Campbell v Kerry M Ryan Pty Ltd (No 2) [2012] QCAT 422
CITATION: Campbell v Kerry M Ryan Pty Ltd (No 2)
[2012] QCAT 422
PARTIES: Stephen John Campbell
(Applicant)
v
Kerry M Ryan Pty Ltd
(Respondent)
APPLICATION NUMBER: BDL266-10
MATTER TYPE: Building matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Michelle Howard, Acting Senior Member
DELIVERED ON: 7 September 2012
DELIVERED AT: Brisbane
ORDERS MADE: 1. The application for costs is
dismissed.
CATCHWORDS : COSTS – DOMESTIC BUILDING DISPUTE
– where building contractor failed to reduce
variations to the contract to writing as
required by the Domestic Building Contracts
Act 2000 – where applicant homeowner
wholly unsuccessful on claims made against
the contractor
Queensland Building Services Authority Act
1991
Queensland Civil and Administrative
Tribunal Act 2009
Lyons v Dreamstarter Pty Ltd [2011] QCATA
142
APPEARANCES and REPRESENTATION (if any):
This matter was heard and determined on the papers pursuant to s 32 of the
Queensland Civil and Administrative Tribunal Act 2009 (QCAT Act).
-- 1 of 4 --
2
REASONS FOR DECISION
[1] Mr Campbell made a claim against Kerry M Ryan Pty Ltd (referred to as
KMR), a house removalist business for damages arising out of a contract
for the sale and delivery of a removal house.
[2] I heard the matter over two days. Mr Campbell was wholly unsuccessful
on his claim. I dismissed the claim and made directions for the making of
any costs application and submissions.
[3] KMR now seeks its costs on the District Court Scale, on the basis of the
original quantum of the claim of $178,649.83. At hearing, the quantum of
damages sought, for breach of contract was amended to $71,592.55.
The parties’ submissions
[4] In support of its claim, KMR submits that because of complexity, leave
was granted for legal representation. Also, it says that Mr Campbell
should have exhausted his complaints regarding the issues raised in the
proceeding with the Building Services Authority (BSA) and allowed KMR
to complete rectification required, before applying to the Tribunal. It
further submits that the unsuccessful application for security for costs
made by Mr Campbell during the proceedings occasioned unnecessary
costs for KMR. Further, KMR submits that the ‘exceptionally broad’ claim
was without merit noting that it was dismissed entirely, despite Mr
Campbell being allowed to adduce further evidence at the hearing.
[5] It argues that KMR is a family-run, business which does not have
significant funds to spend on litigation and that the costs of the proceeding
have been significant.
[6] Mr Campbell submits that both parties should bear their own costs.
Although he acknowledges that the success of KMR in the proceeding
weighs in favour of an award to it, he submits that other relevant factors
weigh in his favour.
[7] He says that the BSA complaint process is not relevant since the
proceeding turned on the Tribunal’s findings about the contractual
arrangements between the parties and the parties’ rights and obligations
arising from those arrangements. The BSA could not resolve these
issues but the Tribunal could. He argues that the application for security
for costs is not a basis for awarding costs generally in the proceeding. He
points also to KMR’s failure to fully comply with directions to file its
material, necessitating further directions being made and costs being
incurred in this process. Complexity, of itself, he argues does not give
rise to an order for costs.
[8] Mr Campbell further argues that the decision turned largely on questions
of credit, and the Tribunal’s preference of evidence presented by KMR is
merely a determination on the balance of probabilities of the relevant
facts. Therefore, it is incorrect, Mr Campbell argues, to proceed on the
basis that his claim lacked merit. He submits that he did not proceed
against documentary or other independent evidence contradicting his
-- 2 of 4 --
3
claim. Further, he submits that KMR’s failure to reduce the variations to
the contract to writing as a contractor is required to do under the Domestic
Building Contracts Act 2000 (DBC Act) led to a situation where application
to the Tribunal became inevitable.
[9] Lastly, he argues that he is a school bus driver with an ‘average’ income,
leaving him little after expenses, tax and mortgage. Accordingly, an order
for costs would be a severe impost.
Discussion and decision
[10] The Queensland Building Services Authority Act 1991 (QBSA Act) is the
enabling Act under which the Tribunal has jurisdiction for building
disputes. It provides for a broad general discretion to make costs orders
which displaces the usual contra-indication against costs provided for in
the QCAT Act.1 The erosion by legal costs of a party’s success at hearing
has been considered not to be in the interests of justice.2
[11] Mr Campbell’s application was filed on 24 August 2010. Both parties
were granted leave for legal representation from early in the proceedings,
orders having been made on 1 December 2010.
[12] The quantum of Mr Campbell’s claim was originally $178,649.83, although
at hearing it was significantly reduced to $71,592.55. There were a
number of components to his claim relating to the location of the removal
house; the height of the building; the demolition of components of the
existing dwelling on Mr Campbell’s land; the materials used to construct
the gable end walls; damage to external cladding; the roof sheeting and
roof void. All aspects of his claim failed and his application was
dismissed. Numerous factual disputes had to be determined. I did
generally prefer the evidence of KMR and its witnesses where there was
conflict in the evidence given.
[13] In my view, the security of costs application is not of significance in the
current consideration.
[14] If a costs order is not made, the success of KMR in the proceedings will
be eroded to some extent. That said, KMR had responsibility under the
DBC Act to reduce any variations to the written contract to writing. It
failed to do so. At the very least the contest about some aspects of the
claim in respect of which Mr Campbell relied upon oral variations to the
written contract to support his claim would likely have been unnecessary if
KMR had complied with its responsibilities under the DBC Act. I do not
find the argument that Mr Campbell should have exhausted the BSA
complaints process before commencing proceedings compelling in
circumstances where there was dispute about the contractual
arrangements between the parties.
1 QBSA Act, s 77(2)(h); and see discussion in Lyons v Dreamstarter Pty Ltd [2011]
QCATA 142.
2 Tamawood Ltd v Paans [2005] 2 Qd R 101, [33]; Stuart Homes and Renovations v
Denton [2012] QCAT 43.
-- 3 of 4 --
4
[15] On the evidence before me, neither party is well placed to bear the costs
of the failed claim.
[16] In my view, the balance weighs against making a costs order in favour of
KMR, despite the total failure of the claim, in recognition of KMR’s failure
to discharge its obligations under the DBC Act.
[17] I make orders accordingly.
-- 4 of 4 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2012/422