Connell Enterprises Pty Ltd v Oakvale Homes Building Group Pty Ltd [2012] QCAT 218
CITATION: Connell Enterprises Pty Ltd v Oakvale Homes
Building Group Pty Ltd [2012] QCAT 218
PARTIES: Connell Enterprises Pty Ltd
(Applicant)
v
Oakvale Homes Building Group Pty Ltd
(Respondent)
APPLICATION NUMBER: BDL208-10
MATTER TYPE: Building matters
HEARING DATE: 30 September 2011
HEARD AT: Maroochydore
DECISION OF: P Hanly, Member
DELIVERED ON: 31 May 2012
DELIVERED AT: Brisbane
ORDERS MADE: 1. The applicant Connell Enterprises Pty Ltd
is to pay the respondent Oakvale Homes
Building Group Pty Ltd the sum of
$1,400.00 by 30 June 2012.
2. Each party is to pay its own costs.
CATCHWORDS: Painting contract – terms of agreement –
defects period – painting in a proper and
workmanlike manner – whether appropriate film
build achieved
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Mr Wayne Connell
RESPONDENT: Mr Warren Hansen
REASONS FOR DECISION
[1] The applicant, Wayne Connell, a director of Connell Enterprises (Qld) Pty
Ltd (Connell Enterprises), lodged an application in the Tribunal on 13 July
2010 seeking an order relieving his company from payment to Oakvale
Homes Building Group Pty Ltd in the sum of $21,891.33. That sum had
been contained in a letter of demand dated 26 May 2010 forwarded by
solicitors acting for Mr Warren Hansen and Oakvale Homes Building
-- 1 of 9 --
2
Group Pty Ltd (Oakvale) in relation to painting rectification work at two
premises owned by Oakvale – 16 Cross Street Gympie and 47 Clematis
Street Gympie.
[2] Connell Enterprises had undertaken painting work for Oakvale at both
premises in November 2008. The Clematis Street work had been
completed in approximately December 2008 and the Cross Street work
had been completed in approximately January 2009.
[3] The agreement entered into between Connell Enterprises and Oakvale
included terms contained in an HIA standard form entitled Period Trade
Contract Conditions, which was forwarded to Oakvale by Connell
Enterprises on 1 April 2008. Connell Enterprises also provided Oakvale
with terms and conditions1. A key term of the contract was that a touch
ups and defects list had to be presented within 30 days of the work being
completed. Once payment for the work was received, Oakvale was taken
to have accepted all work carried out by Connell Enterprises.
[4] Connell Enterprises issued a tax invoice in relation to Cross Street on
3 April 20092 which was paid by Oakvale on 16 April 2009. A tax invoice
was issued in relation to Clematis Street on13 February 20093 which was
paid by Oakvale on 2 March 2009.
[5] Oakvale lodged a response, seeking that the application be dismissed,
and counter-claiming that Connell Enterprises be ordered to pay it
$21,891.33, on the basis that the painting work was not performed in a
proper and workmanlike manner.
[6] The matter was heard on 30 September 2011.
[7] At the commencement of the hearing, Mr Hansen advised that, based on
the expert evidence following testing of paint samples, he had
recalculated his counter-claim at $9,833.00. This figure, based on his
own estimate of the cost of carrying out rectification work, comprised
$1,733.00 for Clematis Street, $900.00 for the interior of Cross Street, and
$7,200.00 for the western wall of Cross Street. The further breakdown of
the $7,200.00 comprised $3,500.00 for signwriting, $2,500.00 for scaffold
hire and $1,200.00 for cleaning and repainting.
[8] The written evidence of Mr Connell4 is summarised as follows:
Connell Enterprises applied the requisite number of coats of paint in
a skilful and tradesman like manner to both subject properties.
The reports from Dulux dated 10 January 2011, 25 January 2011
and 3 March 20115 confirm that all samples of paint taken from
subject properties meet the required film build thickness.
1 Attachment D to Exhibit 1 – statement dated 5 July 2011 by Wayne Connell.
2 Attachment E to Exhibit 1.
3 Attachment F to Exhibit 1.
4 Exhibit 1.
-- 2 of 9 --
3
Mr Hansen is an experienced builder who supervised works on
behalf of Oakvale and raised no objections to the work performed at
the time, or in accordance with the trade terms.
Dec Con’s reports (dated 29 March 20106 and 10 January 20117)
lack credibility due to the testing methods. In addition some of the
alleged defects were so minor that they were missed in the first
report.
The reports from Dulux were based on results obtained from more
accurate methods of testing and should be preferred over the Luxury
Paints report8 and Dec Con’s reports.
[9] Mr Connell also gave evidence of attending at 16 Cross Street after
having received the initial complaint from Mr Hansen in approximately
January 20109. Mr Hansen was noted to be using a solvent to clean the
walls, which was dissolving the paint. Instead Mr Connell recommended
that the walls be cleaned with a soap detergent. Mr Connell advised Mr
Hansen that he (Mr Connell) would arrange for a Dulux representative to
speak with Mr Hansen about cleaning the paintwork.
[10] Subsequently, Mr Adrian Townsend from Dulux Trade attended at the
premises and demonstrated to Mr Hansen that painted areas that were
marked could be satisfactorily cleaned using a magic wipe cleaning
sponge without any damage or deterioration to the paint film.10
[11] Mr Connell obtained quotes11 for rectification work after receiving the first
of Dec Con’s reports. The total cost of rectifying the allegedly defective
work at the subject premises was $1,040.00. This did not include any
component for the western wall at Cross Street.
[12] Mr Connell also did his own calculations for the rectification work, which
totalled $772.00.12 This figure similarly did not include any component for
the western wall at Cross Street.
[13] There were expert reports from two sources related to the testing of paint
samples from the subject premises. There was also an expert who
provided a series of reports concerning visual inspection of alleged
defects at these premises. However, as noted by the Dulux Trade
representative, Mr Townsend, on 16 September 201013 visual inspection
and the use of onsite micrometers to measure paint film build is less
accurate than laboratory inspection using stereo-microscopes calibrated
for dry film build.
5 Attachments M N & R Exhibit 1.
6 Attachment H Exhibit 1.
7 Attachments O & P Exhibit 1.
8 Attachment T Exhibit 1.
9 Paragraph 14 Exhibit 1.
10 Attachment G Exhibit 1.
11 Attachments J & K Exhibit 1.
12 Paragraph 23 Exhibit 1.
13 Attachment L Exhibit 1.
-- 3 of 9 --
4
[14] Mr George Englert of Dec Con Pty Ltd (Dec Con) first inspected the
subject premises at the request of Mr Hansen on 23 March 2010, after
which he prepared two reports, both dated 29 March 2010.14 Both reports
set out items which required rectification. The report on Cross Street did
not make any reference to mould or algal growth on the western wall.
[15] Mr Englert re-inspected the subject premises on 5 January 2011. On this
occasion, Mr Hansen, Mr Connell, a Dulux representative and Mr Weiss
(Mr Connell’s expert) were also present. As before, Mr Englert prepared
two reports, both dated 10 January 2011.15 Each report set out items
which required rectification, and in respect of the western wall at Cross
Street, noted mould on the weatherboards on top of the roof, and also on
the wall itself. In both cases Mr Englert expressed the opinion that the
lack of film build had been a contributing factor to the development of the
mould. He also stated that the raised grain of the sheeting on the wall
was another contributing factor, which, combined with the lack of film
build, trapped dirt which in turn allowed the mould to grow in damp
conditions.
[16] Subsequently, eleven paint samples were taken from various locations at
the subject premises. Mr Connell and Mr Hansen were both present
when these samples were taken. The samples were tested by Dulux for
film build thickness measurements (reports dated 10 January 2011 –
7 samples – and 25 January 2011 – 4 samples)16 and Luxury Paints
(report dated 28 March 2011).17 Prior to the Luxury Paints report, Mr
Hansen requested a more comprehensive report for individual layers,
colours and dry film build from Dulux, which provided a further report
dated 3 March 2011 on all 11 samples.18 None of these samples was
from the western wall at Cross Street.
[17] Mr Connell, noting that there was no sample tested from the western wall,
later took a sample from that wall, and had it tested by Dulux (report dated
29 April 2011).19
[18] At the hearing, Mr Hansen objected to this test result on the western wall
sample. He stated that he did not know when it was taken, nor from
which part of the wall. In response to that objection, Mr Connell gave
evidence that he had contacted “Dianne”, Mr Hansen’s office manager,
and requested that he be permitted to attend at the Cross Street premises
and take a paint sample from the western wall. He further stated that
when he arrived at the premises, Dianne acknowledged his presence,
although she did not accompany him outside when he took the sample.
Mr Connell said that there was a ladder available outside which he used
to climb up and take the sample. He was unable to state definitively on
14 Attachments H & I Exhibit 1.
15 Attachments O & P Exhibit 1.
16 Attachments M & N Exhibit 1.
17 Attachment T Exhibit 1.
18 Attachment R Exhibit 1.
19 Attachment S Exhibit 1.
-- 4 of 9 --
5
which date he had taken the sample, but clearly it was after January 2011
and before 29 April 2011.
[19] Mr Hansen did not request the Tribunal to allow him to call evidence from
Dianne to refute Mr Connell’s testimony. Mr Hansen also did not request
an adjournment to allow him to have the sample tested by Luxury Paints.
He said that the testing was “irrelevant” and challenged the results, but
was unable to say why an independent body should have provided
erroneous results on this occasion, and not on the earlier occasions when
the eleven samples were tested. Mr Hansen concluded that “there was
enough material” before the Tribunal in relation to the western wall to
allow a finding to be made.
[20] Evidence was given by Mr Connell’s employee, Mr Timothy Donovan.20
He confirmed that the work carried out by him at both Clematis Street and
Cross Street had involved the application of one sealer undercoat and two
finish coats on interior areas with puttying carried out after the doors and
frames received the first coat of acrylic sealer and undercoat. This was
stated by Mr Weiss, to whose evidence reference will be made later in
these reasons, to be “industry standard”.21
[21] Mr Donovan also stated that exterior balustrades were sanded and given
one oil based primer undercoat, which was allowed to dry for 24 hours
before two coats of acrylic finish were applied to the balustrades, and also
to the walls.
[22] The first of the experts to give evidence was Mr Caleb Weiss.22 In his
written statement, he acknowledged that there were areas in both
Clematis Street and Cross Street which required touch-up work to be
carried out. He concluded that neither job required a complete repaint.
However in relation to the western wall at Cross Street, he expressed the
opinion that the problems (with mould) had been caused by the weather
and not the lack of film build.
[23] Mr Weiss’ oral evidence focussed predominantly on the western wall at
Cross Street23 (which was variously referred to throughout the hearing as
the south-facing wall, the western wall and the wall with the sign). Mr
Weiss stated that the discolouration on the wall was caused by algal
growth, which is a common problem on a wall that remains damp for a
large part of the day. He explained that the algal growth is promoted by
warmth, sunlight and moisture. This particular wall, being a western wall,
is in shade for the morning, then warms up with the afternoon sun. After
sunset, the warm wall attracts the evening moisture (part of the climatic
conditions prevailing in Gympie), leading to condensation. That moisture
remains throughout the night, and during the following morning, before it
again receives the afternoon sun.
20 Exhibit 3 – statement dated 29 August 2011.
21 Exhibit 4 – statement dated 26 July 2011.
22 Exhibit 4 supra.
23 Exhibit 6 – photograph tendered by Applicant.
-- 5 of 9 --
6
[24] Mr Weiss conceded, in answer to questions from Mr Hansen, that there
might also be mould on the wall, but considered that it was predominantly
algal growth. Mr Weiss distinguished between mould and algal growth by
explaining that algal growth, like a plant, requires sunlight, whereas mould
flourishes in damp, dark conditions, much as a mushroom does. Mr
Weiss did not consider that the thickness of the paint film was material to
the development of algal growth. He stated that even an unpainted
surface can develop algal growth. The painted surface is however easier
to wash. Mr Weiss further stated that in his view, highway grime was not
relevant to the development of the algal growth.
[25] In answering the proposition that the roughness of the surface of the
western wall, as well as lack of film build, would have enhanced the
development of mould (trapping dirt particles which in turn allowed mould
to grow, as opined by Mr Englert), Mr Weiss stated that mould can grow
on a glass surface, which is very smooth. He did not accept Mr Englert’s
view.
[26] Mr Weiss advised that in order to keep the algal growth at bay, a chlorine
based solution should be used to wash the wall, at least once per year.
When questioned as to why the Clematis Street property did not develop
algal growth, Mr Weiss explained that the Cross Street property was in a
slight gully, whereas Clematis Street was more elevated, thus allowing
better air drainage.
[27] Mr Weiss was then asked his views about the costs of rectification for the
various defects detailed in the material. He stated that he had not been
asked to provide a quotation, and had therefore not turned his mind to the
issue at the time of his inspection. When the various figures proposed by
Mr Hansen were put to him, he could do no more than comment that the
figures did not sound “outrageous”.
[28] Further expert testimony was provided by Mr Englert.24 In his written
statement he addressed the painting defects at both Clematis Street and
Cross Street. In relation to the western wall at Cross Street, he said “the
lack of sanding to tops of F.C. weatherboards traps dirt and grime which
supplies food for mould to grow, if the tops were adequately sanded and
sufficient paint was applied to the top of these weatherboards the dirt
would be washed off with normal rainfall.”
[29] In oral evidence, Mr Englert explained that the lack of film build means
that the rough grain in the surface is not filled, and this allows dirt to
attach, which in turn provides “food” for the mould to grow. Mr Englert
stated that algal growth and mould were very similar, however he
conceded that he was a painting expert, not an expert in algal growth and
mould. Mr Englert observed that mould requires dark, damp conditions to
grow. In response to questions about the prevailing weather conditions in
Gympie, he replied that climatic conditions have some impact on mould
growth.
24 Exhibit 5 – statement of George Englert undated.
-- 6 of 9 --
7
[30] Mr Englert expressly refuted the need to wash down painted surfaces
every 12 months, and stated that in his view every 2-3 years would be
adequate. He expected that a wash down with a chlorine based solution
would clean up a wall such as the western wall in question.
[31] Mr Englert was also questioned about his view of the costs calculated by
Mr Hansen for rectification works. He, too, confirmed that he had not
been requested to provide a specific quotation for such works. In relation
to the Clematis Street property (for which Mr Hansen had calculated
$1,733.00, and Mr Coyne had quoted $590.00) Mr Englert estimated
$1,200.00 to $1,400.00, based on 3 days work at $50.00 per hour plus
about $150.00 for materials.
[32] In relation to the interior of Cross Street (for which Mr Hansen had
calculated $900 and Mr Coyne had quoted $450.00), Mr Englert estimated
that it would take more than one day and probably closer to two days, so
that it was likely to be closer to $900.00.
[33] Neither of the experts was able to do any more than say that the figures
calculated by Mr Hansen in relation to the western wall (comprising
scaffold hire, cleaning and repainting and sign writing) seemed
reasonable.
[34] I have considered the technical evidence in relation to Clematis Street and
Cross Street (minus the western wall). With the exception of off white
internal walls in sample 2 (first lot – 34 & 37 microns on two separate
samples within that packet) as described by Luxury Paints, all samples
have the requisite film build thickness applicable to the number of coats
as per the specification, and the evidence given by Mr Donovan. In the
Dulux testing on the white internal walls sample, average film build was
80 microns, approximately 3 coats. All other samples similarly exceed the
requisite 2 coats. I am therefore satisfied that there has been compliance
with the specification, and the contractual agreement between the parties.
[35] In any event, as Mr Connell has conceded at the commencement of the
hearing that there is some minor rectification work required at both
premises excluding the western wall at Cross Street, I shall now address
the quantum of that work.
[36] Mr Connell obtained an independent quotation for the work from Mr
Coyne25. Mr Connell also did his own calculations of how much it should
cost26. Mr Hansen on the other hand did not obtain an independent
quotation, and only did his own calculations, which he did not reduce to
writing. In so doing, he conceded that he is not a painting contractor, but
considers that his experience as a building contractor equips him to make
a fair and reasonable assessment of the costs involved. This may well be
so if Mr Hansen were providing the assessment to a third party, but in this
instance it is for his own potential benefit. On that basis, I do not intend to
25 Attachments J & K Exhibit 1.
26 Pages 3 & 4 Exhibit 1.
-- 7 of 9 --
8
give the same weight to Mr Hansen’s calculations of the costs as I would
to an independent quotation. Similarly, I give lesser weight to Mr
Connell’s calculations than I give to his independent quotation.
[37] I have also considered the comments made by both experts when Mr
Hansen’s figures were put to them. I do not consider the experts’
comments to be anything more than indicative. They were not specifically
requested to quote. Neither of them had seen the premises for many
months by the time of the hearing. Neither of them had any notes to
which they could specifically refer in making their comments. I did not find
that these comments assisted me in my determination, beyond allowing
me to find that Mr Hansen’s figures were not “outrageous”. That of course
is not the test. I am required to make my determination based on what
has been substantiated and shown to be reasonable.
[38] Mr Coyne provided his quotes in October 2010. The subsequent Dec Con
reports of January 2011 noted some further small areas requiring
attention at both properties. I have therefore taken that additional work
into account in my determination.
[39] I am satisfied that the amount which should be allowed for Clematis Street
is $750.00. I am further satisfied that the amount which should be allowed
for Cross Street (excluding the western wall) is $650.00. I have ordered
accordingly.
[40] In making these determinations, I am mindful that the terms of the
agreement required Mr Hansen to notify of any defects within 30 days,
and that following payment of the invoices for the work, he was taken to
have accepted all work.
[41] However, Mr Connell’s concession at the hearing that there was a small
amount of defective work requiring rectification, in my view permits the
findings made.
[42] Turning to the western wall, I am satisfied that the sample taken by Mr
Connell from that wall has been tested by Dulux. In the absence of any
cogent evidence that those results are flawed, I accept them. On that
basis therefore, I reject Mr Hansen’s and Mr Englert’s assertions that the
western wall did not have sufficient film build. I similarly reject their
assertions that the mould and/or algal growth were promoted because of
the lack of film build.
[43] I find Mr Weiss’ evidence of the manner in which algal growth is promoted
on such a wall to be more persuasive than Mr Englert’s version,
particularly as Mr Englert’s version is largely predicated upon the
erroneous view that there is insufficient film build on the wall’s surface.
-- 8 of 9 --
9
[44] I am also satisfied that the mould and/or algal growth could have been
kept at bay by a proper maintenance programme undertaken by Mr
Hansen, as recommended by Dulux27 and confirmed by Mr Weiss.
[45] In relation to the carport28 I accept the evidence of Mr Weiss that the
colourbond sheet metal of this structure would allow it to cool and heat
more quickly, thereby providing a different environment for the potential
development of mould or algal growth when compared to the 8-9mm thick
fibrous cement wall of which the western wall is constructed.
[46] It follows that I am not satisfied that Connell Enterprises should be held
accountable for any rectification or repair work to the western wall at
Cross Street.
27 Attachment G Exhibit 1 Dulux Paint Maintenance Guide Page 5 of 12 Sect 4.3.
28 Exhibit 8 photograph tendered by Mr Hansen.
-- 9 of 9 --