Bach and Anor v Majestic Pools & Landscape Pty Ltd [2012] QCAT 132
CITATION: Bach and Anor v Majestic Pools &
Landscape Pty Ltd [2012] QCAT 132
PARTIES: Russell Edward Bach
Clare Veryan Bach
v
Majestic Pools & Landscape Pty Ltd
APPLICATION NUMBER: BD243-07
MATTER TYPE: Building matters
HEARING DATE: 18, 19, 20 and 21 April 2011, Directions
given on 2 December 2011
HEARD AT: Brisbane
DECISION OF: Mark Plunkett, Member
DELIVERED ON: 26 March 2012
DELIVERED AT: Brisbane
ORDERS MADE: 1. The Tribunal orders pursuant to s 77
of the Queensland Building Services
Authority Act 1991:
(a) The Applicants pay to the
Respondent the sum of $5,413.73
plus interest at 10% calculated
from 17 November 2006, such sum
to be paid within 30 days;
(b) The Respondent:
(i) pay to the Applicants the
sum of $500 for rectification
for shaving the 40 mm wall
encroachment, such sum to
be paid within 30 days;
(ii) make rectification:
by repairing the control
joint in the west wall;
as set out by Mr Wenck
for the counterfort wall
at the north-western
corner of the swimming
pool as detailed in the
drawings that
accompany the Form 15
-- 1 of 50 --
2
prepared by Leisure
Engineering Pty Ltd;
(c) the Amended Application of the
Applicants and the Amended
Defence of the Respondent are
otherwise dismissed.
2. No order is made as to costs.
CATCHWORDS: Building dispute – domestic pool – breach of
warranty – provisional sum – role of certifier
– demolition – rectification
APPEARANCES and REPRESENTATION:
APPLICANT: Self represented Ms Clare Bach
RESPONDENT: Self represented Mr Andrew Jakovac
REASONS FOR DECISION
Introduction
[1] Russell Edward Bach and Clare Veryan Bach (the Applicants) are home
owners of a residence located at 33 Hipwood Ave, Coorparoo, Brisbane,
Queensland.
[2] Majestic Pools & Landscape Pty Ltd (the Respondent) is a licensed building
contractor (licence no. 44312) under the provisions of the Queensland
Building Services Authority Act 1991 (the QBSA Act) and carries on business
as a pool builder in a full range of projects ranging from simple pool and
coping to complex jobs involving decks, gazebos, retaining walls and other
structures.
[3] On 11 August 2006 the Applicants and the Respondent entered into a
contract for the installation and construction of a domestic swimming pool,
retaining walls and landscaping for the sum of $178,000 at their residence
(the Contract).
[4] The date for practical completion of the Contract was 11 March 2007.
[5] At the end of February 2007, as the project was approaching completion, a
dispute about extra excavation and extra concrete costs in the amount a few
thousand dollars cascaded into a series of other disputes concerning the
engagement of the certifier, the certification process, unsatisfactory
professional conduct of the certifier, the state of the engineering plans,
allegations of defective retaining walls, allegations of unlawful suspension of
work, and breaches of the Building Regulation 2006. The Applicants made
complaints about the Respondent to the Swimming Pool and Spa Association
of Queensland (SPASA), the Queensland Building Services Authority
(QBSA), the Board of Professional Engineers, the Office of Fair Trading and
the Brisbane City Council (BCC).
-- 2 of 50 --
3
[6] By mid-March 2007 the working relationship between the parties deteriorated
and the near completed works came to a standstill.
[7] On 29 May 2007 the Applicants filed a Domestic Building Dispute Application
with the Commercial and Consumer Tribunal (the CCT) claiming damages for
breach of contract, distress and inconvenience and loss of enjoyment
together with costs for experts consulted in the preparation of the claim.
Jurisdiction of QCAT for Building Matters
[8] The CCT has amalgamated into the Queensland Civil and Administrative
Tribunal (QCAT). QCAT hears and decides all matters previously dealt with
by the CCT: s 256 Queensland Civil and Administrative Tribunal Act 2009
(the QCAT Act). Where a matter to which the transitional provisions of the
QCAT Act apply, QCAT has the functions and decision making power that
existed in the CCT: s 217 of the QCAT Act.1
[9] Justice Alan Wilson, President observed in Avenell v Oxygen Pools Pty Ltd &
Anor [2010] QCAT 284:
[9] In its transitional provisions, addressing the disbandment of previous
tribunals and their absorption into QCAT, the QCAT Act distinguishes between
the final decisions of former tribunals, and pending proceedings before them at
the time they ceased to operate.
[10] A pending proceeding, defined in s 245 of the QCAT Act, is an existing
proceeding in the former Tribunal which that Tribunal had not begun to hear, or
had begun to hear but in which it had not started to consider the evidence for
the purpose of making its final decision. Those proceedings are taken to be
proceedings before QCAT, with which it has jurisdiction to deal: s 256.
[10] In accordance with ss 9 and 10 of the QCAT Act, the QCAT has original
jurisdiction, including jurisdiction conferred upon it under an enabling Act.
[11] The enabling Act in the present instance is the QBSA Act. By virtue of s 77 of
the QBSA Act, the QCAT has the power to make orders in an endeavor to
resolve this dispute.2
[12] Relevantly, by s 77 of the QBSA Act it is provided as follows:
“77 Tribunal may decide building dispute
(1) A person involved in a building dispute may apply, as provided under the
QCAT Act, to the tribunal to have the tribunal decide the dispute.
(2) Without limiting the tribunal‟s powers to resolve the dispute, the tribunal
may exercise 1 or more of the following powers--
(a) order the payment of an amount found to be owing by 1 party to
another;
(b) order relief from payment of an amount claimed by 1 party from
another;
(c) award damages, and interest on the damages at the rate, and
calculated in the way, prescribed under a regulation;
(d) order restitution;
1 Smith v Condie [2010] QCAT 365.
2 MSN Shop & Office Fitting Pty Ltd v Cox t/a Gi Gi Beauty Clinic [2010] QCAT 582,
Member Jarro at [2]; Bach v Majestic Pools & Landscapes Pty Ltd [2010] QCAT 581,
Senior Member Kerrie O‟Callaghan at [21].
-- 3 of 50 --
4
(e) declare any misleading, deceptive or otherwise unjust contractual term
to be of no effect, or otherwise vary a contract to avoid injustice;
(f) avoid a policy of insurance under the statutory insurance scheme;
(g) order rectification or completion of defective or incomplete work;
(h) award costs.”
[13] By definition in Schedule 2 and s 4 of the QBSA Act:
“building dispute” means a domestic building dispute;
“building contractor” means a person who carries on a business that consists of
or includes carrying out building work, and includes a subcontractor who carries
out building work for a building contractor;
“domestic building contract” means a domestic building contract under the
Domestic Building Contracts Act 2000;
“domestic building dispute” means
(a) a claim or dispute arising between a building owner and a building
contractor relating to the performance of reviewable domestic work or a
contract for the performance of reviewable domestic work;
(b) a claim or dispute arising between 2 or more building contractors
relating to the performance of reviewable domestic work or a contract
for the performance of reviewable domestic work; or
(c) a claim or dispute in negligence, nuisance or trespass related to the
performance of reviewable domestic work other than a claim for
personal injuries;
“domestic building work” see the Domestic Building Contracts Act 2000,
schedule 2;
“reviewable commercial work” means tribunal work other than reviewable
domestic work;
“reviewable domestic work” means domestic building work under the Domestic
Building Contracts Act 2000, except that for applying section 8(8) of that Act, the
definition excluded building work in that Act is taken not to mean anything
mentioned in paragraph (b), (c) or (d) of the definition.
[14] By s 7 of the Domestic Building Contracts Act 2000 (the DBC Act):
“A domestic building contract” is:
(a) a contract to carry out domestic building work; or
(b) construction management contract under the Queensland Building
Services Authority Act 1991 for the provision of building work services
for domestic building work; or
(c) another contract to manage the carrying out of domestic building work.
[15] By s 8(3) of the DBC Act:
“Domestic building work” includes--
(a) work (associated work) associated with the erection, construction,
removal or resiting of a detached dwelling; and
(b) work (associated work) associated with the renovation, alteration,
extension, improvement or repair of a home
-- 4 of 50 --
5
(4) Without limiting subsection (3), associated work includes--
(a) landscaping; and
(b) paving; and
(c) the erection or construction of a building or fixture associated with the
detached dwelling or home.
Examples of buildings and fixtures for subsection (4)(c)--
retaining structures, driveways, fencing, garages, carports, workshops, swimming
pools and spas
[16] Hence the QCAT has jurisdiction in “building disputes” under s 77 of the
Queensland Building Services Authority Act 19913 which includes disputes
about the construction of retaining structures, fencing, and swimming pools.
[17] The procedure for a proceeding is at the discretion of the QCAT, subject to
this Act, an enabling Act and the rules: s 28(1).
[18] In all proceedings, the QCAT must act fairly and according to the substantial
merits of the case: s 28(2).
[19] By s 28(3) of the QCAT Act in conducting a proceeding, the QCAT:
a) must observe the rules of natural justice; and
b) is not bound by the rules of evidence, or any practices or procedures
applying to courts of record, other than to the extent the tribunal adopts
the rules, practices or procedures; and
c) may inform itself in any way it considers appropriate4; and
d) must act with as little formality and technicality and with as much speed as
the requirements of this Act, an enabling Act or the rules and a proper
consideration of the matters before the tribunal permit; and
e) must ensure, so far as is practicable, that all relevant material is disclosed
to the tribunal to enable it to decide the proceeding with all the relevant
facts.5
[20] The words of s 28 of the QCAT Act must be read in context. In addition to an
obligation to act fairly, it must also promote the consistency of tribunal
decisions (s 3(c)), enhance the consistency of decisions (s 3(d)) and ensure
like cases are treated alike (s 4(d)).
[21] As observed by Member Peta Stilgoe in Clarke v Cascade Pools (Qld) Pty Ltd
[2010] QCAT 323 at [3]:
“The Queensland Civil and Administrative Tribunal Act (“QCAT Act”) intends that
parties conduct their own proceedings in this tribunal. The Act also intends that
proceedings in this tribunal are to be informal and that the tribunal is not bound
by the rules of evidence. Further, the QCAT Act makes it clear that the tribunal
has an inquisitorial function. For these reasons, no member expects a self-
represented party to present a case in the same way as would be expected from
3 French v NPM Group Pty Ltd [2008] QSC 48; Callum Constructions v Anderson
[2011] QCAT 37, Member Ms Forbes at [2]; and respect to the former Tribunal see:
Skaines v Kovac Enterprises Pty Ltd [2006] QSC 120, Fraser Property Developments
Pty Ltd v Sommerfeld & Ors [2004] QSC 363.
4 MR v Adult Guardian and The Public Trustee of Queensland [2011] QCATA 211
Justice Alan Wilson, President, Clare Endicott, Senior Member, Patricia Hanly,
Member.
5 Lyons v Dreamstarters Pty Ltd [2011] QCATA 142.
-- 5 of 50 --
6
a member of the legal profession. There are, however, limits. In the face of
poorly prepared material, the tribunal cannot make assumptions or guess at facts
and events or the meaning or importance of material. The tribunal cannot make
findings of fact where there is no evidence. It cannot award damages if there is
no material that points to the quantum of the damage suffered. Parties must take
responsibility for the preparation of their own case.”
The Pleadings
[22] On 14 January 2010 the Applicants filed an Amended Claim with QCAT for:
a) damages for negligence and breach of contract in an amount to be
quantified;
b) damages for distress and inconvenience and loss of enjoyment in an
amount to be determined;
c) an alternate claim for demolition and replacement of the pool and retaining
walls;
d) costs.
[23] The Amended Claim, relying upon the provisions of the Contract, implied
warranties, provisions of the DBC Act and Building Act 1975, set out the
Applicants‟ grounds under headings as follow:
a) failure in relation to compliance with the engineering drawings;
b) substantial breach in relation to variations;
c) breach of warranty in relation to provisional sum allowance/s;
d) breach of contract in relation to extension of time;
e) breach of contract in relation to time of completion;
f) failure to rectify defects;
g) construction of defective block retaining walls;
h) breaches in relation to provision of engineering drawings;
i) breaches by respondent in relation to engagement of certifier;
j) failure by respondent to notify owners of engagement of certifier;
k) failure by respondent to notify owners of certifier‟s requirement;
l) breach of Building Regulations;
m) unlawful suspension of work by contractor;
n) repeated unlawful entry to Applicant‟s property after termination of the
contract;
o) breach of duty of care owed to the Respondent by the Applicant (sic);
p) loss and damage suffered by the Applicants as a result of the
Respondent‟s breach of contract;
q) orders.
[24] The Applicants‟ case proceeded on the basis that the Respondent:
a) failed to obtain engineering plans prior to construction;
b) failed to carry out construction according to any engineering plans;
c) failed to carry out the works in an appropriate and skilful way, with
reasonable care and skill;
d) carried out defective work which requires:
i) demolition and replacement; or
ii) rectification.
-- 6 of 50 --
7
[25] In final submissions the Applicants sought orders from the Tribunal that the
Respondent pay to the Applicants:
a) the costs of demolition of the entire pool and walls and the cost of building
a replacement estimated to be between $233,525 and $243,891;
b) in the alternative, the cost of rectification of defects and completion of the
pool and wall structure in the amount of $74,231.60;
c) reimbursements for:
i) Completing the contract (filling pool water and pool accessories not
provided $5,105.00
ii) Securing premises (locks) $44.00
iii) Correcting leaks $4,546.00
iv) Excavation, concrete and pool equipment $21,063.00
d) Costs of:
i) expert reports in the amount of $30,390.50
ii) miscellaneous (application fee, copying, parking) $836.00
[26] On 22 March 2010 the Respondent filed an amended Defence denying the
allegations of the Applicant.
[27] The Respondent admitted that the contract comprised:
a) SPASA domestic swimming or spa pool instruction/construction contract
no. C19227;
b) Drawing by Neville Cox labelled “Perspective”, undated (par 4 of Defence
referring to par 3 of the Claim);
c) Appendix A dated 7 August 2006;
d) Appendix B dated 7 August 2006 together with an application for
insurance.
[28] The Respondent acknowledged that the DBA Act provides for warranties to
be implied into all domestic building contracts but denied that it breached
them.
[29] The Respondent asserted that it discharged its obligation to carry out the
works in an appropriate and skilful way, with reasonable care and skill, and in
accordance with the plans and specifications.
[30] The Respondent argued that if there was any breach of obligation or warranty
arising out of the engineering of the footings of walls (which was denied) then
it was the certifier and not the Respondent that was liable.
[31] The Respondent sought an order dismissing the Applicants‟ claim and by way
of a counter claim seek an order that the Applicants pay to the Respondent
the:
a) balance of the excavation and extra concrete costs $2,240.00
b) extra supervision costs $1,623.60
c) the cost of the increase of their claim wall size $1,550.73
d) the cost of the wall assessment report $3,278.00
e) interest on these amounts calculated pursuant to the contract.
The Extra Excavation and Extra Concrete Costs
-- 7 of 50 --
8
[32] A threshold dispute that has vexed this protracted conflict has been the cost
of:
a) excavation above the provisional estimate of $4,000; and
b) extra concrete cost.
[33] Twelve years prior to entering into the Contract, the Applicants had obtained
technical advice on excavation of earth at their residence for a carport and
retaining structures which envisaged the construction of a swimming pool on
the subject site at some stage in the future.
[34] On 14 November 1994 the Applicants had obtained a Soil Test Report from
Soiltest Australia Pty Ltd which revealed the presence of extremely
weathered rock at .8 metre and weathered rock within a depth at 1 metre
below the surface from two test drills conducted at the proposed pool site.
[35] The Applicants say from the outset they were uneasy about entering into the
Contract and were concerned to ensure they were doing business with a
reputable builder. They searched the licence details of the Respondent and
found that there had been no complaints recorded on the web site of the
Building Services Authority against the Respondent. From the outset Mrs
Bach said she was anxious about what would happen if they did not get on
well with the works supervisor for the project.
[36] Before signing the contract the Applicants had active discussions on site with
Mr Neville Cox, a salesperson for the Respondent and Mr John Jakovac, the
Managing Director for the Respondent. Mr Cox stated that it was company
policy to put a margin on top of excavations in excess of $1,000. He stated
that he had written an amount of $4,000 in the Contract as a nominal sum for
excavation, knowing that this figure was provisional only because they were
dealing with an uncertain substrate, although he knew at an indeterminate
depth there may be weathered shale and rock. Mr Jakovac said it was
impossible to ascertain an accurate cost of excavation because at some
unknown level shale turns to more solid rock. Accordingly it was decided to
charge the Applicants for the actual cost below $4,000 or to charge for actual
costs above $4,000 at cost price only.
[37] The Applicants wanted accuracy in the formation of a realistic estimation of
the provisional costs of excavation. They recall offering to locate for Mr Cox
the 1994 soil test report from a nearby room, as other prospective pool
contractors had requested it, but the Applicants say this was declined.
[38] On 11 August 2006 the parties signed the Contract.
[39] The Provisional Sums Schedule (clause 13) set out:
“Standard Dig Allowance” provides for the estimated costs of a standard
excavation to accommodate the structural shell, together with the cost of carting
any excavated material to a suitable „free cost” tip site, located within 5km by
road from the site” in the provisional sum of $4000.00.
[40] A handwritten entry provided:
“Any lessor amount shall be refunded & costs incurred above $4000 will be
invoiced at cost price.”
[41] Under NOTES CONCERNING EXCAVATION:
-- 8 of 50 --
9
“Excavation & Disposal (including re-location of material, or, removal of
overburden) to be carried out by [TICK] machine…..Details of excavating
equipment including trucks: To be determined by Project Manager”.
[42] The Contract also set out ADDITIONAL CHARGES which provided:
“Additional Rates (for items not included in the Contract Price) are to be paid by
the Customer at the Contractor Cost, or as agreed by written Variation to the
Contract, or in accordance with the following rates: Mechanical excavation, incl.:
removal relocation; $80 per M3 (minimum charge $200) Manual excavation, incl.:
removal relocation; $200 per M3 (minimum charge $200) Rock excavation, incl.:
removal relocation; $200 per M3 (minimum charge $200) …..”
[43] The Contract provided that tree removal was to be arranged by the customer
with a side note reading:
“NOTE: MAJESTIC CAN ORGANISE TREE REMOVAL AT COST AS PART OF
THE DIGGING PROCESS.”
[44] For CONTRACTOR‟S MARGIN, the Contract provided:
“For the purpose of Variations, Prime Cost items & Provisional Sums Schedule,
the Contractor‟s Margin is [BLANK SPACE]% (15% unless otherwise stated).”
[45] The Applicants were keen to proceed with the installation of the pool hoping
to enjoy its use by summer and they waived the five (5) day cooling off period.
[46] Things did not get off to a good start, however.
[47] On 7 September 2006 the workmen arrived at the site and waited for the
supervisor to arrive to mark out the pool excavation area. The Applicants
observed that the workers not working on site, and they became concerned
because they were paying for the workers at an hourly rate. They raised this
with the supervisor and the workmen became indignant. That evening the
Applicants installed video cameras over the site with a view to recording the
construction work.
[48] The next morning, the workers complained about the cameras recording them
on site. After they objected and some discussion the Applicants removed the
video surveillance. Mr Bach explained that he felt most uneasy about the
contractors they employed because “I considered that they were not worthy of
my trust.” Both the Applicants stated that they “felt very uncomfortable about
the events proceeding on our property.”
[49] Work commenced. As the diggings got underway the workers hit weathered
rock and eventually hit hard rock. Heavy machinery had to be brought in to
effect the excavation.
[50] Two days later, Mr Jason Jakovac for the Respondent advised the Applicants
that the $4,000.00 nominated provisional sum had been exhausted and that
approximately $10,000.00 may be required for excavation.
[51] The work and cost performed from 6 September 2006 to 18 September 2006
for excavation and extra concrete costs totalling $21,313.15 was forwarded to
the Applicants on 17 October 2006. From this amount the allowance of
$4,000 was deducted. The extra concrete was $5,694.
[52] The excavation cost and the extra concrete costs were hotly disputed and the
trigger for other on-going conflicts that marred the entire project.
-- 9 of 50 --
10
[53] The Applicants say that they were over-charged for excavation costs in
diggings for the pool by the Respondent:
a) for an extra $19,619.15 for excavation; and
b) the Respondent failed to present a document of variation for the additional
costs.
[54] By a letter dated 5 November 2006 the Applicants stated that they were
astounded that an experienced pool company could have under estimated the
cost of the excavation by a factor of five.
[55] By a letter dated 20 November 2006 the Respondent advised that excavation
cost estimates were an impossible science, especially given that rock was
involved.
[56] The Respondent said that the Contract expressly excluded pre-cut, cartage of
top soil, cartage in excess of 5km of the site, tip fees, additional machine and
truck time/supervision costs, and tree removal.
[57] The Applicants obtained their own advice on these amounts and produced
engineering reports that a reasonable estimate for excavation would have
been in the order of $11,000 to $22,000. Mr Brett Mills of Mills Engineering
Pty Ltd considered a proper estimate of cost was $25,203. These estimates
of cost were based on volumetric excavation varying from 233m3 (Mr Mills),
278m3 (Mr Bradtman) and 400m3 (Mr Morgan).
[58] The Respondent observed that this wide disparity in after the event range of
estimates demonstrates the unreasonableness of the Applicant‟s case and
the reasonableness of the Respondent‟s “provisional estimate”.
[59] Further the Respondent pointed out that tree removal was never included in
the provisional sum. The note to the ADDITIONAL CHARGES stated that the
tree removal would be at cost as part of the digging process.
[60] The Respondent submitted that the Applicants‟ experts included items that
are specifically excluded from the $4,000.00 provisional sum and have set out
a comparable analysis chart to demonstrate the unreasonableness of these
post facto estimates.
[61] The Applicants complained that they were over-charged for the laying of
concrete for the pool shell by the Respondent:
a) for an extra $5,694.00 for concrete laid on 23 September 2007 with
$2,774.00 outstanding;
b) and the Respondent failed to present a document of variation for the
additional concrete costs.
[62] The Applicants submitted that:
a) the imposition of both additional amounts was in breach of the warranty in
relation to provisional sum allowances in ss 48, 59 and 61 of the DBC Act;
b) the Applicant should not have to pay these additional sums by reason of
clause 11 of the Contract concerning variations and the provisions of
ss 79, 82 and 83 of the DBC Act.
[63] The Respondent:
-- 10 of 50 --
11
a) submitted that the contact special conditions provide that the excavation
allowance was only an estimate as actual costs which are extremely
difficult to estimate;
b) said actual excavation costs can vary from the initial allowance from
unforeseeable circumstances including:
i) difficulty to extract or dump that material;
ii) type of material being excavated;
iii) distance to tip site;
iv) rejection of material from the tip site;
v) traffic on the day of dumping;
c) observed that the excavation of rock and shale was excluded from the
contract price;
d) denied a breach in relation to the excavations because the extra costs
were provisional sums expressly included in the contract;
e) asserted that excavation and disposal costs were excluded from the
contract and contract price;
f) submitted the provisional cost for excavation was not an unreasonable
estimate giving the expressed inclusions and exclusions contained in the
contract and information available at the time and that excavation of rock
and shale was excluded;
g) rejected the Applicants‟ engineering evidence of the Applicants‟
reasonable estimates, even in hindsight, because they:
i) are widely variable by as much as 45m3;
ii) included excluded items, rocks and trees;
iii) were hypothetical compared to the actual excavation carried out by the
Respondent;
h) denied any breach of s 59 of the DBC Act because the provisional sum
was reasonable in the circumstances;
i) said additional work and concrete was required because of cavities
created by rock fallout and the nature of the rock also incurring extra costs
pumping, shaping, spraying, extra steel, extra steel fixing costs, drilling
into rock, supply and installing extra gravel and supervision at a rate of
$390m3 for materials and labour;
j) observed that the extra-costs for excavation and concrete:
are the costs actually incurred;
are not a variation because a provisional sum has been given for
the cost in the contract as being provisional;
not governed by Clause 11 of the general conditions of the contract
or ss 79, 82 and 83 of DBC Act.
[64] The work was required to be carried out in accordance with relevant laws and
legal requirements including the Building Act 1973 and s 43 of the DBC Act.
[65] The works were also required to be carried out by the Respondent in an
appropriate and skilful way with reasonable care and skill: s 44.
[66] By s 48(2) of the DBC Act the Respondent warranted that provisional sums
were calculated with reasonable care and skill, having regard to all the
information reasonably available when the contract is entered into (including
information about the nature and location of the building site).
-- 11 of 50 --
12
[67] A provisional sum, for a domestic building contract, is an amount that is an
estimate of the cost of providing particular contracted services: s 14(1) of the
DBC Act. However, this requirement applies only to contracted services for
which the building contractor, after making all reasonable enquiries, cannot
state a definite amount when the contract is entered into: s 14(2) of the DBC
Act.
[68] The Respondent could not enter into a regulated contract stating a provisional
sum that was less than the reasonable cost to providing the contracted
services to which the sum relates: s 59(1)(b).
[69] In deciding what is a reasonable cost, regard must be had to the information
the building contractor had, or reasonably should have had, when the contract
was entered into and the nature and location of the building site: s 59(3).
[70] The Respondent was not permitted to enter into a regulated contract
providing for a prime cost item or provisional sum unless the contract
contained a separate schedule stating required details for each item or sum:
s 61(1).
[71] The Tribunal may on an application by the building owner, reduce the building
owner‟s liability, for the item or contracted services to which the stated
amount or sum relates, to the extent the tribunal considers appropriate:
s 60(3).
[72] By Clause 1(1): “The Contractor must carry out the Works and accordance
with the Contract, and must, unless the Contract provides otherwise, supply
everything necessary for the carrying out of the Works”.
[73] By Clause 1(3) “the following statutory warranties are incorporated in the
Contract under Part IV of the Act:
a) The Contractor will carry out the Works:
i) In an appropriate and skilful way;
ii) With reasonable care and skill;
iii) In accordance with the plans and specifications and any other contract
document described in the Contract Schedule: and
iv) In accordance with all relevant laws and legal requirements. (Clause
3(a)).”
[74] By Clause 1(3)(c) “prime costs items and provisional sums have been
calculated with reasonable care and skill.”
[75] By the terms of the Contract the Respondent undertook an obligation to carry
out the works in an appropriate and skilful way, with reasonable care and skill,
and in accordance with the plans and specifications: Clause 1.3(a).
[76] By Clause 13(1) the Contract Price includes the items of work shown in the
Provisional Sums Schedule, which sets out the Contractor‟s allowance of the
cost of carrying out each item of work which the Contractor cannot give a
definite price.
[77] The Contractor may, at is discretion, allow the Customer a reasonable
opportunity, upon the given of adequate notice, to be present at the site
during the performance of any work included as a Provisional Sum in order to
verify the actual cost of work: Clause 13(2).
-- 12 of 50 --
13
[78] If the actual cost for a Provisional Sum is greater than the amount allowed,
the excess amount, together with the Contractor‟s margin on the excess
amount is to be added to the Contract Price: Clause 13(4).
[79] Unless otherwise agreed in accordance in writing by the parties, any
adjustments to the Contract Price in accordance with this clause are to be
claimed or allowed in the next progress payment: Clause 13(5).
[80] The Contractor must provide a copy of any relevant invoice; receipt or other
document evincing the cost of the work at the time payment is requested:
Clause 13(6).
[81] The Schedule to the Contract sets out:
“PROVISIONAL SUMS
”Standard Dig Allowance” provides for the estimated cost of a standard
excavation to accommodated the structural shell, together with the cost of any
carting any excavated material to a suitable “free cost” tip site, located within
5Km by road from the site $4000
Any lesser amount shall be refunded & costs incurred above $4000 will be
invoice at cost price.
Total Provision Cost Amounts $4000.”
[82] The Schedule to the Contract sets out:
“SPECIAL CONDITIONS
SPECIAL CONDITIONS & CONTRACTUAL EXPLANATIONS
EXCAVATIONS: As per page 8 of the Contract, your evacuation allowance is
only an estimate, and factual costs are extremely difficult to estimate. Therefore,
factual costs may or may not reflect the actual costs incurred when the work is
complete. Actual excavation costs can vary from the initial allowance for may
unforeseeable reasons, including but not limited to distance to tip site, rejection
of material at the tip site, traffic on the day, type of material being evacuated and
difficulty to extract or dump that material, access or ease or operation around the
dig site or other travel areas, etc. In summary, all subsurface material and
consequential costs associated with it are the complete responsibility of the
customer, and if factual costs arrive lower than the allowance, then Majestic will
forward a refund for the difference.”
[83] The Schedule to the Contract sets out:
“EXCLUDED ITEMS
Unless stated elsewhere in the Contract, the following items are excluded from
the Contract and Contract Price:
…… excavation of rock, shale or other unforeseeable items and/or disposal of
additional overburden, disposal or handling of spoil, levelling or spreading of
excavated material, pumping to remove water, formwork and back filling below
existing ground level, shoring or retaining walls or other means of stabilisation to
ensure stability or overburden, excavation and/or to protect adjacent buildings,
pierings or other special structural requirements below existing ground level…”
[84] A variation, of a domestic building contract, is an addition of domestic building
work to the subject work or an omission from the subject work: s 16(1) of the
DBC Act. For a cost plus contract, an addition or omission is a variation only
if the addition or omission is not reasonably contemplated by the contract:
s 16(2) of the DBC Act.
-- 13 of 50 --
14
[85] Any variation of the contract agreed to between the building contractor and
building owner is put into written form within the shortest practicable time:
s 79(1).
[86] As soon as practicable after an appropriate variation document is made, the
building contractor must sign the document and take all reasonable steps to
try to ensure the document is signed by the building owner: s 82.
[87] As soon as practicable (but within five business days) after a variation of a
regulated contract is agreed to between the building contractor and building
owner, the building contractor must give the building owner a readily legible
signed copy of an appropriate variation document for the variation: s 83.
[88] Section 84 of the DBCA provides that a building contractor may only recover
an amount for a variation if, relevantly, sections 79 and 80 of the Act have
been complied with or with the Tribunal‟s approval, given on application by
the building contractor.
[89] Section 84(4) of the DBCA provides that the Tribunal may approve recovery
of an amount by a building contractor for a variation only if the Tribunal is
satisfied that:
a) there are exceptional circumstances to warrant the conferring of an
entitlement on the building contractor for recovery of an amount for the
variation; or
b) the building contractor would suffer unreasonable hardship by the
requirement for a written variation; and
c) it would not be unfair to the building owner for the building contractor to
recover an amount.
[90] Clause 11 makes provision for variations and provided that the work to be
done, or the materials used, under the Contract may be varied:
a) by agreement between the parties;
b) where there is a Latent Condition, in order to overcome the Latent
Condition; or
c) where due to requirement of a private certifier, statute, local authority or
other body having jurisdiction of the carrying out of the Works, in order to
comply with the requirement.
[91] Clause 11(13) sets out the procedures for variation. It provides:
“Before commencing any work comprising of variation, the Contractor must
ensure that the details of the variation are put in writing in a Variation document
signed by both parties, and initialled as necessary by the Customer.”
[92] Clause 11(14) the Variation document must:
a) describe the variation of the work to be carried out;
b) if the variation was requested by the Contractor, state the reason for the
variation;
c) state the Contractor‟s estimate of any delays;
d) state the change to the Contract Price involved, or how the price of the
variation will be calculated; and
e) state when any adjustment to the Contract Price is to be claimed or
allowed (which must be initialled by the Customer).
-- 14 of 50 --
15
[93] By Clause 11(16) where appropriate, the price or the variation is to be
calculated in accordance with the additional dates set out in the Schedule.
[94] By Clause 11(17) any claim for an extension of time due to a variation must
be made in accordance with Clause 9.
[95] Before commencing any work comprising a variation, the plaintiff had to
ensure that the details of the variation were put in writing in a variation
document signed by both parties and initialled as necessary by the applicant:
Clause 11(13).
[96] By setting a provisional cost in a contract the parties do not try to price the
works accurately with any precision at all. They simply include a sum as their
best guess only.
[97] By definition there is an inherent risk in using provisional sums. The cost of
the proposed works cannot, and is not, exactly determined, so the costs of
the works are including as a provisional sum. As the works proceed, the
provisional sums are to be replaced with the actual costs of the work done,
where the final cost may go up or down.
[98] Plainly, by the terms of agreement, the parties agreed that a provisional sum
would eventually, after the excavation, be replaced by the actual cost of the
work.
[99] In the result, the Respondent would be entitled to a refund of the actual
cost, less than the provisional cost, or the contractor is entitled to the
provisional sum, plus the actual cost involved.
[100] The fact of the matter is that the pool cavity had to be excavated as a first
step in the project. The provisional cost nominated was no more than an
estimate as the actual cost which could not be calculated until the actual
digging works were completed. The diggings encountered rock which
incurred labour and other costs beyond that originally nominated as a
provisional cost of $4,000.
[101] The actual costs of excavation incurred were accurate and reasonable as
demonstrated by the after the event cost estimates provided by the
engineers for the Applicants.
[102] The terms of the Contract expressly set out that the evacuation allowance
was only an estimate because factual costs are extremely difficult to
estimate.
[103] The special conditions warned that, factual costs may or may not reflect the
actual costs incurred when the work is complete and that actual excavation
costs can vary from the initial allowance for many unforeseeable reasons.
[104] The Contract expressly excluded certain items from the Contract and
Contract Price which included excavation of rock, shale or other
unforeseeable items.
[105] The Tribunal finds given these exclusions and special conditions the $4,000
provisional sum was reasonable.
[106] However, even if the Contract did not contain such special conditions and
exclusions, the Tribunal finds the $4,000 provisional sum was arrived at
-- 15 of 50 --
16
with sufficient care and skill based on reasonable inquiry as to reasonably
estimate the likely cost in all of the circumstances.
[107] On the site before entering into the Contract the parties engaged in mutual
discussions about estimating the provisional sum. If Mr Cox did decline the
Applicants‟ offer to collect it from the nearby room and/or if the Applicants
chose not to collect it and put it under his nose, the provisional estimate
was still reasonable as the exact sum was unknowable at the time.
[108] The Applicants, Mr Cox and Mr Jakovac knew the site would have
contained shale and that at some stage it would or may turn in to variable
stages of weathered rock, to extremely weather rock and to hard rock. The
soil test report would have confirmed this obvious fact and made little
difference to the reasonableness of the provisional estimate. Given the
limited nature of 1994 testing for the soil test report (two drills on a slope),
having the report before the Respondent would not have altered the
reasonableness of the estimate. The Tribunal is not satisfied of the
Applicants‟ assertion that they would not have entered into the Contract had
they known the ultimate cost of the excavation. Within months they were
prepared to pay the increased costs of tiles of a substantial amount and
showed themselves prepared to engage engineers at some cost to check
on the Applicants.
[109] The pool site was on a slope which was required to be cut into in order to
create a flat base foundation. No contour survey had been carried out. No
one was able to prepare a final price for the earthworks needed to provide a
level site for the pool. By its nature the provisional sum was a nominated
amount of money, where the exact scope and cost of specific work could
not be determined at the start of the contract, because it involved the
removal of an unknowable amount of weathered shale and rock.
[110] On 21 March 2007 the Applicant engaged Mr Robert Morgan, an engineer
of Morgan Consulting Engineers to seek advice about the engineering
drawings and the costs charged for excavation and concrete.
[111] By letter dated 16 May 2007 Mr Morgan wrote to the Applicants advising
that after examining the photographs of the rock encountered in the
excavation of the structural shell, from a civil contract view point, the extra
costs of rock excavation ie. the use of super breakers or rock cutters, was a
legitimate extra. As to quantum Mr Morgan carried out an estimate of the
quantities of materials to be excavated for the pool. The bulk excavation to
provide a level platform was 250m³ and to excavate the pool was 150m³.
Mr Morgan said: “Using a current civil engineering rate for excavation to
spoil of $25 per cubic metre, this equates to the pool excavation of only
$3,750.00. The figures close to the provisional cost item allowed for the
pool excavation only of $4,000.00.”
[112] The Tribunal finds the Respondent did not breach any obligation under the
Contract or statute in estimating the provisional sum for excavation.
[113] The Applicants were liable to make payment for the full cost of the
excavation, equivocated in doing so, and the amount remains outstanding.
[114] As a result of the cutting into hard rock, rock roll out occurred around the
cavity as it was being excavated.
-- 16 of 50 --
17
[115] In order to construct the pool shell, the rock roll out space was required to
be filled with more concrete and steel than originally estimated. While this
does not appear to be the cost of a building pool wall it is a proper cost for
the bulk filling of voids created by over excavation of rock.
[116] The Respondent claimed 30m³ of concrete was allowed for in its costing
and sought to claim the cost of an extra 12m³ of concrete. This was for raw
bulk concrete, pumping/spraying/shaping of concrete, extra steel, extra
labour for steel-work associated with cavities, extra supervision and extra
gravel for the pool base.
[117] The cost price was a raw cubic metres to determine a standard cost price
formula of $390/m3 for materials and labour compared to a costs per
invoice using rounded m3 amounts, costs per invoices using accurate cubic
metre amounts.
[118] When Mr Bach received the invoices for the extra concrete on 27 February
2007, he examined them in detail, questioning items such as a loading for
Saturday work, extra cutting, an unknown delivery address for steel, and the
amount of lineal metres of steel used.
[119] Carefully measuring off from the photographs taken of the steel structure
before being the concrete fill, Mr Bach, after consulting with Mr Brett Mills of
Mills Engineering, made a detailed analysis of steel calculations which he
set out in a spread sheet summary. Mr Bach could not see 735 lineal
metres of steel used in the cavities.
[120] Despite this meticulous analysis, Mr Bach stated he could only give a “ball
park” figures to get a “gut feeling”6 which was supported by assumptions
and intricate calculations contending that all of the steel did not go into the
pool shell structure. He said because there were no actual detailed
engineering drawings, it was difficult to prove their suspicion that the
Respondent‟s demand for an extra payment for concrete and steel was an
over estimate.
[121] The Tribunal is satisfied that the Applicants have made out the cost of the
extra concrete as fair and reasonable in accordance with the ADDITIONAL
CHARGES as set out in the Contract.
[122] The Tribunal finds that the extra costs for the excavation and the concrete
were costs fairly incurred which were charged to the Applicants at cost.
There was no add-on profit for the Respondent. The Tribunal is satisfied
that the excavation and concrete costs were fair and reasonable.
[123] A variation is an alteration, modification, revision of the design, quality or
quantity of works or amendment of the original intent of the contract and/or
its works. Variations are common occurrences during the design or
construction phase. Ordinarily a variation is an amendment or change to
the existing plans or specifications for the works to include some alteration
addition or removal of some previously agreed feature in the structure.7
6 Evidence given on 20 April 2011.
7 D & C Builders v Rees [1967] 3 All E R 837.
-- 17 of 50 --
18
[124] The statutory scheme seeks to protect the consumer from an increased
contractual price by ensuring variations are put in writing is to ensure a
record of amendment in order to maintain contractual certainty in relation to
many aspects of the contract, for example the addition or omission of
specified work.8
[125] The excavation of the void to make space for the pool and the concreting of
the shell structure to fill rock fall out were not alterations to the design or
scope of the works being a pool of defined dimensions. As such the
increased costs were not variations requiring a written variation document
under the contract or the DBC Act.
[126] Moreover the Respondent also advised the Applicants that it was not
possible to produce “cost only” variations prior to actually knowing what the
costs actually were, and drew attention to Clause 11(18) that: “…the
requirements for a signed variation document prior to the carrying out of any
work does not apply if, in the contractor‟s opinion,… it is not reasonably
practical to produce a variation document prior to the carrying out of the
work…”
[127] Further the ADDITIONAL CHARGES provisions of the Contract did not
include these items as it was not ticked whereas the box stating additional
costs to be “at the contractors costs” was ticked. Hence in any event, a
variation document under the terms of the Contract was not required.
[128] On 25 April 2007 the Respondent wrote to Mr Morgan setting out their
understanding of the terms of the contract in respect of excavations,
“unforeseeable costs summary” and the reasons for the variation not being
required in writing and that the contract was “quite strict with deeming bills
as unequivocally payable where they have not been appropriately
challenged in writing within five (5) days of the bill being issued”.
[129] The Tribunal finds that the extra costs for excavation beyond the provisional
sum and the extra costs for concrete were not variations and written
variation documents were not required.
[130] At no stage did the Applicants give notice in accordance with Clause 10(7)
of the Contract, which provides that where the customer disputes the
amount stated in any progress claim, the customer must pay to the
contractor that part of the dispute on the balance, within five working days
of receiving the contractor progress claim.
[131] The Respondent requested payment for these outstanding amounts on
17 October 2006, 20 November 2006, 12 December 2006, 14 February
2007, 22 February 2007 and 8 May 2007. The Respondent asserted their
right to suspend works under Clause 15(1)(b) & (c) for the time that non-
payment had persisted.
[132] On 18 February 2007 the Applicants paid part of the excavation costs and
extra concrete costs, but did not pay the full amount which was disputed.
8 Nautilus Pools Pty Ltd v Rollo, G. & A. [2004] QCCTB 152.
-- 18 of 50 --
19
[133] Although the Applicants made progress payments as requested they have
refused to make payment for these outstanding amounts notwithstanding
subsequent requests by the Respondent.
[134] The Applicants will be ordered to pay the Respondent the balance of the
excavation and extra concrete costs of $2,240.00.
[135] After examining the invoices and rate of costs for construction in the project
I am satisfied that the Respondent has made out its case for the cost of
extra supervision costs of $1,623.60, the cost of the increase of their claim
wall size of $1,550.73 together with interest on these amounts calculated
pursuant to the contract.
[136] Under section 77(2)(c) of the QBSA ACT, interest may be awarded as
prescribed by regulation from the date an amount becomes payable until it
is paid. If the parties entered into a contract, interest awarded is payable at
the rate specified in the contract or at the rate of 10%: Queensland Building
Services Authority Regulation 2003, section 34B. The interest is payable
on and from the day after the day that the amount became payable until and
including the day the amount is paid.
[137] The Tribunal will order that the Applicants pay to Respondent the sum of
$5,413.73 plus interest at 10% calculated from 17 November 2006.
The Engineering Plans, Certification and Soundness of the Structure
[138] The Applicants exercised their lawful rights by scrutinising most aspects of
the construction, taking many photographs of the works as it was underway,
carefully checking costs, subjecting invoices to detailed analysis, obtaining
independent engineering assessments, making complaints to regulators
and ultimately instituting proceedings in the CCT and the QCAT which has
attempted resolution by convening conclaves of engineers and mediation to
no avail. Mrs Bach stated that “I have been motivated to proceed against
the Respondent in the hope that the efforts of [Mr Bach] and myself, though
at times seeming inordinately demanding, will one day make pool
construction an easier task for future consumers in Queensland and
ultimately reduce the suffering which we have endured.”
[139] The excavation and extra concrete conflict escalated into a general debate
about the soundness of the entire structure. The Applicants stated that:
“had the Respondent not insisted on claiming the charge for extra concrete
we would never have uncovered the truth of the events which occurred.”
[140] The Applicants passed a fine tooth comb over many aspects of the
construction of the work searching for error which they were entitled to do.
[141] The Respondent considered this an attack of their professional integrity and
regarded the Applicants‟ zeal as an unwarranted interference in their ability
to finish the job.9
9 See Cube Building Services Pty Ltd v Fois (Domestic Building) [2011] VCAT 311
where it was said: “It is apparent that the Owners, as lay people, have little
understanding of matters to do with building. They seem to have fundamentally
misunderstood their role as owners, which is to allow the Builder to get on with the
-- 19 of 50 --
20
[142] The Applicants‟ case focussed on Construction Note 13 of the plans
(04B013/S1) provided that “masonry walls must not be built off walkways
unless so detailed”. Reliance was placed on s 70(2) of the Building Act
1975 (the BA Act) which provides that “work on any footings for the building
work must not start until the drawings and details for the footings have been
approved by the building certifier”. Further “a stage of the building work
must not be started until the drawings and details for the stage have been
approved by the building certifier”: s 70(3).
[143] An engagement of a private certifier must be written and state the fees
payable by the client for an engagement of a private certifier, the employer:
s 141.1. The mere making of a building development application to a
private certifier does not, of itself, constitute and engagement of the certifier
by the applicant: s 141.2.
[144] The Applicants state that the Respondent failed to provide engineering
drawings to specify where “the walls to be engineered designed with
footings”. Further, the Respondent failed to do all things as may be
reasonably necessary to obtain all approvals required for the
commencement of works in not arranging engineering drawings for the
retaining walls as requested by the certifier and therefore not obtaining
building approvals for the construction of the retaining walls.
[145] The Applicants also say that the Respondent breached Clause 1 of the
General Conditions in s 141 of the BA Act in that it failed to engage the
certifier in writing and failed to state the fees payable by the client to the
certifier. Further, the Applicants complain that the Respondent failed to
notify them in writing of the appointment of the building certifier. The
Applicants further contend that the Respondent, in contravention of
Clause 5, failed to inform them of the conditions attached to the certifier‟s
approval and the obligations contained therein.
[146] The Applicants criticised the Respondent‟s engineering report of September
2007 because it:
a) does not accurately depict the cranking of the steel started bars;
b) does not detail the location of control joints in the pool.
c) nominated the pool walls at 180mm thickness.
[147] The Applicants claim that the pool was deficient in the design code for a
load of soil of 1.6m high when the actual retaining wall was 3.2m high, the
pool wall thickness should have been 350mm, the control joints were
constructed without dowel or key blocks and this is to ensure that each side
of the joint did not move to a greater degree than the other. The Applicants
said that the appropriate limit of work stress in the reinforcing steel for the
pool was in the order of 130MPa. However, the working stress at the area
of the pool through the bench opposite the curved entry stairways, when full
design loads were applied, would be approximately 939MPa or 7.2 times
the appropriate limit. The working stress in the area of the pool between
job. I think that is the likely explanation for their extraordinarily high level of
interference with the work and lack of co-operation with the Builder.”
-- 20 of 50 --
21
the bench and the south-west corner of the pool, when full design loads
were applied would be approximately 512MPa or 3.9 times the appropriate
limit. Hence the Applicants argued that the pool structure is over stressed
and not structurally safe.
[148] Further in the alternative, the Applicants stated that if it considered that it
was not reasonable and necessary for the pool and retaining walls to be
demolished and replaced, then remedial work was required to remove the
pool lining from the floor and southern walls, and epoxy grout pins into the
face and respray concrete to build the wall thickness up from the existing
150mm to approximately 450mm. The Applicants say that even upon this,
the pool dimensions will be smaller than those contracted for and well
outside the acceptable tolerances as detailed in Clause 20 of the contract.
[149] It is necessary to set out a chronology of some events, assessments and
engineering reports about the pool structure.
[150] The works commenced on 7 August 2006, the site was cut, the steel form
work was completed and the project was ready for building approval by the
third week in September 2006.
[151] On 3 September 2006 Mr Bernie Davis, engineer and senior consultant of
Qantec McWilliam advised the Respondent that the pool was of a “normal
depth for domestic use” where “normal construction/reinforcing details can
be followed for the shell with additional horizontal bars longitudinally in floor
and both walls”. Mr Davis advised as to gravel with Ag drain, the retaining
wall, footings, starter bars.
[152] On 5 September 2006 the Respondent appointed Mr Suresh Chandra of
Building Approvals and Inspections Consultants Pty Ltd as project certifier.
He was provided with the textual engineering detail provided by Mr Bernard
Davis and Engineer of Qantec McWilliam engaged by the Respondent. Mr
Chandra accepted this as sufficient and acceptable because he was an
engineer. The works which included the cross section and perspective
drawings were stamped “APPROVED”.
[153] On 11 September 2006 Mr Davis drew the POOL AND WALL LAYOUT
PLAN (Detailed set-out, As per sketch plans) to the Respondent which
detailed a typical section of the extended coping.
[154] On 14 September 2006 the Respondent forwarded the plans to Mr
Chandra.
[155] On 21 September 2006, before the concrete pour commenced, Mr Chandra
went to the site inspected the works and steel frames and approved the
works.
[156] Mr Chandra says he was aware that construction on the wall had
commenced but he said this was common practice in the building industry
as amended plans are sometimes lodged after work has been completed.
[157] The Respondent has always maintained that having engaged the certifier,
supplied him with textual engineering detail prepared by Mr Davis, they had
complied with lawful requirement to obtain certification, which was obtained.
-- 21 of 50 --
22
[158] On 19 September 2006 the Applicants made their first progress instalment
payment.
[159] On 22 September 2006 as the concrete pour appeared imminent after a
query by the Applicants, they were advised that the engineering inspection
of steel had occurred the previous day. Mrs Bach also requested a copy of
the engineer‟s design drawings, but was advised that these would be
delivered with all documents upon completion of the project.
[160] On 23 September 2006 the concrete was poured and sprayed for the pool
structure.
[161] On 26 September 2006 the Applicants made progress payments.
[162] By a letter dated 27 September 2006 the Applicants confirmed their verbal
request for copies of the structural drawings.
[163] By a letter dated 27 October 2006 the Applicants received the tax invoice
for the excavation costs and extra concrete.
[164] By a letter dated 5 November 2006 the Applicants protested the excavation
costs and sought invoices for the extra concrete. They made part payment
and sought further clarification about the extra concrete before considering
payment of the balance.
[165] By a letter dated 20 November 2006 the Respondent set out information
seeking to answer the Applicants‟ queries and requested full payment.
[166] By a letter dated 12 December 2006 and 18 December 2006 the
Respondent again made claim for the outstanding half of the second
payment.
[167] On 20 December 2006 the Applicants made a further payment to the
Respondent but held back on the disputed claim.
[168] On 22 December 2006 the Applicants approved a variation to the pool tiles.
[169] On 29 December 2006 the Applicants again queried the amount of concrete
allocated for the pool and questioned how the amount was calculated.
[170] On 14 December 2006 after the tiling was completed leaking of water into
the empty pool structure was detected by the Applicants.
[171] In January 2007 there were on-going discussions about water line tiles.
[172] On 6 February 2007 the Respondent made requests for the third progress
payment.
[173] By a letter dated 7 February 2007 the Applicants wrote to the Respondent
asking for the name of the engineer for the project because they had
questions to ask the engineer before they proposed settling the final
account.
[174] By the letter dated 14 February 2007 the Respondent:
a) set out how details on how the extra concrete was calculated;
b) made an adjustment concession on the allied earthmoving invoice;
c) sought payment for the excavation and extra concrete costs by
19 February 2007;
-- 22 of 50 --
23
d) advised the Applicants that they did not normally put customers in
touch with their engineers directly given that the contractual
relationship exists solely between them and the engineer;
e) claimed an extension of two (2) weeks for inclement weather on an
unspecified date.
[175] By a letter dated 18 February 2007 the Applicants:
a) paid part of the excavation costs and extra concrete costs, but held
back payment because of the dispute;
b) sought to inspect the engineer‟s plans for the pool to ensure that the
Respondent had adhered to them and to determine whether the
200mm is an acceptable width of a pool wall and that footings were
engineer designed.
[176] On 22 February 2007 at the request of the Applicants, Mr Chandra came on
site with a view to discussing approval for the pool fence. Mr Chandra
advised them he was an engineer, had inspected the steel, certified the
structure and issued the Pool Steel Inspection Certificate (dated
22 February 2007) certifying that the reinforcement that he inspected was
placed in accordance with the supplied approval structural documentation.
[177] Also on 22 February 2007 the Respondent by a letter:
a) stated a “wish to sincerely convey our desire to resolve all relevant
issues amicably and punctually. We also wish to say that such
extensive “letter writing” (albeit validly requested by you) is in our
opinion counterproductive, and which we trust that this will be curbed
in future, by way of the extensive information contained herein”;
b) addressed the concrete usage (including surrounding issues) by
setting out the method of charging;
c) sought payment of the outstanding amount for excavation and extra
concrete within five days;
d) advised that it was not possible nor reasonably practicable to provide a
written variation for excavation of rock prior to the commencement of
incurring the costs;
e) advised of the failure to comply with clause 10(7) which sets out the
time frame for withholding payment;
f) advised of the flow-on effect of extending contractual timeframe for the
period of non-payment;
g) reserved the right to also suspend the works under Clause 15(1)(b)
and (c) from the time the non-payment over the extra-excavation and
concrete costs persisted;
h) advised that a “legalistic approach to the construction timeframe is
unproductive” especially having regard to rain and the Christmas
break;
i) enclosed copies of the engineering drawings applicable.
[178] By a letter dated 25 February 2007 the Applicants said they were glad to
see the project approaching completion, paid for the tiling, and set out six
matters concerning defective grout, tile adhesion lumps and an expansion
-- 23 of 50 --
24
joint which they considered required attention before the installation of the
glass fence.
[179] By letter dated 27 February 2007 the Applicants faxed to the Respondent:
a) again disputing the extra concrete costs;
b) advising that they were seeking independent engineering reports to
ensure that the original provisions were reasonable given that the
estimates did not include allowance for footings and the pool thickness
of 20cm may not be within the engineering specifications for retaining
wall greater than 2 metres in height;
c) stating that they would not be in a position to settle the outstanding
amount (if any) until these independent were obtained;
d) advising that hey would not be paying a loading for concrete being
provided on Saturday;
e) disputing the amount charged by Shotcrete for an unnamed item,
walkway and extra cutting;
f) asserting the payments were variations never approved by the
Applicants;
g) expecting a completion date of 11 March 2007;
h) complaining that as set out on page 3 of the Contract: “Where
construction approval or similar design authorisation additionally
requires a detailed engineering design, or foundation data, soil tests,
contour surveys etc as part of such approval, then such plans, designs
or certificates must be attached to, and included upon the signing of
the contract”;
i) complaining that they had not been provided with the approval
conditions arising from Mr Chandra‟s certification;
j) advising that a copy of the Council approval had not been forwarded to
them.
[180] At 9:00 am on 27 February 2007 Mrs Bach telephoned Mr Jakavoc about
the matters raised in their letter faxed that morning to the office of the
Respondent. Mr Jakavoc said he had not been in the office and had not
received any faxed letters from the Applicants. She asked when work was
to resume. Mr Jakavoc said he did not know when the filtration equipment
or the glass fence would be installed.
[181] Mrs Bach advised Mr Jakavoc that he ought to make sure his secretaries
bring her faxes to his attention, which “brought about an explosion of abuse
and shouting from Jason over the phone.”
[182] The conversation was terminated by Mr Jakovac saying: “You are too hyper
for me to talk to, I am going to terminate this call and do not call me back on
this number”.
[183] Later that day the Applicants contacted the SPASA which is a non-profit
trade association dedicated to maintaining and improving standards within
the industry for the betterment of consumers, pool builders and supplier and
in a letter to the Respondent complained about the difficulty in making
-- 24 of 50 --
25
communication with Mr Jakovac requesting the Respondent appoint of
another project manager.
[184] On 12 March 2007 the Applicants sent the Respondent five photographs
showing slight soil stains below the pipes from the pool wall apparently
caused by water coming into the pool.
[185] On 13 March 2007 the Applicants wrote to the Respondent advising they
had sought the advice of an engineer in relation to the pool construction,
enclosing photographs of leaking alongside pipes at the western wall,
seeking rectification. They said: “Our engineer has raised some concerns
about construction issues and we wish to discuss these with you, if possible
and negotiate mutually agreeable solutions in a meeting „without prejudice‟.”
[186] On 21 March 2007 the Applicant engaged Mr Robert Morgan, an Engineer
and Managing Director of Morgan Consulting Engineers, to seek advice
about engineering drawings and excavation and concrete costs. Mr Morgan
offered to attend to mediate the issues on a „without prejudice‟ basis
between the Respondent and the Applicants.
[187] On 21 March 2007 Mr Jakovac and Mr Bach attended the office of Mr
Morgan. By a letter dated 23 March 2007 Mr Morgan advised the
Applicants of the water proofing material used and that he had checked the
figures in relation to the additional concrete pour inviting them to look at the
original invoices. Mr Jakovac offered to do the calculations together. He
said: “I would appreciate if we could do this as two professionals without the
emotions of the client”.
[188] On 23 March 2007 the Respondent advised that they would treat any leaks
after the pool was filled with water. The Respondent argued that the pool
would not have leaked had they had the opportunity to finish it.
[189] On 31 March 2007 the Applicants sought notification of the date of practical
completion.
[190] Around mid-March 2007 work slowed to stand still and on several occasions
to May 2007 the Applicants asked when work would resume and the project
completed.
[191] The Applicants allege that the Respondent unlawfully suspended work in
contravention of Clause 15 of the General Conditions on or around mid
March 2007.
[192] The Respondent denied the allegation that it was in breach in relation to the
extension of time saying that those extensions were for true delays in the
progress of the work outside the control of the Respondent, the alleged
breach would not give rise to any loss or damage as claimed by the
Applicants, the delays were notified to the Applicants verbally and then
confirmed in writing, and any delays in progressing the works was a direct
result of the negligence of the certifier.
-- 25 of 50 --
26
[193] The Respondent deny the allegation that it failed to complete the works by
the date for practical completion because it says the Applicants had
unlawfully terminated the contact thereby preventing it from bringing the
contract to a stage of practical completion, the Applicant was responsible
for, or had contributed to the alleged delays due to it raising the height of
the retaining wall in an unauthorised manner, due to its failure to complete
its payment obligations in accordance with the contract and any alleged
delays in progressing the works was as a direct result of the negligence of
the certifier.
[194] On 25 April 2007 the Respondent wrote to Mr Morgan setting out their
understanding of the terms of the contract in respect of excavations,
“unforeseeable costs summary”, the reasons for the variation not being
required in writing and that the contract was quite strict with deeming bills
as unequivocally payable where they have not been appropriately
challenged in writing within five (5) days of the bill being issued. The
Applicants did not issue a notice in accordance with Clause 10(7) within five
(5) days from the relevant invoices being issued, and absence of such
compliant notice therefore unequivocally deems the relevant invoices as
due and payable. The letter noted that the total amount which remained
outstanding was $48,064.00 which they required to be paid by the customer
within seven (7) days. The letter advised that if the amount was not
received within the time frame and the Respondent reserved all rights
associated with the outstanding amounts, including the right to claim
interest as per Clause 5 of the Contract.
[195] On 28 April 2007 the Applicants made a complaint to the QBSA that the
Respondent had failed to complete the Contract and had not rectified
defects which consist of a long list of small items concerning leaks, the
fence, grout in tiles, crooked pool lights, and skimmer box flaps not fitted,
etc.
[196] By letter dated 29 April 2007 the Applicants set out in detail the matters
which they required to be addressed by the Respondent. These included
the ongoing dispute about the reasonableness of excavation costs, the
extra concrete cost, and the leaking around the PVC penetrations into the
currently unfilled pool. The Respondent observed that it was evident that
the plans of the engineering consulting firm Qantec McWilliam were used in
the Council application for the pool construction were of a generic nature.
They advised that they had lodged a complaint with the Office of Fair
Trading in relation to misleading quotation against the Respondent. They
also advised that they had lodged a complaint with the QBSA for failure to
rectify. In addition to the previously notified defect relating to the PVC
penetrations, they formally notified the Respondent of further defects and
the work which required correction concerning the paling fence post, grout
in the tiles at the site of the glass gate being cracked, the leaking at the end
of the backwash pipe and existing plumbing, the crooked pool lights, the
unfinished PVC penetrations, the set of colour filters for the pool lights
missing, and skimmer box flaps not fitted etc.
-- 26 of 50 --
27
[197] On 8 May 2007 the Respondent wrote to the Applicants again addressing
the extra concrete issues.
[198] By a letter dated 10 May 2007 the QBSA advised the Applicants that after
an assessment of the file the QBSA determined that the QBSA could not
assist in the matter.
[199] On 15 May 2007 the Applicants wrote to the Respondent asking when their
works would be completed, seeking further clarification as to how the
disputed amount for excavation and concrete was calculated.
[200] On 29 May 2007 the Applicants filed a Domestic Building Dispute
Application with the CCT.
[201] The Applicants, at their own expense, conducted repairs which were not
effective. The Applicants contended the leakage was a result of poor
workmanship (and as such a breach of contract) or a consequence of the
unlawful suspension by the Respondent.
[202] After consulting engineers and leak consultants it was decided to drain the
pool and to treat each leak penetration, which could not effectively be
repaired until tiles were removed from around each of the penetration areas
to be drilled and resealed.
[203] A conclave of leak consultants reported that it was necessary to drain the
pool and to treat each penetration. The leaks were not repaired effectively
until tiles were removed from around each of the penetration and each
penetration was drilled around and resealed and this would have been done
by the Respondent had they completed the pool sometime in 2007.
[204] The leaking around the pool may have occurred because it was left
standing without water for ten (10) months. During this time there may have
been concrete shrinkage around the penetration.
[205] The leaks were treated and the pool no longer leaks.
[206] By letter dated 27 July 2007 Mr Rob Morgan of Morgan Consulting
Engineers advised that the pool should be filled for two reasons because
the pool was cut into a bank and if there is prolonged rain the water tide will
rise and the pool may lift out of the ground if the pressure relief valve is not
adequate which is a matter of serious concern and concrete cures better
under water and there would be less chance of shrinkage cracking.
[207] On 30 July 2007 the Applicants made a complaint to the QBSA against Mr
Chandra alleging that he should not have approved the works because he
was relying on concept drawings and that he failed to protect them from the
poor engineering practices of the Respondent.
[208] On 30 July 2007 the parties attended at the Tribunal for a mediation, but
this did not resolve the matter.
-- 27 of 50 --
28
[209] On 2 August 2007 the Applicants took their complaints to their local
government BCC Councillor with whom they met on 8 August 2007.
[210] On 17 August 2007 Gregory Schonfelder, the Principle Development Officer
of the Building Licensing Compliance section of the Brisbane City Council
attended on site. He reviewed the submitted plans and building
development permit and concluded:
a) there is no engineering details for the masonry structure arch (water
curtain);
b) there are no plans and certification for the masonry retaining walls
more than 1.0m in height nor plans for the walls/screens more then 2.0
metres in height, although they scaled higher on the drawings
(elevations), and
c) Construction Note 13 on the Engineering Drawings which are not part
of the approved plans stated that Masonry walls must not be built off
walkways unless so detailed. There is no detailing of any of the walls
or arch, which are attached to the pool.
[211] In Mr Schonfelder‟s opinion the “building work should not have advanced to
the next stage (from the pool steel inspection stage) because it would have
been obvious at that time that the building work would not comply with the
approved plans and that amended plans would need to be submitted to you
for approval with the relevant engineering certification.”
[212] On 23 and 27 August 2007 Mr Schonfelder wrote to Mr Chandra advising
that his review of the submitted plans and documentation for the
development revealed there were no engineering drawings for the masonry
arch, no plans of certification for the masonry retaining walls more than one
metre in height, no plans for the wall screens more than two metres in
height and referred to Construction Note 13 of the engineering drawing.
[213] On 30 August 2007 the Applicants telephoned Mr Chandra and advised him
that the QBSA had informed them that he had not yet responded to their
complaint. Mr Chandra advised that he had communicated the contents of
Mr Schonfelder‟s letter to the Respondent and had left it with them to
provide him with plans.
[214] On 30 August 2007 the Applicants terminated the engaged of Mr Chandra.
[215] By a letter dated 4 September 2007 the Applicants wrote to Mr Davis
attacking his conclusion that he “certified that all aspects of the site are
structurally sound in accordance with relevant requirements”. They advised
Mr Davis that as the matter was before the Tribunal they would be applying
to compel his attendance to give evidence on his involvement in the project.
They warned: “In short, the process and evidence by which you have
scrutinised the construction work on our property as compliance will be
closely scrutinised by third parties and us”.
[216] On 11 September 2007 Mr Davis of Qantec McWilliam lodged with the BCC
a compliance certificate for building design in Form 15 for the concrete pool
-- 28 of 50 --
29
shell and attached reinforced concrete block walls indicating that the
reference documentation was the general concept plan.
[217] On 22 September 2007 and 15 October 2007 the Applicants advised the
Council of the discontinuance of Mr Chandra and requested the
appointment of another certifier.
[218] The Applicants‟ grounds for the notice of discontinuance of Mr Chandra
alleged he failed in his duty of care as a private certifier by approving
inadequate/incomplete engineering plans for proposed work and failed to
notify them of the approval of conditions. They also alleged inadequate
inspection of the steel and included failure to respond to a complaint made
to the QBSA.
[219] By a letter dated 29 October 2007 to the Applicants, the Respondent noted
that the decision to disengage the private certifier had been made of their
own accord. This, they said, had resulted in the requirement to obtain a full
retrospective approval for the works, including evidence of a range of many
aspects of the works.
[220] On 12 November 2007 Mr Des Newport, a consulting engineer, having
inspected the pool on Friday 2 November 2007, told the Applicants he was
unable to provide a Form 15 because in his opinion: “All pools should have
their own individual plans that cater for the individual conditions that make
up a pool. Given the fact the pool has not been designed in accordance
with prevailing conditions, I regret to inform you that I am unable to issue a
Form 15 for a pool when I cannot be sure it has been constructed to meet
its purpose. I viewed photographs of the construction, but these are not
sufficient for me to determine if its construction would meet the specification
design that is suitable to the conditions on your block”.
[221] On 12 November 2007 the Applicants made a complaint to the Board of
Professional Engineers against Mr Davis. They allege he failed in his duty
as a professional engineer in the drawing of the plans for the work required
at the property and that he did not demonstrate appropriate knowledge, skill
and judgment in the utilisation of generic pool plans for the project proposed
at their property. They contended that “specific plans should have been
drawn by Bernard Davis taking into account the large retaining walls,
located less than 2 metres from the property boundary and greater than 1
metre in height”. It was their view that the pool should have been modified
in thickness and design where the retaining walls were located on the
coping and footings should have been designed for all retaining walls.
Notwithstanding they had a soil test from 1994, they complained that “a soil
test should have been requested by Bernard Davis as nearly 100m³ was to
be evacuated up to 4m in depth from the natural soil level, all less than
4 metres from the house of our adjoining property”. The complaints also
included the fact that Mr Davis did not provide an engineering design
certificate and did not inspect the steel in the footings at any time.
[222] By letter dated 13 November 2007 the Respondent said that the approval
process was completely satisfactory as far as the private building certifier
-- 29 of 50 --
30
was concerned and that all documents were completely in order, observing:
“Although this may not be evident to you thus far, we suggest in your
interest that you refrain from focusing on this aspect of the dispute, as we
are more than confident that you would see in time that your efforts to prove
otherwise will have been in vain”.
[223] On 29 November 2007 the Applicants obtained Mr Chandra‟s letter dated
13 November 2007 to the BCC including structural drawings for
construction of the retaining walls and a Form 15 Compliance Certificate for
Building Design or Specification.
[224] By a letter dated 2 December 2007 Mr Chandra wrote a letter to the QBSA
pointing out he did not think there was anything peculiar with the project that
was different from so many others that required extra documentation when
it became at the time of an inspection.
[225] By a letter dated 12 December 2007 Mr Davis explained to the Board of
Professional Engineers that the Applicants appeared to be suffering from a
misconception of his role with the Respondent in domestic pool projects.
He said that Qantec McWilliam had an agreement with the Respondent and
some 18 other pool contractors that they provide a number of site
engineering drawings which they can submit for normal domestic pools
where they have no direct involvement. For pools outside the limits of the
drawings of which have features or locations not covered by the standard
drawing, the Respondent was required to refer it to them before quoting or
seeking building approval. He said: “This system, faithfully followed, has
operated without any structural problems for some twenty years. If required
by the certifier and advised to us by the contractor, we will carry out such
inspections of works in progress as will allow a Form 16 to be prepared”.
He explained to the Board of Professional Engineers his involvement with
the project. In September 2006 he reviewed the concept drawings by Mr
Cox. In June 2007 he was contacted by the Applicants requesting copies of
drawings. In September 2007 the Respondent requested design drawings
defining the structural requirements of the pool and attached features for
submission as part of the building approval and a Form 15 issued for this
design.
[226] On 24 October 2007 the Applicants demanded of the Respondent that they
provide “as built” engineering drawings and a signed Form 15 by
31 October 2007.
[227] On 13 December 2007 the Applicants gave notice pursuant to Clause 17 of
the general conditions of the Contract that the Respondent was in
substantial default of the Contract requiring them to rectify breaches within
five (5) workings days. The grounds were that there had been unlawful
suspension of work from on or about 15 March 2007, had unreasonably
failed to remedy defective work or materials, failed to carry out work in
accordance with the plans, failed to construct retaining walls in accordance
with all relevant law and legal requirements, and failed to comply with
conditions of approval in relation to the retaining walls.
-- 30 of 50 --
31
[228] By a letter dated 13 December 2007 the Respondent advised the
Applicants that they rejected the grounds stated in the Notice and that they
would consider the letter as a notice under Clause 16 dealing with
termination of contract by contractor on the grounds that the customer failed
to make a progress payment or other amount due within the time allowed in
the contract, failed to sign a variation documentation or give its consent to a
variation due to a legal requirement or latent condition, interfered with, or
obstructs, the contractor in the performing of his work, prior to making final
payment of the contract, uses or occupies the works without the contractor‟s
written consent or otherwise prevents the contractor from carrying out the
works and/or is in substantial default of the contract. By Clause 16, the
contractor may, if the failure of a fault is capable of being remedied by the
customer, give the customer a notice in writing setting out the specific
details of the failure or default and stating the contractor‟s intention to
terminate the contract if the failure or default is not remedied within five (5)
working days or such longer time as is specified in the notice. By Clause
16(2) if the customer does not remedy the failure or default within the time
allowed, or if the failure or default cannot be remedied, the contractor may
terminate the contract immediately by giving of further notice to the
customer.
[229] On 21 December 2007 the Applicants claim the Contract was lawfully
terminated.
[230] On 22 December 2007 the Applicants fitted various parts to the pool which
they paid for and filled the pool with water at their own expense.
[231] By letter dated 15 January 2008 the QBSA advised that it had found that Mr
Chandra had engaged in unsatisfactory conduct as certifier.
[232] On 25 January 2008 representatives of the Respondent attended at the site
to inspect works.
[233] On 30 January 2008 the Respondent‟s leak contractor attended at the site
to inspect the pool.
[234] On 4 January 2008 a representative of the QBSA set out the defects
requiring correction, such as leaking around the southern wall where the
PVC pipes penetrate, following which the Respondent gained access to the
property and attended to them.
[235] On 31 January 2008 representatives of the Respondent attended at the site
with Mrs Bach and a representative of the QBSA. By report that day the
QBSA identified some incomplete and defective work concerning leaks,
pipes, fencing, which the Respondent offered to rectify. As regards the
block wall at the northern end of the pool it had not been constructed with a
movement joint as required by the engineer‟s design and the Applicants
pointed out that the short wing wall installed at 90 degrees to the rear of this
wall has no footings. The QBSA upon “visual inspection noted there was no
movement of distress to the masonry block wall”, it appeared “to be
structurally sound and the excavation is in weathered rock according to the
-- 31 of 50 --
32
engineer‟s design”, and “this wall requires to be built in the details and
requirements of the engineer detail of drawing No. RW. 1 dated
11 September 2007”. The recommendation was that the Respondent was
to provide the Applicants engineering certification of this structural retaining
wall.
[236] On 6 February 2008 the Applicants wrote to the QBSA setting out further
complaints and concerns dealing with pipes and leaks.
[237] On 12 February 2008 the Applicants expanded upon their complaints to the
Board of Professional Engineers against Mr Davis to allege the relationship
between the Respondent and Mr Davis was one “which breached the
professional standards, expected of an engineer… we are of the opinion
that Bernard Davis has an arrangement with [the Respondent] by which
generic plans for pool construction may be used without his involvement…”.
The Applicants alleged that Mr Davis has produced a back dated letter to
mislead the Board that liaison between the Respondent and himself
occurred in their case.
[238] On 17 March 2008 Mr Davis advised the Board of Professional Engineers
that with many domestic swimming pool projects there is no formal brief.
He said the level shown on the Cox drawings were adequate to assess the
wall structures. The key design feature for the retaining wall is the height
behind the straight section where the 1.6 m height occurs at a corner and
near return wall sections where the wall structure is much stronger than on
the straight section.
[239] Mr Davis stated that the pool design and adjacent features are not
exceptional by contemporary standards. The arrangement with the
Respondent in respect of the generic plan is a long accepted practice in
building works, where the correct use is up to the contractor.
[240] The Respondent has submitted that it was common place that drawings
attached to a Form 15 (Design Certificate) can differ to that which is actually
constructed on-site. Where this occurs (and it is not uncommon that an on-
site structure can differ from the drawings) the integral principle is that the
consulting engineer is satisfied the structure is sound in accordance with
their opinion.
[241] On 27 March 2008 the Applicants requested Mr Brett Mills of Mills
Engineers Pty Ltd to prepare a report on the adequacy of the retaining walls
and swimming pool reinforcement.
[242] On 31 March 2008 Hughes, Beal & Wright, Consulting Engineers advised
the QBSA that as a result of their inspection conducted on 27 March 2008
they observed some fine cracks (less than 0.1mm wide) and a crack in the
render of the retaining wall along the back right hand boundary near the first
buttress which appears to be the result of some slight lateral movement of
sections of the concrete block retaining wall on either side of an articulation
joint. There was no evidence of corrosion of any reinforcement. As to the
starter bar bends which were cranked at a shallow angle and run down the
-- 32 of 50 --
33
pool wall. While the cranked bars were not as efficient structurally as the
designed shape, there was no evidence that the cranked bars have failed or
yielded in any way.
[243] Hughes, Beal & Wright observed that: “The retaining walls had been
subjected to earth pressures for a period of almost eighteen months during
which time some reasonable rainfalls have been received which will have
increased the load on the walls.”
[244] Hughes, Beal & Wright concluded that the structures were performing
satisfactorily and any damage was primarily cosmetic. In the future most of
the problems are likely to be only cosmetic.
[245] On 17 April 2008 the Respondent sought access to the site for an expert
assessment which was denied.
[246] On 23 April 2008 following ground penetration radar Mr Davis gave a
detailed report on the structure and found that it was adequate. He
concluded that:
a) the extent of present backfill/garden height must not be raised in the
future and consideration must be given to future planting species
adjacent to these walls;
b) the control joint in the west wall should be repaired;
c) with these items attended he “confirmed the retaining walls above the
coping and the cross/arch wall are structurally sound as constructed.”
[247] Mr Davis also prepared the Form 15 with design drawings and Form 16 for
inspection and proof of structural soundness for certification.
[248] On 30 April 2008 the Board of Professional Engineers advised that no
action would be taken on the complaint of the Applicants against Mr Davis.
The Board found that after considering all of the available information in full,
there were insufficient grounds or evidence to believe that Mr Bernie Davis
may have behaved in a way that may provide a ground for disciplining him.
[249] On 15 May 2008 the QBSA prepared a report to the Tribunal on
uncorrected defects which included, the lifting of the tiles at the entrance
gate, the ongoing leak of the pool and the lack of engineering details of the
western wall.
[250] By a letter dated 6 May 2008 the Respondent provided a report of Mr Davis
which confirmed “the retaining walls above the coping and cross/arch wall
are structurally sound as constructed.”
[251] By an engineering two page report dated 7 May 2008 Mr Brett Mills of Mills
Engineers Pty Ltd reported that he had inspected the structures on 2 May
2008 and found that the western end of the pool has begun to rotate
outwards at the control joint and confirmed his earlier assessment that the
western wall retaining walls should be demolished and a new, structurally
adequate walls be constructed. Mr Mills noted the Form 16 dated 22 April
2008 signed by Mr Davis refers to a visual inspection and offers no
-- 33 of 50 --
34
rectification as to the retaining wall reinforcement. Mr Mills says: “There
was no competent person responsible for inspecting and certifying the
retaining wall reinforcement, and available photos indicate that
reinforcement was either incorrectly placed or nonexistence.” Mr Mills
considered the report of Hughes Beal & Wright also expressed concern
regarding the adequacy of the retaining wall reinforcement. Mr Mills was
able to put his hand under the block work of the northern counterfort wall of
the western wall and is uncertain that a footing or cement exists under the
counterfort wall. Mr Mills recommended that “retaining walls not receive
their final approval until these serious structural defects have been rectified”
and “in our opinion, there is a substantial amount of photographic evidence
to confirm the high probability that this retaining wall is failing now and will
continue to be a liability in the next five to ten years.”
[252] On 10 June 2008 Mr Rodney Holder Senior Building Surveyor of Davis
Langdon Building Regulation Consultants advised the Applicants that the
Form 16 of Mr Davis did not certify the wall as structurally adequate as a
result of inspections during construction and was therefore not acceptable.
On the basis of the engineering reports of Mr Mills (unsigned) outlining a
number of deficiencies which could lead to a catastrophic failure of the
retaining walls with recommendations that the walls be demolished and
reconstructed with correct footings and placement and size of
reinforcement, it was Holder‟s view that the works are not structurally
adequate and will require further works, inspections and certification.
[253] But Mr Holder warned that he reached this conclusion not as judge of
whether Mr Davis or Mr Mills was right or wrong or that works are not
structurally adequate and would require further works to be carried out and
inspected by a structural engineer. His decision was a matter of form given
his internal company constraints that the Form 16 could not be accepted
because of an absence of inspections. Mr Holder‟s assessment was not a
matter of substance as to engineering expertise or ultimately of structural
soundness.
[254] On 9 September 2008 SPILLS Australia advised the Applicants to drain the
pool and to apply various sealants.
[255] Between 15 to 17 October 2008 Mrs Bach attended the CCT disciplinary
hearings into Mr Chandra.
[256] On 10 November 2008 the CCT confirmed the QBSA finding that Mr
Chandra had been guilty of professional misconduct.10 The CCT expressed
the view that the practice of a pool builder lodging an amended plan after
work has been completed was a clear breach of s 70 of the Building Act
1975. It found that the Respondent was as at 21 September 2006 in breach
of s 70 of the Building Act 1975 which occurred upon the Respondent
commencing work on the swimming pool wall (an extension of which was
the subject retaining wall) without having engineering drawings and other
10 Chandra, S. v Queensland Building Services Authority [2008] QCCTB 232.
-- 34 of 50 --
35
detail approved by the certifier. The decision was based on a breach of the
Code of Conduct for building certifiers.
[257] The Respondent said that it was not heard in these proceedings, whereas
the Applicants had participated. They denied that they were guilty of any
breach of the Building Act 1975 and were in effect denied procedural
fairness. The Respondent submitted that they had relied upon the
certification approving the construction, were not aware of, and could not be
held liable for, any breaches of the Building Act 1975. In any event the
Respondent says the Building Act 1975 countenances detail other than
diagrammatical format to include textual and other engineering detail.
[258] On 21 November 2008 leak repairs were made.
[259] On 11 December 2008 further leak repairs were carried out to the western
and northern wall.
[260] On 31 January 2008 representatives of the Respondent entered upon the
property and conducted an inspection. By letter dated 31 January 2008
Sawford Voll, Solicitors for the Applicants accused the Respondent of
engaging in intimidatory conduct in relationship to the Applicants by
attending at their residence to deliver correspondence. As a consequence
the Respondent was advised that access would only be permitted upon
prior notification solely for the purpose of undertaking rectifications of
defects.
[261] By a report of Mr Eric Fox of EFC Consulting Engineers dated 5 April 2010
it was concluded that the retaining wall, which comprises the block work
wall and the pool coping which acts as the wall footing, is adequate to resist
the loads from the earth back filling. He concluded that the retaining wall in
the arch feature section was structurally sound. He also concluded that the
load supplied to the pool wall in the most severe circumstances are the
most likely to occur are well within the structural capacity of the wall.
[262] By a report dated 7 April 2010 Mr Davis advised that the pool shell was in
an excellent condition and any suggestion of demolition was totally
unnecessary. He found the side wall was not overstressed, otherwise it
would have long since collapsed.
[263] Following the experts‟ conclave conducted by Senior Member Oliver on
17 May 2010, proposals put were that:
a) The swimming pool shell as constructed is structurally adequate for the
purposes.
b) The retaining wall constructed on the pool coping around the perimeter
of the wall is structurally adequate for the purpose.
c) The return wall on the western wall requires demolition, rebuilding and
rendering.
d) The control joint on the southern wall to be repaired and re-rendered.
e) The issue of the cause of the leaking of the pool was not addressed
because the experts were not briefed on this issue.
-- 35 of 50 --
36
[264] There has been much dispute about what was agreed and not agreed
between the engineers at the conclave and subsequently, but the Tribunal
concludes that there was majority consensus, if not actual agreement, that
the pool shell was structurally adequate.
[265] In June 2010 the Respondent applied to the QCAT to join Mr Chandra in
these proceedings, but this application was declined.
[266] Mr Bach believes that the short two metre wall on the western edge of the
pool coping have moved. Mr Bach stated that northern end of that wall has
rotated outwards 10-15 mm. Inspection by Mills Engineering over the last
three (3) years has detected progressive movement in the retaining walls.
[267] Mr Des Newport, and engineer with specialties in swimming pools was of
the view that construction may fail over time. He was persuaded to the
conclusion by the absence of plans in the construction, the absence of
inspections and the structural failure of an associated structural retaining
wall as being evidence. Mr Newport considered that there may be a late
failure of the southern wall as it has not been fully loaded to the contracted
conditions as the full contracted planting is not in place.
[268] There was no site specific engineering design drawings expressly drawn for
the walls before they were being constructed. The Generic Pool Plan
(04B013/S1) was a generic pool plan essentially setting out the concept
without descending into exacting technical or engineering specifications.
[269] The Applicants say it still remains unknown if there was an extended footing
for coping on the western edge of the pool. The evidence demonstrated
that the starter bars were cranked and not bent. Further starter bars were
not applied at a section of the western wall at the time of the pouring of the
concrete for the footing.
[270] Since June of 2007 Mr Mills has inspected the work on several occasions
and most recently in May of 2011. The Mills‟ engineering drawing 2231
dated 12 March 2009 and the modified amendment plan for the western
wall 2231-b1 dated 25 January 2010 indicate that if rectification occurs
according to those plans, Mills Engineering Pty Ltd could certify the
structure of the swimming pool and retaining walls as structurally adequate
and issue a Form 16 for the certifier for the structure.
[271] On 5 August 2011 the QCAT cancelled Mr Chandra‟s licence, disqualified
him from obtaining a license in the class of Building Surveyor; Assistant
Building Surveyor and/or Building Surveying Technician for a period of not
less than two years and three months (2 1/4) years and ordered that he pay
a penalty to the QBSA in the amount of $12,000.00 within 60 days.11
[272] By a report dated 22 August 2011 Mr Bergin, certifier of the Hendy Group,
outlined what would be required by him as an advisory certifier for the
Brisbane City Council to make a final certificate for the building works.
11 Queensland Building Services Authority v Chandra [2010] QCAT 451.
-- 36 of 50 --
37
[273] The Respondent observed that since early March 2007 the walls have
withstood severe drought, water restrictions, over four full season cycles, a
range of normal Queensland weather, heavy rains and torrential
downpours, the early 2011 flood period (the most severe since 1974) and a
relatively normal weather year through the balance of 2011.
[274] The Respondent submitted that the walls have withstood normal settling in,
post-construction ground settlement, all extremes of weather, settlement
due to heavy rains, and internally withstood the full extent of hydrostatic and
ground pressure to the back of the retaining walls and behind/underneath
the pool shell walls and floor. It was submitted that it would be hard to
imagine a better time frame to test the walls‟ structural integrity.
[275] Mr Des Newport agreed that the structure had withstood a broader
spectrum of climatic conditions over the past two years, but said he was not
in a position to guarantee that it would be safe for the anticipated life of forty
(40) years (which is normal for a structure of this type).
[276] By report dated 7 December 2011 Mr Gary Wenck stated that his company
Leisure Engineering Pty Ltd had reviewed reports of EFC Consulting,
Qantec McWilliam, Des Newport Consulting Engineers, Mills Engineering
Pty Ltd and Hughes Beal and Wright, plans and photographic material and
performed its own assessment of the completed works and their suitability.
[277] Mr Wenck noted: “Calculations suggest the pool‟s southern wall is stable
under the most adverse load conditions likely to be encountered in service.
It is also noted that the pool wall is not subject to bending stresses when the
pool is empty, and the quantity of reinforcement of the pool wall is not relied
upon for its structural adequacy. When the pool is filled with water, the load
on the pool wall is resisted by the direct contact where the rock foundation
of the walls of the excavation.”
[278] On the jointing of the walls Mr Wenck considered the dislodged render and
crack revealed that rotation was minimal over the height of the wall. He
concluded: “….the difference in the crack width top to bottom being no more
than a coupe of millimetres, and in our opinion associated with shrinkage
rather than rotation.”
[279] Mr Wenck concluded that the change of level, and associated counterfort
wall located in the north-western corner of the pool should be reconstructed
and engage with the footing and a section of wall attached to the facing
wall.
[280] Mr Wenck concluded the swimming pool structure and attached retaining
walls are found to be structurally sufficient and conform with relevant
Australian standards. He concluded: “Passage of time and events since
construction are understood to have exposed the pool and associated
structures to drought conditions, a wet season (2009/2010) followed by
flood rains (2010/2011) and one cycle of pool emptying and refilling, with no
consequence that would be regarded as a failure or significant structural
distress.”
-- 37 of 50 --
38
[281] Mr Wenck was also of the view that “detailing and construction of the
counterfort wall at the north-western corner of the swimming pool is
insufficient for its intended duty and the counterfort should be removed and
replaced by a new panel as detailed in the drawings that accompany the
Form 15 prepared by Leisure Engineering Pty Ltd.”
[282] In answers to cross examination, Mr Wenck said he had analysed the
strength of the masonry wall with reinforcement effectively 75mm from the
face of the masonry and found that 15MPa concrete is a sufficient strength
to resist the applied loads which is in accordance with the accepted
engineering principles and specifically with the requirements of AS3600-
2001 Concrete Structures. As the masonry wall is set back some 75-
100mm from the top edge of the pool wall, and the pool concrete is
assumed to be less than 25MPa compressive strength, then the sheer
forces in supporting concrete are significantly less than those in the mating
15MPa concrete masonry section above. He did not accept any collapse
scenario and Mr Wenck again asserted that the southern wall in particular is
“stable under the most adverse load conditions likely encountered in
service”.
[283] Finally, Mr Wenck concluded that the change of level, and associated
counterfort wall located in the north-western corner of the pool should be
reconstructed and engaged with the footing and a section of wall attached
to the facing wall.
[284] Mr Wenck has produced the records of a Form 15 (Design) and Form 16
(Approval) Certificates as necessary to certify the works as structurally
sound providing his reasoning and calculations for so doing (in accordance
with the Brisbane City Council private certifier requirements).
[285] By a report dated 4 September 2011 Stephane Rebibou of Booth Engineers
and Associates Pty Ltd reviewed all of the engineering reports they had
prepared until that time.
[286] Mr Rebibou concluded:
“Based on the information available at the time of writing of this report, we
believe there exists limited evidence to support the case that the pool shell or
walls have failed or there is any potential of a catastrophic failure of these
structures under expected loading conditions. More than this, the „as
constructed‟ details and photographic evidence outlined in the Eric Fox
Consulting Report (EFC) generally reflect the pool walls are generally much
thicker than shown in the generic pool drawings and that the reinforcing steel in
the walls directly above the coping has doubled (12mm bars as 200crs in lieu of
the typical spacing of 400crs) when compared to the other block walls of similar
height. These observations we believe are confirmed by the subsequent
performance of the structures which have now been constructed and subject to a
load for approximately five (5) years with weather conditions having changed
from extreme dry to extreme wet (experiencing significant rainfall) and thus giving
rise to actual layers in accordance with actual real site conditions being realised.
Notwithstanding any of this information, the defects described in the available
-- 38 of 50 --
39
reports and photos indicate that the defects are aesthetic as described by both
HBW and EFC, and are commonly found in other similar structures and at this
stage no actual measurement of any ongoing rotation or failure mechanism has
been presented for objective comments. Defects in the form of cracks to
masonry walls and gaps around construction joints are common place and whilst
not desirable, those are often inevitable. To this point we include that Table C1
from AS2870-Residential Slabs and Footings Code which classifies damage with
respect to walls. While this Code is not strictly applicable in a case where the
structure is being considered, we believe this classification nevertheless
constitutes a useful guide for reference.”
[287] Noting that at no stage did anyone suggest the pool area should be blocked
off from private or public access, Mr Rebibou said: “In other words, no
building professional who has gained access to the site has felt it necessary
to notify the owners of any potential for collapse and possible subsequent
injury or loss or life. In fact, this office has been advised by MPL (the
Respondent). The pool has indeed been used by the owner during the past
five (5) years or so and it was even emptied some months ago to allow for
rectifications to pool lights/waterproofing thus experiencing its worst load
conditions to date.”
[288] According to Mr Rebibou the evidence indicating any structural inadequacy
was a result of limited existing engineering assessment where technical
assumptions were made which were largely simplistic and did not hold up
when scrutinised. These were divided into two categories, the first
concerned the use of the cranked reinforcing bars which ignored the fact
that there are twice as many bars as would typically be required in such a
wall.
[289] Mr Rebibou observed that: “While it is guaranteed that the use of cranked
bars is not as effective and even restricted in some codes of practice
(mainly where the large ….. forces could be expected of such a special
purpose earthquake resistant structure) the bars used in this context clearly
have some useful structural capacity and noted in the HBW report we saw
no evidence where the cranked bars have failed or yield in any way”. ME
does not provide any objective evidence to suggest the bars have failed and
comments such as “the wall rotation has continued” cannot be evaluated by
any physical means other than the authors (sic) judgment.”
[290] The second category which Mr Rebibou addresses is the claim technical in
nature concerning questionable assumptions pertaining to the actual
retaining height of the combined pool wall and retaining wall above the
coping and a possible soil saturation leading to hydro static pressure
compounding the more traditional wall loadings. In this regard Dr Rebibou
considered that the reports such as the Des Newport Consulting Engineers
(DMCE) report represent very simplified calculations at best and whilst
these could be used in preliminary assessment to maybe warrant further
investigation and/or potential monitoring and movement defects. Mr
Rebibou did not consider that these constitute sufficient evidence to claim
the structure is inadequate. He considered the EFC report provided a much
more useful measure of the relevant structural sections and expected loads
-- 39 of 50 --
40
under consideration, which concluded that based on the „as constructed‟
physical parameters of the pool shell walls these items are structurally
sound and adequate to resist the applied loads.
[291] In conclusion Mr Rebibou believed “there is sufficient material in the form of
reports, documents and photographs to support the case that the pool shell
and walls are structurally adequate and can indeed be retrospectively
certified”.
[292] After considering all of the reports and photographs Mr Rebibou‟s found the
defects “that are aesthetic in nature and these do not appear to have
changed significantly since being reported in the HBW report of 2008”. Mr
Rebibou also observed that “since then, the south east has experienced
extremes in weather conditions without negatively affecting the performance
of the structure as may have originally been expressed in other engineering
reports”.
[293] In cross examination Mr Rebibou said that: “The only visible performance
defects and supporting engineering calculations supplied to date concluded
that the defect is cosmetic and directly related and to change in the stiffness
in the wall footings as influenced by reactive clay movement. This common
and expected defect is occurring at an expected control joint position and
since after years of unrestricted use of the pool and surrounding areas, and
following specific recommendations by various professionals and no
allowance has yet been made for this expected movement in the structure,
it should not even be considered as a defect (and is not in fact considered
as a defect in accordance with the NSW guide to standard tolerance for this
reason).”
[294] Mr Rebibou had no doubt that an experienced pool contractor and builder
could easily be able to combine the generic plans and others available,
generic reinforced masonry retaining wall plans to proceed and construct
the work to a structurally acceptable standard and fit for the purpose.
[295] To this end Mr Rebibou said : “Based on my observation and the extensive
photographic record available for such small structures, the builder has
visibly significantly increased the strength of the pool shell and walls with
perhaps twice as much steel required in the walls with pool walls and
coping footings are almost twice as thick as required to meet the minimum
strength requirements to satisfy expected loads to relevant Australian
standards and perhaps to reflect outcomes of discussion with the engineer.
It is my opinion the contractor has generally constructed items which have
exceeded reasonable expected performance criteria from AS3600, AS3700
and AS2870 – Damage with respect to walls to base dwellings and even
exceeded these requirements. Again, since after almost six (6) years of
use by the owners, following years of expert reports and reviews of
extensive photographic records, scans and various reports, the only real
visible defect to comment on remains the possible slight rotation of a
masonry wall/fence and an expected but still lacking control joint and how
this one may imply imminent „sudden‟ and „catastrophic‟ collapse”.
-- 40 of 50 --
41
[296] Mr Rebibou was adamant that “at this stage I have not seen any evidence
to suggest that any form of rectification, other than the addition of expected
control joints” is required. Being regularly involved in the rectification of
failed structures (including failed/rotated/cracked etc… pools, retaining
walls, fences, buildings, etc…) “I would very clearly notify the client that no
amount of rectification can ensure that no cracks, no rotation or effects will
ever return/be exhibited”.
[297] Mr Rebibou considered that items relating to “sudden collapse” were
completely unrealistic under expected load conditions since the load
requires to cause actual collapse of the wall and indeed any reinforced
masonry wall of this type will always far exceed the loads required to
technically “fail” the wall is strictly defined by AS3700 – indeed, a key
feature of all reinforced structures is their ability to show ductile behaviour
and thus give possible warning of possible failure. Typically it is
unreinforced masonry and other brittle elements that would be expected to
exhibit “sudden collapse” failure mechanism not reinforced ones.
[298] Relevantly, Mr Rebibou observed of this that: “The Bernard Davis plans
which were produced nearly a year after construction present a purely
bureaucratic exercise to obtain retrospective approval of the structure in
accordance with the prevailing local bylaws and regulations have no impact
on the physical performance characteristics of the actual structures in situ.
Extensive photographic records and comprehensive scans of the structure
not often available on such small projects have been used to form the basis
of my opinion. My comments relating to the crank bars are simply to outline
how these have had and will continue to have no impact on the life of the
structure and their expected loading conditions considering that the
structures appear to be twice as thick with twice the reinforcing expected in
such structures”.
Rectification
[299] The Applicants described the entire works as a “hotch potch job” which they
could only live with and accept without the surety of safety and longevity of
the structure.
[300] They submitted that it was reasonable and necessary to remove the risk of
failure of the pool, such that the pool and retaining walls would be
demolished and be required to be replaced by a new pool and retaining
walls constructed in accordance with the relevant codes and good
engineering practise.
[301] The Applicants submit demolition and replacement of the entire structure, is
necessary for them to sell their property and adjoining property without
financial compromise.
[302] The Applicants provide expert evidence of the assessment of the costs of
demolition and replacement would be between $234,125.00 and
$221,365.00.
-- 41 of 50 --
42
[303] They contend that if no action is taken the Brisbane City Council may order
demolition of the works in their current state.
[304] The Applicants contend that the dispute is not so much about monitoring a
failing wall but more so about obtaining retrospective certification by the
Brisbane City Council to avoid an order for demolition of the works or
demolition replacement of those works.
[305] On the other hand the Respondent submitted that the Applicants had been
“actively trying to prevent the walls from being retrospectively certified (and
making the structural situation much worse than it is)”.
[306] In building their case against the Respondent to prove defects and
deficiencies in the works, the Respondent says the Applicants were
engaging in a self-defeating exercise against their own interest to obtain
BCC approval.
[307] The Respondent says that despite the many and varies complaints, the
Applicants have had the benefit, enjoyment and active use of the pool over
a long period of time, while contending that they were defective to the point
of sudden catastrophic collapse.12
[308] Essentially, the Applicants‟ claim concerns assessment of damages for
defective building work.13
[309] The general rule is that the measure of damages is the difference between
the contract price the work was contracted for and the cost of making the
work conform to the contract with the addition of any appropriate
consequential damages: See Tabcorp Holdings Ltd v Bowen Investments
Pty Ltd (2009) 236 CLR 272 affirming the principles in Bellgrove v Eldridge
12 See Nguyen v Luxury Design Homes Pty Ltd [2004] NSWCA 178, see Chesire and
Fifoot, Law of Contract (9th Aus Ed, 2008) p 1081.
13 See generally Bryan Thomas, „The Assessment of Damages for Breach of Contract
for Defective Building Work‟ (2004) 20 Building and Construction Law 230; Chris
Fenwick, „Necessity, Reasonableness and Intention to Rebuild: A Reconciliation of
the Australian and English Approaches to Quantification of Damages in Building
Cases‟ (2004) 16 BDPS News: Building Dispute Practitioners’ Society Inc Newsletter
4; Douglas Bates, „The Assessment of Contractual Damages for Defective Building
Work in Australia: Is Loss of Amenity an Available Measure?‟ (1999) 15 Building and
Construction Law 2; Jocelyn Winterton, „The Use of Damages for Rectification Works:
Should the Courts Intervene?‟ (1998) 14 Building and Construction Law 2; John
Dorter and John Sharkey, Law Book Company, Building and Construction Contracts
in Australia: Law and Practice, vol 1 (at Update 67) [1.830]; Doug Jones, Building and
Construction Claims and Disputes (1996) 49–57; Philip Davenport, Construction
Claims (2nd ed, 2006) 184-92; Damien J Cremean, B A (Toby) Shnookal and Michael
H Whitten, Brooking on Building Contracts (4th ed, 2004) 186-95; Ian H Bailey,
Construction Law in Australia (2nd ed, 1998) 92-3; Jeannie Paterson, Andrew
Robertson and Arlen Duke, Principles of Contract Law (3rd ed, 2009) 382-4;
J W Carter, Elisabeth Peden and G J Tolhurst, Contract Law in Australia (5th ed,
2007) 849-50; N C Seddon and M P Ellinghaus, Cheshire and Fifoot’s Law of
Contract (9th Australian ed, 2008) 1105-7; J L R Davis, „Damages‟ in P D Finn (ed),
Essays on Contract (1987) 200, 211-15.
-- 42 of 50 --
43
[1954] HCA 36, (1954) 90 CLR 613, which remains the leading authority
when considering rectification of building works.
[310] In Bellgrove the builder committed “a very substantial departure from the
specifications and, indeed, such a departure as to result in grave instability
in the building.” at 615. The trial Judge found that the defective foundations
required demolition and rebuilding of a house in order to ensure stability.
The decision was upheld by the High Court. In their joint judgment Dixon
CJ, Webb and Taylor JJ made the following observations at 617:
"In the present case, the respondent was entitled to have a building erected on
her land in accordance with the contract and the plans and specifications which
formed part of it, and her damage is the loss which she has sustained by the
failure of the appellant to perform his obligation to her. This loss cannot be
measured by comparing the value of the building which has been erected with
the value it would have borne if erected in accordance with the contract; her loss
can, prima facie, be measured only by ascertaining the amount required to rectify
the defects complained of and so give to her the equivalent of a building on her
land which is substantially in accordance with the contract ... Subject to a
qualification to which we shall refer presently the rule is, we think, correctly stated
in Hudson on Building Contracts (7th ed. Sweet & Maxwell, 1946), p 343 "The
measure of the damages recoverable by the building owner for the breach of a
building contract is, it is submitted, the difference between the contract price of
the work or building contracted for and the cost of making the work or building
conform to the contract, with the addition, in most cases, of the amount of profits
or earnings lost by the breach ...". The qualification, however, to which this rule
is subject is that, not only must the work undertaken be necessary to produce
conformity, but that also, it must be a reasonable course to adopt."
[311] The Court concluded that, in the circumstances, demolition of the structure
and reconstruction was reasonable and necessary to provide a building in
conformity with the contract. In doing so, the Court declined to adopt a less
expensive mode of rectification involving the underpinning or the
replacement of the existing foundations saying at page 620:
"To give to the respondent the cost of a doubtful remedy would by no means
adequately compensate her, for the employment of such a remedy could not in
any sense be regarded as ensuring to her the equivalent of a substantial
performance by the appellant of his contractual obligations."
[312] In doing so, the Court laid down the principle that, in cases of defective
work, the building owner is prima facie entitled to damages representing the
cost of rectification of the work so that it achieves conformity with the
contract, along with any “appropriate consequential damages”: at 617-18.
[313] The Court imposed two qualifications upon the application of such a
measure, first, the work must be necessary to achieve conformity and
secondly, it must be a reasonable course to adopt: at 618.
-- 43 of 50 --
44
[314] As to necessity the work in question must be “apt to conform with the plans
and specifications which had not been conformed with.”14 The requirement
to achieve conformity is assumed within the essence of the contractual
bargain. The limb requires only that the work be „apt‟ (which has
connotations of being „suited to the purpose‟)15 to achieve such conformity.
Thus, work which is not directed towards such conformity may not be
„necessary‟.16
[315] Where the necessary work is not a reasonable method of dealing with the
situation, the Court said that „the true measure of the building owner‟s loss
will be the diminution in value, if any, produced by the departure from the
plans and specifications or by the defective workmanship or materials.”: at
619.
[316] In accordance with these principles, the measure of damage for defective
work performed in breach of contract is the cost of rectification. Both the
manner of rectification and the cost of performing it must be reasonable
having regard to the circumstances of this case. The test is what work is
reasonably required to restore the Applicants to that which should have
been provided had the contract being performed. This may involve, for
example, demolition of the work, even at a cost greater than the contract
price, provided that course is reasonable.
[317] However, where rectification work has or will produce a pool which is better
or lesser than that contemplated by the contract, an adjustment must be
made for the difference in value. For example, if an applicant receive a pool
which is less satisfactory then that which ought to have been provided
under the contract, the damages awarded should include the sum for the
cost of the rectification in compensation for this. On the other hand, where
the rectified pool is more valuable than what is contracted for, the applicant
is not entitled to have the cost of rectification reduced to allow for the
betterment to the applicant.17 The betterment is the result of the voluntary
choice of the proprietor18 or the result of a failure to mitigate the loss; or out
of all proportion to the loss caused by the breach of contract.19
14 Tabcorp [2009] HCA 8; (2009) 236 CLR 272, 288 (French CJ, Gummow, Heydon,
Crennan and Kiefel JJ).
15 Susan Butler (ed), Macquarie Dictionary (5th ed, 2009) 76.
16 Bell, Matthew "After TABCORP, for Whom Does the BELLGROVE Tolls? Cementing
the Expectation Measures as the 'Ruling Principle' for Calculation of Contract
Damages" [2009] Melbourne University Law Review, Volume 32, Issue 3, pp. 684-
717.
17 British Westinghouse Electric and Manufacturing Co Ltd v Underground Electric
Railways Co of London Ltd [1912] AC 673; [1911-13] All ER Rep 63; Harbutt’s
‘Plasticine’ Ltd v Wayne Tank and Pump Co Ltd [1970] 1 QB 447; [1970] 1 All ER
225; [1970] 2 WLR 198 (no credit required merely because destroyed factory
replaced with new building of modern design); Cooke v Rowe [1950] NZLR 410;
Barclays Bank Plc v Fairclough Building Ltd (No 2) (1994) 39 Con LR 144 at 154-5.
18 Hoad v Scone Motors Pty Ltd [1977] 1 NSWLR 88 at 93 per Moffitt P; Richard
Roberts Holdings Ltd v Douglas Smith Stimson Partnership (1988) 46 BLR 50 at 69;
22 Con LR 60, Official Referee.
19 Bacon v Cooper (Metals) Ltd [1982] 1 All ER 397 at 400 pre Cantley J, QB; Hoad v
Scone Motors Pty Ltd [1977] 1 NSWLR 88 at 95 per Moffitt P. Also Ruxley
Electronics and Construction v Forsyth & Ors [1996] 1 AC 344.
-- 44 of 50 --
45
[318] The Tribunal has carefully read and taken into account all of the
engineering reports, other evidence and submissions from both sides.
[319] The Tribunal finds itself comfortably persuaded by the engineering reports,
in particular those of Mr Davis, Mr Fox, Mr Wenck and Mr Rebibou, to
conclude that it is not reasonable or necessary to demolish the pool and
wall structure in whole or in part.
[320] Notwithstanding the Applicants criticises the last two mentioned engineers
for inadequate site inspection, the extensive photographs taken by the
Applicants, and earlier engineering reports, and the passage of time, are
more than sufficient to have formed a proper expert judgment of the
structure.
[321] Whatever the debate about Part 4 of the DBC Act and s 70 of the Building
Act 1975, the role of the certifier and the state of plans, according to the
preponderance of engineering opinion, the pool and wall structure is
fundamentally sound. The Respondent can hardly be held to account for
any misconduct by the certifier outside of their knowledge. The Tribunal is
satisfied that there were engineering plans, even if generic, which were
adequate and sufficient. This was standard acceptable practice of
engineers, certifiers and builders. Departures from the Building Regulation
2006, the DBC Act, and Contract warranties do not necessarily lead to the
conclusion that structure is unsound. The certifier, whatever misconduct
can be attributed to him, was an engineer and satisfied. The other
engineers called by the Respondent are satisfied. To rely on these
provisions to argue for a site specific boutique plan for each and every more
or less standard structure is to read these sections too narrowly. In any
event even if there were deficiencies in the plans (which is not found) and
errors in the certification process by the certifier, such as to make out a
breach of any statutory or contractual warranty, the fact remains that the
pool and walls are fit for purpose and has stood the test of time.
[322] The Tribunal concludes that the Applicants‟ claim for demolition and
replacement is not open, has no proper basis, and must be refused.
[323] Based on the engineers‟ reports, the Tribunal finds the pool structure is
sound and Applicants have not satisfied the Tribunal that the whole, or any
part of the structure should be demolished and replaced by another pool or
wall.
[324] Having carefully considered the evidence, including all of the engineer
reports and submissions, the Tribunal finds that:
a) the pool is structurally sound;
b) the walls are structurally sound;
c) there is no current failure in the walls;
d) failure in the pool and the walls is not likely in the warranty period;
e) the structure has not yielded through the full spectrum of climatic
conditions over recent years;
f) no part of the project structure is likely to suffer sudden or slow failure;
-- 45 of 50 --
46
[325] The Tribunal finds the only issue open for consideration for rectification is:
a) the control joint in the west wall which should be repaired; and
b) an area of the north-western corner wall should be corrected.
[326] The change of level, and associated counterfort wall located in the north-
western corner of the pool should be reconstructed and engaged with the
footing and a section of wall attached to the facing wall.
[327] Mr Wenck was of the view that “detailing and construction of the counterfort
wall at the north-western corner of the swimming pool is insufficient for its
intended duty and the counterfort should be removed and replaced by a
new panel as detailed in the drawings that accompany the Form 15
prepared by Leisure Engineering Pty Ltd.”
[328] The Tribunal does not accept the Form 16 issued by Leisure Engineering is
meaningless because no engineer from that company inspected the
reinforced steel before the concrete was placed and drawings were
produced based on the word of the Respondent. Given the engineering
evidence the Form 16 is sufficient.
[329] Accordingly, the Tribunal will order the Respondent to repair the control joint
in the west wall and to make rectification as set out by Mr Wenck for the
counterfort wall at the north-western corner of the swimming pool.
[330] Upon these repairs and rectification the structure is ready for and should be
certified.
[331] The Applicants submitted that of the requirements for the issuing of a final
certificate by the BBC included the revision of the cadastral survey.
[332] To this end the Applicants commissioned a cadastral survey by Landmark
Consulting at a cost of $4,750.00 which indicated the Respondent‟s building
works (at the end of the return buttress to the concrete retaining wall) at the
western boundary of the property had encroached into the next property by
40 mm. The cost of correction by shaving of the wall is assessed at
$500.00.
[333] The Applicants own the adjoining property on the other side of the western
wall. Needless to say no dispute has arisen as may otherwise have been
with adjoining neighbours, suffering a trifling trespass.
[334] The Tribunal hesitated in being persuaded to make any order for
rectification or damages in the amount claimed on the principle of “de
minimis non curat lex”. However on balance, the Tribunal will order the
Respondent pay the corrective cost of $500 for shaving the wall.
[335] The Applicant made claim for the costs of reimbursements for filling the pool
water and acquiring pool accessories ($5,105) and the cost of correcting
leaks ($4,546).
-- 46 of 50 --
47
[336] The problem for the Applicants is that these amount were incurred after the
Applicants were in breach:
a) by not paying the outstanding excavation and extra-concrete costs;
b) by attempting make good the leaks themselves when the Applicants
were not entitled to enter upon the construction site;
c) or alternatively after the Applicants purported to have terminated the
Contract.
[337] The Tribunal dismisses the claim for pool water, accessories and costs of
correcting leaks.
Unlawful Entry
[338] The Applicants allege that there were repeated unlawful entries by the
Respondent and/or its agents on the Applicants‟ property after termination
of the contract being:
a) on 31 January 2008 when two directors entered upon their property;
b) on 3 March 2008 when three sub-contractors entered the property; and
c) on 6 March 2008 when two sub-contractors entered.
[339] As a result the Applicants fitted locks at the cost of $44.00 to the security
gates and erected signs naming the Respondent as a cost of approximately
$20.00.
[340] As to the repeated unlawful entries the Respondent denies that the Contract
was unlawfully terminated on 21 December 2006 or that it unlawfully
accessed the property.
[341] Further, the Respondent says that the alleged breach of access on 3 March
2008 and 6 March 2008 do not concern the Respondent in the Amended
Claim.
[342] The Respondent says that the complaints of unlawfully entry are not a
building dispute within the meaning of Schedule 2 of the Queensland
Building Services Authority Act 1991, such that the Tribunal does not have
jurisdiction under s 77(1) of the QBSA Act to decide this matter because it is
not a building dispute.
[343] The Tribunal is persuaded by the submissions of the Respondent and
makes no order in terms of the Applicants‟ claim for damages for unlawful
entry.
Claim for stress, inconvenience, etc.
[344] The Applicants seek damages for pain, suffering, loss of enjoyment, stress
and inconvenience arising from the dispute.
[345] By paragraph (c) of the relevant definition in the dictionary in schedule 2 to
the QBSA Act, "Domestic building dispute means ….(c) a claim or dispute
in negligence, nuisance or trespass related to the performance of
reviewable domestic work other than a claim for personal injuries."
-- 47 of 50 --
48
[346] "Reviewable domestic work" is defined as meaning "domestic building work
under the DBC Act except that for applying section 8(8) of that Act the
definition excluded building work in that Act is taken not to mean anything
mentioned in paragraph (b), (c) or (d) of the definition."
[347] Generally, where there is a breach of contract, damages are not
recoverable for non-pecuniary losses such as injured feelings, stress,
anxiety or disappointment.20
[348] A plaintiff may be able to recover damages for injury to feelings in tort, but
in contract such damages are irrecoverable.21
[349] The Respondent denies they are liable for any stress and inconvenience
and loss of enjoyment, but in any event say that this is outside the terms of
the QBSA Act and is not a building dispute for which the Tribunal has
jurisdiction.
[350] More over by statutory definition a claim for personal injuries is not part of a
domestic building dispute.
[351] The Applicants are unable to recover damages under this head of claim in a
building dispute which is contractual in nature, the Tribunal is unable to
order damages for pain and suffering under the QBSA Act. The Tribunal
dismisses the Applicants‟ claim for pain, suffering, loss of enjoyment, stress
and inconvenience arising from the dispute.
Costs
[352] Section 100 of the QCAT Act provides that “other than as provided under
this Act or an enabling Act, each party to a proceeding must bear the party's
own costs for the proceeding.” Ordinarily the Tribunal does have the power
to award costs if it considers the interests of justice require it to do so.
Various factors the Tribunal may have regard to in making that decision are
set out in s 102(3) of QCAT Act.22
[353] However s 77 of the QBSA Act confers jurisdiction on the Tribunal to
determine building disputes such as the one brought by the Applicants.
Section 77(1)(h) provides that, in such proceedings, the Tribunal may award
costs. The section does not provide further guidance or prescription about
the occasions for or conditions of exercise of that power. Accordingly an
enabling Act, the QBSA Act, does, provide otherwise. As a result, the usual
position as to costs in the Tribunal is displaced. That result is reinforced by
20 Addis v Gramaphone Company [1909] AC 488; reaffirmed by the Court of Appeal in
Bliss v South East Thames Regional Health Authority [1985] IRLR 308; Jarvis v Swan
Tours [1973] 2 QB 233; Alexander v Rolls Royce Motor Cars [1995] TLR 254; Baltic
Shipping v Dillon (1993) 176 CLR 344 and Jarvis v Swan Tours Ltd [1973] 1 QB 233.
21 Ibid.
22 Kehl v Board of Professional Engineers of Queensland [2010] QCATA 77.
-- 48 of 50 --
49
other provisions dealing with the relationship between the QCAT Act and
enabling Acts.23
[354] There is no doubt that the parties have spent a considerable amount of
money in obtaining professional advice from lawyers, engineers, certifiers
and quantity surveyors examining the building works.
[355] The Applicants make claim for expert opinions in the sum of $30,390.00.
These were for the inspections, mediation and engineering reports. They
also make claim for $836.00 in miscellaneous (application fee, copying,
parking).
[356] The Applicants have also spent and claimed sums incurred in legal
expenses of their lawyers which they consulted weekly from December
2007 to March 2009.
[357] The Respondent has spent the cost of $3,278.00 for a wall assessment
report and no doubt met the not inconsiderable expenses of obtaining the
reports of Mr Davis, Mr Wenck and Mr Rebibou.
[358] The Respondent denies that it is liable for any cost voluntarily undertaken
by the Applicants in commissioning expert inspections and advice or
securing the property. No doubt the Applicants take a similar view of the
Respondent‟s engineering costs.
[359] It is submitted on the Applicants‟ part that the costs of the engineers
engaged was necessary to find a solution to the problem pertaining to
retrospective certification and on the Respondent‟s part to disprove the
claim for complete demolition and replacement.
[360] This claim relates to the costs incurred to date and the costs which will be
incurred by the Applicants to achieve rectification or construction of the
works to adhere with the regulations of the BCC requirements and the
Building Act 1975.
[361] The Applicants have succeeded in obtaining rectification for repairs to the
control joint and the north-western wall and shaving of the wall, but failed in
the major claim for demolition and replacement. The Respondent has
succeeded on the excavation and extra-concrete costs.
[362] Much good money has been spent of trivial disputes and irrelevancies in an
intense, needlessly adversarial, and personal disputation, which proved
impervious to mediation and engineering conclave.
[363] In the circumstances there will be no order for costs. The applications by
both parties for costs are dismissed.
Orders
23 See Judge Kingham in Lyons v Dreamstarters Pty Ltd [2011] QCATA 142; Justice
Alan Wilson Lida Build Pty Ltd v Miller and Anor [2011] QCATA 219.
-- 49 of 50 --
50
[1] The Tribunal orders pursuant to s. 77 of the Queensland Building Services
Authority Act 1991:
(a) The Applicants pay to the Respondent the sum of $5,413.73
plus interest at 10% calculated from 17 November 2006, such sum to
be paid within 30 days;
(b) The Respondent:
(i) pay to the Applicants the sum of $500 for rectification for
shaving the 40 mm wall encroachment, such sum to be paid within
30 days;
(ii) make rectification:
by repairing the control joint in the west wall;
as set out by Mr Wenck for the counterfort wall at the north-
western corner of the swimming pool as detailed in the
drawings that accompany the Form 15 prepared by Leisure
Engineering Pty Ltd;
[2] The Amended Application of the Applicants and the Amended Defence of the
Respondent are otherwise dismissed.
[3] No order is made as to costs.
-- 50 of 50 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2012/132