Avilake Pty Ltd v Tucker and Anor [2012] QCAT 41
CITATION: Avilake Pty Ltd v Tucker and Anor [2012]
QCAT 41
PARTIES: Avilake Pty Ltd ABN 341 105 202 71
v
William Edward Tucker
Julie Jean Tucker
APPLICATION NUMBER: BD486-09
MATTER TYPE: Building matters
HEARING DATE: 12 & 13 September 2011
HEARD AT: Brisbane
DECISION OF: Ann Fitzpatrick, Member
DELIVERED ON: 6 January 2012
DELIVERED AT: Brisbane
ORDERS MADE: [1] The applicant’s application is
dismissed.
[2] The respondents’ counter-
application is dismissed.
[3] The applicant file and serve any
further submissions in relation to
costs by 13 January 2012.
[4] The respondents’ file and serve any
further submissions in relation to
costs by 27 January 2012.
[5] The applicant file and serve any
reply by 7 February 2012.
CATCHWORDS: Practical completion stage payment – claim
for debt not damages – suspension of works
– validity of notice of intention to terminate
and termination of contract – wrongful
repudiation – time for performance of
defective and incomplete work
Domestic Building Contracts Act 2000, s 67
APPEARANCES and REPRESENTATION (if any):
APPLICANT: Avilake Pty Ltd represented by Mr Kym Flehr
of Kym Flehr Legal Solutions
-- 1 of 32 --
2
RESPONDENT: William Edward Tucker and Julie Jean
Tucker represented by Ms Gemma Robson
of McCarthy Durie Lawyers
REASONS FOR DECISION
[1] The applicant, Avilake Pty Ltd filed an application in relation to a domestic
building dispute in the former Commercial and Consumer Tribunal on
19 November, 2009. The functions of that Tribunal with respect to
domestic building disputes are now performed by the Queensland Civil
and Administrative Tribunal.
[2] By its application, Avilake seeks an order for payment by the respondents,
Mr and Mrs Tucker, of the following sums:
(a) $25,500.00 being the amount alleged to be outstanding under a
residential building contract between the parties;
(b) $3,502.57 being the amount alleged to be owed pursuant to a
preliminary agreement between the parties.
[3] The applicant also seeks interest and costs.
[4] The Tuckers deny that they owe any sum to Avilake and have lodged a
counter-application, seeking orders for payment by Avilake of certain
sums for rectification of alleged defects, completion of building works, the
cost of a building inspection report and legal costs. In their final
submissions, the Tuckers also sought an order that Avilake release all
building certificates it holds.
Background Facts
[5] The following facts are set out in the various statements filed and
tendered in these proceedings. I accept the evidence in relation to these
matters, except where I note that the asserted facts are disputed. In
which case a separate finding will be made, if necessary.
[6] Avilake is a licensed builder. Its Director, Tim Jackson was the builder’s
representative.
[7] The Tuckers proposed that a house be constructed on their land at
15 Alkira Street, Macleay Island.
[8] On 15 June, 2008, Avilake and the Tuckers entered into a written
Queensland Master Builders Association form of preliminary agreement.
Under that agreement the builder agreed to:
have the site surveyed;
obtain the foundations data, e.g. soil test/ contour plan;
have drawings and specifications prepared;
-- 2 of 32 --
3
alter and amend such drawings and specifications as required by
the owner;
prepare an appropriate footings design for the site and if
appropriate a concrete slab design based upon the foundations
data;
make an application to the relevant Local Authority or Private
Certifier for approval of the building work shown on the drawings
and described in the specifications;
make application for approval to any other Authorities from which
it may be necessary to obtain approvals;
pay all fees necessary to obtain such approvals;
prepare a tender to carry out the work shown on the original
drawings and described in the specifications.
Additional tasks:
make amendments to plans on owner’s behalf.
[9] The last dot point item was said to be handwritten by Mr Jackson’s wife.
[10] Item 2 of the preliminary agreement bears the handwritten notation in Mr
Tucker’s handwriting – “Provided cost of building works does not exceed
$170,000”.
[11] Item 3 of the preliminary agreement provides that in consideration of the
builder performing the tasks, the owner agrees to pay the builder, upon
completion of the nominated tasks a certain sum. The parties are in
dispute as to whether the figure noted on the agreement is $1,200.00 or
$7,200.00.
[12] A Tax Invoice document with the words Tax Invoice/Statement struck
through and the word Receipt handwritten, dated 16 June, 2008, notes in
its body – “Received cheque (NAB) being for the amount of $2,118.00 ie
i House plans by draftsman
ii MCU (Preliminary Agreement) for No 15 Alkira St Macleay
Island”.
[13] Mr Jackson sent the Tuckers’ sketch of the proposed house to Butler
Drafting, who did basic plans lodged for Town Planning Approval, dated
29 July, 2008.
[14] A receipt dated 14 November, 2008 from Avilake to the Tuckers notes:
“Received the amount of $935.93 being for preliminary agreement ie
soil test, engineer letter, Redland City Council…”.
[15] Avilake entered into a Master Builder’s Residential Building Contract with
the Tuckers, dated 23 November, 2008, to construct a new house at
15 Alkira Street, Macleay Island (the Works).
-- 3 of 32 --
4
[16] The contract price was $170,000.00. The construction period was 250
days. The parties agreed to progress payments in accordance with
section 66 of the Domestic Building Contracts Act 2000 (DBCA). That is,
the contract was expressed to build all stages with a payment for the
deposit and then payments at the base, frame, enclosed fixing and
practical completion stages. The payment at practical completion stage
was expressed to be $25,500.00.
[17] A spa bath and vanity were expressed not to be included in the contract
price, but were noted as shown on the plans and specifications. The spa
bath, vanity and tiling (tiles and labour), were expressed to be material
supplied or work to be carried out by the owner, with no warranties given
by the builder.
[18] The appendix to the contract dealing with allowances for prime cost items
is blank apart from a notation said to be in Mrs Jackson’s handwriting –
“All prime cost items are standard builders range”.
[19] Mr Jackson attached to his statement, made 23 November, 2010
(Exhibit 1), a copy of what he asserts is a list of standard inclusions to be
included as part of the construction cost. The facts surrounding the
creation and status of this document are disputed by Mr Tucker.
[20] By letter dated 9 December, 2008 from the Redland City Council to
Avilake a development permit was granted following the development
application for a material change of use to construct a dwelling house.
[21] Mr Jackson instructed Butler Drafting Service to draw more detailed plans.
He collected those plans on 18 December, 2008. The plans did not
change the date in the identification box from the date of the earlier plans.
[22] Mr Jackson contends the plans were different to what he had agreed to
construct for the Tuckers, including by reference to a slab detail for the
garage and laundry. Mr Jackson contends that he discussed changes to
the plans with the Tuckers to ensure the construction cost of $170,000.00
was met, particularly in light of the cost of installing a treatment plant
which the Council required and which added $6,000.00-$8,000.00 to the
cost of the Works, not previously included in the cost of construction. He
says that the Tuckers also sought changes to the plans which he agreed
to implement. These conversations are in dispute.
[23] Mr Tucker attached to his affidavit, made 21 January, 2011 (Exhibit 10), a
copy of an invoice from Butler Drafting Service recording total fees of
$1,631.30 for house plans, on stump design, RP Plan from Department of
Natural Resources and prints for Material Change of Use and building
application. After deducting moneys paid, the sum of $643.50 remained
and that is noted as paid on 17 January, 2009.
[24] On 10 February, 2009 the Redland City Council gave a plumbing and
drainage compliance permit. The letter notes two inspections and a final
-- 4 of 32 --
5
plumbing and drainage inspection had been paid for. An Ozzi Kleen
treatment plant is described in the plans attached to the permit.
[25] Mr Jackson amended the 18 December, 2008 drawings to reflect what he
contends was the agreement of the parties, purportedly exercising his
entitlement to do so under the handwritten note on the preliminary
agreement that he might “make amendments to plans on the owners
behalf”. The Tuckers deny that Mr Jackson was entitled to make those
amendments without reference to them.
[26] Mr Jackson submitted to the Redland City Council a request to change an
existing approval, enclosing the drawings he had amended. On 5 March,
2009, Avilake wrote to the building certifier, Applied Building Approvals
requesting the plans be amended to reflect the changed drawings. The
changes noted were:
handrail and balustrading to lower deck deleted;
all decorative material to lower level stumps deleted;
fixed glass panels to front gable end deleted;
size of sliding glass door in rumpus 21.18. Size of sliding glass
door living room 21.18. Size of sliding glass door to dining front of
house 21.18;
laundry door is deleted and moved to rear of rumpus room as
shown on drawings. Laundry wall has been moved back to make
garage larger as shown on drawings;
window size change;
concrete to garage deleted.
[27] Mr Jackson submits that Applied Building Approvals certified the amended
plans, gave a copy to Mr Jackson and sent a copy to the Tuckers on
16 March, 2009. The Tuckers dispute that they received plans on that
date. Mr Tucker attaches to exhibit 10 a copy of the approved decision
notice and approved plans and specifications received on 29 April, 2009
from Approved Building Approvals, contending no amendments are
shown on the approved plans and specifications and no variations were
received or executed. The Tuckers deny receiving amended plans on or
after 16 March 2009.
[28] On 11 March, 2009 the Tuckers paid the base stage payment.
[29] On 23 July 2009 a spa bath was delivered to site. It had the word
“Renovator” printed on the side but otherwise had no markings. Mr
Jackson contends that there were no identifications, specifications or
warranty documents with it upon delivery. There is debate about the
extent of packaging around the spa bath.
[30] Without evidence of compliance with Australian Standards, the plumber
and Mr Jackson were not prepared to install the spa bath.
-- 5 of 32 --
6
[31] On 27 July, 2009 Mr Jackson sent a fax to the Tuckers advising that the
spa:
“does not give sufficient detail to ensure the spa bath installation will
allow the building and approval process to be finalized for your home.
… I am unable to warrant its performance or that I will achieve building
and plumbing final.
…any consequential costs will be at your expense.
If you wish to proceed with the installation of the spa bath as is, I will
require that you acknowledge in writing that you will accept all
responsibility for its performance and any consequential costs that may
occur to achieve a building and plumbing final.
…”
[32] On 28 July, 2009 the Tuckers advised they had referred the matter to their
solicitor.
[33] On 29 July, 2009 Avilake sent a Practical Completion Notice to the
Tuckers. The Notice, although sent ahead of the date, named 5 August,
2009 as the date of practical completion and nominated a final inspection
for that day.
[34] On 29 July, 2009 Avilake sent a tax invoice to the Tuckers for the
progress payment for practical completion.
[35] On 3 August, 2009, the Tuckers responded asserting Avilake was not
entitled to exclude warranties with respect to the spa, requiring installation
to proceed, denying that practical completion could be achieved on
5 August, 2009, requesting a different date for final inspection and
asserting that delivery of an invoice for the practical completion stage was
a breach of the DBCA.
[36] On 4 August, 2009 the Tuckers wrote to Avilake asserting that the
“Inclusions” list sent to them by their bank infringed the prime cost
provisions of the DBCA. They also listed a number of alleged defects and
incomplete items they required rectified and completed.
[37] On 5 August, 2009 Avilake wrote again to the Tuckers indicating it was
not prepared to take any responsibility for the spa and its installation, as
the supplier was not able to provide the required approvals.
[38] On 6 August, 2009 Avilake wrote to the Tuckers confirming 7 August,
2009 as the date for the final inspection.
[39] On 6 August, 2009 the Tuckers responded saying outstanding matters
should be attended to within 14 days and sending a copy of “Table 1
Marking of Products” extracted from a Standards Australia publication and
a document headed “Renovator 1500 x 1500 x 525 or 1300 x 1300 x 500”.
The document appears to be an extract from a Lanark manufacturer’s
product book. The page bears Warranty details and a symbol which by
-- 6 of 32 --
7
reference to the Standards Australia publication page suggests plumbing
safety testing had been undertaken.
[40] By letter dated 6 August 2009 the Tuckers advised that until their
concerns had been addressed and s 67(6) of the DBCA satisfied, they
could not accept 7 August 2009 as the date for final inspection or that the
Practical Completion Notice was valid under the DBCA.
[41] On 11 August, 2009 lawyers for Avilake:
withdrew the Practical Completion Notice, noting that the builder
was still to obtain final certification;
delivered a Notice of breach and suspension of works, asserting
that the Tuckers were in breach of contract by failing to supply a
spa bath which complied the Building Code of Australia and
Australian Standards and able to be fitted to owner’s house. The
Notice gave 10 days for the Tuckers to remedy the breach and
advised that the builder may terminate the contract if the breach
was not remedied.
[42] On 17 August 2009, the solicitors for the Tuckers wrote to the solicitors for
Avilake advising the spa bath is compliant with Australian Standards and
enclosing what was said to be a copy of the spa bath specifications
highlighting the fact “that it is compliant with Australian standards.” The
solicitors for Avilake later said the letter was not received and when it was
later sent said that there was no enclosure. The document referred to as
the enclosure was an extract from AS3861 Australian Standard – Spa
Baths. There was no reference in the documents to the model of spa bath
purchased by the Tuckers or a statement from the manufacturer that the
model in question complied.
[43] The solicitors for the Tuckers sought immediate advice as to why the spa
bath is said to be “non- compliant” and requested the Notice to Remedy
Breach and Notice of Suspension of Works be withdrawn immediately.
Avilake was put on notice that unless work recommenced the Tuckers
would serve a Notice to Remedy Breach.
[44] On 20 August 2009, Applied Building Approvals required Avilake to
provide a Form 15 or certificate from the manufacturer stating compliance
with current Australian Standards for the spa bath to be installed at the
property.
[45] On 21 August 2009 the solicitors for the Tuckers indicated by letter that
the spa bath manufacturer would send through documentation regarding
the spa bath’s compliance and raised other issues of concern, including a
range of defects.
[46] On 25 August 2009 the solicitors for the Tuckers wrote again referring to
the request for a Form 15 and asserting that the manufacturer was not a
competent person to give such a Form. The solicitors suggested that lack
-- 7 of 32 --
8
of a Form 15 was Avilake’s reason for suggesting the spa bath was non-
compliant.
[47] The letter asserts suspension of the works was unlawful as Avilake
“cannot lawfully suspend works due to an issue with the spa bath.”
[48] It was said:
“As your client has refused to recommence works on our clients‟
property, despite numerous requests, we have been instructed to:
1. accept your client‟s conduct of suspending the building works as
repudiation of the building contract; and
2. terminate the building contract.”
Rights were reserved in relation to the Tuckers asserted claims against
Avilake.
[49] By letter dated 27 August 2009, the solicitors for Avilake said that the
certifier, not their client required the Form 15. They pointed out that a
Form 15 is supplied pursuant to regulation 46 of the Building Regulation
2006 to a certifier in relation to the design or specification of a product
being installed as part of building works. They said that the building
certifier would not issue a final certificate until he had the spa bath Form
15 compliance certificate. It was said that it was for this reason their client
had been forced to suspend the works, as the job has not been able to
proceed to practical completion.
[50] It was denied that Avilake had received numerous requests to
recommence works.
[51] It was pointed out that the Notice to Remedy Breach had expired and had
not been complied with. The termination of the contract was not accepted
by Avilake. It was said that if the Tuckers took possession of the house
there would be deemed practical completion.
[52] In response on 31 August 2009 the Tuckers’ solicitor raised complaints in
relation to defects and incomplete work and requested a time for a
building inspector to attend site.
[53] On 1 September 2009, Avilake’s solicitor again requested a Form 15
compliance certificate and said that upon receipt their client would lift the
suspension, complete the works and issue a Notice of Practical
Completion. It was said that the site remained in the possession of the
builder.
[54] On 8 September 2009 the Tuckers’ solicitors requested access to the
property for an inspection and asserted breaches of contract by the
builder. In relation to the spa it was said that the Redland City Council did
not require a compliance certificate. It was submitted that Avilake could
-- 8 of 32 --
9
not lawfully suspend works pursuant to clause 16.1 of the contract as
there are no issues with the spa bath.
[55] On 9 September 2009 the Tuckers’ solicitors faxed to Avilake’s solicitors:
An extract from AS3861 – 1991 Australian Standard – Spa Baths;
SGS Australia Pty Ltd Test Report for “whirlpool baths and
whirlpool spas”.
[56] On 15 September 2009 the Tuckers’ solicitors requested by
16 September, advice as to when an inspection of the property could be
carried out and sought advice by 16 September 2009 as to when Avilake
intended to recommence work.
[57] On 17 September the Tuckers forwarded a Notice of Intention to
Terminate unless breaches were remedied within 10 days. The breaches
and relevant clauses of the contract were described as:
1. Unlawfully suspending works (clauses 16 and 20.1(b)).
2. Breach of the builder’s warranty to carry out works in accordance
with Plans and Specifications, by failing to lay concrete in the
garage as specified in the plans and specifications (clauses
10.1(a)(iii) and 20.1(c)).
3. Unwillingness to compete and abandoning the works (clause
20.1(d)).
4. Failing to allow the owner access to the property despite three
written requests (clause 7.4).
[58] By letter dated 23 September 2009 the solicitors for Avilake denied any
breaches as alleged by the Tuckers in their Notice. They referred to the
earlier purported termination and noted they would proceed on the basis
that the termination notice had been withdrawn. They said that their client
agreed to the Tuckers having access by notice in accordance with the
contact. They requested that the Tuckers give notice to Avilake in relation
to the proposed access. Finally they advised the building certifier had
advised the documentation supplied in relation to the spa bath was
insufficient.
[59] By letter dated 25 September 2009, the solicitors for Avilake wrote to the
solicitors for the Tuckers enclosing a letter from the certifier asserting the
amended plans were posted to the Tuckers on 16 March 2009 and that as
the concrete slab in the plan has been deleted Avilake is not in breach of
the contract. It was also said “We reiterate that your client is free to have
access to the premises by notice to our client as per the contract. It is just
a matter of your clients getting in touch with our client direct.”
[60] By letter dated 29 September 2009 the solicitors for the Tuckers advised
that the breaches had not been remedied and that their clients elected to
terminate the building contract. They advised that their clients would take
possession on 30 September 2009.
-- 9 of 32 --
10
[61] The Tuckers engaged a locksmith to give them entry to the house on
3 October 2009.
[62] By letter dated 6 October 2009 Avilake’s solicitors rejected the termination
on the basis that Avilake was not in breach. Avilake accepted the
Tuckers’ conduct in purported termination and re-entry into possession as
repudiating the contract and gave notice of termination of the contract.
They advised that because the Tuckers had taken possession of the
house when not entitled to do so, the works were deemed to have
reached practical completion from the date of possession on 2 October
2009. I note the evidence of the Tuckers that entry into possession
occurred on 3 October 2009. A tax invoice for the practical completion
stage of $25,500.00 and a tax invoice for $3,502.57, being the balance
allegedly owed under the preliminary agreement were delivered under
cover of the 6 October 2009 letter.
Tribunal Directions
[63] On 12 May 2010, this Tribunal directed that a Queensland Building
Services Authority inspector be appointed as an assessor to carry out an
inspection of the defective work, the subject of the respondents counter
claim, and provide a report to the Tribunal.
[64] It was directed that the parties be bound by the findings of the Authority’s
inspector.
[65] On 21 September 2010 the Tribunal directed that the questions for
determination by the Tribunal are:
a. whether the Tuckers lawfully terminated the contract;
b. whether Avilake was entitled to suspend the works because of the
spa bath issue;
c. whether the spa complied with Australian standards;
d. if the spa complied with Australian standards, whether sufficient
evidence was supplied to the applicant;
e. the loss and damage that flows from the above determination.
QBSA Report
[66] As Directed, the Queensland Building Services Authority (QBSA),
provided a report dated 23 June 2010.
[67] Mr Jackson complains that he was excluded from attending the inspection
conducted by the QBSA.
[68] Mr Jackson estimated the cost to remedy the defects found by the
inspector to be $842.00. A quote from another builder to perform the work
for $638.00 was filed in the Tribunal.
-- 10 of 32 --
11
[69] The Tuckers filed in the Tribunal a quote from Gary Phyland, Builder,
dated 7 March 2011 in an amount of $21,475.00 to complete tasks noted
in the QBSA report. This quote included work which Avilake contends
was excluded from the scope of work by agreement.
Claim for balance of money under Preliminary Agreement
[70] This issue was not isolated as an issue for determination in the Tribunal’s
directions of 21 September 2010. However it is a live issue between the
parties and it was fully ventilated at the hearing.
[71] The Tuckers assert that the figure on the preliminary agreement was
altered from $1,200.00 to $7,200.00. Mr Tucker in exhibit 10 says at
paragraph 8 that it is his handwriting on the preliminary agreement from
Item 2 down. He suggests that the figure $1,200.00 is in his hand and
that a stroke has been added in Mr Jackson’s hand to the “1” to create a
“7”.
[72] No forensic handwriting expert was called by either party.
[73] In evidence before me is a poor copy of the preliminary agreement
(Annexure 2 to Exhibit 10), which shows the imprint of the special
conditions on the second page having transposed onto the front page as a
result of the self-duplicating paper used. That document was put into
evidence by Mr Tucker. It is not possible to clearly discern either
“7,200.00” or “1,200.00”.
[74] I also have reference to attachment TJ A1 to the statement of Mr Jackson
made 30 May 2011, Exhibit 3, which is said to be a copy of the owners’
white copy of the agreement, made by Mrs Jackson at the time of making
the agreement, which does not have the transposed handwriting
obscuring the number in question. Mrs Jackson was not called to give
evidence. That document clearly shows the number “7,200.00”. Mr
Jackson also attached a copy of the document as TJ 3 to Exhibit 1,
however that is illegible.
[75] The Tuckers did not tender their original white copy of the agreement and
Avilake did not tender its yellow builder’s duplicate copy of the agreement.
[76] I am unable without expert evidence to say whether the agreement had
been altered to suggest the sum “7,200.00” rather than “$1,200.00”.
[77] Mr and Mrs Tucker’s evidence was that $1,200.00 was the cost of
preparing a plan to submit to the financier and that the cost of council
approval and other work covered by the agreement was to be met on
presentation of invoices. They both gave evidence that invoices were
paid as presented.
-- 11 of 32 --
12
[78] Mrs Tucker gave evidence at the hearing that the claim for $3,502.57 was
not particularized as to what work it covered. Mr Jackson did not give
evidence as to what work was covered by the sum.
[79] Other than an invoice from Butler Drafting dated 28 November 2008
forming part of Annexure 2 to Exhibit 10, no invoice from suppliers of
services required by the preliminary agreement is in evidence. General
descriptions of work appear on the receipts given by Avilake. Working
from those documents it would appear that payment has been made for
soil testing, drawings and specifications being prepared, an engineer’s
letter (this may be a reference to footings design, although there is no
evidence of this) and applications to the local authority for approval.
[80] Those items of work appear to cover the work described in the preliminary
agreement. Without invoices from the parties who performed the work, it
is not possible to say whether all the work anticipated by the preliminary
agreement was completed. I note the evidence of Mrs Tucker that the site
survey was not conducted. This was not disputed.
[81] I do not have sufficient evidence to make a finding as to whether the cost
of work under the preliminary agreement was altered from “$1,200.00” to
“$7,200.00”. I do not consider it necessary to make such a finding in any
event because of the following finding I make.
[82] It is a matter for the applicant to prove his entitlement to the balance of the
sum he alleges was the agreed contract sum. He has failed to do so. It is
not possible on the evidence to say what extent and value of work has
been performed and paid for and what work, if any, has been performed
but not paid for.
[83] On this basis, I am not prepared to order the Tuckers to pay the sum
alleged to be owed under the preliminary agreement.
What variations to the work and what amendments to the plans were
agreed?
[84] The parties are in dispute about whether agreement was reached to
amend the building plans to effect the changes reflected in the 5 March,
2009 request for amendment, made by Avilake to the Redland City
Council and to Applied Building Approvals.
[85] Mr Jackson asserts that the Tuckers agreed to the changes in order to
keep the cost of the construction to the contract price of $170,000.00 in
light of the need to install a treatment plant at the site.
[86] He asserts that some changes required by the Tuckers were also made.
He relied upon the authority to amend the plans referred to in the
Preliminary Agreement for his power to effect the changes to the plans.
The Tuckers deny giving approval for these amendments to be made and
deny receiving a copy of the amended plans approved by Council.
-- 12 of 32 --
13
[87] During cross examination the solicitor for Avilake put it to Mr Tucker that
he had agreed to omit certain items of work in order to cover the cost of
installing the treatment plant required by Council, yet still keep the
construction cost to $170,000.00. Mr Tucker denied making any such
agreement. In particular he refused to agree under cross examination
that he had agreed to drop the height of the front deck and delete the
handrail and balustrade to the downstairs deck.
[88] In his affidavit made 21 January 2011(Exhibit 10), Mr Tucker denied the
allegations made by Mr Jackson at paragraph 22 of his statement made
23 November 2010 in relation to the alleged agreement to offset items of
work to meet the cost of the treatment plant and the extra items of work
required by the Tuckers. However, Mr Tucker did say that Mr Jackson
was authorised to extend a wall behind the rumpus room and alter a rear
door from the rumpus room. He notes that no written variation was
provided for this work.
[89] Mr Tucker denied that Mr Jackson was authorized to alter the building
plans to reflect any changes. During the hearing he said that he had
forgotten about the preliminary agreement and thought it was “done and
dusted” by then.
[90] Of particular significance is whether the plans required a concrete slab in
the garage.
[91] During the hearing Mr Tucker gave evidence he considered, based on the
plans in his possession that he was to have a concrete slab laid.
However, he admitted in evidence that he agreed to forgo the concrete
slab. He said that he and his wife acquiesced to gravel being laid in the
garage, to avoid confrontation with the builder. Mr Tucker also said in
evidence that he thought they would ultimately have to pay for a concrete
slab themselves.
[92] On the basis of this evidence, I find that whether or not the Tuckers
agreed to amend the plans, they subsequently agreed to omit the
concrete slab in the garage and for there to be no consequent adjustment
to the contract price.
[93] The other area of significant dispute between the parties, which was
canvassed thoroughly with Mrs Tucker at the hearing related to the
kitchen. Mr Jackson asserts the cost allocated to the kitchen in his
costings for the contract price was $3,500.00. All sets of plans show a
basic layout for a kitchen. The list of inclusions which according to
Avilake forms part of the contract provided for:
Laminated post formed bench tops;
Dishwasher opening;
Laminated cupboard and pantry doors with handles from Builders
standard range;
-- 13 of 32 --
14
Chrome flick mixer tap & 1.5 bowl stainless steel kitchen sink from
Builders standard range;
Electric hot plates and slide out range hood.
[94] Mrs Tucker required a higher standard of kitchen and provided plans to Mr
Jackson, which the cabinet maker quoted to install for $7,391.00. Mr
Jackson required further payment to install the kitchen drawn up by the
Tuckers. The Tuckers refused to pay any extra sum. In evidence at the
hearing Mrs Tucker said that she was not happy but was prepared to
accept the standard kitchen in fact installed because of the confrontational
nature of Mr Jackson. The kitchen installed did not have overhead
cupboards. Those cupboards were subsequently installed by the builder
Mr Phyland. Mrs Tucker said in evidence that if Avilake had specified that
the value of the kitchen was only $3,500.00, they would not have signed
the contract.
[95] Mr Calvert, the cabinet maker was unavailable to give evidence. His
statement was tendered by Avilake with the consent of the Tuckers. Mr
Calvert’s statement is exhibit 8. His evidence is that he quoted for the
more expensive kitchen the Tuckers required, however, when that was
unacceptable, he drew another plan which was closer to the budget at
$4,251.50, but still had what the Tuckers wanted. The Tuckers signed the
new plans and authorised proceeding with the work. There is no formal
variation under the contract to reflect these changes.
[96] On the basis of the unchallenged evidence of Mr Calvert, I find that the
kitchen as constructed was more expensive than that anticipated in the
original plans. I find that the kitchen was built to the agreed specifications
of the Tuckers. I find that there has been no claim for additional cost by
the builder. Accordingly, the dispute in relation to the kitchen does not
sound in any loss or damage claim by either party.
[97] Other evidence was given by the electrical contractor Mark Thomson of
Macleay Island Electrical Pty Ltd. Mr Thomson was called by the builder
as a witness. His company was engaged by Avilake to provide a basic
electrical layout at the Alkira Street property. Macleay Island Electrical
was paid $4,600.00 plus GST by Avilake. Mr Thomson’s statement, dated
30 May, 2011 (Exhibit 7), records that the Tuckers spoke to him directly
about extra work which was performed on the basis of an agreement to
pay him direct. He rendered an invoice for $2,320.84 to the Tuckers
however that remains unpaid.
[98] Neither party has made any claim for loss or damage relating to the
electrical work. It would not appear to be relevant to the issues in dispute.
Did the Tuckers lawfully terminate the contract?
[99] This is the first of the issues directed to be determined as part of these
proceedings. A determination on this issue requires a consideration and
determination in relation to the other questions set out in the Directions,
-- 14 of 32 --
15
as to whether Avilake was entitled to suspend the works because of the
spa bath issue; whether the spa complied with Australian standards and if
the spa complied with Australian Standards, whether sufficient evidence
was supplied to the applicant.
[100] By facsimile transmission dated 17 September 2009 a Notice of Intention
to Terminate dated 17 September 2009 was sent to the solicitors for
Avilake.
[101] The notice gave Avilake 10 days to remedy four nominated breaches of
the contract by Avilake.
[102] Relevant clauses from the general conditions of the contract are:
7.4 Owner’s right to inspect Works
Upon written request by the Owner, the Builder must give to the
Owner, or a person authorised by the Owner;
(a) reasonable access to the Land, and
(b) a reasonable opportunity to view any part of the Works, provided
the Builder‟s performance is not obstructed.
Access shall be by prior arrangement with the Builder and shall be
during working hours or other times as agreed.
16. Suspension of the Works
16.1 Builder’s entitlement to suspend the Works
The Builder may, without prejudice to any of the Builder‟s rights under
this Contract or at law, suspend performance of the Works where the
Owner;
(a) …
(b) Fails to comply with any of its obligations under Clause 11
…
16.2 Written notice to suspend the Works
The Builder must immediately notify the Owner in writing of the
suspension and the grounds for the suspension. The Date for
Practical Completion Stage is deemed to be automatically extended by
a period equivalent to the date the Builder gives its notice of
suspension until the date the Builder recommences the Works on the
Land.
16.3 Owner to remedy breach within 7 days
The Owner must remedy the breach or breaches stated in any
suspension notice given to the Owner in accordance with Clause 16.2
with seven (7) Days after receiving the notice from the Builder.
11. Owner’s Obligations
11.10 Materials supplied by Owner to be good and suitable for
their purpose
If the Owner supplies materials for use in the Works, the Owner must
supply materials which are good and suitable for the purpose for which
-- 15 of 32 --
16
they are to be used and, unless otherwise stated in the Contract,
materials are to be new.
20. Owner’s Rights To Terminate Contract
20.1 Owner’s right to serve notice of intention to terminate
contract
If the Builder:
(a) …
(b) unlawfully suspends the carrying out of the Works;
(c) refuses or persistently neglects to remove or remedy defective work
or improper materials, so that the Works are adversely affected;
(d) is unable or unwilling to complete the Works or abandons the
Contract;
(e) is in substantial breach of this Contract
(f) …
the Owner may give a written notice to the Builder:
(i) describing the alleged breach or breaches of the Contract by the
Builder; and
(ii) stating the Owner‟s intention to terminate the Contract unless
the Builder remedies the alleged breach or breaches within ten
(10) Days after receiving the Owner‟s notice.
20.2 If Builder fails to remedy breach, Owner may terminate
Contract
If the Builder fails to remedy the breach or breaches stated in any
notice served by the Owner under Clause 20.1, the Owner may,
without prejudice to any other rights or remedies, terminate this
Contract by further written notice to the Builder, provided that such
notice of termination shall not be given unreasonably or vexatiously
and, if so given then any such notice of termination shall be null and
void and of no force or effect.
20.3 Owner may not terminate Contract in certain circumstances
The Owner may not terminate this Contract if the Owner is in
substantial breach of this Contract.
22. Builder’s Rights to Terminate Contract
22.1 Builder’s right to serve notice of intention to terminate
Contract
If the Owner:
(a)…
(b) fails to comply with any of its obligations under Clause 11
…
(a) fails to remedy any breach specified in a notice of suspension given
under Clause 16 within ten (10) Days of receipt of that notice…
the Builder may give a written notice to the Owner;
(i) describing the breach or breaches of the Contract by the Owner;
and
-- 16 of 32 --
17
(ii) stating the Builder‟s intention to terminate the Contract unless
the Owner remedies the breach or breaches within ten (10)
Days after receiving the Builder‟s notice.
22.2 If Owner fails to remedy breach, Builder may terminate
Contract
If the Owner fails to remedy the Owner‟s breach or breaches stated in
any notice served by the Builder under Clause 22.1, the Builder may,
without prejudice to any other rights or remedies, terminate this
Contract by further written notice to the Owner.
22.3 Builder may not terminate Contract in certain circumstances
The Builder may not terminate this Contract if the Builder is in
substantial breach of this Contract.
22.4 Builder’s right to recover upon termination
If the Builder terminates the Contract in accordance with this Clause,
the Builder is entitled to recover from the Owner all loss, costs,
expenses and damages in connection with the Owner‟s breach, and
the termination, as if the Owner had wrongfully repudiated this
Contract.
…
Alleged breaches
[103] The Tuckers allege in their Notice of Intention to Terminate:
“1. In breach of Clause 16 of the Contract (which outlines your
entitlement to suspend works) by unlawfully suspending Works. This
is on the basis that you had no entitlement to suspend Works pursuant
to Clause 16 of the Contract. Clause 20.1 (b) of the Contract gives the
Owners the right to terminate the Contract on this ground.”
[104] By Notice dated 11 August, 2009 delivered to the Tuckers, Avilake
asserted that in breach of Clause 11.10 of the contract, they had failed to
supply a spa bath in accordance with the Contract which complies with
the Building Code of Australia and Australian Standards and able to be
fitted to the Owners’ house.
[105] Avilake required supply of a spa bath in accordance with the Contract
which complies with the Building Code of Australia and Australian
Standards and able to be fitted to the Owners’ house.
[106] Notice was given that work was suspended until the breach was
remedied.
[107] Avilake’s closing submissions assert that the contractual obligation to
supply a spa bath which is “good and suitable for the purpose” means that
the spa bath must comply with Part 1.2 of the Building Code of Australia
-- 17 of 32 --
18
which requires that materials used are “fit for the purpose for which they
are intended.”
[108] It submits that section 1.2.2 of the Building Code provides that evidence to
support a performance requirement includes:
(i) a report issued by a registered testing authority showing that the
material has been submitted to testing to demonstrate suitability
for use in the building;
(ii) a current certificate of conformity or a current certificate of
accreditation;
(iii) a certificate from a professional engineer;
(iv) a current certificate issued by a product certification body ;
(v) any other form of documentary evidence that correctly describes
the properties and performance of the material or form of
construction and adequately demonstrates its suitability for use in
the building.
[109] I accept Avilake’s submissions and find that the Tuckers were obliged
under clause 11.10 of the contract to supply a spa bath suitable or fit for
its purpose and as a necessary incident of that obligation to provide
evidence of that performance requirement.
[110] Avilake submits that there are three schemes which evaluate and certify
building products which will satisfy the requirements of the Building Code,
including Standards Australia product marked Product Certification
Scheme, the Codemark Product Certification Scheme and the Watermark
Certification Scheme.
[111] Avilake submits that there was no Australian Standards mark, no mark
under the Watermark Certification Scheme and no mark under the
Codemark Scheme affixed to the bath or on any document accompanying
the bath to site.
[112] The plumber contracted to install the spa bath Mr Nev Jones gave
evidence and filed a statement (exhibit 6). His evidence was that the spa
bath was delivered wrapped in plastic, but with no cardboard packaging.
He said that there was no evidence of any mark on the spa bath to
indicate compliance with Australian Standards. He observed only the
work “Renovator” stamped on the spa bath.
[113] Mr Jones’ evidence was that he had experience, as a plumber and
plumbing inspector, of non- approved products with pipes blowing off after
installation. He said it was irregular not to have some Australian
Standards marking on a genuine product.
[114] Mr Jones said that he was told by the plumbing inspector from Redland
City Council that if he installed the spa he would be responsible for
anything that went wrong with it.
-- 18 of 32 --
19
[115] I accept the evidence of Mr Jones as to the fact that there was no
evidence of compliance with an Australian Standard on the spa bath or
any accompanying documentation at the time it was delivered. I also
accept the evidence of Mr Jackson on the same issues.
[116] Avilake submits that the Plumbing Code of Australia calls up the
Standards Australia “Manual for the Assessment of Risks of Plumbing
Products”. A Level 1 risk applies to plumbing products whose non-
compliance could have high impact on health and safety, infrastructure,
water conservation and the environment. Such a product is required to
bear a type one mark indicating full product certification. Level 2 applies
to medium impact risk and is satisfied by a “type test” certification mark
which must be on the product.
[117] Mr Jackson gave evidence that he was particularly concerned by the lack
of evidence of certification that the product was fit for its purpose, because
of recent advice from the Building Services Authority about the risk of
imported building products not complying with Australian Standards, his
knowledge of a Public Health fact sheet in relation to the installation of
spas and an article on the drowning of a young girl in a non-compliant
spa. I accept Mr Jackson’s evidence as to the seriousness of the matter.
[118] I accept that it was necessary for Mr Jackson and any plumber installing
the spa to be satisfied the spa bath was certified as fit for its purpose in
accordance with a recognized certification scheme or could be otherwise
deemed fit for its purpose under the Building Code of Australia.
[119] On this basis I find that it was appropriate and in accordance with the
contract for Avilake to suspend work until a spa bath was supplied with
evidence that it complied with the contractual and Building Code of
Australia requirement, that it was fit for its purpose.
[120] As to what was necessary to satisfy the builder the spa bath was fit for its
purpose, on 20 August 2009, the building certifier, Applied Building
Approvals required a Form 15 or certificate from the manufacturer stating
compliance with current Australian Standards for the spa bath to be
installed.
[121] Avilake in its closing submissions refers to the Code of Conduct for
Building Certifiers, issued by the Queensland Government Department of
Infrastructure and Planning 14 November 2003 and section 56 of the
Building Act 1975.
[122] Mr Holley from Applied Building Certifiers gave evidence at the hearing,
that he, not the Redland City Council, was responsible for certifying that
plumbing products are fit for their purpose. He said that the Council are
responsible for plumbing and drainage, not products. He said that he
requires evidence that all spa baths he inspects meet Australian
Standards. He said that the Building Act 1975 and Building Code of
Australia set out the requirements that must be met.
-- 19 of 32 --
20
[123] I accept that in properly fulfilling his functions the building certifier must
decide whether a design or specification complies generally with the
Building Code of Australia and that materials used are fit for their purpose.
[124] Avilake submits that pursuant to section 46 of the Building Regulation
2006 a competent person may give the building certifier a certificate that a
building design or specification will if installed or carried out under the
certificate, comply with the Building Assessment Provisions.
[125] I accept that this is the legal position and that if required, a certificate must
be in the approved form, which is a Form 15. I note and accept Avilake’s
submission that a building certifier may request such a certificate from any
person the building certifier has decided is competent to give the
specification help.
[126] Mr Holley said in evidence that he had recently received a Form 15 from
the manufacturer of the spa bath, Lanark on another job in relation to
another product for another builder.
[127] By the time Applied Building Approvals wrote on 20 August 2009 requiring
a Form 15 or a certificate from the manufacturer, the Tuckers had
provided on 6 August 2011 an extract from the Australian Standards
publication in relation to marking of products and an extract from the
manufacturers product book suggesting the Renovator 1500 x 1500 or
1300 x 1300 x 500 had been type tested. It is not possible to tell if the
model delivered by the Tuckers to site was the model referred to in the
photocopy supplied.
[128] Under cross examination at the hearing Mr Tucker said that the
manufacturer’s product book sheet sent on 6 August 2009 related to a
later model. He asserted that the model spa bath he and his wife
purchased was exactly the same. I do not accept the evidence of Mr
Tucker that the spa he and his wife purchased was exactly the same and
therefore by implication must have the benefit of the type testing which
appears to have been achieved for the later model.
[129] Mr Tucker does not have the expertise to say what technical
manufacturing differences may or may not be present from model to
model.
[130] I also note that under cross examination Mr Jackson denied that the spa
bath depicted in the manufacturer’s product sheet was the same as the
spa bath delivered to site. He said that the blowholes shown on the
photograph were not part of the bath delivered to site. In response to a
question from me, Mr Jackson said that the spa bath depicted in the
photograph in the manufacturer’s product sheet differed from the one
delivered to site in that the one at site had no Lanark marking and no
blowholes.
-- 20 of 32 --
21
[131] On 21 August 2009 the solicitors for the Tuckers said that the spa bath
manufacturer would send through documentation regarding the spa bath’s
compliance.
[132] On 9 September 2009 the Tuckers sent Avilake an extract from AS3861
1991 Australian Standard – Spa Baths and SGS Australia Pty Ltd Test
Report for whirlpool baths and spas. It is not apparent from the face of
the Test Report if the model of spa bath purchased by the Tuckers was
tested and the significance of the testing to the Building Code of Australia
requirement that the spa bath be fit for its purpose.
[133] Under cross examination, Mr Tucker said that he did not know why the
manufacturer had sent that test report.
[134] On 21 September 2009, the Building Certifier wrote to Avilake saying it
was not satisfied with these documents as there was no Form 15 signed
by a competent person. It required information as to the brand of spa
bath given the reference in the testing to “Whirlpool spa and baths”. In
evidence Mr Holley said that he could not confirm the forms he was sent
were for the right spa. He also said he rang Lanark but could not get a
satisfactory response.
[135] As to the Tuckers’ submissions on this point I note their submissions that
the spa bath was delivered new and packaged. That is not the key point.
I accept that the bath delivered was new and was at least wrapped in
plastic.
[136] The key point is whether the builder and the building certifier could be
satisfied, at the time the contract was on foot, that the spa bath met
Australian Standards as to fitness for purpose, by reference to an
acknowledged testing and certification regime relevant to the spa, or by a
certificate in Form 15 under the Building Regulation 2006 given by a
competent person. I find that they could not be satisfied on the basis of
the information provided to them by the Tuckers.
[137] It is not relevant that Mr Holley may now accept that certain Lanark
products comply with Australian Standards. Given the evidence, which I
accept, that the plumbing inspectors’ role relates to plumbing and
drainage work and not the status of particular plumbing products, I do not
think it is relevant that the plumbing at the property complied with
Council’s requirements.
[138] I accept the evidence of Mr Holley, such that, as at 21 September, 2009
the Tuckers had not given any sufficient evidence as contemplated by the
Building Code of Australia that the spa bath at the site was fit for its
purpose. I find that as a necessary incident of their obligation under
Clause 11.10 of the contract the Tuckers were obliged to provide that
evidence.
-- 21 of 32 --
22
[139] I find that the Tuckers failed to comply with their obligations under Clause
11 of the contract and on that basis Avilake was entitled to give the Notice
of breach and suspension of Works, on 11 August 2009. I find that
Avilake did not unlawfully suspend carrying out of the Works which may
have entitled the Tuckers to serve a notice of intention to terminate the
contract under Clause 20.1(b) of the Contract. Accordingly this was not a
ground on which the Tuckers could rely to give their Notice of Intention to
Terminate the Contract.
[140] The next breach alleged by the Tuckers in the Notice of Intention to
Terminate is:
“2. In breach of Clause 10.1 (a)(iii) of the Contract… “you will carry
out the Works
(iii) In accordance with Plans and Specifications”
by failing to lay concrete in the Garage as specified in the
plans and specifications, despite numerous requests by the
Owners.”
[141] I have previously found that the contract was varied by consent to omit the
concrete slab in the garage. Further, I note the evidence of the QBSA in
its report that the house has been built substantially in compliance with
the final approved plans. I have found that there was to be no adjustment
to the contract price as a result of the Tuckers agreement that no concrete
slab was to be laid in the garage.
[142] On this basis I find that Avilake was not in breach of contract by failing to
construct a concrete slab in the garage.
[143] I am conscious that the requirements of the contract and the Domestic
Building Contracts Act 2000 (DBCA) have not been met in relation to
preparation of a variation document to record the variation and agreement
by the building owner. However, a failure to document the agreed
variation does not mean that the variation was not agreed nor that the
works were not constructed in accordance with the consequently changed
plans and specifications. Section 92 of the DBCA provides that a failure
by a building contractor to comply with a requirement under the Act in
relation to a domestic building contract does not make the contract illegal,
void or unenforceable.
[144] I accept the evidence of Mr Jackson that the variations were necessary to
keep the cost of the Works to the contract sum in light of Council’s
requirements that a treatment plant be installed on site. Accordingly, I find
that there is consideration for the variation. The significance of a failure to
prepare a written variation document is the impact on the builder’s ability
to recover the additional cost of varied work, unless the provisions of
section 84 of the DBCA are met.
[145] I find that failure to lay concrete in the garage is not a ground on which the
Tuckers could rely to give their Notice of Intention to Terminate the
-- 22 of 32 --
23
Contract, because there has been no breach of contract by Avilake by
failing to lay concrete in the garage.
[146] The third asserted breach is:
“3. In breach of the Contract in that you are unwilling to complete the
Works and have abandoned the Works…”.
[147] I do not consider there is any evidence that Avilake was unwilling to
complete the Works or had abandoned the Works.
[148] I have found that the works were validly suspended under the contract.
The evidence reveals consistent efforts on the part of the builder and the
certifier to obtain evidence of compliance of the spa bath with the legal
and contractual requirement that it was fit for its purpose so that work
might resume and the construction be completed.
[149] In particular I note the letter from the solicitors for Avilake to the Tuckers’
solicitors dated 27 August, 2009 sent after the first purported termination
of the contract by the Tuckers. It explained the need for a Form 15 and
gave the legal basis for the request for the Form. It denied numerous
requests to recommence work had been received. Indeed there was no
such evidence given in this matter. By a further short letter sent on the
same day the solicitors for Avilake said: “if your client would like to
"unterminate” the Contract (and get the Certifier the Form 15 for the spa
bath) I will get from my client a list of what is needed to be done to finish
the house (and you can get instructions as to whether there are any other
items)”. Again on 1 September, 2009, the solicitors for Avilake advised
that upon supply of the Form 15 their client would lift the suspension,
complete the contract works and give Notice of Practical Completion. It
was said “in the meantime our client is in possession of the works
pursuant to the contract.”
[150] I find that Avilake was not unwilling to complete the Works nor had it
abandoned the Works. Accordingly, I find that Avilake was not in breach
of the contract for these reasons and that failure to complete or
abandonment was not a ground on which the Tuckers could rely to give
their Notice of Intention to Terminate the Contract.
[151] The final breach asserted in the Tuckers’ Notice of Intention to Terminate
is:
“4. In breach of Clause 7.4 of the Contract which provides:
“Owner‟s right to inspect Works
Upon written request by the Owner, you must give to the Owner, or a
person authorised by the Owner;
(a) reasonable access to the Land; and
(b) a reasonable opportunity to view any part of the Works
provided your performance is not obstructed…
-- 23 of 32 --
24
In failing to allow the Owner‟s reasonable access to the property
despite three (3) written requests. This has now become a substantial
breach as you have received three written requests for access to the
property…”.
[152] I find that whatever the position might have been in relation to allowing the
owners access to the site for an inspection prior to service of the Notice of
Intention to Terminate, after receipt of the Notice, the solicitors for the
Tuckers were advised on 23 September 2009 and 25 September 2009
that the builder agreed to the Tuckers having access and requested that
the Tuckers contact the builder direct to give notice in relation to the
proposed access. There is no evidence that the Tuckers did so.
[153] Accordingly, I find that if there was any breach of the contract in this
regard, it was remedied within the specified time so that this was not a
breach on which the Tuckers could rely to terminate the contract.
[154] I find that the Tuckers did not lawfully terminate the contract. In addition
to the reasons for this finding set out above, I find that the Tuckers failed
to supply evidence of the spa bath’s fitness for purpose and were
themselves in breach of contract as at the date of their wrongful
termination. Clause 20.3 of the contract provides that the owner may not
terminate the contract if the owner is in substantial breach of the contract.
The Tuckers conduct in this regard provides further evidence of wrongful
termination.
Findings
[155] On the basis that I have found Avilake was not in breach of the contract
as alleged in the first three grounds of the Notice of Intention to Terminate
and in the case of access to the property, that any breach had been
remedied; I find that the Tuckers did not lawfully terminate the contract as
a result of failure by Avilake to remedy the breaches set out in the Notice.
[156] I have found that Avilake was entitled to suspend the works because of
the spa bath issue.
[157] I make no finding as to whether the spa complied with Australian
Standards as there is insufficient evidence before me to do so. I do not
consider that is in any event germane to the issue of whether Avilake had
validly suspended the works. The relevant issue is whether sufficient
evidence had been supplied to Avilake as to compliance with Australian
Standards. I have found that insufficient evidence was supplied to Avilake
on this issue and that suspension of the works was justified pending
receipt of that information.
[158] For completeness, it is necessary to consider Avilake’s subsequent
actions in terminating the contract.
Avilake’s termination of contract
-- 24 of 32 --
25
[159] By letter dated 6 October, 2009 the solicitors for Avilake wrote to the
solicitors for the Tuckers saying they were instructed “to accept your
clients‟ conduct in purported termination and re-entry into possession as
repudiating the contract and to give on its behalf notice of termination of
the contract. Your clients have taken possession of the house when not
entitled to do so. Accordingly pursuant to clause 17.9 of the contract the
works are deemed to have reached practical completion from the date of
possession on 2 October, 2009.”
[160] I find that the conduct of the Tuckers in delivering a Notice of Intention to
Terminate when there was no default in relation to three of the four
grounds of breach nominated and proceeding to terminate when one
ground of possible breach had been remedied, together with taking
possession of the house, amounts to a repudiation of the contract.
[161] Repudiation involves a party renouncing his liabilities under the contract
by evincing an intention to no longer be bound by the contract.i
[162] I find that Avilake, by the letter of 6 October 2006 has accepted the
repudiation and terminated the contract. That termination has been
effected in accordance with a common law right. The contract at clause
22.2 specifically recognises that termination pursuant to the mechanism
set out in the contract is “without prejudice to any other rights or
remedies”.ii By entering into possession of the house the Tuckers have
made further performance of the contract by the builder impossible,
leaving Avilake with no alternative but to accept the repudiation and
terminate the contract.iii
Loss and Damage
[163] I have found that the contract was terminated on 6 October, 2009, when
Avilake accepted the Tuckers’ repudiation of the contract arising out of
their wrongful termination and taking possession of the property. Avilake
is therefore entitled to recover loss or damage which had accrued at that
time, including any debt owing at the time of termination. Dixon J in
McDonald v Dennys Lascelles Ltd explained the consequences of
termination on existing contractual rights as follows:
“When a party to a simple contract upon a breach by the other
contracting party of a condition of the contract, elects to treat the
contract as no longer binding upon him, the contract is not rescinded
as from the beginning. Both parties are discharged from the further
performance of the contract, but rights are not divested or discharged
which have already been unconditionally acquired. Rights and
obligations which arise from the partial execution of the contract and
causes of action which have accrued from its breach alike continue
unaffected.”iv
-- 25 of 32 --
26
[164] Apart from the sum claimed under the preliminary agreement, which has
been dealt with in this decision, Avilake claims:
the practical completion instalment of $25,500.00; less
the sum of $638 being the quote of Mr Hawkins for repair of minor
defects; plus
interest on the total outstanding amount pursuant to Clause 11.9
of the Contract and Item 19 of the Appendix at 15% per annum
calculated on a daily basis, calculated from the date of
possession on 3 October, 2009 to the commencement of the trial
on 12 September, 2011 and continuing until payment is made.
[165] Avilake relies upon clause 17.9 of the Contract to establish that its
entitlement to the final payment under the contract at practical completion
arose upon the Tuckers taking possession of the house on 3 October
2009.
[166] Clause 17.9 provides that: “If the Owner takes Possession of the Works,
or any part of the Works, when not entitled to do so under this Contract,
the Works are deemed to have reached Practical Completion Stage on
the date of Possession and the Owner is liable to the Builder for any loss
or damage arising as a result.”
[167] The Tuckers admit to taking possession of the works on 3 October 2009.
They took possession without the consent of the builder in circumstances
which I have found amount to a repudiation of the contract. Accordingly, I
find that the Tuckers were not entitled to take possession and there has
been deemed practical completion under clause 17.9 of the contract.
[168] Avilake has not claimed damages for breach of contract. It has claimed
money owing under the contract. That is, it has claimed a debt. The
significance of such a claim is that the amount of the debt is a fixed and
certain sum, due and owing under the contract.
[169] Having found that deemed practical completion occurred under the
contract, it is necessary to determine whether the practical completion
stage payment became payable when that occurred.
[170] Avilake must satisfy the requirements of the contract and section 67 of the
DBCA to demonstrate an entitlement to payment of the practical
completion stage payment.
[171] Clause 11.6 of the contract provides that the “Builder is entitled to claim
payment of the Contract Price progressively, on completion of the stages
set out in Part D of the Appendix to the Schedule. A progress claim must
be in writing, certify that the Works have been completed to the relevant
stage and set out the amount to be paid to the Builder in accordance with
Clause 11.7”.
-- 26 of 32 --
27
[172] Part D of the Appendix refers to the “Practical Completion Stage” and a
value of $25,500.00.
[173] Practical Completion Stage is defined in the contract to mean: “that stage
of the Works when the Works are completed in accordance with the
Contract and all relevant statutory requirements, apart from minor
omissions or minor defects, and the Works are reasonably suitable for
habitation.”
[174] Clause 17.1 of the contract provides that upon reaching the practical
completion stage, the builder must give to the owner the final progress
claim and a practical completion stage notice stating the date the Works
reached practical completion stage and providing for a final inspection of
the works.
[175] Clause 17.3 provides that if the owner fails to attend the inspection the
practical completion stage payment is due and payable.
[176] Clause 17.4 provides that if the owner agrees the works are complete and
that there are no minor defects, the claim becomes due and payable.
[177] Clause 17.5 provides that if at the final inspection the owner claims
defects or the works are incomplete, the builder must give the owner a
defects document and pursuant to clause 17.6 attend to rectification or
completion of agreed items.
[178] However, clause 17.7 provides that on giving the defects document to the
owner and notwithstanding that the practical completion stage may have
been reached with minor omissions or defects, the owner must pay the
final progress claim to the builder in accordance with the Contract.
[179] Finally, if the amount claimed is disputed the owner may pay the claimed
sum into the Master Builders’ Trust Account, take possession and then
resolve the dispute.
[180] The relevance of the contractual obligations as to a date for inspection
and delivery of a defects notice by the builder is that, under the terms of
the contract, the practical completion stage payment does not become
due and payable until these steps have been undertaken. The amount
may not even become due and payable under the contract, if the amount
if disputed and paid into the Master Builders’ Trust Account.
[181] In other words it does appear that the structure of the contract is that mere
practical completion or deemed practical completion is a trigger for
payment of the practical completion stage payment without further steps
having been taken.
[182] As to Avilake’s statutory obligations upon claiming the practical
completion stage payment, section 67 of the DBCA provides that a
building contractor must not demand all or part of the completion payment
-- 27 of 32 --
28
unless the practical completion stage has been reached. If the owner
claims the stage has been reached with minor defects or minor omissions
a defects document must be given by the builder to the owner. The Act is
cast in mandatory terms. The evidence reveals that the Tuckers had
been complaining of defects and incomplete work for a considerable
period of time before the contract was terminated.
[183] By letter dated 6 October 2010, Avilake terminated the contract and under
cover of that letter delivered an invoice for the practical completion stage
payment. It is a nice question as to whether the invoice was delivered
before or after the termination. If it was delivered after communication of
acceptance of the Tuckers’ repudiation of the contract and consequent
termination of the contract, the practical completion stage payment claim
may not have been made under the contract and may not be enforceable.
[184] In any event, Avilake did not prior to termination set a date for inspection
of the property and deliver a defects document as required by the contract
and section 67 of the DBCA. An earlier purported delivery of a practical
completion notice and nomination of a time for inspection was withdrawn
some time before.
[185] Avilake made an unequivocal decision to accept the Tuckers’ wrongful
repudiation and to terminate the contract.
[186] Similar issues arising out of the same form of contract have been
considered in the case of Martin v Cahillv. Member Armitage of the former
Commercial and Consumer Tribunal, said at paragraph 160:
“The operation of clause 17.9 of the GCOC (general conditions of
contract) does not give rise to a demand being made for payment of all
or part of the „completion payment‟ or an entitlement for the applicant
to receive all or part of the „completion payment‟ as a consequence of
the respondent having taken possession of the works when not entitled
to do so under the Contract. Nor does it give rise to an obligation for
the respondent to pay all or part of the „completion payment‟ to the
applicant irrespective of whether or not the requirements of section 67
had been satisfied. Clause 17.9 of the GCOC provides that the
respondent is liable to the applicant for any loss or damage arising as
a result of her having taken possession of the works when not entitled
to do so under the Contract. There is a clear distinction between a
right to monies owing under a contract, such as a progress payment or
completion payment, and a right to damages for breach of contract.
I consider that section 67 of DBCA applies to the former, and not the
latter. Although I accept that the natural meaning of section 67 of the
DBCA may operate to prevent a builder from being able to validly
demand or receive a completion payment under the contract in
circumstances where an owner has taken unlawful possession of the
works before the builder is able to meet the requirements of section 67,
I am unable to accept that section 67 of the DBCA operates to also
prevent a builder from claiming loss or damage suffered as a result of
-- 28 of 32 --
29
having been denied the ability to validly demand or receive a
completion payment due to the unlawful conduct or breach of contract
of the owner. Such a construction is not supported by the plain words
of section 67 and would lead to the absurd result of permitting an
owner to take advantage of the non-fulfilment of the section 67 pre-
conditions in circumstances where the owner‟s conduct has denied the
builder the ability to fulfil the statutory requirements.”
[187] As its claim is currently cast Avilake cannot succeed against the Tuckers
for the amount of the practical completion stage payment, because the
practical completion stage payment was not due and payable at the date
of termination. The payment was not due and payable because the
requirements of both the contract and section 67 of the DBCA had not
been met in relation to delivery of a defects notice by Avilake to the
Tuckers. I have considered the principle which “exonerates one of two
contracting parties from the performance of a contract when the
performance of it is prevented and rendered impossible by the wrongful
act of the other contracting party”vi. It is arguable that the Tuckers
conduct in wrongfully repudiating the contract meant that Avilake could
not fulfil the contractual requirement to arrange an inspection and deliver
a defects notice and that the Tuckers thereby lost the right to the defects
notice, with the result that the practical completion payment became due
and payable. Whatever view one takes of that argument, I do not think it
applies in the case of a statutory obligation such as that set out in section
67 of the DBCA. I agree with the reasoning of Member Armitage in
Martin v Cahill.
[188] Although Avilake may have a claim for damages for breach of contract
against the Tuckers, I am unable to determine such a claim because it
has not been formulated as part of these proceedings.
[189] For these reasons, I find that Avilake fails in its claims for the practical
completion stage payment of $25,500.00 and interest.
[190] Upon the same principle as set out earlier from McDonald v Dennys
Lascelles Ltd, the Tuckers are entitled to pursue a claim for damages
which has accrued up to the date of termination of the contract. The
Tuckers have claimed in their Amended Response and Counter-
application:
(a) $5,478.00 for rectifying paint work;
(b) $1,500.00 for reinstallation of the tank;
(c) $2,600.00 for enclosing underside of the property and installing
one entry door;
(d) $2,100.00 for installation of handrails;
(e) Rectification work recommended by Rod Hall – cost to be
advised;
(f) $1,245.00 for rectification of rain-water connection; and
(g) $800.00 for building inspection report.
-- 29 of 32 --
30
[191] The Tuckers later filed a Scott Schedule which set out claims for
rectification of defects and completion of work, consistent with the BSA
report. The Tuckers rely upon a quote from Gary Phyland, Builder, dated
7 March 2011 in a total amount of $21,475.00. That sum includes
$10,583.00 for rectification work; $3,751.00 for installation of head
flashings for all external windows and doors and $7,141.00 for installation
of a concrete slab, wall linings and an exit door in the garage.
[192] Avilake estimated the cost of rectification of defects, excluding head
flashing for external windows and the slab, linings and door in the garage,
for which it denied any liability, in the amount of $842.80. Avilake filed a
quote from Glen Hawkins Constructions Pty Ltd, for rectification of the
same defects, in an amount of $638.00.
[193] Avilake’s evidence was that upon provision of a Form 15 compliance
certificate for the spa bath and subsequent lifting of the suspension, it
would complete the contract works and give a notice of practical
completion, including a proposed time and date for a final inspection in
relation to defects (see attachment TJ 44 to the statement of Tim Jackson
dated 23 November, 2010).
[194] I find that the effect of the Tuckers’ repudiatory conduct in wrongful
termination of the contract and taking possession of the house, which
gave rise to termination of the contract; was that Avilake was prevented
from completing the work, inspecting the work, preparing a defects list and
attending to rectification of agreed defects.
[195] I find that it was the Tuckers’ own conduct which resulted in them having a
range of defects and incomplete work at the house exposing them to the
cost of rectification and completion.vii I find that at the date of termination
of contract, no cause of action for breach of contract arising out of
incomplete or defective work had accrued.
[196] Clause 19 of the contract provides that the builder must rectify defects
and omissions in the works which become apparent and are notified to the
builder during the defects liability period. Provided the works have been
brought to practical completion, there is no contractual obligation to attend
to defects at any earlier time. In the absence of a contrary provision in the
contract the builder is not obliged to rectify defective work at the time
when it becomes apparent but may wait until the work has reached
practical completion or final completion.viii
[197] On the basis that at the date of termination of the contract:
the works were lawfully suspended;
there was no obligation to attend to completion of work during a
period of suspension;
the time for rectification of defects during the defects liability
period had not arisen; and
-- 30 of 32 --
31
the Tuckers’ repudiation of the contract prevented performance of
the contract by Avilake.
I find that there was no breach of contract by Avilake which might give rise
to an entitlement by the Tuckers to damages for the cost of rectification or
completion of works.
[198] Accordingly, the Tuckers’ counter-application fails.
Building Certificates
[199] The Tuckers submit that they have suffered loss and damage in that they
are unable to complete the house as Avilake will not release certification
for various building work.
[200] Under cross examination, Mr Phyland, the builder who undertook further
work at the request of the Tuckers upon termination of the contract with
Avilake, said that he had received the sum of $20,000.00 for the
performance of construction work, but was unable to finalize the job
because he did not have the relevant certificates. He referred to the
energy efficiency certificate, framing certificate and foundations certificate.
The solicitor for Avilake put it to Mr Phyland that the certificates were held
by the Certifier, but would not be handed over until the final instalment
had been paid to Avilake. Mr Phyland agreed that was usual and that he
himself only hands over certificates when paid.
[201] The claim made by the Tuckers for provision of the relevant building
certificates was not raised at a time which enabled Avilake to call
evidence or to respond. In these circumstances I am disinclined to make
the orders sought. The Queensland Building Services Authority Act 1991
empowers the QBSA to direct a builder to rectify or complete work.
Provision of relevant certificates forms part of the completion of work. It is
possible that the QBSA may on application to it give consideration to
requiring provision of the certificates by Avilake to the Tuckers.
Costs
[202] Each party seeks costs. Avilake seeks costs on an indemnity basis.
[203] Avilake has submitted that consequent upon the determination of the
Tribunal on the merits, it reserves its rights to make a further submission
on costs on the basis of the QCAT Act and Rules.
[204] I therefore order that Avilake file and serve any further submissions in
relation to costs by 13 January 2010; that Mr and Mrs Tucker file and
serve any further submissions in relation to costs by 27 January 2012;
that Avilake file and serve any reply by 7 February 2012.
Orders
-- 31 of 32 --
32
[1] I order that:
(a) the applicant’s application is dismissed;
(b) the respondents counter-application is dismissed;
(c) the applicant file and serve any further submissions in relation to
costs by 13 January, 2012;
(d) the respondents file and serve any further submissions in relation
to costs by 27 January, 2012; and
(e) the applicant file and serve any reply by 7 February, 2012.
i Shevill v Builders Licensing Board (1982) 149 CLR 620 at 625-626.
ii Amann Aviation Pty Ltd v The Commonwealth (1990) 92 ALR 601.
iii White and Carter (Councils) Ltd v McGregor (1962) AC 413.
iv McDonald v Dennys Lascelles Ltd (1933) 48 CLR 457 at 476-477.
v [2008] QCCTB 37.
vi Panamena Europea Navigacion (Compania Limitada) v Frederick Leyland & Co Ltd
[1947] AC 428 cited with approval by Muir J in QLine Interiors Pty Ltd v Jezer
Construction Group Pty Ltd & Ors [2002] QSC 088.
vii Ibid.
viii Lexis Nexis Butterworths, Halsbury‟s Laws of Australia, Vol 3 (2) (as at 28 December,
2011), 65 Building and Construction, “Contractor‟s Liability to Proprietor” (65-1505).
-- 32 of 32 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2012/041