Board of Professional Engineers of Queensland v Narsey [2012] QCAT 32
CITATION: Board of Professional Engineers of
Queensland v Narsey [2012] QCAT 32
PARTIES: Board of Professional Engineers of
Queensland
(Applicant)
v
Sunil Narsey
(Respondent)
APPLICATION NUMBER: OCR233-10
MATTER TYPE: Occupational regulation matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Kenneth Barlow SC, Member
DELIVERED ON: 6 January 2012
DELIVERED AT: Brisbane
ORDERS MADE: a) Mr Narsey be reprimanded;
b) Mr Narsey pay the Applicant the sum
of $5,000.00 by way of penalty, such
amount to be paid by 6 February
2012;
c) Mr Narsey’s registration as a
registered professional engineer be
suspended for a period of 3 years
from the date of this order.
CATCHWORDS: Occupational Regulation – disciplinary
proceeding against engineer – professional
misconduct established – appropriate
penalty
Professional Engineers Act 2002, ss 3, 36,
131
APPEARANCES and REPRESENTATION (if any):
APPLICANT: ClarkeKann Lawyers
RESPONDENT: McInnes Wilson Lawyers
-- 1 of 7 --
2
REASONS FOR DECISION
Introduction
[1] This is a disciplinary proceeding brought by the Board of Professional
Engineers against Mr Narsey, who is a registered engineer.
[2] The Board alleges that Mr Narsey conducted himself in a manner that
constitutes unsatisfactory professional conduct, being conduct of a
lesser standard than that which might reasonably be expected of a
registered professional engineer by the public or the engineer’s
professional peers; conduct that demonstrates incompetence or lack of
adequate knowledge, skill, judgment or care in the practice of
engineering; and/or conduct that was misconduct in a professional
respect.
[3] In essence, there are two complaints against Mr Narsey:
a) first, that he issued a compliance certificate, under s 10 of the
Building Act 1975 and s 46 of the Building Regulation 2006, in
relation to design drawings of a building which he had made, in
which he certified that, if installed or carried out under the
certificate, the building would comply with the Building Act 1975,
when the drawings contained significant design defects;
b) secondly, that he issued an inspection certificate certifying that
defects in the structure of the frame of the building had been
rectified by the builder, when he had not, and could not properly
have, satisfied himself that that was the case – in particular, he
issued the certificate on the basis of photographs provided to him
by the builder, rather than a personal inspection, and even the
photographs demonstrated that the building defects had not been
rectified.
[4] For the purpose of this proceeding, the parties have filed a statement of
agreed facts, and each party has filed separate written submissions on
penalty. Mr Narsey admits that his conduct constitutes unsatisfactory
professional conduct. The Board submits that the appropriate penalty
should be that Mr Narsey be reprimanded, that he pay a $5,000 penalty,
that his registration as an engineer be suspended for a period of three
years from the date of the order and that there be no orders as to costs.
Mr Narsey submits that those sanctions are appropriate.
[5] Notwithstanding that the parties have agreed on what may be
appropriate sanctions, this Tribunal must, of course, exercise its own
judgment in imposing sanctions and in determining the seriousness of
Mr Narsey’s conduct. To that end, it is necessary to give some
consideration to the facts, particularly to the nature and extent of Mr
Narsey’s conduct.
The facts
[6] It is unnecessary to set out all of the agreed facts, but rather it is
appropriate to summarise them.
-- 2 of 7 --
3
[7] Mr Narsey has been a registered civil engineer since 1994 and a
registered structural engineer since 2010. He has been practising as a
professional engineer for 21 years.
[8] In April 2009, Mr Narsey issued a Compliance Certificate for building
design or specification (referred to as the “design certificate”) in relation
to design drawings of a portal framed industrial building to be built at
Mareeba, near Cairns. Mareeba is, of course, in a cyclone-prone area
of Queensland.
[9] In the design certificate, Mr Narsey certified that the items referred to in
it, if installed or carried out under the certificate, including any reference
to documentation, would comply with the Building Act 1975.
[10] The builder commenced constructing the building, and a frame
inspection was carried out by an engineer employed by the Tablelands
Regional Council on 7 September 2009. That engineer issued an
inspection certificate failing the inspection and setting out a number of
deviations from the design drawings, as well as a number of structural
deficiencies (some stemming from the design drawings themselves).
[11] Following issue of the Council’s certificate, the builder asked Mr Narsey
to issue a certificate of inspection to the effect that he had inspected the
building and it complied with the building development approval.
However, rather than physically inspecting the frame, Mr Narsey was
asked (and agreed) to issue the certificate based upon photographs
supplied to him by the builder. The photographs revealed, and Mr
Narsey ought to have been aware, that the building still had a number of
defects, namely incorrectly sized wall and roof battens, incorrectly fixed
wall bracing, incorrectly orientated mullions, incorrectly fixed fly bracing,
unlapped wall battens and roof battens, and end wall mullions which
were incorrectly fixed to the slab.
[12] Notwithstanding those defects, on 24 September 2009 Mr Narsey
issued an inspection certificate in which he certified, in essence, that the
defects set out in the Council’s certificate had been rectified and that the
work was within the design requirements. Mr Narsey did not personally
inspect the building. However, he did record, in his certificate, that the
certification was based upon photographic evidence provided to him.
[13] In October 2009, the Council issued another inspection certificate failing
the frame, following a further inspection by its engineer. It identified a
number of additional defects in the building construction, as well as
some original defects that had not been rectified.
[14] Mr Narsey subsequently wrote to the Council, enclosing altered
drawings which, in a number of respects, meant that the frame as built
complied with the altered drawings even though it did not comply with
the original drawings.
[15] The Council inspector complained to the Board about Mr Narsey’s
conduct and the Board conducted an investigation. The investigator
reported that, in his opinion, the design certificate for the drawings
should not have been issued because the drawings included serious
defects. In particular:
-- 3 of 7 --
4
a) the roof battens and purlins were significantly under-designed, with
over-stress (having regard to proper design criteria) of between
260% and 350% (that is, they were at between 22% and 28% of
their required capacity);
b) the end wall mullions were significantly under-designed, in that they
were over-stressed according to design criteria by between 84%
and 360% (that is, they were at between 22% and 54% of their
required capacity);
c) the wall battens and girts were significantly under-designed, in that
they would be over-stressed by between 308% and 410% (being
rated at between 19% and 25% of their required capacity);
d) the structural model for the portal frames on the building were
under-designed, with the pinned base portal frame columns being
over-stressed by between 105% and 155% and the fixed base
portal frame columns being overstressed by between 52% and
90%;
e) for those and other less significant reasons, the primary structural
elements of the building, upon which it relied for its stability and
integrity, fell well short of the requirements of the Building Code.
[16] The parties have agreed that the issuing of the design certificate and a
number of statements made by Mr Narsey during the course of the
investigation were unjustifiable having regard to proper engineering
practices and principles and demonstrated that Mr Narsey had a
fundamental lack of understanding of, or regard for, proper engineering
practices and principles required to safely design the building and
similar structures.
[17] The parties have also agreed that the certifications contained in Mr
Narsey’s inspection certificate, following the issue of the first Council
certificate, were misleading, in that the final structure of the building as
constructed was not in accordance with the structure required by the
design certificate and a number of defects had not been rectified.
Furthermore, Mr Narsey had no reasonable grounds to believe that the
work he certified had been completed to the standard certified, because
he had not carried out a physical inspection but had relied only on
photographs and, even relying on the photographs, he ought to have
been aware of the existence of defects.
[18] Mr Narsey has admitted that he did not generally issue inspection
certificates but he had been persuaded to do so by the builder, who was
apparently in financial difficulty because the owner had refused to pay
him because the frame inspection had failed.
[19] The report indicated, and the parties have agreed, that had the building
been constructed in accordance with the drawings certified by Mr
Narsey, it would have been unsafe and would have created risk to both
the structure itself and persons using it. Furthermore, the building was
not even built in accordance with that design certificate.
-- 4 of 7 --
5
[20] Finally, had the inspection certificate been accepted and the building
constructed without further rectification, the design deficiencies would
have been exacerbated and the building would have been susceptible to
failure at far lower wind gust speeds than the Code specified.
The parties’ submissions
[21] The Board alleges, and Mr Narsey agrees, that the facts disclose that
he engaged in unsatisfactory professional misconduct in the respects
identified in the introduction above.
[22] I agree with those submissions. Mr Narsey’s conduct fell far below the
standard that might reasonably be expected of a registered professional
engineer such as him, and in some respects demonstrated
incompetence.
[23] The term “misconduct in a professional respect” has been said to
encapsulate “conduct that violates or falls short of, to a substantial
degree, the standard of professional conduct observed or approved by
members of the profession of good repute and competency”.1
[24] I agree with the parties’ submissions that Mr Narsey’s conduct in this
case falls so far short of the standard of professional conduct required
as to constitute misconduct in a professional respect.
[25] The Board submits that, even though this is the first time, in his long
professional career, that Mr Narsey has faced disciplinary sanction
under the Act, his conduct, and the safety issues which it created, justify
a significant penalty in order to protect the public and to provide a
meaningful deterrent against similar conduct by other registered
professional engineers.
[26] Mr Narsey accepts that the appropriate sanction is that proposed by the
Board and points out that, in accepting that sanction, he will be able to
continue to work under supervision in his current employment. He
intends to avoid any further involvement in any cold formed steel design
or engineering work such as was involved in this case.
Relevant considerations
[27] The main objects of the Professional Engineers Act 2002 are set out in
s 3. They are:
a) to protect the public by ensuring professional engineering services
are provided by registered professional engineers in a professional
and competent way;
b) to maintain public confidence in the standards of services provided
by registered professional engineers; and
c) to uphold the standards of practice of registered professional
engineers.
[28] It has been said, of professional engineers, that:
1 Adamson v Queensland Law Society Inc [1990] 1 Qd R 498.
-- 5 of 7 --
6
“The standard to be expected of engineers, because of the at times critical
nature of the responsibilities attaching to their decisions taken during the course
of practice of their discipline, must be set significantly higher than other
occupations, where such conduct might not give rise to such potentially grave
and serious repercussions.”2
[29] As I have said, I am satisfied that Mr Narsey’s conduct, in both of the
respects complained of, constitutes unsatisfactory professional conduct
in each of the manners complained of by the Board.
[30] When initially confronted, by the investigator, with the opinion that his
conduct was unsatisfactory, Mr Narsey appeared to attempt to justify
that conduct. However, in this Tribunal he has been prepared to accept
that his conduct was unsatisfactory. It is appropriate for the Tribunal to
take into account Mr Narsey’s response to the complaints against him in
determining the appropriate penalty.
[31] Of course, the Tribunal must also take into account the seriousness of
the conduct giving rise to the finding of unsatisfactory professional
conduct. In this case, Mr Narsey’s conduct was seriously deficient in
that, if the building had been constructed in accordance with his original
design or in accordance with his inspection certificate, it would have had
serious structural flaws that could have led to very serious property
damage or personal injury or death. It would have been entirely
inadequate for its purposes and particularly in a cyclone prone area
such as Mareeba. It appears, in fact, that Mr Narsey’s conduct in
providing the inspection certificate was a result of pressure brought to
bear upon him by the builder. It seems that he knew (and certainly he
ought to have known) that the inspection certificate was inadequate, that
the building was inadequately constructed and that the design was
inadequate, but he nevertheless issued the inspection certificate. While
it is not alleged in this proceeding that his conduct amounted to
dishonesty, it appears to border on it.
[32] In response to a request by the Tribunal, the parties’ solicitors have
helpfully provided to the Tribunal information about the outcomes of
disciplinary decisions against professional engineers made by this
Tribunal and its predecessor, the Commercial and Consumer Tribunal,
and submissions as to the appropriateness of the penalties suggested in
this case. Of course, each case depends upon its own facts and
circumstances, but the penalties imposed by the Tribunal must, in my
opinion, bear a reasonable relationship to penalties that have been
imposed in other cases in broadly analogous situations.
[33] The most recent decision referred to me is that of Senior Member Oliver
in Board of Professional Engineers of Queensland v Wu. In that matter,
Mr Wu engaged in fraud (in fact, forgery). The Tribunal disqualified Mr
Wu from obtaining registration for 3 years, but that was in circumstances
where Mr Wu had not been registered, due to the Board’s refusal to
2 Board of Professional Engineers v Jutte (2004) CCT K005-03. This has been
reiterated in Board of Professional Engineers of Queensland v Djakovic (2006) CCT
ED006-6 and, more recently, in Board of Professional Engineers of Queensland v Wu
[2011] QCAT 330.
-- 6 of 7 --
7
allow his registration to be renewed, for at least four years before the
decision was made. In effect, he would effectively be without
registration for a total period of seven years.
[34] In Board of Professional Engineers v Jutte, Mr Jutte had been dishonest
and had also contested the proceeding against him.
[35] In this case, as I have said, Mr Narsey’s conduct bordered on
dishonesty. When investigated, he sought to justify his conduct by, in
effect, blaming the behaviour of the Council inspector and the pressure
brought to bear on him by the builder. It was not until this proceeding
was well advanced that he has acknowledged, and expressed regret for,
his unsatisfactory conduct.
[36] Mr Narsey is still registered. He will be able to retain his employment if
his registration is suspended, as his employer has apparently indicated
that it will continue to employ him and he can work under supervision
during that period.
[37] Mr Narsey has a long unblemished career before this incident.
[38] In all the circumstances, I consider that the penalties sought by the
Board, with which Mr Narsey agrees, are appropriate.
[39] I therefore order that:
a) Mr Narsey be reprimanded;
b) Mr Narsey pay the Applicant the sum of $5,000.00 by way of
penalty, such amount to be paid by 6 February 2012;
c) Mr Narsey’s registration as a registered professional engineer be
suspended for a period of 3 years from the date of this order.
[40] The Board did not seek an order that Mr Narsey pay the Board’s costs
of the investigation or this proceeding, and therefore I shall make no
order as to those costs.
-- 7 of 7 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2012/032