Anderson v Nick Ruhle Homes Pty Ltd and Anor [2012] QCAT 372
CITATION: Anderson v Nick Ruhle Homes Pty Ltd and Anor
[2012] QCAT 372
PARTIES: Mrs Renine Anderson
(Applicant)
v
Nick Ruhle Homes Pty Ltd
(First Respondent)
Ambience Designer Pools & Spas
(Second Respondent)
APPLICATION NUMBER: BDL333-10
MATTER TYPE: Building matters
HEARING DATE: 10 August 2012
HEARD AT: Toowoomba
DECISION OF: Michael Wood, Member
DELIVERED ON: 20 August 2012
DELIVERED AT: Brisbane
ORDERS MADE: 1. That the Second Respondent pay to the
Applicant the sum of $25,200.00;
2. I direct that the parties file evidence and
submissions in relation to the costs of
the proceedings and that the claims for
costs be determined on the papers not
before 7 September 2012.
CATCHWORDS: Building Contract – breach of warranties –
reasonableness of damages claimed
Bellgrove v Eldridge [1954] HCA 36
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Mr John Wiedman, Hede Byrne & Hall Solicitors
RESPONDENT: First Respondent – Mr Chris Neville, Condon
Charles Lawyers
Second Respondent in person
-- 1 of 8 --
2
REASONS FOR DECISION
[1] These proceedings relate to contracts for building work undertaken by the
First and Second Respondents on a property owned by the Applicant.
[2] On the 5 March 2009 the Applicant entered into a Contract with the First
Respondent for the construction of a residential home with a Contract
price including GST of $565,300.00. The Contract was a Housing Industry
of Australia Standard Contract and by a written Variation dated 21 October
2009 it was agreed between the First Respondent and the Applicant that
the Building Contract was varied to include:
“labour and materials to bed and lay paver tiles to spa area and pool and
pergola (including silicone expansion joints)”
The amount of that Variation including GST was a total of $11,640.20.
[3] The Contract between the Applicant and the Second Respondent was a
Pool Building Contract on the Standard Queensland Master Builders
Contract to construct a Concrete Pool or Spa described as a “10 x 5 x 2
metre pool and separate spa including heat pumps, fencing etc” for a total
price of $87,455.00. The Variation to this Contract is the supply of pavers
and the laying of coping tiles.
[4] The Applicant on the suggestion of Mr Todorovic, a Director of the Second
Respondent, attended at the premises of a supplier with which the Second
Respondent dealt where she initially obtained some paver samples and
then ultimately selected pavers including coping tiles.
[5] A client selection sheet dated 20 March 2009 was in evidence before the
Tribunal indicating the selections made and invoices from the Second
Respondent to the Applicant dated 7 October 2009 for $4,620.00 for
services rendered in conjunction with supplying coping tiles and applying
bedding and fixing tiles to bondbeam and further for the supply of pavers
in the sum of $8,539.20. These 2 invoices represented the Variation
agreed to that Contract. The pavers and coping tiles were all
manufactured by a company Stone Directions with the only difference
between the paving tiles and the coping tiles being that the coping tiles
have a rolled edge (Bullnose).
[6] It was common ground between the parties that the Contracts as Varied
required that the Second Respondent supply and install the coping tiles,
approximately 26 lineal meters, to the pool edge and that the balance of
the tiling comprising the fixing of pavers to the existing concrete bedding
was to be undertaken by the First Respondent.
[7] The Second Respondent engaged a Sub-Contractor (Contemporary Tiling
and Paving Pty Ltd) to lay the coping tiles which they did. The Second
Respondent did not actively participate in the laying of those tiles. The
First Respondent engaged its Sub-Contractor (Cheka Tiling Pty Limited) to
lay the pavers in the balance of the area which they then did.
-- 2 of 8 --
3
[8] The evidence was that the tiles were laid some time in the middle of 2009
but prior to the handover of the property by the builder to the owner in
September 2009.
[9] The evidence not challenged was that prior to handover there was an area
of 10 square metres of tile which at the suggestion of the First
Respondent‟s tiling sub-contractor were lifted and replaced as being
defective.
[10] The Applicant‟s evidence was that in November 2009 the Applicant and
her husband noted problems with the pavers in that initially they started to
discolour with a yellowish tinge as opposed to a latte colour. The pavers
were manufactured by a company called Stone Directions and Mr David
Wecker from that company attended the Applicant‟s property on the
18 January 2010 to inspect the pavers. In cross-examination the
Applicant‟s evidence was that Mr Wecker made an offer to replace all of
the tiles on behalf of Stone Directions but that offer was rejected as no
offer was made to the Applicant to meet the labour and other costs of
installing those pavers.
[11] By January 2010 the pavers had started to lift and crack and those that
had not yet lifted or cracked were appearing discoloured and loose. The
Applicant‟s evidence was that by January 2011 there were 30 pavers that
were damaged or starting to lift or crack in the alfresco area and there
were 103 pavers that were lifting or cracking with grout lifting in the pool
area. In the spa area there were 44 damaged pavers which were starting
to lift or crack and of the coping tiles around the pool 14 had started to
crack and lift of the 26 lineal metres. Whilst not all of the pavers had de-
bonded from the concrete surface underneath they no longer presented a
level surface but there was some lipping as between pavers. In addition
the pavers were „drummy‟.
[12] The primary issue to be determined by the Tribunal is the cause of the
„drumminess‟ and failure of the tiles as outlined above.
Causation
[13] The Applicant submits that the problems now evident are either as a result
of the manner of installation of the pavers or the pavers themselves and
that regardless of the findings as to the cause it would amount to a breach
of contractual warranties in the First and/or Second Respondent‟s
Contracts.
[14] The First Respondent submits that the Tribunal would find that the
failures, if any, are as a result of the paver not being fit for the purpose for
which they have been supplied in breach of the Second Respondent‟s
obligations pursuant to its Contract with the Applicant.
[15] The Second Respondent submits that I would find that the failures are as
a result of the pavers not being sealed prior to installation.
-- 3 of 8 --
4
[16] The Tribunal was assisted by evidence from Mr Anthony Robert Inglis. Mr
Inglis was called to give evidence on behalf of the First Respondent. In
addition the First Respondent called evidence from Mr David Maker who
was a Director of the Sub-Contract company who laid the pavers for the
First Respondent. In Mr Maker‟s affidavit an inspection of the pavers in
approximately late 2009 revealed approximately 100 square metres of the
area laid where some of the tiles had de-bonded from the concrete and
had cracked. He did not consider that that de-bonding was as a result of
the process that he undertook. His evidence which was not challenged
was that before commencing the work he consulted the section of the
paver‟s manufacturer‟s website heading “Paver Information and Laying
Guide” and complied with it. His evidence was also that he contacted a
reputable adhesive manufacturer prior to commencing the work for
recommendations as to the adhesive. He followed these
recommendations and instead of using a 10 millimetre notched trowel as
suggested on the manufacturers website used a 15 millimetre notched
trowel.
[17] His evidence was that following the complaint being made he sent
samples of the tiles to the adhesive manufacturer Ardex and their report of
31 March 2012 was in evidence before the Tribunal. The conclusion
expressed by Ardex Australia Pty Ltd is as follows:
“Based on the evidence that we have uncovered, it appears that the Pavers
have de-bonded due to high strains that exceeded the adhesive bond
performance, which have resulted from moisture movement in the Pavers.
Somewhat reduced adhesive coverage and suspect surface property for
the Pavers may have contributed to the reduced bond strength.”
[18] Mr Anthony Inglis was called on behalf of the First Respondent and is a
brick layer and tiler having been involved in that industry for 24 years. The
prime focus of his evidence related to a conversation alleged to have
occurred between himself, Mr Nick Ruhle on behalf of the First
Respondent and Mr Troy Anderson the Applicant‟s husband. As that
conversation is alleged to have occurred with a person other than the
Applicant I need not make any findings in relation to it.
[19] Mr Inglis was independent of any other party to the proceedings and when
asked to comment on the report by Ardex and in particular the following
portion of the Ardex report:
“whilst the adhesive coverage appeared fair, it was less than the tiling
standard requires at 85% and would contribute to a reduce adhesive bond
performance as the imposed strains are concentrated over less adhesive.”
He made the observation that an adhesive coverage of 75%, which is
recorded in the Ardex report, would be sufficient. He indicated that he had
noticed the pavers prior to them being laid and he had noticed that there
was some bowing of the paver, the effect of which was that consistent
adhesive coverage would be difficult to achieve. He indicated that his
understanding was that a 15 millimetre trowel was used which meant that
there would have been adequate adhesive coverage and that it would not
-- 4 of 8 --
5
have been that small difference in adhesive coverage which would have
resulted in the de-bonding of the pavers. It is true to say that only small
sample had been provided for testing.
[20] He was also asked about evidence that with the pavers there was a
printed documentation which included the following statement:
“These Pavers are not suitable for laying in wet and salty areas.”
[21] He felt that the pool area was a wet and salty area and that the pavers
were unsuitable for laying in that area. He gave evidence that he had
some dealing with this particular product some weeks earlier on another
separate site and due to the inconsistency in the product he refused to
continue to lay those pavers.
[22] Other evidence relating to the cause of the lifting of the pavers was from
the parties themselves. Mr Nicholas Ruhle a Director of the First
Respondent gave evidence that he had inspected the pavers upon the
complaint being made but did not keep records of any numbers of pavers
which may have been damaged. He was referred to the Applicant‟s
evidence in relation to the number of pavers which were defective but was
unable to comment in relation to each of them.
[23] He agreed that if pavers were damaged they required replacement but
believes that they could be removed on an individual basis and replaced
with pavers which could be found to match. He also gave evidence that at
the time of the delivery of the pavers he saw a document which was the
same as that seen by Mr Inglis relating to laying the pavers in a wet and
salty area. His evidence was that he and Mr Inglis then had a discussion
with Mr Troy Anderson the Applicant‟s husband who instructed them to lay
the pavers in any event. As I have previously observed this conversation
does not bear any relevance on my findings.
[24] Mr Ruhle gave evidence that he did not believe that the pool area was a
wet or salty area and that they were suitable to be laid in the pool area.
He did not suggest that the pavers should not have been laid to Mr
Anderson but most importantly made no comment to Mrs Anderson. Mr
Ruhle has no prior experience of laying pavers in this manner as in the
past he had used ceramic tiles and has used contractors to do so.
[25] Mr Ruhle gave evidence that in his view the cause of the de-bonding of
the pavers is the pavers themselves and not the manner in which they
were laid. Prior to them being laid he was aware that his sub-contractor
had made enquiries about suitable adhesive and then applying it in
accordance with the manufacturer‟s instructions. It is his view that the
manufacturer is responsible for the problems now faced by the Applicant.
[26] Mr Valdan Todorovic is a Director of the Second Respondent and gave
evidence that in his view the fact the pavers were not sealed meant that
they might bow creating a “drummy sound” but this did not mean that they
would de-bond. His view that the problems which were being faced by the
-- 5 of 8 --
6
Applicant were being faced because they did not seal the pavers before
laying. He says that the Applicant was made aware of the requirement to
seal the pavers as on the client selection sheet from the Pool Tile
Company Pty Ltd it has a box ticked as follows:
“It is recommended that any Bullnose or Paver (with the exception of
Porcelain Tiles) be sealed with a high quality, non slip, penetrating and
breathable sealer – such as that supplied by the Pool Title Company.
Sealing is usually not included by the Pool Builder.”
[27] He gave evidence that the purposes of the sealing is to allow proper
bonding with the substrate.
[28] On this issue the Tribunal had the benefit of a Paver Laying Guide
published by Stone Directions dated February 2008. This document was
attached to an unsworn Statement of David Wecker dated the 27 July
2012. The Tribunal was prepared to accept the unsworn statement on the
basis that, as it was not sworn and he was not available for cross
examination, any weight which would be placed on it would be a question
for the Tribunal. I placed no weight on the statement itself however have
had regard to the Paver Laying Guide as it would appear to be a
document produced by the Company. As part of the Paver Laying Guide
that document includes the following:
“For aesthetic reasons (and to make cleaning easier) it is best to seal
Pavers with a high quality surface or penetrating sealer. Each type has
both pro’s and con’s which should be considered before selecting a sealing
type and brand. Stone Directions Pavers should be sealed when the
Paving is dry and as soon as possible after laying.”
[29] It is clear from the Direction that the sealing is to occur as soon as
possible after laying and that the manufacturers of the pavers consider
that the sealing of the Paver is important for aesthetic reasons rather than
structural reasons. This is at odds with the evidence of Mr Todorovic.
[30] The other witness who gave evidence was a builder who was called by the
Applicant primarily to give evidence on quantum rather than causation. Mr
Steinmuller is a builder with significant experience. He was not asked to
give evidence in chief about the cause of the failure but in cross
examination gave evidence that to properly install the pavers you would
need to contact the manufacturer for a laying guide and use the glue as
recommended. He gave evidence that there are many factors which could
cause de-bonding but that if everything was done properly there shouldn‟t
be a problem.
[31] I am satisfied that on the balance of probabilities the failure of the tiles is
by reason of the pavers themselves in that they were not suitable for the
purposes for which they were supplied that is for use in a wet or highly salt
charged area. It is significant to note that the pool is a salt water pool and
that notwithstanding that different tilers were responsible for undertaking
the affixing of the coping tiles to the balance of the area there is a
-- 6 of 8 --
7
consistent failure across these 2 two areas. The common factor in both of
these situations is the paver itself.
[32] The pavers were supplied by the Second Respondent pursuant to the
Varied Building Contract.
[33] The Contract between the Second Respondent and the Applicant is a
standard Queensland Master Builders Pool Building Contract which
includes builders warranties including the following:
“10.1 (b) Material Supplied by the Builder for use in the works will be good
and suitable for the purpose for which they are to be used and unless
stated otherwise in the Contract will be new;....”
[34] The Variation of the Contract between the Applicant and the Second
Respondent means that the pavers are supplied to the Applicant pursuant
to that Contract including that condition.
[35] By reason of my findings in relation to the cause of the failure of the tiling
generally I am satisfied that the Second Respondent is in breach of the
Contract in that the pavers supplied are not suitable for the purpose for
which they were supplied as they are not fit for use in a wet and salty
area.
Quantum
[36] I must then turn to consider the quantum of the compensation sought.
[37] The Applicant provided a quote prepared by the First Respondent
addressed to her dated the 20 October 2011 which was a quote to remove
and replace external pavers. The amount of this quotation was the sum of
$25,200.00. It is this sum that is sought by the Applicant in her application
and the Applicant submits that it is a reasonable figure for the replacement
of all of the pavers.
[38] The First and Second Respondents gave evidence that in their view the
works could be rectified by removing the improperly bonded pavers and
replacing them on an individual basis and that whilst this may create an
aesthetic interference with the finished area this is not a relevant
consideration and it is this calculation of quantum that should be adopted.
Neither proposed a figure for undertaking that work.
[39] Mr Steinmuller who is a builder and business associate of the Applicant‟s
gave evidence that he had inspected the area the subject of this claim.
He is a Director of Steinmuller Constructions and has 40 years experience
in residential and commercial construction. His evidence in chief as
outlined previously was limited to the rectification work. In his evidence he
indicated that some of the pavers had cracked whilst others were
discoloured.
[40] His evidence was that the only way to rectify such a large area would be
to remove all of the existing pavers and replace them with new pavers.
-- 7 of 8 --
8
He gave evidence that it would not be practical in his view to selectively
remove and replace the pavers for a number of reasons including:
a) The impossibility of matching replacement pavers to the existing
pavers; and
b) The risk of damage to pavers surrounding those to be removed.
[41] He expressed the view that the quote provided by Nick Ruhle Homes of
the 20 October 2011 represented a fair and reasonable estimate of the
costs involved to remove and replace the pavers.
[42] The First Respondent‟s legal representative referred me to
Bellgrove v Eldridge1 in relation to the calculation of damages. He submits
and I accept that the remedial work must be both necessary and
reasonable. He submits that the removal of all of the pavers is not
reasonably necessary.
[43] The evidence is that the total area paved was approximately 285 square
metres plus 26 lineal metres of coping tile. The Applicant‟s affidavit of
evidence was that as at January 2011 there was total of 177 damaged
pavers and that there had been a number more damaged since then. No
final figure as to the extent of the damage was available.
[44] The Applicant entered into a Contract for the construction of a not
insignificant dwelling including the paving of the pool and spa area. It was
the Applicant‟s expectation that she would receive consistent paving effect
throughout the area and in that regard I accept the evidence of Mr
Steinmuller as to the difficulties faced in locating and removing and
replacing only those pavers which were obviously damaged. Further
having regard to my findings that the pavers supplied are not suitable for
the purpose it would be reasonable to replace all of the pavers.
[45] In the circumstances I find that the removal and replacement of all of the
pavers supplied by the Second Respondent is reasonable and that the
appropriate measure of damages having regard to all of the evidence is
the amount of the quotation provided by Nick Ruhle Homes Pty Ltd.
I order that the Second Respondent pay to the Applicant the sum of
$25,200.00.
[46] I dismiss the Application as against the First Respondent.
[47] I direct that the parties file evidence and submissions in relation to the
costs of the proceedings and that the claims for costs be determined on
the papers not before the 7 September 2012.
1 Bellgrove v Eldridge [1954] HCA 36.
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2012/372