Bloomer Constructions (Qld) Pty Ltd v O’Sullivan & Anor [2009] QSC 220
SUPREME COURT OF QUEENSLAND
CITATION: Bloomer Constructions (Qld) Pty Ltd v O’Sullivan & Anor
[2009] QSC 220
PARTIES: BLOOMER CONSTRUCTIONS (QLD) PTY LTD
ACN 071 344 100
(applicant)
v
SEAN O’SULLIVAN
(first respondent)
MICHAEL CHRISTOPHER VADASZ TRADING AS
AUSTRALASIAN PILING COMPANY
(second respondent)
FILE NO/S: BS 6449 of 2009
DIVISION: Trial Division
PROCEEDING: Application
ORIGINATING
COURT:
Supreme Court Brisbane
DELIVERED ON: 7 August 2009
DELIVERED AT: Brisbane
HEARING DATE: 10 July 2009
JUDGE: White J
ORDER: The application be dismissed
CATCHWORDS: ADMINISTRATIVE LAW – JUDICIAL REVIEW –
REVIEWABLE DECISIONS AND CONDUCT –
DECISIONS TO WHICH JUDICIAL REVIEW
LEGISLATION APPLIES – EXCLUDED DECISIONS –
OTHER DECISIONS – where the applicant entered into a
contract with the second respondent for building and
construction services – where the second respondent issued a
payment claim under the Building and Construction Industry
Payments Act 2004 (Qld) – where the first respondent
adjudicator was appointed under the Building and
Construction Industry Payments Act and adjudicated in
favour of the second respondent – where the applicant applies
for a prerogative order under Part 5 Judicial Review Act 1991
(Qld) to quash the adjudication decision – where under an
amendment by the Justice and Other Legislation Amendment
Act 2007, Part 3 Division 2 Building and Construction
Industry Payments Act is an enactment to which the Judicial
Review Act does not apply – whether Part 5 Judicial Review
Act is excluded from applying to Part 3 Division 2 Building
-- 1 of 16 --
2
and Construction Industry Payments Act 2004 – whether the
adjudication decision can be subject to review under Part 5
Judicial Review Act
CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – OTHER MATTERS – where
the applicant entered into a contract with the second
respondent for building and construction services – where the
second respondent issued a payment claim under the Building
and Construction Industry Payments Act 2004 (Qld) – where
the first respondent adjudicator was appointed under the
Building and Construction Industry Payments Act and
adjudicated in favour of the second respondent – where the
second respondent held a conditional contractor’s licence –
whether the second respondent was precluded from entering
into a building contract, issuing a payment claim and
applying for adjudication under the Building and
Construction Industry Payments Act
ADMINISTRATIVE LAW – JUDICIAL REVIEW –
GROUNDS OF REVIEW – JURISDICTIONAL MATTERS
– where the applicant entered into a contract with the second
respondent for building and construction services – where the
second respondent issued a payment claim under the Building
and Construction Industry Payments Act 2004 (Qld) – where
the first respondent adjudicator was appointed under the
Building and Construction Industry Payments Act and
adjudicated in favour of the second respondent – where the
second respondent held a conditional contractor’s licence –
whether the adjudicator has no jurisdiction to make the
adjudication decision
Building and Construction Industry Payments Act 2004
(Qld), s 10(2), Part 3 Division 2
Justice and Other Legislation Amendment Act 2007 (Qld)
Judicial Review Act 1991 (Qld), s 18, s 41, s 43, s 48,
Schedule 1 Part 2
Queensland Building Services Authority Act 1991 (Qld), s 31,
s 34, s 35, s 36, s 38, 42. s 48, s 88, s 89, s 97
Supreme Court Act 1995 (Qld) , s 128
Uniform Civil Procedure Rules 1999 (Qld), rr 564–569
Bezzina Developers Pty Ltd v Deemah Stone (Qld) Pty Ltd
[2008] 2 Qd R 495, considered
Brodyn Pty Ltd t/as Time Cost and Quality v Davenport &
Anor (2004) 61 NSWLR 421, cited
Cant Contracting Pty Ltd v Casella & Anor [2006] QCA 538,
considered
Greg Beer t/as G & L Beer Covercreting v J M Kelly (Project
Builders) Pty Ltd [2008] QCA 35, applied
Intero Hospitality Projects Pty Ltd v Empire Interior
-- 2 of 16 --
3
(Australia) Pty Ltd & Anor [2008] QCA 83, considered
J Hutchinson Pty Ltd v Galform Pty Ltd & Ors [2008] QSC
205, considered
Musico & Ors v Davenport & Ors [2003] NSWSC 977, cited
Uniting Church in Australia Property Trust (Qld) v
Davenport & Anor [2009] QSC 134, applied
Walton Construction (Qld) Pty Ltd v Salce & Ors [2008]
QSC 235, considered
COUNSEL: Mr T M Matthews for the applicant
Mr R Holt SC and Ms E J Longbottom for the second
respondent
SOLICITORS: Romans & Romans for the applicant
McCullough Robertson for the second respondent
[1] Bloomer Constructions (Qld) Pty Ltd (“Bloomer”) has brought an “application for
review” and applied for an order in the nature of a prerogative order pursuant to
Part 5 of the Judicial Review Act 1991 (Qld) (“the JR Act”) quashing the entire
Adjudication Decision of the first respondent dated 5 June 2009. Mr O’Sullivan
was the adjudicator appointed under the Building and Construction Industry
Payments Act 2004 (Qld) (“the BCIP Act”) to adjudicate the dispute between
Bloomer and the second respondent, Michael Christopher Vadasz trading as
Australasian Piling Company (“Australasian”).
[2] Two broad issues arise for consideration.
1. Whether by reason of the conditional status of the licence held by
Australasian:
(a) Australasian was precluded from entering into a building contract
with Bloomer, issuing a payment claim and lodging an adjudication
application; and
(b) the adjudicator had no jurisdiction to make his Adjudication
Decision.
2. Whether the Adjudication Decision is open to review pursuant to Part 5 of
the JR Act.
Background
[3] The parties entered into a written contract in November 2008 under which
Australasian was to undertake the design, installation and certification of perimeter
and internal piling on a site at Commercial Road, Newstead for the lump sum price
of $1,261,872 plus GST. According to the Adjudication Decision there is
significant debate between the parties regarding the terms of the contract.
[4] On 14 April 2009 Australasian served a payment claim on Bloomer in the amount
of $1,249,642.88 (incl GST) pursuant to the BCIP Act.
[5] On 27 April 2009 Bloomer served a payment schedule on Australasian scheduling
an amount of $nil on the basis that Australasian was indebted to it “in the order of
$1,320,310 to date”.
-- 3 of 16 --
4
[6] On 11 May 2009 Australasian lodged an adjudication application and on 19 May
Bloomer lodged an adjudication response to the effect that an adjudicator did not
have jurisdiction because:
“at the time of entering into the contract, [Australasian] did not meet
the licensing requirements of the Queensland Building Services
Authority Act 1991 in that the licence held by [Australasian] was
with a qualification.” 1
[7] On 5 June 2009 the adjudicator made his decision in the sum of $415,079.50
(including GST) in favour of Australasian. The adjudicator held that:
“…[Bloomer] has not satisfied me that the apparent qualification on
[Australasian’s] licence would preclude [Australasian] from
undertaking relevant work and more importantly, there is nothing in
the authorities…that establish that [Australasian], in such
circumstances, is not entitled to make a statutory payment claim
under the Act.” 2
[8] The parties filed a consent order before the Chief Justice on 23 June 2009 whereby
Australasian was not to take any steps to enforce the adjudication certificate to
recover the monies the subject of the Adjudication Decision and Bloomer paid the
adjudication sum plus interest plus the adjudicator’s fees into court pending the
hearing and determination of the application for review.
Judicial review of adjudication
[9] By amendment in 2007, 3 Part 3 Division 2 of the BCIP Act was added to Schedule 1
Part 2 of the JR Act as an enactment to which the JR Act did not apply. Part 3
Division 2 in ss 21–32 concerns the “adjudication of disputes”.
[10] Mr Matthews for Bloomer submitted that the exclusion of the BCIP Act from the
purview of the JR Act does not and was not intended by the legislature to exclude
the operation of Part 5 of that Act for injunctive relief by way of prerogative orders.
He relied upon observations of Daubney J in Uniting Church in Australia Property
Trust (Qld) v Davenport4 preferring the approach of Chesterman J (as his Honour
then was) in Intero Hospitality Projects Pty Ltd v Empire Interior (Australia)
Pty Ltd5 to that of Fraser JA in Bezzina Developers Pty Ltd v Deemah Stone (Qld)
Pty Ltd. 6 Mr Holt SC who appeared with Ms Longbottom for Australasian
submitted that the words in the JR Act should be given their plain meaning and
Fraser JA’s view in Bezzina followed. The opinion of Chesterman J in Intero,
although obiter, was that the 2007 amendments to the JR Act applied only to Part 3
applications for a statutory order of review, while Fraser JA disagreed in Bezzina,
also obiter, and stated that the amendments applied to Part 5 as well as Part 3
applications.
[11] Section 18 of the JR Act provides for the Act to have effect “despite any law in
force at its commencement”, but by s 18(2):
1 Adjudication Decision p 5, being Exhibit “H” to the affidavit of Daniel Romans filed 17 June 2009.
2 Adjudication Decision p 5.
3 Justice and Other Legislation Amendment Act 2007 (Qld).
4 [2009] QSC 134.
5 [2008] QCA 83.
6 [2008] 2 Qd R 495 at footnote 25.
-- 4 of 16 --
5
“… this Act does not –
(a) …
(b) apply to decisions made, proposed to be made, or required to be
made, under an enactment mentioned in schedule 1, part 2.”
[12] When the JR Act was enacted its purpose was twofold: to provide a process for
reviewing administrative decisions and to simplify the procedure for seeking
prerogative relief. The writ processes for such relief were abolished but not the
underlying power of the court to review. Section 41, which is in Part 5, provides
that:
“(1) The prerogative writs of mandamus, prohibition or certiorari
are no longer to be issued by the Court.
(2) If, before the commencement of this Act, the court had
jurisdiction to grant any relief or remedy by way of a writ of
mandamus, prohibition or certiorari, the court continues to
have the jurisdiction to grant the relief or remedy, but must
grant the relief or remedy by making an order, the relief or
remedy under which is in the nature of, and to the same
effect as, the relief or remedy that could, but for subsection
(1), have been granted by way of such a writ.”
[13] Section 43(1) provides that the procedure for a prerogative order or injunction
“must be made by way of an application for review.” This is instead of the previous
cumbersome order nisi to review procedure returnable before the Full Court. An
application for a declaration or injunction (other than a prerogative injunction) may
also be made by way of application for review if appropriate. 7 If the court
concludes that an application for a declaration or injunction (other than a
prerogative injunction) made under s 43(2) ought to have been commenced by
claim8 or originating application, it may order the proceeding to continue as if
commenced in that way. The Uniform Civil Procedure Rules (“UCPR”)
contemplate in rr 564–569 a close correspondence between an application brought
for a statutory order of review and an application for review, that is, Part 3
applications and Part 5 applications.
[14] A number of recent decisions have considered the effect of the 2007 amendments to
the JR Act. The first in time is Intero. The observations by Chesterman J about the
effect of the amendments on Part 5 of the JR Act were obiter since the court was
concerned with an application under Part 3 and the relation between s 13 of the JR
Act (provision for review in another Act) and s 100 of BCIP Act (preserving civil
proceedings). His Honour said: 9
“[60] …With the enactment of the Justice and Other legislation
Amendment Act 2007 judicial review of adjudications made
pursuant to the Building and Construction Industry
Payments Act 2004 (‘the Act’) will no longer be reviewable
pursuant to Part 3 of the JR Act.
7 Judicial Review Act, s 43(2).
8 See Supreme Court of Queensland Act 1991 (Qld), s 130, for reading writ of summons or originating
summons as claim or application.
9 [2008] QCA 83 at [60]–[62].
-- 5 of 16 --
6
[61] Adjudications will, however, continue to be reviewable
pursuant to Part 5 of the JR Act which regulates the
jurisdiction the Court formerly had to control proceedings of
inferior courts and domestic tribunals. The grounds on
which review might be sought are those established by the
well known principles of administrative law. They are of
course more circumscribed than the grounds for review
given by s 20, s 23 and s 24 of the JR Act.
[62] Mr Bond SC who appeared with Mr [sic] Hindman for the
applicant held out the prospect that builders dissatisfied with
adjudications will continue to seek judicial review of them,
utilising the provisions of Part 5 and seeking guidance, no
doubt, from the New South Wales jurisprudence in which
there have been numerous attempts to review adjudications
pursuant to the general principles of an administrative law
dehors a Judicial Review Act.”
[15] His Honour opined that since s 48, which permits the court to stay or dismiss an
application it considers inappropriate or without reasonable basis, applies to both
Part 5 as well as Part 3 applications, it could be used to curtail such threatened
applications for review of the BCIP Act adjudications.
[16] In Bezzina the 2007 amendments were not applicable to the dispute between the
parties. However, Fraser JA, with whom the President and Keane JA agreed, said
of the effect of those amendments: 10
“From the commencement of that Act [the 2007 amending Act],
adjudication decisions are not reviewable under the Judicial Review
Act 1991 (Qld).”
His Honour added in a footnote: 11
“In my respectful opinion, adjudications are no longer reviewable
under any part of the Judicial Review Act 1991 (Qld): cf Intero
Hospitality Projects Pty Ltd v Empire Interior (Australia) Pty Ltd
[2008] QCA 83 at [61].”
[17] The parties in J Hutchinson Pty Ltd v Galform Pty Ltd & Ors,12 perhaps mindful of
the observations in Bezzina, brought an originating application seeking a declaration
that a certain adjudication under the BCIP Act was void and should be set aside and
for other interlocutory and injunctive relief, not pursuant to the JR Act, but s 128 of
the Supreme Court Act 1995 or the inherent jurisdiction of the court. Section 128
empowers the court to make a “merely declaratory decree” and grant no other relief.
Chesterman J was the judge hearing that application. His Honour said, after
referring to the mode of the application: 13
“…but as I pointed out in Intero Hospitality Projects Pty Ltd v
Empire Interior (Australia) Pty Ltd and Hanlon [2008] QCA 83, the
effect of the amendment is only to remove adjudications made
10 [2008] 2 Qd R 495 at [75].
11 [2008] 2 Qd R 495 at footnote 25.
12 [2008] QSC 205.
13 [2008] QSC 205at [27].
-- 6 of 16 --
7
pursuant to the Act from the purview of judicial review under Part 3
of the JR Act. Adjudications remain reviewable under Part 5 of the
JR Act which preserves the jurisdiction the Court formerly had to
control proceedings of inferior courts and domestic tribunals.
Section 41(1) of the JR Act forbids the Court from issuing writs of
prohibition of [sic] certiorari but confirms the power to grant relief to
the same effect as the forbidden writs. A writ of certiorari when
made absolute quashed the decision with respect to which the writ
was sought.”
[18] Justice Philip McMurdo concluded in Walton Construction (Qld) Pty Ltd v Salce &
Ors14 that it was unnecessary to consider these views expressed in Intero and
J Hutchinson that an adjudication decision is still susceptible to an application for
review under Part 5 of the JR Act notwithstanding the 2007 amendments because:
“…as appeared to be ultimately conceded, this Court has jurisdiction
to declare void an adjudicator’s decision which was given without
jurisdiction, quite apart from the operation of the Judicial Review
Act.”15
His Honour’s analysis followed that of the New South Wales Court of Appeal in
Brodyn Pty Ltd v Davenport16 that the operation of the adjudication process in the
BCIP Act depends for its foundation upon the existence of a construction contract to
which that Act applies. 17
[19] In the final case to which I was referred, Uniting Church, the court was asked to
restrain an adjudicator appointed under the BCIP Act from making a correction to
his award that he advised the parties he proposed doing. Since the proposed
correction fell outside the ambit of s 28(1) of the BCIP Act, 18 Daubney J concluded
it constituted an act of jurisdictional error and the court could prevent such error “by
granting appropriate relief, whether declaratory or, if necessary, injunctive.” After
referring to the 2007 amendments his Honour observed: 19
“It is far from clear that the inclusion of the [BCIP Act] in Part 2 of
Schedule 1 of the [JR Act] has the consequence of excluding an
entitlement on the part of a contracting party to make application for
injunctive relief under Part 5 of the Judicial Review Act 1991.”
His Honour noted the observations of Fraser JA in Bezzina and those of
Chesterman J in Intero and preferred to adopt the approach of the latter noting at
[41]:
“One can well understand on policy grounds, particularly the
imperative for the [BCIP Act] to provide an expeditious means of
decision-making for the purposes of progressing an ongoing building
project, that the legislature intended that adjudicators’ decisions
should not be subject to statutory orders of review under the [JR
14 [2008] QSC 235.
15 [2008] QSC 235at [6].
16 (2004) 61 NSWLR 421, especially per Hodgson JA at 441 para 53.
17 See also his Honour’s earlier decision in Cant Contracting Pty Ltd v Casella [2006] QCA 538;
[2007] 2 Qd R 13 at [59]–[61] to the same effect.
18 Adjudicators may correct clerical mistakes.
19 [2009] QSC 134 at [40].
-- 7 of 16 --
8
Act]. The underlying objective for this scheme was neatly explained,
in the context of the cognate New South Wales legislation, by
Barrett J in Greenaways Australia Pty Ltd v CBC Management Pty
Ltd:20
‘15 The aim of the Building and Construction Industry
Security of Payment Act is to ensure that progress payments
are made, whether or not provided for in the contract, so that
the party carrying out building work receives, on account, a
summarily assessed sum as compensation for work done.
That the adjudicator does or does not take into account a
particular item or treats it in a particular way is irrelevant to
ultimate questions of the contractual liabilities of the parties
to one another. In Multiplex Constructions Pty Ltd v
Luikens [2003] NSWSC 1140, Palmer J summarised the
system embodied in the legislation as “pay now, argue
later”. In Brodyn Pty Ltd v Davenport [2004] NSWSC 394,
Hodgson JA said that the Act reflects a legislative intention
“to ensure that disputes concerning the amount of such
payments are resolved with the minimum of delay”, the
payments themselves being “only payments on account of a
liability that will be finally determined otherwise.”’
That policy is, however, a far cry from suggesting that citizens
should be precluded from having recourse to the courts to seeks [sic]
orders in the nature of prerogative remedies or which otherwise lie
generally within the inherent discretion of the Court without an
express legislative exclusion.”
Mr Matthews relied upon those observations.
[20] As set out above, s 18(2)(b) of the JR Act expressly states that the Act does not:
“apply to decisions made, proposed to be made or required to be
made, under an enactment mentioned in schedule 1, part 2.”
Schedule 1 Part 2 is headed “Enactments to which this Act does not apply” and
includes the BCIP Act Part 3 Division 2 which concerns the adjudication of disputes.
Both the plain meaning of the words used and the Explanatory Note support the
conclusion that the legislature intended to exclude the whole of the JR Act.21 It
should also be noted that s 97 of the Queensland Building Services Authority Act
1991 (Qld) (“the QBSA Act”) excludes the JR Act in relation to “a proceeding for a
20 [2004] NSWSC 1186 at [15].
21 “…will fully exempt the decisions of adjudicators made under the Building and Construction
Industry Payments Act 2004 from review under the Judicial Review Act 1991. This amendment is
consistent with the objective of the Building and Construction Industry Payments Act 2004 to create
a dispute resolution process whereby adjudicators can quickly resolve payment disputes between
parties to a construction contract on an interim basis.” Justice and Other Legislation Amendment Bill
2007 Explanatory Note p 978. It should be noted that while the NSW cognate legislation is in
relevant material respects the same as the BCIP Act, s 69 of the Supreme Court Act 1970 (NSW) is
similar in its effect to s 41 of the Queensland JR Act, so that, notwithstanding the privitive terms of,
for example, the NSW equivalent of s 31(4) of the BCIP Act, parties could call in aid that provision
to seek review on the grounds of jurisdictional error, Musico v Davenport [2003] NSWSC 977 of
31 October 2003 at [47]–[52]; Brodyn per Hodgson JA at [49]–[51].
-- 8 of 16 --
9
minor domestic building dispute” decided by the Commercial and Consumer
Tribunal except where:
“(a) the tribunal had or has no jurisdiction under the Act to hear
and decide the proceedings; or
(b) a breach of the rules of natural justice happened in relation
to a party to the proceeding.” 22
This demonstrates, if it were necessary to do so, that the legislature, in a
complementary Act to the BCIP Act had expressly turned its mind to the question of
‘saving’ what might broadly be termed Part 5 reviews. If there were intention to do
so when Part 3 Division 2 of the BCIP Act was excluded from the JR Act there was a
legislative model available.
[21] I conclude that the 2007 amendments to the JR Act apply to exclude the whole of
that Act from the provisions of the BCIP Act relating to adjudicator’s decisions.
[22] However, the jurisdiction of an adjudicator to enter upon his adjudication is
dependent upon the existence of a construction contract of the kind contemplated by
the Act. It includes, by virtue of s 10(2) of the BCIP Act, building work within the
meaning of the QBSA Act for which a person must be licensed. Section 42 of that
Act prohibits a person from carrying out building work unless that person holds an
appropriate licence. If an unlicensed person carries out building work, that person
is not entitled to any monetary or other consideration for doing so.23 As McMurdo J
reasoned in Cant 24 it cannot be the case that the BCIP Act, in its avowed purposed
of making available to a contractor progress payments under a construction contract,
intended to give de facto enforceability to a contract unenforceable by virtue of s 42
of the QBSA Act. His Honour concluded: 25
“In my view, the [BCIP Act] operates only when there is a
construction contract of which the terms as to payment are
enforceable by the builder.”
[23] If an adjudicator enters into an adjudication in respect of which he had no
jurisdiction or, conversely, declines to carry out an adjudication which comes within
the purview of the Act, he has fallen into jurisdictional error and the court has
power under s 128 of the Supreme Court Act to declare the adjudication void for
want of jurisdiction or, as the case might be. It is unnecessary, on this application,
to go further and consider whether this court’s inherent power to control error in
subordinate or inferior courts and tribunals extends to the decision of an adjudicator
under the BCIP Act, 26 or whether that power extends to other examples of error such
as failure to accord natural justice beyond what the BCIP Act requires. The
legislature clearly does not want the process of speedy cash flow for contractors
frustrated by access to the courts “obtained from the rear”. 27
[24] The conclusion is that the application for review is not apt to challenge the alleged
want of jurisdiction in the adjudicator. If the argument otherwise is sound the court
could proceed as if the application was by originating application.
22 Queensland Building Services Authority Act, s 97(2).
23 Queensland Building Services Authority Act, s 42(3) except for the limited bases in s 42(4).
24 [2006] QCA 538 at [61].
25 [2006] QCA 538 at [61].
26 Musico v Davenport [2003] NSWSC 977 at [55].
27 Musico v Davenport [2003] NSWSC 977 at [28]–[41].
-- 9 of 16 --
10
The conditional licence
[25] The licence held by Mr Vadasz as at 13 October 2008 issued by the Queensland
Building Services Authority described Mr Vadasz’s licence class as “Foundation
Work (Piling and Anchors)”. The condition was in the following terms:
“1. The holder of this licence may not carry out any building
work of a kind as defined by the QBSA Act 1991 until the
financial requirements for licensing are satisfied.
2. Appropriate financial information must be provided within
fourteen (14) days of the date of the imposition of this
condition.”
The start date of the licence is 1 February 2008. There is no information as to
whether the information required was provided in the time limited by the condition
when the parties entered into their contract in November 2008. A search made by
Bloomer’s solicitors on 15 June 2009 shows that Mr Vadasz’s licence was then
without conditions. This application has been argued on the assumption that the
licence was conditional when the contract was entered into between the parties and
throughout the period of the contract.
[26] Bloomer contends that the condition on the licence disentitled Australasian to any
monetary or other consideration for performing the building work. Section 42 of
the QBSA Act provides, relevantly:
“42 Unlawful carrying out of building work
(1) A person must not carry out, or undertake to carry out,
building work unless that person holds a contractor’s licence
of the appropriate class under this Act.
(3) Subject to subsection (4), a person who carries out building
work in contravention of this section is not entitled to any
monetary or other consideration for doing so.
…
(9) A person who contravenes this section commits an offence.”
[27] It is common ground that the work carried out by Australasian was building work
within the meaning of the QBSA Act. The question is whether the imposition of an
unsatisfied condition meant that Australasian could not enter into and perform a
contract, issue a payment claim pursuant to that contract and lodge an adjudication
application under the BCIP Act.
[28] In Greg Beer t/a G & L Beer Covercreting v J M Kelly (Project Builders) Pty Ltd28
the Court of Appeal considered the effect of the prohibition in s 42 on a contractor
holding a licence subject to a condition. The condition restricted the scope of work
the contractor could perform within the licence class. The contractor performed the
work and made a claim pursuant to the BCIP Act for work within the scope of work
permitted by the licence class but outside the scope of the condition. The issue for
decision on appeal was whether the words “licence of an appropriate class” in
s 42(1) of the QBSA Act was to be read subject to any condition imposed on the
28 [2008] QCA 35.
-- 10 of 16 --
11
licence. The court concluded that the prohibition in s 42 did not extend to work
done in breach of conditions imposed on the licensee. Mr Holt SC and
Ms Longbottom for Australasian seek to apply that reasoning to the present case
while Mr Matthews for Bloomer argues that Beer is distinguishable.
[29] Before discussing the decision further it is necessary to set out some of the relevant
provisions of the QBSA Act.
“31 Entitlement to contractors licence
(1) A person (not being a company) is entitled to a
contractor’s licence if the authority is, on application
by that person, satisfied that –
(a) the applicant is a fit and proper person to
hold the licence; and
(b) the applicant has the qualifications and
experience required by regulation in relation
to a licence of the relevant class; and
(c) the applicant satisfies the relevant financial
requirements stated in the board’s policies;
and
…”
“34 Grant of licence
(1) If the authority is satisfied, on an application under
this division, that the applicant is entitled to a
licence, the authority must issue a licence of the
appropriate class.
(2) A licence is to be in the form of a card and must –
(a) state the licensee’s name and licence number;
and
(b) state the type of licence; and
(c) state the class of building work the licensee is
licensed to carry out; and
…”
“35 Imposition of conditions etc. on grant of licence
(1) A licence may be granted subject to such conditions
as the authority considers appropriate.
…
(3) Without limiting subsection (1), a contractor’s
licence is subject to the condition that –
-- 11 of 16 --
12
(a) the licensee’s financial circumstances must at
all times satisfy the relevant financial
requirements stated in the board’s policies;
and
(b) variations of the contractor’s turnover and assets
must be notified, or notified and approved, in
accordance with the relevant financial
requirements stated in the board’s policies.”
[30] The authority may impose conditions after the issue of a licence. Section 36
provides:
“36 Subsequent imposition of conditions etc
(1) If the authority has reason to believe –
(a) that a licensee may have insufficient financial
resources to meet possible liabilities in
relation to building work; or
(b) that there is some other proper ground for
imposing a condition on the licence;
the authority may notify the licensee of the proposed
condition and invite the licensee, within a period
specified in the notice, to make written
representations on the proposal.
(2) After considering the written representations (if any)
made by the licensee, the authority, if satisfied that
the condition is appropriate, may, by notice to the
licensee, impose the condition.
(3) A condition may be imposed preventing the licensee
from continuing to carry on business until the
licensee has lodged with the authority appropriate
security against possible liabilities in relation to
building work.
…
(4) The authority may, by subsequent notice to the
licensee, vary or revoke a condition imposed under
this section.
(5) A notice imposing or varying a condition must
inform the licensee of the licensee’s right to apply
for a review of the authority’s decision to impose or
vary the condition.”
[31] The authority has power to suspend the licence if a licensee fails to pay the
appropriate licence fee within the time allowed under the regulation and:
-- 12 of 16 --
13
“(3) If a licence has remained in suspension under this section
for more than 3 months, the authority may, by notice to the
licensee, cancel the licence.” 29
[32] By s 48 the authority may suspend or cancel a licence if:
“(h) the licensee contravened a condition to which the licence is
subject under section 35 or that is imposed under section 36
on the licensee’s licence…”
[33] The tribunal established under the Commercial and Consumer Tribunal Act 2003
(Qld) has jurisdiction to hear an application by the Queensland Building Services
Authority as to whether proper grounds exist for taking disciplinary action against a
person subject to the Act. 30 By s 89 proper grounds exist for taking a disciplinary
action against a licensee if:
“(k) the licensee contravenes a condition of the licence…”
There is no evidence that any disciplinary action was taken against Mr Vadasz and
nothing is noted on the “History” of his licence.
[34] The following extracts from the reasons of judgment of Muir JA (with whom
Holmes JA and Mackenzie AJA agreed) in Beer identifies the process of reasoning
of the court in reaching its conclusion that s 42 cannot be construed to mean a
licence without conditions.
“[19] Under the literal approach favoured by the appellant ‘a
contractor’s licence of the appropriate class’ in s 42(1)
means a licence having the class described in the licence; in
this case ‘Painting and Decorating’. That conclusion draws
support from the Act’s structure. It provides for the issuing
of licences to carry out either all classes of building work or
the building work of the class or classes specified in the
licence…
[20] The words ‘a licence of the appropriate class’ also apper in
s 34. In that section it is apparent that the words mean a
licence for the class of building work specified in the licence
application and in respect of which the requirements of the
Act have been satisfied. It would be a little surprising if the
same collocation of words in s 42 meant something quite
different, namely:
‘A contractor’s licence under which the work may be
carried out… [or] a contractor’s licence of the
appropriate class without a condition, restriction or
limitation by virtue of which such work may not be
carried out.’
[21] Having regard to the Act’s scheme, under which a
contractor’s licence may only be issued in respect of a
specific class or specific classes of work after the Authority
is satisfied that the applicant for a licence is a fit and proper
29 Queensland Building Services Authority Act, s 38.
30 Queensland Building Services Authority Act, s 88.
-- 13 of 16 --
14
person and has appropriate qualifications and experience,
the prohibition in s 42(1), literally construed, is perfectly
sensible. The Act does not contemplate that a licence for a
class of work will be issued to a person who is not
competent to do that work or who has otherwise failed to
meet the Act’s requirements for licence applications. There
was thus no drafting imperative to frame the prohibition in s
42(1) by reference to the holding of a licence which
permitted the subject work to be undertaken. Subsections
(5), (5A) and (7) of s 42, by referring respectively to ‘a
licence of an appropriate class’, ‘work allowed by the class
of licence’ and ‘work of the relevant class’, further illustrate
the assumptions underlying s 42(1) that a licence will not be
issued in respect of a class of work unless the licensee is
duly qualified and that the class of work for which a licence
is issued defines the scope of the work authorised by the
licence.
[22] The literal approach to the construction of s 42 is supported
also by the principle, admittedly rather diminished in force
in recent times, that ‘statutes creating offences are to be
strictly construed.’ 31
…
[25] I readily accept that a primary object of s 42 is the
protection of consumers and that the general legislative
intention of subsection (1) is to prevent contractors doing
work which they are not licensed to do so as to protect
consumers from the hazards arising from building work
undertaken by unqualified or unsuitable contractors.
[26] But it is not the role of the court, under the guise of an
exercise of statutory construction, to supplement the words
of a statute so as to remedy a perceived omission by the
legislature, particularly where such a course would be
inconsistent with the statute’s structure.
[27] The limitations on the power of the court, when construing a
statute, to interfere with the language chosen by the
legislature is explained by Lord Nicholls of Birkenhead in
the following passage from his reasons, with which the other
members of the court agreed, in Inco Europe Ltd v First
Choice Distribution32 :
‘This power is confined to plain cases of drafting
mistakes. The courts are ever mindful that their
constitutional role in this field is interpretative. They
must abstain from any course which might have the
appearance of judicial legislation. A statute is
expressed in language approved and enacted by the
31 Beckwith v R (1976) 135 CLR 569 at 576.
32 [2000] 1 WLR 586.
-- 14 of 16 --
15
legislature. So the courts exercise considerable
caution before adding or omitting or substituting
words. Before interpreting a statute in this way the
court must be abundantly sure of three matters: (1)
the intended purpose of the statute or provision in
question; (2) that by inadvertence the draftsman and
Parliament failed to give effect to that purpose in the
provision in question; and (3) the substance of the
provision Parliament would have made, although not
necessarily the precise words Parliament would have
used, had the error in the Bill been noticed. The
third of these conditions is of crucial importance.
Otherwise any attempt to determine the meaning of
the enactment would cross the boundary between
construction and legislation: see per Lord Diplock in
Jones v Wrotham Park Settled Estates [1980] AC 74,
105. In the present case these three conditions are
fulfilled.’ 33
…
[29] …Also there may have been sound policy reasons other than
those discussed already, for confining the prohibition in s
42(1) to persons not holding ‘a contractor’s licence of the
appropriate class’. If the prohibition were to be extended to
work done in breach of conditions or exceeding limitations
imposed by licences, penal sanction could be visited on
contractors for trivial transgressions unlikely to have any
detrimental impact on consumers. It is of particular
significance that the Act makes specific provision, in
sections 48 and 89, for action which may be taken in the
event of a breach of a condition of a licence. Under s 48 the
Authority may suspend or cancel the licence. The penalties
for breach of conditions are flexible and permit the
imposition of penalties which reflect the gravity of the
breach. That, one would think, is likely to accord with the
legislative intention.”
[35] Mr Matthews seeks to distinguish Beer on the ground that the condition imposed
was in relation to the extent to which the work of the appropriate class could be
performed within that class and not a blanket prohibition imposed by reason of the
non-satisfaction of “one of the fundamental entitlements”34 to a contractor’s licence.
In support of that distinction Mr Matthews referred to the passage at [21] that:
“The Act does not contemplate that a licence for a class of work will
be issued to a person who is not competent to do that work or who
has otherwise failed to meet the Act’s requirements for licence
applications.”
The difficulty with that argument is that the authority did issue Mr Vadasz with a
licence and, on this application at least, that is not reviewable. If he did not provide
33 [2000] 1 WLR 586 at 592.
34 Applicant’s submissions, p 4.
-- 15 of 16 --
16
the necessary financial information within the time limited then the authority had
power to cancel or suspend that licence. It clearly did not do so. It may then be a
discipline matter. There is no arguable distinction in this case from the process of
reasoning in Beer.
[36] The conclusion must be that whilst there may be jurisdiction to correct jurisdictional
error on the face of the record, no such error can be discerned.
Orders
[37] The application is dismissed.
-- 16 of 16 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2009/220