ABM Investments (TAS) Pty Ltd v Ceccato [2012] QCAT 243
CITATION: ABM Investments (TAS) Pty Ltd v Ceccato and
Anor [2012] QCAT 243
PARTIES: ABM Investments (TAS) Pty Ltd
v
Mrs Andrea Ceccato
Mr Robert Ceccato
APPLICATION NUMBER: BDL320-10
MATTER TYPE: Building disputes
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Alexander Crawford, Member
DELIVERED ON: 18 June 2012
DELIVERED AT: Brisbane
ORDERS MADE: That the applicant pay the:
1. Respondents’ costs of the application and
counter application to be assessed on the
standard basis, in accordance with the
District Court Scale of Costs and certified
as fit for counsel, by Hickey & Garrett,
Legal Costs Assessors, Level 21, 141
Queen Street, Brisbane; and
2. Costs of such assessment as also so
assessed, within fourteen days of such
assessment.
CATCHWORDS: BUILDING DISPUTE – APPLICATION FOR
COSTS – other factors that affect the discretion
to award costs
Queensland Building Services Authority Act
1991, s 77
Lyons v Dreamstarter Pty Ltd [2012] QCATA 71
Lyons v Dreamstarter Pty Ltd [2011] QCATA 142
Tamawood Ltd v Paans [2005] QCA 111
Foots v Southern Cross Mine Management Pty
Ltd (2007) 234 CLR 52
Latoudis v Casey (1990) 170 CLR 534.
Donald Campbell & Co v Pollak (1927) AC 732
APPEARANCES and REPRESENTATION (if any):
-- 1 of 4 --
2
This matter was heard and determined on the papers pursuant to s 32 of the
Queensland Civil and Administrative Tribunal Act 2009 (QCAT Act).
REASONS FOR DECISION
[1] On 14 March 2012 the Tribunal following the hearing of the building
dispute ordered as follows:
1. The Application is dismissed.
2. The Applicant pay to the Respondent the sum of $207,440.88 on or
before 4:00 pm on the 20 April 2012.
3. The Applicant pay to the Respondent interest on the sum of
$148,083.88 at 10% from 24 August 2010.
4. The Respondent’s submissions, if any, as to costs, to be filed and
served on the Applicant by 4:00 pm on the 20 April 2012.
5. The Applicant’s submissions, if any, as to costs, to be filed and served
on the Respondent’s by 4:00 pm on the 21 May 2012.
6. The issue as to costs to be determined on the papers.
[2] On 18 April 2012 the respondents’ solicitors filed in the Tribunal a copy of
their clients’ submissions as to costs.
[3] No submissions as to costs have been filed by the applicant.
[4] The respondents submit that it is now accepted, in respect of the
determination of building disputes, the Tribunal has an unfettered
jurisdiction to award costs although that jurisdiction must be exercised
judicially.1
[5] The decision regarding costs referred to in the footnote below has been
referred to by the President of the Tribunal Justice Alan Wilson in Lyons v
Dreamstarter Pty Ltd [2012] QCATA 71 where His Honour says as follows:
[6] Under the QCAT Act the usual position is that parties will bear their own
costs: s 100. That provision contains, however, an introductory phrase
(‘Other than as provided under this Act or an enabling Act…’) and, as
the Deputy President identified in her decision in Mr Lyon’s appeal, there
is a relevant enabling Act which applies to the dispute here and contains
a provision about costs: s 77 of the Queensland Building Services
Authority Act 1991 which, in s 77(2)(h) gives the Tribunal a power to
award costs.
[7] As the learned Deputy President also identified, this is what ss 6 and 7
of the QCAT Act refer to as a ‘modifying provision’ and it prevails over
the provision of the QCAT Act which must therefore be read, with any
1 See s 77 of the Queensland Building Services Authority Act 1991 in particular
subsections (1), (2) and (2)(h) and also the decision of Her Honour Judge Kingham in
Lyons v Dreamstarter Pty Ltd [2011] QCATA 142 at [30]-[38] in particular [32]-[34].
-- 2 of 4 --
3
necessary changes, as if the modifying provision was part of the QCAT
Act.
[8] The effect, as the learned Deputy President went on to say, is to give
QCAT a broad general power to award costs in cases caught by these
enabling provisions which, in the case of s 77(2)(h), is to be exercised
‘judicially’2.
[9] In building cases that have elements of complexity, the Queensland
Court of Appeal has suggested that costs awards will not be surprising.3
That case concerned, however, costs provisions in different legislation
governing QCAT’s predecessor Tribunal.
[10] In any event, the power to award costs under the QBSA Act, while
expressed in succinct terms, indicates that the question of costs is to be
addressed in markedly different terms from s 100 of the QCAT Act.
[11] The High Court has said that there is no automatic rule that costs ‘follow
the event’ (i.e., the outcome of the proceeding) or that the unsuccessful
party must compensate the successful one.4 The discretion to award
costs starts with the proposition that it is just and reasonable that a party
who causes another to incur costs should reimburse the other party for
them.5 Otherwise, the factors affecting the discretion will vary in each
case.6
[6] The respondents submit that in the present case the usual and applicable
rule should apply namely that costs follow the event.
[7] They say they have been wholly successful and there are no
countervailing factors against the making of an award to warrant the
Tribunal to make an award of costs in their favour.
[8] Alternatively they say that another basis to make an award of costs is in
the interests of justice, that is if the costs regime in the QCAT Act were to
apply without contrary legislative intent being evident.
[9] The Tribunal considers the appropriate procedure is to award costs
particularly bearing in mind the decision in footnote 1 and the further
exposition by the President in the paragraphs referred to above.
[10] The Tribunal notes that in the last paragraph of the President’s decision he
states the discretion to award costs starts with the proposition that it is just
and reasonable that a party who causes another to incur costs should
reimburse other party for them. Otherwise, the factors affecting the
discretion will vary in each case.
[11] In the present case the elements of the discretion must include the fact
that the respondents have been wholly successful.
2 Lyons v Dreamstarter Pty Ltd [2011] QCATA 142, at para [33]; Latoudis v Casey
(1990) 170 CLR 534 at 557.
3 Tamawood Ltd v Paans [2005] QCA 111, per Keane JA at [32].
4 Foots v Southern Cross Mine Management Pty Ltd (2007) 234 CLR 52 at [26].
5 Latoudis v Casey (1990) 170 CLR 534.
6 Donald Campbell & Co v Pollak (1927) AC 732 at 811-12.
-- 3 of 4 --
4
[12] The additional elements of the discretion, some of which elements appear
in the respondents’ submissions and the Tribunal has taken into account,
include the following:
(a) While the applicant was the progenitor of the litigation it attempted
to abandon it at the outset;
(b) The applicant’s conduct of the hearing caused it to become
protracted such that it had to be adjourned part heard and took
twice the estimated time. For example about one half of the first
day of the hearing was lost due to the applicant having failed to pay
a costs order made against it (due to an earlier trial date having
been aborted through the applicant’s failure to comply with the
Tribunal’s directions) resulting in the applicant’s claim being stayed
until the applicant paid those costs so the hearing could proceed;
(c) The dispute involved complex questions of fact and law.
(d) The respondents, being homeowners, have had to fund the
litigation, from their own resources and not as part of any business
enterprise which was the applicant’s case; and
(e) The respondents had leave to be legally represented, this being
given by the Tribunal on 15 December 2010 after application by
them.
[13] The Tribunal notes that the applicant also chose to be legally represented
until the eve of the hearing.
[14] Accordingly the Tribunal considers the respondents are entitled to an order
for the applicant to pay their costs both of the application and
counterclaim.
[15] The Tribunal accepts the respondents’ submission that the correct
approach is to adopt an assessor, the costs of which should be paid by the
applicant, to determine the respondents’ standard costs by reference to
the District Court scale of costs.
[16] Accordingly the Tribunal makes the following orders.
That the applicant pay the:
1. Respondents’ costs of the application and counter application to be
assessed on the standard basis, in accordance with the District
Court Scale of Costs and certified as fit for counsel, by Hickey &
Garrett, Legal Costs Assessors, Level 21, 141 Queen Street,
Brisbane; and
2. Costs of such assessment as also so assessed, within fourteen
days of such assessment.
-- 4 of 4 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2012/243