Claudia Tiller Holdings Pty Ltd v Poulton [2012] QCAT 460
CITATION: Claudia Tiller Holdings Pty Ltd v Poulton
[2012] QCAT 460
PARTIES: Claudia Tiller Holdings Pty Ltd trading as
Luxury Gold Coast Pools
v
Ivana Poulton
APPLICATION NUMBER: MCDO262-12
MATTER TYPE: Other minor civil disputes matters
HEARING DATE: 14 August 2012
HEARD AT: Southport
DECISION OF: Christine Trueman, Adjudicator
DELIVERED ON: 11 September 2012
DELIVERED AT: Southport
ORDERS MADE: 1. That the Respondent pay to the
Applicant the sum of $7,202.00
within 30 days.
CATCHWORDS: Contract for the construction of swimming
pool – withdrawal from contract during
“cooling-off” period – statutory rights to
terminate the contract – requirements and
consequences for withdrawal and liability for
contractor – expenses reasonably incurred
Acts Interpretation Act 1954
Domestic Building Contracts Act 2000
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Mr Lupton Scott on behalf of Luxury Gold
Coast Pools
RESPONDENT: Ms Ivana Poulton
REASONS FOR DECISION
[1] This is a case involving a dispute about the construction of a swimming
pool. Gold Coast Luxury Pools was contracted to construct a swimming
pool at a residential property located at 5 Bexley Place, Helensvale on the
-- 1 of 6 --
2
Gold Coast. The contract price was $24,160.00 and dated 5 August 2011.i
The property was owned by Ms Poulton‟s parents and Ms Poulton entered
into and signed the contract with Gold Coast Luxury Pools on their behalf.
[2] Ms Poulton terminated the contract with Mr Lupton in writing by letter dated
11 August 2011ii where she said she delivered the letter to the premises of
Gold Coast Luxury Pools. The date the letter was served on Luxury Gold
Coast Pools is disputed.
[3] Mr Lupton claims that Ms Poulton owes Luxury Gold Coast Pools the sum
of $7,607.00 plus filing fee and interest. He states that this amount is for
cancellation costs of the contract and includes amounts for outstanding
accounts, consultancy fees, engineering drawings, administration fees and
loss of profit. Mr Scott provided an invoiceiii and evidence of some of the
expenses incurred in preparing for the construction of the pool.
Was the withdrawal from the contract affected during the “cooling off
period”?
[4] The first issue to be determined in this case is whether Ms Poulton
terminated the contract within the “cooling off period”. The General
Conditions of the Contractiv state that the owner may withdraw from the
contract during the cooling off period.v Subject to clause 5.2 the Owner
may withdraw from the Contract within five (5) Business Days after
receiving both a signed copy of the contract and a copy of the Contract
Information Statement approved by the Authority. It is not disputed that the
date of signing the contract was 5 August 2011.
[5] Ms Poulton claims she withdrew from the Contract within the “cooling off
period” and Mr Scott alleges the withdrawal was after the “cooling off
period” had lapsed.
[6] Ms Poulton states that she wrote and delivered the letter terminating the
contract during the “cooling off period” on 11 August 2011. She said she
got “Bev” from Luxury Gold Coast Pools to sign a copy of the letter as
having received the letter. The letter was not dated but signed and
returned to Ms Poulton. Mr Lupton states that “Bev” dated the letter after
Ms Poulton had left and only dated the copy she retained as being received
on 12 August 2011. Mr Scott provided an affidavit sworn by Bev Graham
on 18 May 2012vi deposing that Ms Poulton hand delivered the termination
letter to her at 11.20am on 12 August 2012.
[7] Mr Scott states that in his business he does not work Monday to Friday and
that therefore business days for him include Saturday and Sunday. He
stated that the calculation of days for the “cooling off period‟ should
“include all days of the week being business days” as they were “for his
business”.
-- 2 of 6 --
3
[8] It is clear that a business day means a day that is not a Saturday or
Sunday or a public holiday, special holiday or bank holiday in the place in
which any relevant act is to be or may be done.vii
[9] Ms Poulton signed the contract on Friday 5 August 2011. She stated that
as she withdrew from the contract during the “cooling off period” she is not
required to pay any funds at all to Mr Scott.
[10] It must be determined if two particular criteria were met before turning to
the claim by Mr Scott. They are:
a) Firstly, if Ms Poulton withdrew from the contract during the “cooling
off period;” and
b) Secondly, if the notice to withdraw complied with the Domestic
Building Contracts Act 2000.
These must be considered and determined and if found that both these
criteria were satisfied, then Mr Scott‟s claim will fail.
[11] The actual definition of the time frame for the “cooling off” period is
relevant. The parties disagreed as to when the “cooling off period” expired.
Mr Scott stated that the date when the cooling off period ended was
Thursday 11 August 2011. Ms Poulton agreed with Mr Scott on this point.
Ms Poulton said she served the withdrawal notice on the 11 August 20011.
Mr Scott disagreed and said the withdrawal notice was served on his office
of Luxury Gold Coast Pools on Friday 12 August 2011. He relied upon the
evidence of Bev Graham in that regard.
[12] The issue to consider is the actual time from when the 5 business days
begin and end and that time frame that is referable to the determination of
the actual “cooling off period”.
[13] The period is calculated from when the contract was signed and the
calculation of 5 business days from that date is calculated therefore from
6 August 2011. The period beginning on a given day, act or event that is
provided or allowed for a purpose by an Act and the period is to be
calculated by excluding the day, or the day of the act or event.viii That is
the date of the signing of the contract is excluded from the calculation
period.
[14] It is the case that if the period is expressed to be a specified number of
clear days or at least a specified number of days then it is to exclude the
day on which the purpose is to be fulfilled.ix In this case the period is not
expressed as clear days. In all other cases the period is calculated by
including the day on which the purpose is to be fulfilled.x The period of
cooling off is then calculated at 5 days from the day after the contract was
signed, being the Monday 8 August 2011 and therefore the “cooling off
period” ceases on Friday the 12 August 2011.
-- 3 of 6 --
4
[15] I find that the letter giving notice to terminate the contract was therefore,
served during the relevant “cooling off period”.
Did the notice to withdraw from the contract comply with the Domestic
Building Contracts Act 2000?
[16] The second criteria provide that the obligation on the owner is that the
owner must withdraw from the contract by giving a written notice to the
contractor.xi The general conditions state that the written notice must state
that the owner withdraws from the contract under section 72 of the
Domestic Building Contracts Act 2000.
[17] Ms Poulton must provide in her written notice to withdraw from a regulated
contract under section 72 stating that she withdraws from the contractxii,
leave a withdrawal notice at the address shown as the building contractor's
address in the contractxiii and the withdrawal notice must state the section
of the Act under which the withdrawal is made.xiv
[18] The withdrawal notice prepared, signed and served by Ms Poulton on
Luxury Gold Coast Pools states that the reason for the withdrawal from the
contract is due to “increased site costs since the contract has been signed”.
The withdrawal notice does not refer to the reason of withdrawal being for
reasons under the cooling off period nor any reference to Part 6 section 72
of the Domestic Building Contracts Act 2000.
[19] The withdrawal from the contract does not give notice under the relevant
section of the Domestic Building Contracts Act 2000. Ms Poulton has not
given the appropriate notice to withdraw from the contract during the
cooling off period. As such I find that the contact remains in force.
[20] Ms Poulton claims in the notice to withdraw that she is terminating the
contract due to increased costs. An owner is entitled to terminate a
contract as a statutory right if the contract price increases by 15% or more
after the contract is entered into because of the operation of a cost
escalation.xv
[21] Mr Scott said that he advised Ms Poulton that there would be an increase
in the cost of the pool works but only gave an estimate, the amount was not
reduced to writing and it was estimated to be due to additional costs of
preparing the site due to it being highly reactive and classified as an “H”
site. Mr Scott stated that the engineer had advised him orally of this
information after soil test reports were to hand. Mr Scott stated that he
never actually provided a written quote for the extra costs as after the
phone call with Ms Poulton “all contact ceased and there were no further
discussions” and that the contract was terminated by Ms Poulton before he
could speak to her about the matter or prepare the quote.
[22] Mr Scott states that the contract has not been lawfully terminated and the
owner‟s statutory rights to terminate the contract, which is suggested in Ms
-- 4 of 6 --
5
Poulton‟s notice to terminate, is referable to a right under section 90 of the
Domestic Building Contracts Act 2000.
[23] Ms Poulton states in her withdrawal notice that the reason she is
withdrawing from the contact is due to the increased site costs. She states
that “since the contract has been signed she had been advised that there
were going to be possible price increases over and above the contact
price.” The parties both gave oral evidence on this point. It was
uncontested that Mr Scott did tell Ms Poulton that there would be an
increase in site costs due to the fact that after the contract had been signed
he had been advised, by the engineer, that a soil test had revealed that the
location for the pool was rated a “H” site and highly reactive. It is agreed
this conversation occurred and Ms Poulton stated that after this discussion
with Mr Scott she “became nervous” and worried as she had a “strict
budget” for the pool works and could not afford any additional costs. She
said she got advice from the BSA and a solicitor who advised her to
terminate the contract during the “cooling off period”. However I note that
her notice to withdraw does not mention the reason for withdrawing from
the contract as she is entitled to during the “cooling off period” but relies on
the fact of increased site costs.
[24] Mr Scott states that the increased site costs were permitted in the contract.
I agree with Mr Scott on this point. The contract states in its “General
Conditions” that if the contract price increases by 15% or more after the
contract is entered into the owner may terminate. In this case though the
estimated additional costs of $1,500.00 is approximately 6.5%. As the
additional increase in costs is less than the specified percentage in section
90 of the Domestic Building Contracts Act 2000 the owner does not have a
statutory right to terminate under this provision.
[25] If the notice of withdrawal is defective in that it does not comply with the
Domestic Building Contracts Act 2000 then Mr Scott has an entitlement to
make a claim for costs and expenses.
[26] If the contract has been unlawfully ended by Ms Poulton then Mr Scott may
be entitled to be paid a reasonable amount for the value of the works
carried out under the contract to the date the contract is ended.xvi He will
be not entitled to receive an amount that is more than the amount the
building contractor would have been entitled to receive under the
contract.xvii
[27] Mr Scott has claimed for the sum of $7,607.00 which are for the following:
a) Consultancy fee including 3 site visits & marking out poo $1450.00
b) Engineering Drawings 330.00
c) Administration fees 495.00
d) Loss of profit (20% builders margin) 4832.00
e) Legal expenses 500.00
TOTAL $7607.00
-- 5 of 6 --
6
Findings
[28] The claim for legal expenses and costs are refused in this claim. If Mr
Scott obtained legal advice or assistance in preparing his claim then that is
a matter for him and such costs must be borne by him.
[29] I find that Ms Poulton did not affect service of a notice of withdrawal during
the “cooling off period” on Mr Scott and therefore the contract remained in
operation. The claims for the expenses incurred by Mr Scott in relation to
the pool works appear to be therefore reasonable in all the circumstances.
[30] I find that Ms Poulton then has unlawfully terminated the contract for the
pool works and that Mr Scott is therefore entitled to be paid for the profit he
would have made if the contract had proceeded. I am satisfied that the
calculation of lost profit at the builders margin of 20% is a fair calculation in
all the circumstances.
[31] I find that Ms Poulton must pay costs of fees, expenses and loss of profit in
the sum of $7,107.00 accordingly. I will not allow the claim for interest but
will permit the claim for the filing fee of $95.00.
ORDERS
[1] That the Respondent pay to the Applicant the sum of $7,202.00 within 30
days.
i Exhibit 1.
ii Attachment „b‟.
iii Attachment „a‟.
iv Exhibit 2.
v Masters Builders Pool Building Contract General Conditions 5.1.
vi Exhibit 4.
vii Acts Interpretation Act 1954, section 36.
viii Acts Interpretation Act 1954, section 38 (1).
ix Acts Interpretation Act 1954, section 38(1)(a).
x Acts Interpretation Act 1954, section 38(1)(b).
xi Masters Builders Pool Building Contract General Conditions 5.2.
xii Domestic Buildings Contract Act 2000, section 75(1)(a).
xiii Domestic Buildings Contract Act 2000, section 75(1)(b).
xiv Domestic Buildings Contract Act 2000, section 75(2)(b.
xv Domestic Buildings Contract Act 2000, section 90(1)(a).
xvi Masters Builders Pool Building Contract General Conditions 21.3.
xvii Domestic Buildings Contract Act 2000, section 77(3).
-- 6 of 6 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2012/460