Davana Timber Industries Pty Ltd v Cool [2012] QCAT 201
CITATION: Davana Timber Industries Pty Ltd v Cool [2012]
QCAT 201
PARTIES: Davana Timber Industries Pty Ltd
v
Mr Adrian Cool
APPLICATION NUMBER: REO016-11
MATTER TYPE: Other civil dispute matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Mr Jim Allen, Member
DELIVERED ON: 15 May 2012
DELIVERED AT: Brisbane
ORDERS MADE: 1. The application to reopen matter BDL122-
11 is granted.
2. The Tribunal is to hear and decide all of
the issues in the proceeding again.
CATCHWORDS: REOPENING – where continuing ill-health of
director of Respondent
Queensland Civil and Administrative Tribunal Act
2009, ss 136-140
APPEARANCES and REPRESENTATION (if any):
The matter was heard and determined on the papers pursuant to s 32 (2) of
Queensland Civil and Administrative Tribunal Act 2009 (QCAT Act).
REASONS FOR DECISION
[1] Mr Cool filed an application in the Tribunal against Davana Timber on
13 May 2011 claiming $49,090.80 in respect of damage allegedly caused
by the supply of flooring timber which he claimed was faulty. An amended
application was filed on 20 May 2011. Davana Timber did not file a
response to the application within the 14 days limited by the Tribunal
Rules1.
[2] The Tribunal made directions for the progress of the application on 27 July
2011 giving Davana Timber to the 10 August 2011 to file its response to
the application. If a response was filed the matter was set down for a
1 Rule 44 of the QCAT Rules 2009.
-- 1 of 4 --
2
compulsory conference on 30 August 2011. If no response was filed by
Davana Timber, Mr Cool was directed to file any further statements of
evidence by 24 August 2011 and the application was then to be
determined on the papers.
[3] Davana Timber still had not filed a response to the application by
10 August 2011. A directions hearing was held on 31 August 2011 and
the application was listed for an oral hearing on 28 September 2011. Mr
Cool was directed to file and serve any further evidence to be relied on at
the hearing by 21 September 2011.
[4] Davana Timber did not appear at the hearing on 28 September 2011 and
the Tribunal delivered its decision on 27 October 2011. The order of the
Tribunal was that Davana Timber pay to Mr Cool the sum of $48,070.80
within 21 days.
[5] Davana Timber has now filed an application for the proceedings to be
reopened2. A reopening application is decided based on the submissions
provided by the parties without a hearing and the application may be
granted only if the Tribunal considers a reopening ground exists3.
[6] There are two reopening grounds set out in the QCAT Act:
a) The party did not appear at the hearing of the proceeding and had a
reasonable excuse for not attending the hearing; or
b) The party would suffer a substantial injustice if the proceeding was not
reopened because significant new evidence has arisen and that
evidence was not reasonably available when the proceeding was first
heard4.
[7] The effect of a reopening being granted is that the Tribunal must
determine the issues that must be heard and decided again by way of a
fresh hearing on the merits5. The Tribunal may then confirm, amend or set
aside the Tribunal’s previous final decision and if the decision is set aside
then substitute a new decision6.
[8] The grounds raised by Davana Timber for the reopening application are
that the director of Davana Timber, Mr David Collision had been ill
throughout the year since the floods on 10 January 2011. That he has
been in and out of hospital for both observation and surgery and that it is
believed that he may have picked up a virus when cleaning out his house
immediately following the floods. That Mr Collison has separated from his
partner, who previously worked in the office for his business, and the
business was not able to trade for much of this year. Davana Timbers did
not have any office staff at the time and only had casual labour working in
the mill so there was no-one to attend to matters on behalf of the
company. Mr Collision was not aware of the proceedings being
commenced against the company and did not file any material in
2 Section 138 of the QCAT Act.
3 Section 139 of the QCAT Act.
4 Section 137 of the QCAT Act.
5 Section 140 of the QCAT Act.
6 Section 140 of the QCAT Act.
-- 2 of 4 --
3
response. He received a copy of the reasons for decision and wishes to
reopen the matter to allow Davana Timber to respond in this matter.
[9] Davana Timbers has provided to the Tribunal hospital discharge and
appointment summaries which are said to show that Mr Collision spent
30 days in hospital with 19 separate occasions of admissions and had
44 appointments at hospital during the period. Mr Collison’s admissions to
hospital commenced on 13 April 2011 and included admissions on
31 August 2011 and 28 September 2011. Mr Collison also had an
appointment at hospital on 27 July 2011 which he failed to attend. It is
submitted by Davana Timbers that even when Mr Collison has not been in
hospital, he has been extremely ill, so ill, that his ability to take part in
proceedings has been impaired to such a state that it has rendered him
incapable of doing so.
[10] Davana Timbers submitted in regard to the merits of the claim that Davana
Timbers had never contracted with Mr Cool and the proceedings have
been incorrectly brought against Davana Timbers. Davana Timbers had
only ever contracted with the builder. It is noted that Mr Cool admits that
another person contracted with him and installed the material and so it
would be especially unjust and unfair not to allow a reopening of the matter
so that a response can be prepared. Further that it was the handling and
installation process that was the cause of the issues with the timber and
Davana Timber wishes to place evidence before the Tribunal in this
regard. There should also be afforded an opportunity to refute the
evidence in regard to quantum.
[11] Mr Cool in his response to the reopening application stated that Davana
Timbers was aware of the issues with the timber flooring from September
2010. That he disputed that marital problems and ad hoc hospital visits
could prevent someone from opening their mail. He had not seen any
medical evidence which shows the applicant was permanently
incapacitated during 2011. The dispute process went on all year without a
single response. This was consistent with Mr Collison refusing to answer
Mr Cool’s phone calls during 2010 and early 2011, prior to lodging the
tribunal claim. That Mr Collison had eventually answered the phone when
Mr Cool’s wife rang him from a number, which he did not recognise. And
at that time he sent a text saying that he would come to a resolution, but
no further correspondence was received. He believes that the only reason
why we are hearing from him (Mr Collison) now is because Mr Cool
instigated recovery action through the Magistrates Court and the threat of
arrest has prompted action.
[12] Mr Cool states that the contract for the supply of timber was with him and
the builder arranged the order on his behalf as his agent. When the timber
was delivered it was to Mr Cool at his home and was paid by him directly.
That subsequent to the installation he had discovered that the timber
species was not what he had ordered. He says this is evidence of poor
quality control and attention to detail.
[13] In this case it would appear Mr Collison was in hospital on the day of the
hearing. If Davana Timber had participated in the hearing process up to
that date and the hospitalisation had been an emergency admission and
there was therefore no time to advise the Tribunal of Mr Collison’s inability
-- 3 of 4 --
4
to attend then this would have clearly been a reasonable excuse for not
attending the hearing. Mr Cool has submitted that Mr Collison’s ill health
should not be taken as a reasonable excuse.
[14] The Tribunal is being asked to accept Mr Collison’s overall state of ill-
health during the year as constituting a reasonable excuse for not
attending the hearing. It is clear that Mr Collison had major health issues
which is evidenced by the number of admissions and appointments he had
at hospital during the period of the hearing process. The Tribunal accepts
these as showing that Mr Collison’s state of ill-health during this period
was to such an extent that it totally compromised his ability to participate in
the hearing process and constitutes a reasonable excuse for not attending
the hearing and a ground for reopening the application.
[15] Having found a reopening ground the Tribunal will not give further
consideration to the other grounds raised by Davana Timbers.
[16] The Tribunal is required to decide the issues which must be heard and
decided again. As Davana Timber has not presented any material for the
consideration of the Tribunal then all of the issues in respect of the original
hearing must be heard and decided again.
[17] The application to reopen matter No. BDL122-11 is granted and the
tribunal is to hear and decide all of the issues again.
-- 4 of 4 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2012/201