scope of Works.
[6] As stated, the Tribunal found on 12 September 2013 that Cyclone had made
application for review of the amended Scope of Works within time.
The matter of the stay application was not dealt with at that time, and that is
the matter presently requiring attention.
[7] The Commission submits the stay should be refused because there is no
utility in making such an order. The claim under the statutory insurance
scheme has already been approved. The rectification work has already been
completed. The rectification work has been paid for.
[8] The Commission accepted the owner’s claim under the statutory insurance
scheme in a timely fashion because amongst other things there was the
potential for further deterioration in the dwelling. There was nothing
objectionable in that. Indeed the owner probably thought it was only
appropriate.
[9] There was unfortunate confusion in Cyclone’s application for review of the
Scope of Works and notice of the review was only given to the Commission
subsequent to acceptance of the owner’s claim under the insurance.
[10] The extent of Cyclone’s liability will appropriately be determined during the
review of the Scope of Works application. There is no utility or sense in
ordering a stay in the operation of the Scope of Works at this late stage3.
[11] The application for a stay should be refused.
1 Cyclone Constructions Pty Ltd v Queensland Building Services Authority [2013] QCAT
484.
2 Cyclone Constructions Pty Ltd v Queensland Building Services Authority [2012] QCAT
621.
3 Russell v Queensland Building Services Authority [2013] QCAT 329.
-- 2 of 2 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2014/003