Cavalier Homes Brisbane Pty Ltd v Queensland Building Services Authority [2012] QCAT 6
CITATION: Cavalier Homes Brisbane Pty Ltd v
Queensland Building Services Authority
[2012] QCAT 6
PARTIES: Cavalier Homes Brisbane Pty Ltd
(Applicant)
v
Queensland Building Services Authority
(Respondent)
APPLICATION NUMBER: GAR101-11
MATTER TYPE: General administrative review matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Dr Bridget Cullen, Member
DELIVERED ON: 4 January 2012
DELIVERED AT: Brisbane
ORDERS MADE: 1. Cavalier Homes’ Application to
extend the time limit for filing an
Application to Review the
16 December 2010 decision of the
QBSA is dismissed.
CATCHWORDS: ADMINISTRATIVE REVIEW MATTERS –
Extension of time to file review application –
Review of decision of Queensland Building
Services Authority – Application for
extension of time to file dismissed
Queensland Building Services Authority Act
1991, ss 86(1)(f), 87
Queensland Civil and Administrative
Tribunal Act, ss 33, 61
Hunter Valley Developments Pty Ltd v The
Honourable Barry Cohen, Minister for Home
Affairs (1984) 3 FCR 344
McClintock v QBSA [2010] QCAT 340
Gallagher v QBSA [2010] QCAT 383
Choice Homes Queensland Pty Ltd v QBSA
[2000] QBT 121
-- 1 of 6 --
2
Body Corporate “Avalon on Rawlins” v
QBSA [2008] QCCTB 40
Sherred v QBSA [2006] QCCTB 58
Hart v QBSA [2008] QCCTB 163
Ralkon v Aboriginal Development
Commission (1982) 43 ALR 535
Lucic v Nolan (1982) 45 ALR 411
APPEARANCES and REPRESENTATION (if any):
No appearances, decision made on the papers.
REASONS FOR DECISION
Overview
[1] This is an application by Cavalier Homes Brisbane Pty Ltd for an
extension of time within which to file an application to review a decision of
the Queensland Building Services Authority (“QBSA”).
[2] Cavalier Homes seeks to review a decision made by the QBSA on
16 December 2010 that rectification works completed by Cavalier Homes
after the QBSA had issued Cavalier Homes with a Direction to Rectify
were not completed to a satisfactory standard.
[3] It is beyond contention that the direction to rectify issued by the QBSA on
16 December 2010 is a decision that is subsequently reviewable, by
QCAT1. However, in order to proceed with a review application, Cavalier
Homes requires an extension of time within which to file its review
application.
[4] In the ordinary course of events, a review application such as this must be
made within 28 days after the “relevant day”.2 The relevant day is defined
to mean “the day after the applicant is notified of the decision”.3
[5] In its Application to review a decision, filed on 12 April 2011, Cavalier
Homes says that it received the QBSA’s decision on 20 December 2010.
The date of filing is well beyond the 28-day timeframe prescribed by the
QCAT Act, such that Cavalier Homes first requires an extension of time
within which to file.
[6] In making this application for an extension of time within which to file its
review application, Cavalier Homes seeks to rely upon s 61 of the
Queensland Civil and Administrative Tribunal Act 2009 (“QCAT Act”).
Section 61 permits the tribunal, by order, to:
1 Queensland Building Services Authority Act 1991, ss 86(1)(f) and 87.
2 QCAT Act, s 33.
3 QCAT Act, s 33(4)(a).
-- 2 of 6 --
3
extend or shorten a time limit fixed by this Act, an enabling Act or
the rules.
The law relating to extensions of time, in an administrative law context
[7] The QBSA, in written submissions opposing an extension of time, has
drawn my attention to the decision of Justice Wilcox in Hunter Valley
Developments Pty Ltd v The Honourable Barry Cohen, Minister for Home
Affairs (1984) 3 FCR 344. Therein, Justice Wilcox set out several factors
that should be considered when determining applications to extend time,
in an administrative law context. Summarised, these are:
An acceptable explanation for the delay and that it is fair and
equitable in the circumstances to extend.4
Any action taken by the applicant, other than by making an
application for review under the Act, to inform the decision
maker that the finality of the decision is contested. This reflects
public policy supporting a need to ensure finality in disputes, and
to prevent difficulties that result from fading memory as time
languishes.5
Whether there has been any prejudice to the respondent
occasioned by the delay.6 However, the mere absence of
prejudice is not enough to justify the grant of an extension. A
delay which may result, if the application is successful, in the
unsettling of other people or of established practices is likely to
prove fatal to the application.7
The merits of the substantial application.8
Considerations of fairness.9
[8] The QBSA points out that these principles have been adopted not only by
QCAT10, but also by QCAT’s predecessors, the Commercial and
Consumer Tribunal and the Queensland Building Tribunal.
Application of ‘Hunter Valley’ principles to this application
Acceptable explanation for the delay
[9] The primary argument advanced by Cavalier Homes is that it was “in
negotiations” with both Mr Chris Boyle and Mr Leslie Brain (Dispute
Resolution Manager) of the QBSA, and believed that the matter could
4 Hunter Valley Developments Pty Ltd v The Honourable Barry Cohen, Minister for
Home Affairs (1984) 3 FCR 344 at 18.
5 Ibid at 19.
6 Ibid at 20.
7 Ibid at 21.
8 Ibid at 22.
9 Ibid at 23.
10 For example, McClintock v QBSA [2010] QCAT 340; Gallagher v QBSA [2010] QCAT
383; Choice Homes Queensland Pty Ltd v QBSA [2000] QBT 121; Body Corporate
“Avalon on Rawlins” v QBSA [2008] QCCTB 40; Sherred v QBSA [2006] QCCTB 58;
Hart v QBSA [2008] QCCTB 163.
-- 3 of 6 --
4
have been resolved without resort to QCAT. This view is not shared by
the QBSA; rather, the QBSA expressly denies that there were any
negotiations in the aftermath of its 16 December 2010 decision.
[10] In a signed statement11, Mr Brain states that he recalls a brief discussion
with Mr Boyle, wherein they agreed that it would be more appropriate for
Mr Brain to manage the Cavalier Homes matter. Further, Mr Brain
explains that there is not one scintilla of evidence on the QBSA’s files
indicating that there were “negotiations”, nor even discussions with
Cavalier Homes after 16 December 2010.
[11] Mr Brain explains that the QBSA utilises a software program called
“Contractor Management System” to record case notes about the
progress of QBSA files, and that it is the ordinary (and required) practice
of QBSA employees to include details of any telephone conversations
relating to the matter. Exhibit 21 to Mr Brain’s statement supports his
statement that there were no further or ongoing discussions with Cavalier
Homes, yet exhibit 21 does reveal that there were several further phones
calls to the owners of the property on which the allegedly unsatisfactory
works had been performed.
[12] Viewing its argument at its highest, I might find that Cavalier Homes
mistakenly believed that further negotiations with the QBSA were still
ensuing. However, even if I did so find, a one-sided perception that there
were negotiations on foot does not afford any sufficient basis to justify an
extension of time. The 28-day time limit is not something to be ignored12,
particularly in circumstances where the adverse decision actually advises
the prospective applicant of its right to review the decision before QCAT.13
[13] Cavalier Homes also makes reference to there being extensive rain in
November and December 2010; the January 2011 Queensland flood
disaster, and what it calls the “21 day building industry shutdown” from
22 December 2010 until 11 January 2011. As the work that was the
subject of the Direction to Rectify was to be completed by 1 October 2010,
I fail to see how the heavy rains in November/December together with the
floods in January 2011 could have had any bearing whatsoever on
Cavalier Homes’ ability to file its review application within time.
[14] As for the existence of otherwise of an alleged “industry wide shutdown”,
I agree with the QBSA that there is no officially scheduled industry-wide
closedown. That said however I think it safe to observe that many
tradespeople in the building and construction industry do cease work for a
number of weeks in the Christmas/New Year period. Regardless of that
phenomena, Cavalier Homes did not file its review application until
12 April 2011, months after the end of the unofficial industry shutdown.
11 Statement of Mr Leslie Brain, 3 August 2011.
12 See the decisions in Ralkon v Aboriginal Development Commission (1982) 43 ALR
535 at 550 and Lucic v Nolan (1982) 45 ALR 411 at 416 on this point.
13 Decision of the QBSA dated 16 December 2010, paragraph 4.
-- 4 of 6 --
5
As such, these arguments do not support the granting of an extension of
time.
Actions taken by Cavalier Homes
[15] Other than claiming to have been in negotiations with the QBSA, as
referred to, above, Cavalier Homes has produced no evidence indicating
that it took any steps to advise the QBSA that it intended to dispute the
16 December 2010 decision. In my view, this lends weight to the QBSA’s
argument that the extension should not be granted.
Questions of Prejudice and the underlying Merits of the Application for
Review
[16] If the tribunal were to allow Cavalier Homes an extension of time within
which to file its application to review the decision of the QBSA made on
16 December 2010, there would be considerable prejudice to the QBSA.
On 19 October 2010, the QBSA notified Cavalier Homes of a potential
debt arising under the QBSA’s Statutory Insurance Scheme, should it
incur costs to have another contractor fix the defective work. Following
receipt of this letter, there were communications between the parties in
relation to completion of the defective works. Ultimately, following an
inspection on 14 December 2010, the QBSA determined that the
rectification works remained defective, and 2-days later informed Cavalier
Homes of its decision that the Direction to Rectify had not been
satisfactorily complied with.
[17] On 3 February 2011, the QBSA advised Cavalier Homes that an
insurance claim of $21,895.45 had been approved.14 The owners of the
property in reliance upon the QBSA’s representations, then hired another
contractor to complete the rectification works, and as at 29 June 2011, the
works were complete.15
[18] The prejudice to the QBSA, if an extension of time to review were granted,
is significantly higher than that to the applicant. If Cavalier Homes were
successful on the merits of a review application, the fact that the works
are now complete would have the effect of denying the QBSA the
opportunity to present further evidence in support of its position that the
works were not of a satisfactory standard. This would be the seminal
issue in any ensuing review application. I agree with the QBSA that
Cavalier Homes’ arguments that the Direction to Rectify was
unreasonably issued and were not defective in the first place and that the
items in the Scope of Works were not reasonable or necessary are not
relevant matters in any forthcoming review. This is because the decision
Cavalier Homes wants to review relates only to whether the rectification
previously attempted by Cavalier Homes was satisfactory.
14 Statement of Mr Leslie Brain, 3 August 2011, Annexure 19.
15 Ibid, Annexure 21.
-- 5 of 6 --
6
[19] Further, if Cavalier Homes were successful on its review application, the
QBSA would be in a position where it has expended insurance resources
unnecessarily. The reasons given by Cavalier Homes for its late
lodgement are insufficient and inadequate. When coupled with the polar-
opposite evidence of the QBSA, and the extent of prejudice to the QBSA
should an extension of time be granted, the granting of an extension
would not only be inappropriate, it would be unjust.
Orders
[1] Cavalier Homes’ Application to extend the time limit for filing an
Application to Review the 16 December 2010 decision of the QBSA is
dismissed.
-- 6 of 6 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2012/006