Darveniza v Deen; Deen v Darveniza & Anor [2009] QSC 99
SUPREME COURT OF QUEENSLAND
CITATION: Darveniza v Deen [2009] QSC 99
Deen v Darveniza & another [2009] QSC 99
PARTIES: BOJAN DARVENIZA
(plaintiff)
v
SULTAN MOHAMMED DEEN
(defendant)
and
SULTAN MOHAMMED DEEN
(plaintiff by counter-claim)
v
BOJAN DARVENIZA
(defendant by counter-claim)
LEISURE KART CITY PTY LTD
ACN 009 841 374
(defendant added by counter-claim)
FILE NO/S: 5759 of 2007
DIVISION: Trial
PROCEEDING: Claim
ORIGINATING
COURT:
Supreme Court
DELIVERED ON: 7 May 2009
DELIVERED AT: Brisbane
HEARING DATE: 11-12 December 2008
JUDGE: Fryberg J
ORDER: 1. Judgment for the plaintiff on the claim for
$269,984.00.
2. Judgment for the defendants to the counterclaim.
CATCHWORDS: Contracts – General contractual principles – General offers
and their acceptance – Matters giving rise to a binding
contract – Particular instances – No proof of acceptance
COUNSEL: P Hackett for the plaintiff and the second defendant to the
counterclaim
-- 1 of 8 --
2
R Myers for the defendant
SOLICITORS: H Drakos and Company for the plaintiff and the second
defendant to the counterclaim
John M O’Connor & Company for the defendant
[1] FRYBERG J: The plaintiff sues to recover a loan. The defendant admits the loan
but claims a set off to the full extent of the amount owing. The set off is said to
arise from the price payable under a contract for work and services allegedly
performed by the defendant for the plaintiff. The defendant counterclaims for the
un-set off balance of the price. The plaintiff denies the existence of any such
contract and denies that the defendant did any work or performed any services for
him in accordance with the alleged contract. No technical issues about set off are
raised. Despite the pleadings no issue as to parties is raised on either side. It should
be simple.
Background
Undisputed facts
[2] Mr Darveniza is a property owner. Mr Deen is or represents an earthmoving,
demolition and civil engineering contractor. They have been personal friends and
have dealt with each other in business for many years, Mr Deen performing
earthworks for Mr Darveniza. In late September 2006 Mr Deen was in financial
difficulty. He was unable to finance some new equipment which he needed. He
approached Mr Darveniza for a loan. Mr Darveniza agreed to lend him $240,000
secured on the new equipment. No interest was payable, but Mr Deen forwent
payment of $24,000 which was part of the amount owing to him for work done for
Mr Darveniza at Eagle Farm. In addition it was agreed that the loan would be
repaid by one payment of $100,000 on 30 November 2006 and a second of
$150,000 on 31 December 2006.
[3] The work at Eagle Farm was duly completed and the $24,000 duly appropriated.
However Mr Deen was unable to repay the payment due on 30 November. On 29
November he wrote to Mr Darveniza seeking an extension of time. There was no
response to his letter but neither did Mr Darveniza take action to recover the loan.
Mr Deen again defaulted on the payment due on 31 December 2006. On 17 January
Mr Darveniza agreed to extend time for two months, making $100,000 repayable by
30 January 2007 and $150,000 repayable by 28 February 2007 on the basis that Mr
Deen would pay interest at 10% per annum calculated on daily rests.
[4] Mr Deen agreed to that proposal but did not make the payments required under it.
On 5 February he wrote to Mr Darveniza seeking a further extension for an
unspecified period. Mr Darveniza granted an indefinite extension provided interest
owing to date was paid immediately and future interest was paid on a weekly basis.
It appears that Mr Deen agreed to that proposal also. However by 17 April he still
had paid nothing. On that day Mr Darveniza demanded payment in full of the claim
and interest. It was not forthcoming.
-- 2 of 8 --
3
[5] Shortly thereafter Mr Darveniza requested Mr Deen to perform some earthworks at
a property located at Gosport Road, Hemmant, the price to be set off against Mr
Deen's indebtedness. Mr Deen submitted a quotation of $33,000 to do the work on
that basis, and Mr Darveniza accepted the quotation. The work comprised the
following:
“1. Sweep out sheds with Bobcat sweeper
2. Clean up rubbish and remove.
3. Construct concrete apron around 2 x Field Gully Pits
4. Fill, with roadbase, depression in centre of yard, so falls to
Field Gully
5. Grade rear yard”.
Paragraph 6 of the defence
[6] Mr Deen pleaded:
“6. The quotation was duly accepted by the plaintiff. The work
was duly performed to the defendant’s satisfaction. The
work was completed on or about 20 May 2007 and the sum
of $33,000.00 was offset against the defendant’s
indebtedness to the plaintiff.”
Mr Darveniza admitted that paragraph.
[7] This was one of several cases where the pleadings bore no relationship to the
reality. The first error in para 6 emerged fairly early in Mr Darveniza's cross-
examination. Mr Myers (for Mr Deen) put to Mr Darveniza that the work under that
contract was performed “between about the 11th and the 23rd or thereabouts of
May”. The latter date subsequently took on some significance. No explanation of
why the defence alleged 20 May was ever advanced.
[8] The second error was the allegation that the work in the quotation was duly
performed. Notwithstanding Mr Darveniza's admission of that fact, it was not
correct. It was common ground that Mr Deen did not fill the depression in the
centre of the yard with road base. Instead, he used a material called profile. Profile
is the detritus salvaged when a bitumen road is torn up. It consists of lumps of
bitumen with gravel embedded. It is much cheaper than road base, but unlike road
base, it cannot be compacted.
[9] The third error in para 6 was the allegation that the work was performed to the
defendant's satisfaction. It emerged at the beginning of the defendant's case that the
pleader meant to say “to the plaintiff's satisfaction”. Mr Myers sought and was
granted leave to amend the defence. Mr Hackett, for the plaintiff, did not oppose
the amendment provided he had leave to amend the reply and answer in
consequence. The following exchange then took place:
“MR HACKETT: Your Honour, do I have the consequential leave?
HIS HONOUR: Yes.
MR HACKETT: Thank you, your Honour.
HIS HONOUR: You do. But you will need to turn your mind to
persuading me that the original admission wasn't made on the
understanding that it referred to the plaintiff.
MR HACKETT: I hear your Honour.”
-- 3 of 8 --
4
In the event, no amendment was made to the reply and answer. I infer that it was
always the plaintiff's intention to admit the paragraph as amended.
[10] That leads to the fourth pleading error in relation to para 6: the plaintiff's admission
of the paragraph. Mr Darveniza asserted vigorously in cross-examination that the
work under the contract was not duly performed in that Mr Deen used profile
instead of road base. No objection was taken to the admission of that evidence
notwithstanding the fact that it contradicted the pleading. Doubtless that reflected
the fact that both sides accepted the profile had indeed been used. The errors in the
pleadings were simply irrelevant to them.
Difficulties in assessing credibility
[11] I have had considerable difficulty in assessing credibility of witnesses in this case.
All four major witnesses, Mr Darveniza, Mr Deen, Mr Thompson and Mr
Duncombe, were argumentative and prone to giving unresponsive answers.
Answers about what was said in conversations were often given in the form of
summaries or interpretations of what was said and these were accepted as sufficient
answers by the questioner. From time to time all of them seemed to be answering in
a way best calculated to serve the interests of the side which called them. English
was not Mr Darveniza's first language and he had some difficulty with tenses. Mr
Deen was not called first in the defence case and was allowed to remain in court to
hear Mr Duncombe’s evidence before he gave his own evidence. I have approached
the evidence of all four witnesses with scepticism. Assessment was not helped by
the fact that questions in cross-examination often enquired of more than one topic or
were unhelpfully vague, particularly by failing to specify to what point in time the
question related. By contrast I thought Mrs Darveniza an honest and accurate
witness, although her evidence was quite short.
The use of profile
[12] Mr Darveniza asserted vigorously that he did not approve the use of profile. It was
put to him that he had a conversation with Mr Deen about profile before it was laid.
Mr Darveniza agreed. It was suggested that in the course of that discussion he was
told that profile could not be compacted. Mr Darveniza denied that and said that he
was told it was just as good as road base. It was suggested that Mr Duncombe
drove a truckload of profile to the site for his approval as material to be used on the
site, that he looked at it and that there was a discussion with Mr Deen about its
qualities. Mr Darveniza was asked if he understood the question and he replied in
the affirmative; but he was not asked to answer it. It was suggested that he was told
that to use road base as opposed to profile would substantially increase the cost of
the job. He denied that. It was again suggested that profile was brought to the site
on a truck driven by Mr Duncombe for his approval as a material to be used and he
denied the suggestion. It was suggested that he quite consciously and deliberately
approved the use of profile because of the lesser cost involved. Mr Darveniza
replied:
“I didn't approve of the profile being put there when I found out it
can't be compacted, even though at the time I had no intentions of
putting bitumen there, but I still wanted the land to be compacted so
hard that it wouldn't create any dust or for the land to get holes in it
or tracks.”
-- 4 of 8 --
5
[13] At that point, objection was taken to the line of questioning. Mr Myers took
instructions and then announced that he was “instructed to withdraw that in any
event, the cost saving aspect”.
[14] Mr Darveniza said that he did not find out about the un-compactability of profile
until after it had been laid. Its use was unacceptable to him because it could not be
compacted, a process which was necessary for the proposed use of the premises by
transport vehicles. Shortly afterwards he decided to have the whole area bitumened
to comply with the requirements of a tenant or of the Council. Profile was
unacceptable as a material beneath bitumen, but his decision to use bitumen was not
the reason he found profile unacceptable.
[15] When he realised that the profile could not be compacted, Mr Darveniza said, he
told Mr Deen to remove it from the area where it had been laid. He said that it
could be pushed to a back paddock and did not have to be removed from the site. He
asked Mr Deen what the latter was going to do to earn his $30,000 and Mr Deen
offered to excavate some soft spots which were in a different part of the premises,
fill them and compact them. He did not require Mr Deen to acquire and lay road
base in the original area, even though that was a requirement of the contract. Mr
Deen subsequently removed the profile but did not do the soft spots (although
elsewhere Mr Darveniza said Mr Deen did work on the soft spots). Nonetheless Mr
Darveniza was content to allow him credit for the $33,000 contract price.
[16] Mr Deen's evidence was that three or four days after the contract was signed and
before any profile was brought on site, he told Mr Darveniza that profile would be a
better material for the job. That was because there would remain several low-lying
areas where road base would simply turn to mud if it became wet. He did not testify
unequivocally that he told Mr Darveniza that road base could not be compacted. He
said that in addition to placing profile in the depression in the centre of the yard, he
excavated three low lying spots elsewhere and filled them with road base,
notwithstanding that the contract did not require that work to be done. He thought
the work was virtually completed by 24 May.
[17] In cross-examination Mr Deen recognized that the contract required filling with
road base so that the fall was to the two drains, which would necessarily be elevated
somewhat from their existing position. He could not explain how porous profile
would achieve this. There was, he testified, no necessary cost saving in using
profile as opposed to road base and he had not instructed his counsel to suggest that
there was. He organised a truckload of profile to be brought to the site and tipped,
and Mr Darveniza then approved its use. Mr Duncombe drove the truck and was
standing next to him during the conversation.
[18] Mr Duncombe described the work which Mr Deen told him to do in relation to the
first contract as including digging out the soft spots. He said that Mr Deen told him
to do this on about 14 or 15 May. At about the same time Mr Deen told him to use
profile for the filling. He was not aware of what the contract provided for the filling
and had not been instructed prior to this to use road base. Mr Deen (not Mr
Duncombe) brought a load of profile in and Mr Deen and Mr Darveniza looked at it
and decided it would do. Subsequently, after 26 May, Mr Duncombe went back and
dug out the profile because, as far as he knew, it was not going to be heavy enough
to run trucks on; there was insufficient depth. Stabilised road base, a mix of
concrete and road base, was then introduced.
-- 5 of 8 --
6
The contract for bitumen
[19] It is common ground that on or about 24 May Mr Darveniza told Mr Deen that he
now wanted to bitumen the whole area and asked for a quote. The whole area was
two to three times the area involved in the first contract. The work necessarily
involved digging out the three low-lying spots referred to above and filling them
with non-porous material, importing road base and compacting, before applying
bitumen. Mr Deen responded the same day with a oral quote for $360,000. Mr
Darveniza testified that he immediately rejected that quote because it was too high.
Mr Deen testified that Mr Darveniza accepted the quote.
[20] Mr Deen claimed that over the next three weeks his men performed work pursuant
to that contract. Mr Darveniza said that Mr Deen's men did little work over the next
three weeks apart from filling in and compacting three or four holes, and that the
work they did was simply excavating and filling and compacting the soft (low-
lying) spots, as Mr Deen had agreed to do in lieu of placing the road base required
under the first contract. Mr Deen claimed his men did a substantial amount of work
directed toward the bitumening of the whole area. However after about three
weeks, he said, Mr Darveniza approached him and asked his permission to allocate
the bitumening to another contractor. Because of their friendship, he agreed to this.
At this time Mr Darveniza agreed, according to Mr Deen, that $240,000 worth of
work had been done to date. Mr Darveniza denied all of these allegations.
[21] Mr Deen was conspicuously unable to produce any documentation to support his
claim regarding the work which was done. He said he did not have to purchase road
base because his firm kept a large supply of it at its depot. He said he had no
records of where his men worked or who worked on this job. His firm’s records of
fuel usage likewise did not identify the job concerned. In fact there was nothing
which his firm had purchased specifically for this job. He did however have a
handwritten quotation to do the bitumening work for $360,000 which would have
been sent to Mr Darveniza about 24 May. Generally quotes were faxed to Mr
Darveniza by a member of the staff. However the firm did not keep a record of
faxes sent. Indeed he could not be certain whether the fax was sent from his home
machine or his office machine.
[22] Mrs Darveniza, who was responsible for the administration of her husband's
companies, testified that the fax had never been received.
[23] Mr Darveniza claimed that having rejected Mr Deen's tender, he contacted Mr
Thompson of Ace Bitumen. Mr Thompson testified that he went to the site on
28 May with a view to giving a quote for the bitumening work. He returned a few
more times before providing his quotation to do the work for $209,000 on 12 June.
He insisted that Mr Deen's men and equipment be off the site before he began work.
He was extremely scornful of the quantity and quality of any work which they had
done.
Findings
[24] It was common ground between the parties that only two questions were to be
resolved in this case. The first was whether the oral quotation for $360,000 was
accepted by Mr Darveniza and the second was whether Mr Deen performed work to
the value of $240,000 pursuant to it.
-- 6 of 8 --
7
[25] The first question depends to begin with on word against word, the word of Mr
Darveniza against the word of Mr Deen. I have already referred to the
unsatisfactory nature of the evidence given by both men. I do not feel confident in
relying on either of them except where their evidence is uncontradicted or
corroborated in some respect or consistent with plain common sense. Mr Deen
submitted there was corroboration of his version in the fact that his men were (albeit
only from time to time due to wet weather) working on site for up to three weeks
after 24 May, and performed a substantial amounts of work; and that they did so not
only following the oral agreement but also following the dispatch of the written
quotation by facsimile.
[26] As I have said, I accept Mrs Darveniza's evidence that no fax was ever received. I
found Mr Deen's evidence regarding the written quotation singularly unconvincing.
If the document were genuine one would have expected there to be working
documents used in the preparation of the quotation. None was produced or referred
to it. No attempt was made to establish the provenance of the document: where and
by whom it had been filed or what was filed near it; and Mr Deen's explanation of
why it was not typed (as were his other quotations and his correspondence) was
limp. He claimed that when he did quotations himself he wrote them and when he
did them from the office they were typed. He claimed he would be able to produce
many handwritten quotes sent to Mr Darveniza. In the event, no attempt was made
to do so. Nor was there any attempt to produce records from his telephony provider
to show that a call was made to Mr Darveniza at the relevant time. I think it is more
probable than not that the handwritten quotation was spurious and was never faxed
to Mr Darveniza.
[27] Nor am I prepared to accept Mr Deen's evidence regarding the amount of work done
after 24 May. Its quality is insufficient to convince me of its accuracy, unsupported
as it is by any documentation. No doubt it would not have been possible to produce
evidence at the standard of that of a quantity surveyor; but I find it difficult to
accept that Mr Deen's office would be so devoid of records that he would be
required to do the calculations from memory. The quantity of work alleged is
challenged by both Mr Darveniza and Mr Thompson. While their evidence has its
own problems, it is enough to challenge Mr Deen to produce something more
convincing than he has done. Mr Duncombe provided some support for Mr Deen's
evidence, but it did not stand up in detail. The number of man hours able to be
calculated from his diary bore no relationship to the alleged value of the work.
Significantly, none of Mr Deen's calculations was put to Mr Thompson. Mr
Thompson had no interest beyond an emotional involvement apparently founded on
indignation. I accept his evidence, given repeatedly with vehemence, that there was
no road base on the site when he visited it, except perhaps in the soft spots.
[28] Mr Darveniza's explanation for why the Mr Deen's men were on site from time to
time over a period of three weeks or so after 24 May is suspiciously convenient.
That explanation -- that he was performing work on the soft spots pursuant to his
oral agreement to vary the first contract -- is inconsistent with his admission of
para 6 of the defence. It emerged for the first time in cross-examination. That
could be explained by the fact that the evidence in chief was extremely short, having
regard to the fact that the onus of proof lay on Mr Deen, were it not for the pleading
inconsistency. But the weight to be attributed to it is diminished by Mr Deen's own
errors on the same point.
-- 7 of 8 --
8
[29] I find that Mr Darveniza's evidence regarding the placement of profile is more likely
to be accurate than that of Mr Deen. I infer that Mr Deen's initial instructions to
counsel were that Mr Darveniza agreed to use profile in order to save money. When
it emerged in the midst of cross-examination that the conversation regarding profile
must have occurred after the formation of the first contract, so that any money saved
would be for the benefit of Mr Deen, he withdrew those instructions and when he
gave evidence claimed he had never given such instructions. He then said that there
was no necessary price difference between road base and profile. I do not accept
that evidence. I infer that had Mr Deen's claim that he never gave such instructions
been correct, his lawyers would have done as any honourable lawyers would do in
that situation: they would have provided evidence corroborating his claim. That did
not happen.
[30] It may be that when he was first told of the intention to use profile Mr Darveniza
raised no objection. I am however satisfied that he was not then told that it could
not be compacted, and that he objected as soon as he found out that fact. I
disbelieve Mr Deen's evidence that he not only obtained approval in advance or the
use of profile but also explained in advance that it could not be compacted.
[31] Mr Darveniza found out about the impossibility of compacting profile only shortly
before he decided to bitumen the whole area. There was some confusion regarding
the sequence of conversations, but I find that Mr Darveniza's version is more likely
than that of Mr Deen.
[32] It follows that the fact that Mr Deen had men on the site from time to time for up to
three weeks after about 24 May does not corroborate his evidence about Mr
Darveniza's acceptance of his quote.
Conclusion
[33] I am unable to accept the evidence of either side as representing an accurate and
reliable version of what Mr Darveniza said in response to Mr Deen’s oral quote of
$360,000. Mr Darveniza's version is more probable than that of Mr Deen. The
onus of proving the pleaded set off lies on the latter. He has not proved that the
contract upon which the set off is founded was made, nor has he proved that the
work in it (save perhaps for excavating and filling the soft spots with road base) was
performed. The plea of set off fails. So does the counterclaim.
[34] The plaintiff's calculation of his claim including interest to 11 December 2008 is
$261,244.64 and that amount was undisputed. Further interest has accrued since
that time. The final amount for judgment must include that further interest. I shall
hear the parties on that question and on costs.
-- 8 of 8 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2009/099