AGL Energy Ltd v Queensland Competition Authority & Anor; Origin Energy Retail Ltd v Queensland Competition Authority & Anor [2009] QSC 90
SUPREME COURT OF QUEENSLAND
CITATION: AGL Energy Ltd v Queensland Competition Authority &
Anor; Origin Energy Retail Ltd v Queensland Competition
Authority & Anor [2009] QSC 90
PARTIES: AGL ENERGY LTD ACN 115 061 375
(Applicant)
v
QUEENSLAND COMPETITION AUTHORITY
(First Respondent)
MINISTER FOR MINES AND ENERGY
(Second Respondent)
ORIGIN ENERGY RETAIL LTD ACN 078 868 425
(Applicant)
v
QUEENSLAND COMPETITION AUTHORITY
(First Respondent)
MINISTER FOR MINES AND ENERGY
(Second Respondent)
FILE NO/S: BS 7793 of 2008
BS 8576 of 2008
DIVISION: Trial Division
PROCEEDING: Application
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: 28 April 2009
DELIVERED AT: Brisbane
HEARING DATE: 9-11 March 2009
JUDGE: McMurdo J
ORDER: Declare that the decision of the Queensland Competition
Authority dated 30 May 2008 was not made in accordance
with the Electricity Act 1994 (Qld) because:
1. in working out the benchmark retail cost both for
the relevant tariff year and the preceding tariff
year, the Authority did not form a view of the
-- 1 of 35 --
2
likely total of the costs to be incurred during that
year to purchase energy to supply the NEM load of
the State for that year, as required by s 92(1) of the
Act;
2. in working out the total benchmark retail cost for
the preceding year, the Authority used data which
had not been used in working out that cost when
the year to 30 June 2008 had been the relevant
tariff year, and which the Authority was not
otherwise entitled to use in this decision.
CATCHWORDS: ADMINISTRATIVE LAW – JUDICIAL REVIEW –
GROUNDS OF REVIEW – ERROR OF LAW –
IRRELEVANT CONSIDERATIONS – IMPROPER
PURPOSES – where Act requires Authority to calculate the
cost “to supply all of the NEM load of the State” – where Act
requires Authority to base estimate on the “long run marginal
cost of energy” – whether this requires exclusion of directly
connected customers or whether it permits reference to the
entire Queensland load – whether the Authority is to adopt
the previous year’s BRCI or whether it is to recalculate the
BRCI each year
Electricity Act 1994 (Qld) s 23(8), s 90(1), s 90(4), s 90(5),
Sch 5, s 91B, s 91D, s 91E, s 91F, s 91G, s 92, s 93, s 94
Electricity and Other Legislation Amendment Act 2006 (Qld)
Electricity–National Scheme (Queensland) Act 1997 (Qld) s 6
Judicial Review Act 1991 (Qld)
Electricity Regulation 2006 (Qld) s 104, s 105, s 106, s 107, s
108, s 109, s 110, s 111
National Electricity Rules, ch 10
National Electricity (South Australia) Act 1996 (SA)
Hunter Resources Ltd v Melville (1987-88) 164 CLR 234
Webster v McIntosh (1980) 32 ALR 603
COUNSEL: N C Hutley SC, with R C A Higgins, for AGL Energy
P J Flanagan SC, with J M Horton, for Origin Energy Retail
J McKenna SC, with M Hoch, for the Authority
P J Freeburn SC, with A A Horneman-Wren, for the Minister
SOLICITORS: Gilbert + Tobin for AGL Energy
Clayton Utz for Origin Energy Retail
Mallesons Stephen Jaques for the Authority
Crown Law for the Minister
-- 2 of 35 --
3
[1] Full competition in the retail supply of electricity was introduced in Queensland on
1 July 2007. Since then, electricity retailers have been able to offer their own prices
to customers and most customers have been able to choose between retailers. But
customers who are not offered a contract price, or who choose not to accept one,
may purchase their electricity at what is called a notified price.1 These customers
are referred to as non-market customers. 2
[2] Notified prices are fixed by the Minister for Mines and Energy, or by the Minister’s
delegate, the Queensland Competition Authority (“the Authority”), under the
Electricity Act 1994 (Qld) (“the Act”). The Minister or the Authority (in either case
called “the pricing entity”3 ) must decide these prices, or the methodology for fixing
them, each year.4 In deciding the notified prices, the pricing entity must comply
with the regime for annual indexation of prices which is prescribed by Div 3 of Ch 4
of the Act. It requires the pricing entity to apply a certain formula so that, broadly
speaking, the prices will change from one year to the next commensurately with the
change to the retailers’ costs of supplying their customers.
[3] This case concerns the application by the Authority of that formula in fixing
notified prices for the year ending 30 June 2009 (“the 2009 year”). The applicants,
AGL Energy Limited (“AGL”) and Origin Energy Retail Limited (“Origin”) are
retailers. They say that the Authority’s decision, which was dated 30 May 2008
(“the decision”), was not made in accordance with the Act. On their case, the
Authority has misinterpreted the Act and regulations made under it in at least
three respects. But before going to the legislation and the respective arguments, it is
necessary to describe some features of the electricity industry.
[4] In 1996, there was established a so-called national electricity market covering
Queensland and most other States and the Australian Capital Territory. In each of
these jurisdictions there is uniform legislation providing for this market, the
Queensland statute being the Electricity – National Scheme (Queensland) Act 1997
(Qld). It provides for the application in this State of the National Electricity Law
which is set out in the schedule to the National Electricity (South Australia) Act
1996 (SA) as in force for the time being.5
[5] This national scheme has relevantly two elements. The first is an interconnected
power system between the jurisdictions known as the national grid. Under the Act,
this term takes its meaning from the so-called National Electricity Rules6 which are
made under the National Electricity Law, and by those Rules the national grid is:
“the sum of all connected transmission systems and distribution
systems within the participating jurisdictions”.7
[6] Transmission systems or “networks” are the plant and equipment which transport
relatively large quantities of electricity at high voltages from major electricity
generators. The term is defined in the National Electricity Rules by reference to
certain levels of voltages. A distribution system or network is plant and equipment
1 Electricity Act 1994 (Qld) s 90(4).
2 s 23(8).
3 s 90(5).
4 s 90(1).
5 Electricity – National Scheme (Queensland) Act 1997 (Qld) s 6.
6 By the definition in Schedule 5 of the Act.
7 Chapter 10 of the National Electricity Rules.
-- 3 of 35 --
4
by which electricity is transported but which is not a transmission network. These
are lower voltage networks which are typically used to transport electricity from
connection points with transmission networks to consumers such as households and
most businesses.
[7] Section 6 of the Act defines the term “transmission grid”, so that it effectively
means the “transmission system” to which I have referred. It provides:
“6. Transmission grid
(1) A transmission grid is a system, or part of a system,
of electric lines, substations and associated
equipment providing connection between generation
facilities and supply networks or customers not
supplied through supply networks.”
Section 8 of the Act defines the term “supply network”, so that it effectively means
the “distribution system” to which I have referred. It provides:
“8 Supply network
A supply network is a system, or part of a system, of electric
lines, substations and associated equipment, other than a
transmission grid, for distributing electricity to customers,
whether or not generating plant is connected to it.”
[8] Section 6 recognises the existence of the so-called directly connected customers:
those who are supplied directly from the transmission grid rather than through a
supply (distribution) network. Accordingly, the load which is conveyed from a
transmission grid to a supply network does not include that which is consumed by
directly connected customers. The distinction between directly connected
customers and customers serviced through a supply network is central to this case.
The applicants contend that the electricity consumed by directly connected
customers should have been entirely excluded from consideration in the Authority’s
assessment of the costs of retailers.
[9] The other presently relevant element is the spot market for electricity. This is
conducted by the National Electricity Market Management Company
(“NEMMCO”). The sellers in this market are typically electricity generators and
the buyers are typically electricity retailers or, in some cases, large consumers. The
market is compulsory in that generators across the participating jurisdictions are
required to transact through it with NEMMCO as the counterparty. Electricity
generators are required to submit offers detailing how much power they are willing
to sell and at what price. NEMMCO matches this information with the
requirements of buyers with the objective of ensuring that total supply equals total
demand and at the lowest feasible cost to the buyer, and by this means spot prices in
the market are derived. The market is divided into geographic regions which
presently correspond with the respective participating jurisdictions. Wholesale spot
prices are determined for each region.
[10] Spot prices can be very volatile. According to Mr Price, a consultant economist
with wide experience in the energy sector, the level of spot prices can rapidly
increase (or decrease), such as from an average level of about $40 per megawatt
-- 4 of 35 --
5
hour to about $10,000 per megawatt hour. Generally spot prices are higher during
the day than at night, and on weekdays than at weekends, corresponding with
different levels of demand. The level or quantity of demand, and thereby the level
supply, is generally referred to as the load. The variation in that load over time is
described as the load shape or demand profile. Some electricity consumers have
what is called a flat load shape, meaning that their level of demand varies little
across a day. Examples are some large industrial consumers of electricity such as
aluminium smelters and major manufacturing plants. Some types of consumers
have what is called a “peaky” shape or profile, meaning that the demand varies
greatly across a day or otherwise over time. For example, households often have
volatile load shapes, particularly through the use of air conditioning units.
The fixing of tariffs under the Act
[11] Within Pt 2 Div 2 of Ch 4, s 90 provides that the pricing entity must, for each tariff
year, decide the prices, or the methodology for fixing the prices, that an electricity
retailer may charge its non-market customers. The prices or methodology must be
in the form of a tariff schedule.8 But prices, or the methodology for fixing prices,
may be made from time to time and not just once a year.9 The price or prices so
fixed are called the notified prices.10 A retailer must charge non-market customers
the notified prices.11
[12] The annual indexation of tariffs is required by s 91B as follows:
“91B Operation and application of div 3
(1) This division requires the annual indexation of tariffs
in the current tariff schedule to the extent the tariffs,
or components of the tariffs, will continue to apply
in the next tariff year (the relevant tariff year).
(2) However, indexation under this division only applies
to prices for customer retail services decided or fixed
under section 90(1).
(3) Also, this division does not prevent the pricing entity
from, under section 90, adding to, removing or
changing a tariff when indexation is required under
this division.
(4) each tariff indexed under this division applies from
the start of the relevant tariff year.”
The term “customer retail services” means the sale of electricity for consumption at
certain prices. 12
[13] Section 91D prescribes the relevant formula as follows:
8 s 90(2).
9 s 90(2A)(a).
10 s 90(4).
11 s 91A(2).
12 Defined in Schedule 5 of the Act.
-- 5 of 35 --
6
“91D Indexation formula
(1) Each tariff in the current tariff schedule must be
indexed by applying the following formula –
Ty = Ty-1 × By ⁄ By-1
where –
Ty is the tariff component for the relevant tariff year.
Ty-1 is the relevant tariff component for the preceding
tariff year.
By is the benchmark retail cost index for the relevant
tariff year, as worked out under subdivision 3.
By-1 is the benchmark retail cost index for the
preceding tariff year.
(2) For subsection (1), the benchmark retail cost index
for the preceding tariff year is worked out under
subdivision 3 as if a reference in the subdivision to
the relevant tariff year were a reference to the
preceding tariff year.
(3) In this section –
tariff component, for the relevant tariff year, means
each separate charge or fee stated in the notified
prices that applies for a particular tariff category.
Examples of tariff components –
Service fees, demand charges, energy charges, annual
payments and minimum payments”
[14] Accordingly, the tariff is to be varied by the extent of the variation in the so-called
benchmark retail cost index (the “BRCI”) from one year to the next. In the present
case, the “relevant tariff year” was the 2009 year and the “preceding tariff year” was
the year to 30 June 2008 (“the 2008 year”). The Authority’s decision was dated
30 May 2008. According to the submissions for the Authority and for the Minister,
s 91D permitted and indeed required the Authority, in fixing the 2009 prices, to
calculate the BRCI for the 2009 year, and at the same time the BRCI for the
2008 year.
[15] Of course, by its previous decision which fixed the prices for the 2008 year, the
Authority had had to make a calculation of the BRCI for that 2008 year. But this
time around, the Authority saw fit to recalculate the BRCI for 2008, using a
different methodology and different data. That is the subject of complaint by the
applicants. They contend that the Authority was not obliged to recalculate the 2008
BRCI, and indeed was not entitled to do so except in certain limited respects.
-- 6 of 35 --
7
[16] The calculation of each BRCI was to be in accordance with s 91E to s 94 of the Act.
Section 91E provides:
“91E Benchmark retail cost index
The benchmark retail cost index for the relevant tariff year is
the index, expressed in c/kWh, for the State, worked out by
applying the following formula –
B = R ⁄ L
where –
B is the benchmark retail cost index for the year.
R is the total benchmark retail cost for the year.
L is all of the NEM load of the State for the year.”
The denominator, the “NEM load of the State for the year”, is defined13 to mean “the
State’s NEM load, as worked out under s 91F” as follows:
“91F Working out NEM load
(1) The pricing entity must work out the State’s NEM
load for the relevant tariff year.
(2) The NEM load is the pricing entity’s view of the
total of the loads for the State supplied at each
transmission connection point to a supply network,
as adjusted for any matter prescribed under a
regulation.
(3) The total must be expressed in kilowatt hours.
(4) The pricing entity must consult with interested
persons about the methodology it proposes to use to
form the view.
(5) In this section –
transmission connection point means a Queensland
transmission network connection point as defined
under the National Electricity Rules.”
[17] In the National Electricity Rules, a transmission network connection point is defined
as “a connection point on a transmission network”, and the term “connection point”
is defined in terms which would include both the points of supply from a
transmission grid to a supply network and from a transmission grid to a directly
connected customer. Accordingly, in s 91F(2) “the total of the loads supplied at
each transmission connection point” would include electricity supplied to directly
13 By s 91C.
-- 7 of 35 --
8
connected customers. However, s 91F(2) limits the NEM load to loads for the State
supplied at each transmission connection point to a supply network. The result, as
all parties accept, is that under the Act, the NEM load is not the entire load for the
State which is delivered by the grid, but is that part of it which is conveyed through
the supply network.
[18] Accordingly, when calculating the denominator for the BRCI formula in s 91E, the
Authority correctly excluded that part of the State’s load which went to directly
connected customers. It is the Authority’s calculation of the numerator, which is
the total benchmark retail cost, which the applicants challenge.
[19] The total benchmark retail cost is defined by s 91G as follows:
“91G Total benchmark retail cost
(1) For section 91E, the total benchmark retail cost,
expressed in cents per kilowatt hour, for the relevant
tariff year is the estimated total cost of supplying
customers in the State during that year, as worked
out by the pricing entity.
(2) The total cost must be the total of each of the
following (each a benchmark retail cost element) as
fixed by the entity –
(a) the cost of energy, as worked out under
section 92;
(b) network costs, as worked out under
section 93;
(c) retail costs, as worked out under section 94;
(d) any other relevant costs the pricing entity
considers relevant.
(3) In fixing a benchmark retail cost element other than
network costs, the pricing entity must consult with
interested persons in the way prescribed under a
regulation.
(4) The working out of any particular benchmark retail
cost element is subject to any relevant fixed
principle.
(5) If the fixed principle is inconsistent with the
operation of a section stated in subsection (2), the
principle prevails to the extent of the inconsistency.”
[20] If read alone, s 91G would appear to refer to the entire Queensland load, rather than
that part of it which supplies customers through a supply network. In particular,
s 91G(1) refers to the estimated total cost of supplying “customers in the State”.
-- 8 of 35 --
9
However, that is affected by s 92, which provides for how the pricing entity is to fix
the cost of energy. Section 92 provides:
“92 Cost of energy
(1) The cost of energy must reflect the pricing entity’s
view of the likely total of the costs to be incurred
during the relevant tariff year to purchase energy to
supply all of the NEM load of the State for the
relevant tariff year.
(2) The view must be based on the pricing entity’s most
recent estimate of the long run marginal cost of
energy in the part of the State connected to the
national grid, after taking into account –
(a) the Queensland gas scheme under
chapter 5A; and
(b) the scheme under the Renewable Energy
(Electricity) Act 2000 (Cwlth).
(3) The estimate must take into account the most
efficient combination of generating plant to supply
all of the NEM load of the State for the relevant
tariff year.
(4) Unless the cost of energy is subject to a fixed
principle, the long run marginal cost estimate must
be prepared at least every 3 years.
(5) Subsection (4) does not prevent the pricing entity
preparing the long run marginal cost estimate more
frequently.
(6) In estimating the long run marginal cost, the pricing
entity must comply with any methodology
prescribed under a regulation.”
The questions
[21] In essence there are three questions in these proceedings, and two of them concern
s 92. First, the applicants contend that s 92(1) required the Authority to assess the
likely cost to purchase the energy needed to supply not all of the Queensland load,
but that part of it which was the NEM load of the State. Whilst it has not always
clearly accepted that interpretation, the Authority argues that nevertheless, it did
make that assessment. The applicants argue otherwise, and say that the Authority’s
reasoning involves a misinterpretation of s 92(1).
[22] Secondly, there is a question of the proper interpretation of s 92(2). Again, the
applicants’ complaint is that the Authority made an estimate under this provision by
-- 9 of 35 --
10
reference to the entire Queensland load and not the NEM load of the State which,
they argue, required exclusion of directly connected customers.
[23] Thirdly, there is a complaint about the Authority’s reassessment of the BRCI for the
2008 year.
[24] At this point it is necessary to say something more about the market for which these
provisions were enacted.
[25] Large industrial customers are in some instances directly connected customers and
in others are customers through a supply network. Some of them, such as
Queensland Rail, are directly connected in some parts of the State but connected to
a supply network in others. These large industrial customers do not pay the notified
price but instead negotiate their own contracts. Regardless of whether they are
directly connected customers, they can buy from a retailer or buy from NEMMCO
at the spot price. This has been the case at least prior to the enactment of these
indexation provisions in 2006.
[26] About 27 to 30 per cent of customers within Queensland receive electricity as non-
market customers. For the most part, these are residential customers. None of them
is a directly connected customer. But because large industrial users are sometimes
directly connected and sometimes not, a consideration of the retailer’s costs of
supplying all of those who are not directly connected would not be confined to the
customers who will be affected by the outcome of the indexation: those who will
pay the notified prices. Logically the Act might have required an assessment of the
cost of supplying the load of residential customers, or that part of the State’s load
which was likely to go to customers who would pay the notified prices. In theory at
least, this would have made for a closer correlation between a retailer’s costs and its
prices as fixed under this regime.
[27] Alternatively, the Act might have provided that the prices were to be varied
according to movements in the costs of supplying the entire Queensland load. That
might have been thought appropriate, especially because many directly connected
customers are supplied by retailers. Indeed that would have been the effect of the
Act if the relevant Bill had been enacted in its original terms. By cl 91C of the
Bill14 , “NEM load” was defined to include the whole of the load served by the
national grid in Queensland. The definition was in these terms:
“NEM load, of the State, means the total kWh of the loads supplied
at each Queensland transmission network connection point as
defined under the National Electricity Rules.”
As noted already, under those Rules, such a connection point could be one
conveying electricity to a supply network or to a directly connected customer. The
Explanatory Note for the Bill included the following:
“Insertion of new ch 4, pt 2, div 3
Clause 25 inserts a new ch 4, Pt 2, Div 3 (Requirements for deciding
notified prices for a tariff year) into the Electricity Act 1994. This
implements the Government policy of having tariffs linked to
changes to an electricity cost index.
14 Electricity and Other Legislation Amendment Bill 2006 (Qld).
-- 10 of 35 --
11
… The new section 91G (Total benchmark retail cost) makes it clear
that, for section 91F, the total benchmark retail cost, expressed in
c/kWh, for the relevant tariff year, is the estimated total cost of
supplying customers in the State during that year, as worked out by
the pricing entity …” [emphasis added]
In the Second Reading Speech, the Minister said:
“The uniform tariff will be varied in accordance with an ‘electricity
cost index’. That is, each year, regulated tariffs will be adjusted
based on changes in electricity supply costs.
This change will ensure that changes in uniform tariffs reflect cost
rises and falls in the electricity sector and allow the benefits of any
productivity improvements in the sector to be shared with electricity
customers.”
Again this was consistent with the original terms of the Bill, which provided for
variation of the notified tariffs according to changes in costs across the entire
Queensland electricity load, rather than only according to changes to that part of it
which is serviced through a supply network.
[28] However, the Bill was amended to insert a different definition of “the NEM load”,
which was in the terms now found in s 91F(2) of the Act. The important change
was to add after the words “each transmission connection point” the words “to a
supply network”. According to the second Explanatory Note, this was one of
several amendments intended to:
“provide for some fine tuning of the formula which should provide
further clarity for the [Queensland Competition Authority] when it
undertakes the calculation…
The purpose of this new section [91F] is to provide a clearer
definition of ‘NEM load’ which is one of the components in the
formula to work out the electricity cost index.”
That seems to have overlooked the effect of the amendment rather than providing an
explanation for it. Nor was the effect of this amendment identified in the Second
Reading Debate, when the Minister said:
“The Bill provides for the Queensland Competition Authority to
calculate an electricity cost index which reflects the changes of the
cost of electricity supply. The index will be used to adjust regulated
tariffs on an annual basis. This will allow changes in the government
regulated tariffs to reflect the cost rises and falls in the electricity
sector, rather than relying upon the CPI…
In relation to the expected costs or dollar value of the application of
the new electricity cost index, I think it would be fair to say that one
needs to be very cautious about indicating any particular dollar
value. As I said in my second reading speech, … the index will
reflect the rise and fall in costs unique and particular to the electricity
-- 11 of 35 --
12
industry rather than the basket of goods and services that are
captured in the formulation of the CPI.” [emphasis added]
[29] In the electricity industry across Australia, it seems that the term NEM load is
commonly understood as referring to the total demand for electricity across the
participating NEM jurisdictions, including the demand of directly connected
customers. Had the Act been passed according to the original Bill, the present
debate about directly connected customers would not have arisen. Nevertheless, it
is the Act in its present terms which must be applied, and as the submissions for the
Authority and the Minister appear to accept, the terms “NEM load” or “NEM load
of the State” take their meaning from s 91F(2), so as to exclude directly connected
customers.
The first issue: s 92(1)
[30] There are two distinct but related complaints about the Authority’s application of
s 92. The first is that in its consideration of s 92(1), the Authority did not reach a
view of the likely cost to be incurred to purchase energy to supply only those
customers who take from a supply network, but instead reached a view as to the cost
of supplying the entire Queensland load connected to the grid and then simply
apportioned that cost according to the percentage of the Queensland load which was
consumed from the supply network. By adopting one set of the calculations of its
independent consultants, the Authority did approach the s 92(1) question in that
way, and the issue is whether this involved a reviewable error.
[31] The second complaint is that in the purported application of s 92(2), the Authority
adopted its consultants’ estimate of the long run marginal cost of energy across the
whole of the Queensland load connected to the national grid, rather than making an
estimate on the hypothesis that what was to be produced was only that which would
be consumed from the supply network.
[32] The inclusion of directly connected customers makes for a difference under both
s 92(1) and s 92(2) because, overall, directly connected customers are relatively
cheaper to supply because of the quantities they consume and because of the
relatively flat load shapes of their consumption.
[33] A significant part of a retailer’s costs of purchasing electricity comes from the
volatility of spot prices in the compulsory wholesale market. In order to minimise
their exposure to the risks from that volatility, retailers and generators employ
several means of hedging, such as those described as swap contracts, cap and floor
contracts and collar contracts. By these means the risk from that volatility can be
markedly reduced, and, in theory, eliminated. But for the retailer there is a trade-off
between the extra cost from this hedging and the extent of the risk to be avoided,
and retailers are unlikely to hedge to the extent that all of their risk is eliminated.
[34] Accordingly, the consultants engaged by the Authority, CRA International Pty Ltd
(“CRA”), approached the exercise under s 92(1) by modelling which assumed not
only certain spot prices, but also a particular mix of hedging contracts resulting in a
certain increment in the retailers’ total costs of acquiring their electricity. Because
the volatility in spot prices is largely determined by the load shape, or in other
words the relative “peakiness” of demand, the formulation of relevant assumptions
about the nature, extent and cost of hedging required certain assumptions to be
made about load shapes. At least for this reason, the assessed costs under s 92(1)
-- 12 of 35 --
13
from such modelling will be affected by whether the load shape is derived by
including directly connected customers with their relatively flat levels of demand.
That was well illustrated, and indeed quantified, within CRA’s report.
[35] In that report, CRA wrote:
“3.3.4 Shape of the load being modelled
Concerns were raised that the Draft Report was based on
modelling energy purchase costs for the full Queensland
load, rather than excluding the directly connected load …
We have given much consideration to the question of
whether the load to be modelled should be the full
Queensland load or whether it should exclude the directly
connected load. While the legislation does define “all of the
NEM load” to exclude the directly connected customers in
evaluating the denominator “L” of the BRCI equation, it is
not necessarily the case that this same definition should be
used in all parts of the energy cost calculation. An at-scale
retailer that serves a cross-section of the Queensland load
would be expected to be serving some directly connected
customers as well as non-directly connected customers,
unless those directly connected customers are specifically
excluded.
The key difference between inclusion and exclusion of these
customers is that the directly connected customers
would have a much flatter usage pattern than the
non-directly-connected customers. Increased peakiness of
load year-on-year can be attributed to the non-directly
connected rather than directly connected customers.
Including the directly connected customers effectively
spreads the increased year-on-year peakiness of the load
across a wider load base, and thus affects year-on-year
changes in energy purchase costs in the calculation of the
BRCI.
One of the reasons why inclusion of directly connected
customers is perhaps preferable is because of the
significantly higher robustness of the data that is available
pertaining to the Queensland load as a whole, including a
substantial body of historic and forecast data, based on
NEMMCO’s historic records and SOO forecasts. In
contrast, the non-directly connected load data has to date
only been made available to the Authority from NEMMCO
up to 31 December 2007.
Therefore, in the calculation of the BRCI for 2008-09:
• Including the directly connected customers, we have
actual data up to date (to 30 April 2008), and robust
-- 13 of 35 --
14
load forecasting methods from 1 May 2008 to 30 June
2009 to produce the necessary load data for modelling
purposes; whereas
• Excluding the directly connected customers, we have
actual data only up to 31 December 2007, and less
robust methods of forecasting the remaining load data
– which covers a longer period – from 1 January 2008
to 30 June 2009.
In this Addendum, we present two sets of results – with and
without the directly connected customers.
…
B.1.1 Half-hourly load data used for the purposes of
constructing a hedging strategy
In all cases (including the alternative calculations set out in
section 6), half-hourly load data that is used for the purposes
of constructing a hedging strategy is based only on data and
information that was available before the beginning of the
tariff year in question. Thus the half-hourly load data used
for the purposes of constructing a hedging strategy for the
tariff year 2007-08 is based only on data and information
that was available up to 30 June 2007, while the half-hourly
load data used for the purposes of constructing a hedging
strategy for the tariff year 2008-09 is based on data and
information that was available up to the cut-off date for the
finalisation of the input data for this Addendum (this being
30 April 2008).
Including directly connected customers
Half-hourly load data including directly connected
customers represents the whole of the Queensland load.
This data is held in our STEMM model of the NEM, from
where it has been extracted for use in this estimation of the
cost of purchasing energy.
Excluding directly connected customers
We do not hold data for the Queensland load excluding
directly connected customers, and only have that data that
has been provided by NEMMCO to the Authority for
this purpose, which is all the Queensland half-hourly
load data excluding directly connected customers, from
1 January 2005 to 1 December 2007.
Because the half-hourly load data for the tariff year 2007-08
is based only on data and information that was available up
-- 14 of 35 --
15
to 30 June 2007, we have estimated the half-hourly load data
for 2007-08 based only on using observed changes in the
peak and in the total energy for this group of customers
between the year ending 30 June 2006 and the year ending
30 June 2007, and applying those changes going forward to
create new values for the peak and for the total energy for
this group of customers for the tariff year 2007-08.
The half-hourly load data (excluding directly connected
customers) for the tariff year 2006-07 is then used as a
load shape to which these peak and energy projections for
2007-08 are fitted – a “least squares” method is applied
which achieves the forecast peak and energy for 2007-08,
while mapping approximately to the observed load shape
from 2006-07.
For the tariff year 2008-09, we were unable to use the same
method based on using observed changes in peak and energy
for this group of customers between the year ending 30 June
2007 and the year ending 30 June 2008, because we did not
have the full data for this group of customers for the full
year ending 30 June 2008 – rather we only had the first six
months worth of data for this year – i.e. up to 31 December
2007. Therefore we compared the change in energy
between the six months ending 31 December 2006 and the
six months ending 31 December 2007, and used that to
create a total energy forecast for this group of customers for
the full tariff year ending 30 June 2009, as a change from
the previous full tariff year (in this case the previous tariff
year comprising actual data from July to December 2007,
and estimated data from January to June 2008). We
estimated the peak energy use of this group of customers in
2008-09 based on the growth estimated in the peak energy
in the full NEM load in Queensland (including directly
connected customers) from 2007-08 to 2008-09, and
assuming that peak growth could be attributed fully to the
non-directly connected customers. Based on these energy
total and peak values we then created half-hourly load data
values for this group of customers for 2008-09, again on the
“least squares” method as discussed above.
B.1.2 Half-hourly load data used for the purposes of
settlement
In the calculations presented in section 3.3, the half-hourly
load data used for the purposes of settlement is the same as
the half-hourly load data used for the purposes of
constructing a hedging strategy, as discussed immediately
above.
-- 15 of 35 --
16
However, in the calculations set out in section 6, alternative
results are presented for 2007-08, based on settlement using
data up to a later date, as discussed there.
…
B.2.2 Calculating swap and cap contracts to be modelled
Based on the above half-hourly load data, we modelled
swap and cap contract purchases as follows for each quarter
of each tariff year, and for each scenario of including or
excluding directly connected customers:
• Flat swaps are purchased up to the 80th percentile of
off-peak load;
• Peak swaps are purchased up to the 90 th percentile of
peak load; and
• $300 caps are bought beyond the cover of swaps to
cover up to 105% of the maximum peak load.”
[36] CRA set out a summary of its calculations on the alternative bases of including and
excluding directly connected customers, which demonstrate that there is a
significantly greater cost, and a greater increase in cost, if directly connected
customers are excluded.
[37] In an earlier draft, CRA had calculated only on the basis of including directly
connected customers. Its alternative calculations apparently resulted from
submissions it subsequently received from the present applicants and others. A few
days prior to CRA’s presenting its final report,15 a CRA employee sent an email to
the Authority, referring to the alternative sets of calculations:
“We are asked to take a position re with or without directly
connected [customers] in energy purchase costs. The same could
apply to the LRMC two sets of calcs. It would certainly make it
easier for me to present one set of data. On energy purchase costs, I
would tend to excluding directly connected [customers], on the basis
that that seems to be what the Act implies. Should I go ahead and
make that recommendation?
…
[W]e have reconsidered based on submissions, and if we need to
come down on one only, I reckon on excluding direct[ly] connected
[customers] for energy purchase costs. But as we say in the report at
the moment we have not ruled out either.”
[38] The Authority disagreed with that recommendation. In its decision, the Authority
noted that CRA had made these two sets of calculations and referred to what CRA
had written in its report that the inclusion of directly connected customers was
15 Dated 26 May 2008.
-- 16 of 35 --
17
preferable because of the “significantly more robust data available for the
Queensland load as a whole”. The Authority wrote:16
“Relevant load
Some questions were raised in submissions regarding the load and
load shape used in estimating energy costs. For example, AGL […]
questioned the measure of load that had been used in calculating the
LRMC and purchase cost of energy and suggested there was no basis
for using total Queensland system load and that there should be a
nexus between the method of calculating the LRMC and purchase
cost of energy and the load supplied under regulated tariffs.
Australian Power and Gas […] also noted that using a whole-of-state
load profile would result in a flatter load than that associated with
small customers only.
Chapter 5 of this Decision considers the relevant load to be used as
the denominator in calculating the change in the BRCI. Section 91E
of the Electricity Act requires that the BRCI be determined by
dividing the total benchmark retail cost by the Queensland NEM load
in order to determine the unit cost of supplying electricity, expressed
in c/kWh.
For that purpose, the Queensland NEM load is to be calculated from
the loads supplied at each transmission connection point to the
distribution networks of Ergon Energy and Energex. Isolated
distribution networks and customers directly connected to the
transmission network are therefore excluded from the Queensland
load.
In calculating the LRMC of energy, Section 92(3) of the Electricity
Act requires the Authority to “take into account the most efficient
combination of generating plant to supply all of the NEM load of the
State for the relevant tariff year”.
Section 92(1) of the Electricity Act requires the Authority to
calculate the cost of purchasing energy based on the “likely total of
the costs to be incurred during the relevant tariff year to purchase
energy to supply all of the NEM load of the State”.
The requirements in relation to the relevant load to be used in
calculating LRMC and purchase cost are two fold. In the case of the
LRMC, the Authority is required to consider the combination of
generating plant to meet the Queensland NEM load and, in the case
of purchase costs, the Authority is required to consider the likely
costs to meet the Queensland NEM load.
In considering the LRMC, CRA has calculated the LRMC of energy
to meet the entire Queensland load forecast by NEMMCO in its
Statement of Opportunities report. This load includes the NEM load
16 Pages 20 and 21 of its decision of May 2008.
-- 17 of 35 --
18
of the State, as defined above, plus loads directly connected to the
transmission network. CRA took this approach because the
generation system that the LRMC estimate is seeking to capture
would be built to service the entire Queensland load, not just loads
supplied through the distribution networks.
Similarly, in considering the purchase cost of energy, CRA
suggested that the requirements of the legislation did not mean that
energy costs should be estimated to meet only the defined NEM load.
The likely cost of meeting the NEM load of the State will be
determined in the market to supply electricity generally in the State.
There are not two separate markets operating to supply the two load
segments identified in the legislation nor are there energy prices
determined independently for either segment. Like generation
capacity, the reality is that energy is supplied to meet all uses
concurrently and not in isolation.
As a result, CRA has calculated two sets of energy purchase costs –
one to meet the NEM load of the State in isolation and another to
meet the NEM load of the State plus loads directly connected to the
transmission network. CRA noted that the latter approach is perhaps
preferable because of the significantly more robust data available for
the Queensland load as a whole.
The Authority considers that, while the defined NEM load of the
State will be a subset of the total load of the State, the prices and
costs for meeting that subset will be determined in the wider context
and not in isolation. To disregard this reality would be to ignore the
economies of scale actually present in the market and would be
counter to the objective of this whole exercise, which is to consider
changes in the actual costs of efficiently supplying energy to
customers. The Authority considers that this approach is consistent
with the requirements of the legislation. The Authority has
calculated the LRMC and purchase costs associated with meeting the
NEM load and has allocated the total costs across the NEM load (as
discussed in Chapter 5). However, the costs and prices associated
with meeting the NEM load are those determined in the context of
the actual market supplying the total load of the State rather than
those that might prevail in a non-existent smaller market.”
[39] That extract sets out the critical reasoning of the Authority on the issue under
s 92(1), as well on the related question under s 92(2). As to s 92(1), the Authority
decided that the calculations which included directly connected customers should be
adopted essentially for two reasons. One was that the data which was used in these
calculations was more “robust.” It is unnecessary to discuss the respects in which
CRA had explained that this was so. There can be no complaint, at least within the
present proceedings, about the Authority’s conclusion that the data was more
robust. But that consideration did not allow the Authority to depart from the
requirements of s 92(1), if that was the result of including directly connected
customers. And the Authority did not say that it was impossible to reach a view of
-- 18 of 35 --
19
the likely cost to purchase energy to supply all but directly connected customers;
indeed CRA had demonstrated by its alternative calculations that it was possible.
[40] The Authority’s point about robustness of data is weakened by evidence which was
given by a witness whom it called, Mr Breslin. He is the principal of an economic
consulting firm and has considerable experience in the energy sector. In particular
from 1990 to 1995 he was the Director General for the Queensland Department of
Minerals and Energy, and in that capacity was closely involved in the establishment
of the national electricity market. In his second report, he said that the concerns
raised by CRA in relation to the robustness of the data were legitimate but that “an
experienced analyst could develop and articulate a methodology for projecting the
NEM load in a way that was transparent and reproducible”, and that concerns about
the robustness of the data were not so “great or insurmountable as to justify using
data for the aggregate State load to calculate the energy purchase costs”.
[41] The other reason provided by the Authority was that:
“the likely cost of meeting the NEM load of the State will be
determined in the market to supply electricity generally in the State
[and that t]here are not two separate markets operating to supply the
two load segments identified in the legislation nor are there energy
prices determined independently for either segment.”
The Authority was correct in observing that there are not two separate markets
operating to supply, respectively, the directly connected customers and other
customers. In particular, there are not separate wholesale markets and separate
regimes for spot pricing according to whether the end user will be a directly
connected customer.
[42] However, what had to be assessed under s 92(1) was the likely total of the costs to
be incurred to purchase energy. These costs include the significant costs of hedging
contracts. As discussed, those costs varied significantly according to whether
directly connected customers were included in their assessment. Therefore the fact
that there were not separate markets operating to supply the “two load segments
identified in the legislation” with “energy prices determined independently for
either segment” did not mean that a retailer’s costs overall were the same in one
segment as in the other. As CRA’s alternative calculations demonstrated, they
would significantly differ.
[43] The Authority thereby blurred the distinction between spot prices and the costs
involved in the purchase of electricity. Spot prices will be higher in times of peak
demand, and this is one reason why the cost of supplying customers who consume
at peak times will be higher than the cost of supplying those with a flat demand
profile. Further, there is the cost of hedging, by purchasing the so-called “contract
cover” to meet a forecast load. The higher the “peakiness” of that forecast load,
then the higher will be the cost of the hedging.
[44] In each of its alternative calculations, CRA used the aggregate State load shape to
arrive at spot prices. I accept that this was appropriate for reasons explained by
Mr Breslin. In his first report he wrote:
“31. For the simulation modelling to derive spot prices, the only
appropriate load shape to be used is, in my opinion, the
aggregate load shape for the State (including directly connected
-- 19 of 35 --
20
customers). Direct customers are an important part of the
market. The profile of their load is flat and dominated by the
smelter at Gladstone. The effect of a large flat load is to cause
more base load plant to be running and supplying the market.
This additional load has two effects on the market:
• Firstly, it causes more low cost base load generating plant
to be operating which lowers the average pool price.
• Secondly, it results in more low cost reserve being available
to the market and generally reduces costs for all wholesale
consumers.
32. Deriving spot prices on the basis of a market that excludes the
effects of directly connected customers would provide, in my
opinion, an incorrect estimate. The load from directly
connected customers changes the wholesale price outcome and
should be included in the calculation.”
AGL tendered a report of Mr Price which expressly agreed with that evidence.
[45] But the costs of hedging are another matter, as Mr Breslin explained in his first
report:
“34. For the financial modelling which uses the spot prices and
contract cover [ie hedging] to estimate the cost of
purchasing energy, it is, in my opinion, appropriate to use
the NEM load (excluding directly connected customers). It
is my understanding that, in respect of this modelling, CRA
undertook alternative calculations; one using data for the
NEM load (excluding directly connected customers) and the
other using data for the aggregate State load (including
directly connected customers).
35. For this part of the estimation of energy purchase costs, my
preference would have been to adopt the calculation based
on the data for the NEM load (excluding directly connected
customers).” [emphasis added]
[46] The Authority argues that its assessment was valid, because it was required to reach
a view of the likely cost which would be in fact incurred, rather than to consider “a
hypothetical market where only the NEM load is being supplied”. This submission
somewhat misstates the position. The approach under s 92(1) for which the
applicants contend, which is exemplified by CRA’s alternative calculation, involves
reaching a view as to what will be the actual costs to retailers in a real market in
which they will participate. In that market, some customers are more expensive to
supply because of their load shapes. What has to be assessed is how much it is
likely to cost to acquire such of the load which is to be actually supplied to a class
of consumer, constituted by those who are not directly connected. That requires
some hypotheses to be made. In particular, it requires assumptions about the size
and shape of the relevant load, and of the extent to which retailers would seek to
manage the risk of price volatility in those circumstances and the mix of measures
by which they would do so. But the modelling based on the entire State load
-- 20 of 35 --
21
requires assumptions of the same kind. In that way, the exercise under either
alternative is hypothetical.
[47] Although in practice, a retailer’s costs may not be distinctly incurred for a specific
transaction or transactions of retail supply, nevertheless costs can be sensibly
apportioned to transactions, or to groups of transactions such as those comprising
the NEM load. As the witness Mr Allan17 explained, electricity retailers often do
just that, in assessing the likely costs of supplying a certain customer, or group of
customers, based on the interaction of particular load shapes and market prices, in
order to quote prices to such customers. The alternative calculations by CRA,
which excluded directly connected customers, are such an assessment.
[48] Overall the language of the decision gives the impression that the Authority adopted
the alternative which it did, not only because of the perceived robustness of the data
under that alternative, but also because of what it perceived to be a justification in
policy for indexing notified prices according to the retailers’ overall costs of supply,
rather than their costs of supplying the NEM load of the State. As I have said, the
first of those reasons did not justify a departure from the statute. The second of
them could be argued as a matter of policy, but it does not accord with the
requirements of s 92(1). It would accord with a statute enacted in terms of the
original Bill, but not with this Act which confines the NEM load of the State to
customers serviced by a supply network.
[49] It was argued that the Authority’s decision in this respect did not involve an error of
law, or a failure to take into account some necessary consideration, but that the
applicants were complaining about the merits of the Authority’s view under s 92(1).
That submission cannot be accepted. The Authority has asked the wrong question
because it has formed a “view”, purportedly under s 92(1), as to the cost per
megawatt hour to purchase for the entire Queensland load, rather than for the
relevant part of it. That is not disproved by the Authority’s describing its
assessment within the decision as one in terms of the subsection. The Authority
was aware that the two were not the same, as CRA had demonstrated by its
alternative calculations, which proved what was likely to be the actual position in
the 2009 year: that the unit cost to retailers to acquire energy to service customers
taking from the supply networks will be different from the unit cost to acquire
energy for the entire Queensland load.
[50] Counsel for the Minister made an argument to the effect that the cost savings from
the economies of scale referred to in the passage from the Authority’s decision set
out above at [38] were “negative costs”, and that they were rightly brought into
account as “other relevant costs” under s 91G(2)(d). There are two reasons for not
accepting that submission. The first is that, in fact, this was not the Authority’s
reasoning. Secondly, this notion of “negative costs” is not within s 91G(2)(d) on
any reasonable interpretation of what might be “other relevant costs”.
[51] Accordingly, the applicants’ case on the first question is established.
The second issue: s 92(2)
[52] The estimate required by s 92(2) is not a distinct component to be added with others
to reach the total benchmark retail cost. Rather the estimate is to be the basis for the
17 A consultant who advises retailers and generators on load forecasting and retail pricing.
-- 21 of 35 --
22
pricing entity’s view of the cost of acquiring energy under s 92(1). As the
applicants argue, and the respondents appear to accept, the requirement that the s
92(1) view “must be based on” the s 92(2) estimate means that it must be reached
by reference to that matter. The way in which the s 92(2) estimate was used by
CRA in its modelling to arrive at the s 92(1) figure is not challenged. The
complaint is in the way in which the s 92(2) estimate was made.
[53] The cost referred to in s 92(1) is a cost to purchase energy. The cost in s 92(2) is a
cost to produce energy. The long run marginal cost (of energy), it is agreed, should
be understood for the Act as economists use the term. So as Mr Price explained, a
marginal cost measures the change in total cost as a result of an incremental change
in output and the long run marginal cost is the amount of that change in the long
run, which is that period of time during which the inputs of all factors of production
are variable. Thus the long run marginal cost of energy (“the LRMC”) is the change
in the total cost of meeting a specified load as a result of an incremental change in
that load, given that the stock of generation plant and all other inputs are variable.
This accords with CRA’s understanding, reflected in their draft report, where they
wrote that:
“the LRMC is commonly defined as the additional cost of servicing
additional demand in the long run. The long run represents the
useful service life of new capacity that is required to meet expected
incremental demand.”
[54] But what is the relevance of the cost of producing electricity to the cost of
purchasing it? The answer would appear to be that the former can provide an
indication of the wholesale price of electricity, because in the long run and on the
assumption of a perfectly competitive market, generators would be expected to offer
to produce and supply electricity at a price equal to their marginal cost of
production.
[55] Mr Breslin said that existing and potential investors are interested in the LRMC as a
long-term indicator of the upper level or market cap on wholesale electricity prices.
He said that the
“objective of estimating the LRMC is to gain an assessment of the
underlying trend of generation costs… It provides an indication of
how the costs of electricity generation are forecast to change over
time. It is based on costs not prices. In the consideration of the costs
of energy, the LRMC and energy purchase costs represent different
facets of those costs. Taken together, they give a more complete
picture of the costs of energy (that is, current and trending) than if
they were considered in isolation.”
[56] Mr Price wrote in his second report that:
“The LRMC of energy can be used for a number of purposes. I
would agree that, in order to use the LRMC of energy as an
indication of spot prices in the long run, the aggregate State load
(including directly connected customers) should be used. Any other
load shape would not provide a meaningful forecast of spot prices in
the long run, simply because spot prices for each region are
determined with reference to the aggregate State load and all of the
-- 22 of 35 --
23
generation available to meet that load. However, the LRMC of
energy can be used for other purposes.
The LRMC of energy is essentially the resource costs of meeting a
particular load. The appropriate load to use in modelling LRMC
depends on the question you are trying to answer. Certainly, one
useful question might be: what is the resource cost of meeting the
aggregate State load of Queensland (including directly connected
customers)? To answer this question, the LRMC should be
estimated by reference to the aggregate State load of Queensland
(including directly connected customers). However, an equally valid
question is: what is the resource cost of meeting the load for a
particular customer or group of customers? To answer this question,
the LRMC should be estimated by reference to the load shape of the
particular customer or group of customers.”
Yet in cross-examination, Mr Price disagreed with the suggestion that the long run
marginal cost gave an indication of the upper level of wholesale prices. He
described it as:
“a measure of an ideal world where you’ve got the opportunity to
completely rebuild the generation system in the most optimal manner
and it doesn’t have a lot of regard to real world constraints, including
political constraints … There’s always the level of market power in
any market and it certainly exists in the national electricity market.”
[57] For the purposes of reaching a view of the likely cost to be incurred in purchasing
energy, Mr Price said that the LRMC should be estimated by reference to the
particular load shape of the NEM load for Queensland, i.e. upon the assumption that
the only load to be supplied is that which is conveyed through the supply network.
In his view:
“to calculate the cost of purchasing energy with reference to the
NEM load for Queensland but the LRMC of energy with reference to
the aggregate State load provides estimates that are inconsistent with
one another.”
[58] On the other hand, Mr Breslin’s opinion is that the load shape which should be used
is the aggregate load shape for Queensland and indeed that this is the only
“sensible” way of estimating the LRMC for the purposes of s 92(1). In his view:
“the LRMC is the cost of new plant to meet the next increment in
demand. This is determined by looking at the market as it exists. If
the LRMC is estimated by reference to a hypothetical market
(excluding the directly connected customers) the estimate will not
reflect the cost of a new entrant coming into the market as it exists in
Queensland. In my opinion, an estimation of the LRMC that was
referable to the NEM load (excluding directly connected customers)
and not to the market as it exists, would be a meaningless exercise.
… The NEM was specifically designed to include all loads and all
generators in one pool so that the market as a whole would have
access to the most competitive prices and the lowest cost reserve.
Reserve is an important concept in electricity markets as electricity
demand and supply must be matched at each instant and, if supply is
-- 23 of 35 --
24
lost the reserve generation must be brought up to speed quickly.
Some of the lowest cost reserve comes from plant that is already
operating but at less than full capacity. A number of partially
operating plants can move quickly to increase their output and to
cover the cost of a unit of supply. … [T]he most efficient
combination of generating equipment to supply all of the NEM load
of the State would supply that load in the context of the existing
NEM, including the reserve capacity that comes from generating
plant which services directly connected customers.”
[59] Mr Allan said that the LRMC should be estimated by excluding directly connected
customers, but apparently because of his interpretation of s 92 and certain
regulations which are discussed below.
[60] The present question, of course, is one of statutory interpretation. The fact that a
witness with considerable experience in the electricity industry reads the statute in a
particular way does not resolve that question. Nor is that question to be answered
by preferring the evidence on this point of one of Mr Price and Mr Breslin over the
other. Each was an impressive witness with extensive experience. The fact that
they hold these different views shows that with the benefit of an understanding of
the industry which the evidence here would provide, neither interpretation is plainly
correct.
[61] Returning then to s 92(2), the relevant estimate is to be that of the “long run
marginal cost of energy in the part of the State connected to the national grid”. The
first and most obvious point is that s 92(2) does not employ the expression “the
NEM load of the State”. Next, on at least one view (that explained by Mr Breslin),
there would be a logical basis for requiring an estimate of the LRMC by reference to
the aggregate State load, rather than upon the hypothesis, as the applicants argue,
that the generators would be acting in response only to a hypothetical market in
which the only consumers would be those taking from the supply network.
[62] Accordingly, the applicants must go beyond s 92(2) to identify the prescription that
the LRMC is to be estimated upon that hypothesis.
[63] The applicants point to s 92(3), which provides that the estimate of the LRMC
“must take into account the most efficient combination of generating plant to supply
all of the NEM load of the State for the relevant tariff year”. They would have this
provision read as if the relevant words were “to supply all of but only the NEM load
of the State…” In my view this is not the effect of s 92(3). In particular, the
reference to the “NEM load of the State” in s 92(3) is not so clear as to displace the
effect of the use of a different term (“the part of the State connected to the national
grid”) within s 92(2). That is not the apparent purpose of s 92(3). Rather, the
purpose of s 92(3) is to require the estimate of the LRMC to assume the most
efficient combination of generating plant. As Mr Breslin explained, the most
efficient combination to supply the NEM load of the State is in fact the “lowest cost
combination of generating plant to supply not only that load in isolation but all of
that load as part of the National Electricity Market”.
[64] Section 92(6) provides that in estimating the LRMC, the pricing entity must comply
with any methodology prescribed under a regulation. But any such regulation could
not be inconsistent with the Act, and as the submissions for the applicants appear to
-- 24 of 35 --
25
accept, any such regulation in this context could not be used to interpret s 92. In
Webster v McIntosh,18 Brennan J, with whom Deane and Kelly JJ agreed, said that:
“the intention of Parliament in enacting an Act is not to be
ascertained by reference to the terms in which a delegated power to
legislate has been exercised.”
Similarly, in Hunter Resources Ltd v Melville,19 Mason CJ and Gaudron J said:
“it is not permissible to interpret a statute by reference to the
regulations [purportedly made under the Act].”
[65] However, I will refer here to the regulations which are relied upon by the applicants
for this argument. They are relevant to the third question, considered below, which
is whether the Authority was obliged or able to recalculate the BRCI for the 2008
year. Sections 104 to 107 of the Electricity Regulation 2006 (Qld) (“the
Regulation”) provide:
“104 Prescribed methodology for estimating long run
marginal cost of energy – Act, s 92(6)
For section 92(6) of the Act, the prescribed methodology for
estimating the long run marginal cost of energy for the
relevant tariff year is a theoretical framework that complies
with this division.
105 Required principles for framework
The theoretical framework must comply with the following
principles –
(a) it is generally recognised and understood in
economic theory;
Example –
working out the new entrant price of various electricity
generation technologies with the actual electricity generating
plant mix optimised to efficiently supply the NEM load of
the State for the relevant tariff year
(b) the application of the theoretical framework should
result in a cost per unit of electricity, expressed in
$/MWh, that constitutes the cost of energy;
(c) the long run marginal cost of energy should be
calculated to meet the demand profile (called the
NEM load shape) formed over each half hour
electricity trading period of the State for the previous
calendar year;
18 (1980) 32 ALR 603, 606.
19 (1987-88) 164 CLR 234, 244.
-- 25 of 35 --
26
(d) there must not be double-counting of the cost of the
schemes mentioned in section 92(2) of the Act.
Example of paragraph (d) –
In working out the optimal generation plant mix to supply
the NEM load of the State for the relevant tariff year, the
framework could be unconstrained with the mix being
decided without regard to the schemes, but the resulting
energy price uplifted to take account of them. If the mix
contains 10% gas generation, but 13% is required under the
Queensland gas scheme, the price should only be uplifted to
account for the 3% shortfall to comply with that scheme.
106. Matter the framework must take into account
The theoretical framework must take into account ancillary
services needed to meet the NEM load of the State for the
relevant tariff year.
107 Consistency of framework with previous tariff years
(1) The theoretical framework must be the same, or
substantially the same, from tariff year to tariff year
unless –
(a) the pricing entity considers that there is a
clear reason to change it; and
(b) the pricing entity has, under section 99,
published draft decision material about the
reason for the change.
(2) If the pricing entity changes the theoretical
framework, the pricing entity must work out what
the benchmark retail cost index for the previous
tariff year would have been based on the changed
framework.”
[66] The applicants seek to make much of the fact that these regulations refer several
times to the NEM load or the NEM load of the State.
[67] Where they appear in the examples within s 105 of the Regulation, what I have said
about s 92(3) of the Act could equally apply. The same would go for the terms used
in s 106 of the Regulation.
[68] Section 105(c) of the Regulation appears to suggest that the relevant demand profile
is that for customers serviced through the supply network because of its reference to
“the NEM load shape”. This particular expression, “NEM load shape”, appears
only within s 105 of the Regulation, apparently as an intended means of referring in
other regulations to “the demand profile”. The term does not appear elsewhere in
the Regulation. It was submitted for the Authority that if it were relevant to the
interpretation of the Act, s 105(c) of the Regulation could not assist because it is not
in terms which limit the estimate of the LRMC to an assumption that the demand
-- 26 of 35 --
27
profile must be that of customers taking through the supply network. In other words
the provision does not affect what would otherwise be the relevant demand profile,
which according to s 92(2) would be that for all of the State which is connected to
the national grid. In my view that submission would have some force if this
regulation were relevant to the interpretation of the Act. But instead, the
requirement within this regulation must be understood in the context of the Act, so
that “the demand profile” should be understood as referring to the aggregate State
load, consistently with s 92(2) of the Act.
[69] The applicants argue that the whole indexation regime is concerned with measuring
the costs, and increases in the costs from year to year, of supplying the NEM load of
the State as defined, so that it would be illogical for the Act to require, as part of
that exercise, an estimate of the LRMC of supplying some wider market. However,
effect should be given to the words which are used if they have a logical explanation
which is consistent with the objects of the Act. And apart from the deliberate use of
the different words within s 92(2), there is the fact that the pricing entity’s view
under s 92(2) must be based on its most recent estimate of the LRMC. Because the
s 92(1) figure must be based on the LRMC, it need not be a precise function of the
LRMC. Moreover, because the LRMC could be relevant as an indication of spot
prices (as Mr Price argued in his second report), and because, as he wrote, “spot
prices for each region are determined with reference to the aggregate State load and
all of the generation available to meet that load”, there is no necessary lack of logic
in using the LRMC of the whole of the State connected to the national grid in
assessing costs under s 92(1) where spot prices are an important ingredient. Put
another way, the estimate of the LRMC as undertaken by CRA could indicate long
run movements in spot prices and, as discussed already,20 it is the regional spot
price in the market which is relevant to s 92(1), rather than some price that might
prevail in the artificial context of a market where there were no directly connected
customers.
[70] Accordingly, the estimate required by s 92(2) is the pricing entity’s most recent
estimate of the long run marginal cost of energy for the aggregate State load which
is connected to the national grid. Section 92 does not require the estimate to be
reached upon the hypothesis that it would be only the NEM load of the State which
would have to be supplied. This ground for challenging the estimate of CRA which
was adopted by the Authority therefore fails.
The third issue: recalculating the index
[71] The indexation in question was the second occasion on which the Authority
undertook this task. The first was for the 2008 year. On that occasion, the
Authority had to work out the BRCI for the 2008 year.
[72] But this time around, what was the Authority to do about the BRCI for the
2008 year? Was it simply to adopt the figure which it had worked out in the
previous round? Or was it to recalculate the 2008 BRCI?
[73] It is convenient again to set out the formula which is contained with s 91D:
Ty = Ty-1 × By ⁄ By-1
20 Above at [44].
-- 27 of 35 --
28
where –
Ty is the tariff component for the relevant tariff year.
Ty-1 is the relevant tariff component for the preceding tariff
year.
B is the benchmark retail cost index for the relevant tariff
year, as worked out under subdivision 3.
By-1 is the benchmark retail cost index for the preceding
tariff year.
At least absent s 91D(2), but read with subdivision 3, that formula might be applied
by using as By-1 the figure which had been calculated as By in the previous round of
indexation. Subdivision 3 is in terms which refer to a working out of the BRCI only
“for the relevant tariff year”. And in s 91D(1), By is defined as the BRCI “as
worked out under subdivision 3”, whereas By-1 is defined not as a figure to be
worked out, but apparently as a figure already derived.
[74] However, s 91D(2) must be considered. Again, it provides as follows:
“(2) For subsection (1), the benchmark retail cost index for the
preceding tariff year is worked out under subdivision 3 as if
a reference in the subdivision to the relevant tariff year were
a reference to the preceding tariff year.”
The respondents argue that s 91D(2) makes it clear that, year by year, the pricing
entity is not only to calculate By but also to recalculate the BRCI for the preceding
year.
[75] The applicants argue that s 91D(2) has a different and limited operation. They say
that its operation is necessarily confined to what I have described as the first round
of indexation. That was for the 2008 year. Because there had been no similar
exercise for the year to June 2007, there had been no calculation of a BRCI for the
2007 year. Therefore in applying the formula for the 2008 year, some figure had to
be found for By-1. The applicants say that s 91D(2) was inserted to provide the
answer in that particular context but otherwise it is to be disregarded.
[76] The applicants’ argument, that it is to operate it only once, rather than year by year,
lacks any strong indication in the language of s 91D(2). The applicants say that
there is such an indication from use of the definite article “the preceding tariff year”
in s 91D(2). But in this, the subsection simply repeats the equivalent expression
where it is used in s 91D(1), and there clearly in the context of an indexation year
by year.
[77] The applicants argue that their interpretation is consistent with the predictive nature
of the exercise under subdivision 3 and that it would be inconsistent with that for
the pricing entity to revisit its assessment of the BRCI for the previous year on the
basis of what had actually occurred. Of course, on their own argument, there would
be that difficulty in the operation of s 91D(2), albeit only once. And the working
out (again) of the BRCI for the preceding tariff year would not be entirely
retrospective. Section 96 requires the pricing entity to ensure that notified prices
-- 28 of 35 --
29
indexed under subdivision 3 are gazetted at least one month before the relevant
tariff year starts (although a failure to do so does not invalidate or otherwise affect
the indexation). Accordingly, under this regime, the indexation is to occur when the
“relevant tariff year” is yet to begin and the “preceding tariff year” is yet to end.
[78] I have considerable evidence as to what is described as indexation practice. The
evidence is helpful but it must be kept in mind that this is a question of statutory
interpretation. Nevertheless, from that evidence there are at least two points which
are presently relevant because of what they might indicate about the effect in
practice of each interpretation upon the promotion of the objects of this indexation
scheme.
[79] The first is that some indices, such as the Consumer Price Index, are “rebased” from
time to time. The frequency of rebasing may vary from case to case and although
that creates a discontinuity, it is not considered to deprive an index of its utility
when that occurs. So as a former Australian Statistician, Mr Trewin, explained in
his evidence, the CPI is an example where from time to time there is a rebasing
from a change to the weighting of expenditure or to items within the CPI basket.
[80] Secondly, an indexation according to the respondents’ argument, by a reworking of
what is now By-1 to use actual rather than forecast data, would not necessarily lead
to a more accurate correlation between changes in retailers’ costs and changes in
notified prices. This can be explained by the example of a particular change made
by the Authority in its reworking of the 2008 BRCI. This time around, it discovered
that it had understated in its previous calculation of the 2008 BRCI a certain item of
cost by $4.9m, meaning that the ratio of the 2008 BRCI to the 2007 BRCI was
lower than it should have been and that tariffs were increased for the 2008 year by
less than they should have been. This time around, the Authority thought that it
should correct the error by including $4.9m in its reworked 2008 BRCI. But rather
than remedying the problem, this tended to distort the result. This is because the
formula, at least if applied according to the applicants’ interpretation, should have
what is described as the “self-correcting property” of many indices. As Mr Allan
explained, this exists because the numerator of one year’s index becomes the
denominator in the following year’s index. Therefore, had no change been made to
the 2008 BRCI for that $4.9m, the result this time around would have been that the
$4.9m cost had the impact on 2009 tariffs just as it would have had if it had been
included in the previous round of calculations. But by the Authority’s reworking
the 2008 BRCI to include it the result was distorted. The reason is that the ratio of
the 2009 BRCI to the reworked 2008 BRCI is still being applied to the 2008 tariffs,
which were affected by the omission of the $4.9m. So rather than correcting the
matter for the 2009 tariffs, the recalculation compounded the error. And, of course,
the reworking of the 2008 BRCI was irrelevant for the tariffs for the 2008 year,
which remained unaffected by the present round of indexation. Accordingly, the
notion that a reworking of the preceding year’s BRCI with the advantage of more
accurate information is not as attractive as may first appear.
[81] As explained by another witness, Dr Fallon, the reworking of the previous year’s
BRCI may provide the best estimate of the change in costs for a single year, but it is
another matter when considering the impact of the indexation process over two
years or more. Again, this is because the ratio of the respective BRCIs is still
applied to tariffs which had been derived from the application of different data for
the same year in the previous round of indexation.
-- 29 of 35 --
30
[82] Of course, there could be other circumstances which would lead to some
“discontinuity” in this process of indexation. An example is that which is provided
for by the regulations, which was where it is thought necessary or appropriate to
change what is described as the theoretical framework for assessing certain costs.
Nevertheless, this self-correcting feature of the index that would result from the
applicants’ interpretation makes that interpretation more consistent with the object
of the indexation regime, which is to have the notified prices vary over several years
commensurately with variations in the relevant costs.
[83] Under the respondents’ interpretation, the task of the pricing entity, year by year,
would be considerably increased. For example, there is s 91F(4), which requires the
pricing entity to consult with interested persons about the methodology it proposes
to use to form “the view” of the NEM load. In effect, having consulted in the
previous round about the methodology to predict that matter, it would be obliged to
consult again as to the methodology to reach a view which was largely an
assessment of what had occurred, rather than what is to occur. The same applies to
the consultation required by s 91G(3).
[84] Apparently recognising the practical inconvenience and questionable utility of
recalculating the previous year’s BRCI in all respects according to subdivision 3,
counsel for the Authority submitted that the pricing entity would be obliged to do so
only if its “view hasn’t changed from the previous year”. That is difficult to
reconcile with what the Authority did, in reworking the 2008 BRCI by using data
which was quite different to that used originally. Inevitably, the use of the new data
would result in the Authority reaching a different “view”.
[85] AGL argues that its interpretation is “reinforced” by the view taken by the then
Minister where, in delegating to the Authority the task for the 2008 year, it was said
that:
“In order for the Minister to carry out the functions required under
sections 90(5) and 91D of the Electricity Act 1994, the [Authority]
must calculate the index for the relevant tariff year and the preceding
tariff year – unless the index has already been provided for the
previous tariff year and there have been no changes to the
methodology used to calculate the index.” [emphasis added]
However, the view which the then Minister held as to the interpretation of s 91D is
not presently relevant, except that it indicates that the interpretation argued by the
applicants is one which could make for a practical and appropriate operation of the
scheme.
[86] The applicants’ argument has some support in the Explanatory Note to the relevant
Bill.21 Referring to what became s 91D of the Act,22 the Note was as follows:
“The new section 91E (Formula for working out each tariff in tariff
schedule for relevant tariff year) requires each tariff in the tariff
schedule to be calculated by multiplying the relevant tariff
component from the previous year by the benchmark retail cost index
for the relevant tariff year divided by the benchmark retail cost index
from the preceding tariff year. The benchmark retail cost index for
21 Electricity and Other Legislation Amendment Bill 2006.
22 Then proposed to be numbered s 91E.
-- 30 of 35 --
31
the preceding tariff year, expressed in c/kWh, is calculated by
dividing the total benchmark retail cost for the preceding tariff year
by the NEM load for the State for the preceding tariff year.”
The Note’s description of what is B y-1, as the benchmark retail cost index from the
preceding tariff year, favours the applicants’ argument. Confronted with this point,
counsel for the Authority submitted that the word “from” must be the result of a
typographic error, a submission which is not immediately persuasive. And in the
next sentence from that extract, where there is a description of how the BRCI for the
preceding tariff year is calculated, it is not said that such a calculation is to occur in
respect of the same tariff year over two successive rounds of indexation. Rather,
there is simply an explanation that the component which is By-1 will be a figure
which has been calculated in the way there described.
[87] On any view s 91D is no model of clarity and consequently, each of these
interpretations is arguable. Ultimately, neither argument should be completely
accepted. The applicants say that the pricing entity is bound to use as By-1 the figure
which it had used as By in the previous indexation. The respondents say that By-1
“is to be calculated afresh in the current indexation”.23 In my conclusion, what is
required is that the pricing entity apply a formula which has an element, By-1, which
at some time has been worked out according to subdivision 3. Under this
interpretation, the entity may recalculate the BRCI for the preceding tariff year, but
is not bound to do so. The section requires that there be a benchmark retail cost
index for the preceding tariff year. But I am not persuaded that this must be a figure
which has been worked out at the same time as the BRCI for the relevant tariff year.
Nor must it be a figure worked out in the previous round of indexation.
[88] There are several reasons why the respondents’ interpretation should not be
adopted. First, there is the considerable administrative burden which would be
imposed upon the pricing entity, each and every year, to recalculate a figure when
there may be no good reason for the exercise. But secondly and importantly, the
effect of assessing the BRCI again could be to distort the indexation process as I
have discussed and the result would be inconsistent with the statutory purpose.
[89] On the other hand, in some circumstances, there could be a good reason,
consistently with the purposes of the scheme, to revisit the figure which had been
calculated for the preceding tariff year. An example may be provided by the
circumstance which is the subject of s 107 of the Regulation, which provides that
the pricing entity is to use the same “theoretical framework” from year to year
unless it considers that there is a clear reason to change it and that if it does make
that change, it must work out “what the benchmark retail cost index for the previous
tariff year would have been based on the changed framework”. In that instance,
where there is a perceived need for a change in methodology, the objects of the
scheme might be furthered by revisiting the previous calculation. The effect of the
applicants’ argument is that the regulations could not authorise the use of a
recalculated BRCI because the Act requires the original figure to be reused as By-1.
The applicants’ interpretation should not be accepted unless it is clearly compelled
by the words of the section. That is not the case: the section does not in terms
preclude the employment of a recalculated BRCI.
23 Submissions for the Authority, [492].
-- 31 of 35 --
32
[90] Accordingly, it was open to the Authority, at least to some extent, to revisit its
calculation of the BRCI for the 2008 year. The major complaint of the applicants is
not that it did so at all, but that it did so to an extent not permitted by the relevant
regulations, to which I now turn.
[91] Relevant here are sections 104 to 107 of the Regulation set out above at [65]. They
deal with the methodology for estimating the LRMC. Also relevant are sections
108 to 111, which prescribe the methodology for forming a view as to another cost
component, which is the retail costs to be worked out under s 94 of the Act, as
follows:
“108 Prescribed methodology for forming view of likely cost
of providing customer retail services – Act, s 94(2)
For section 94(2) of the Act, the prescribed methodology for
forming the pricing entity’s view (the retail cost view) of the
likely cost of providing customer retail services is the
matters stated in this division.
…
111 Provision about changes to retail cost framework
(1) This section applies if the pricing entity proposes to
change the framework it uses to form the retail cost
view in relation to the relevant tariff year.
(2) The pricing entity must work out what the
benchmark retail cost index for the previous tariff
year would have been based on the changed
framework.”
[92] In the decision, the Authority changed the theoretical framework for assessing both
the LRMC and retail costs. There is no challenge to the use of the different
methodology. What is challenged is the use of different data this time around.
[93] In this recalculation of the 2008 BRCI, the Authority used fresh data in the course
of recalculations which were affected by its changes to the methodology. In several
other instances, the Authority recalculated by the use of new data with respect to
components which were not the subject of changes in methodology. In each
category, the applicants say that the use of different data was contrary to the
regulations. As to the former category, they contend that the pricing entity was
obliged by s 107(2) or s 111(2) to work out what the BRCI for the 2008 year
“would have been based on the changed framework”, which they say required the
Authority to adhere to the data previously used but to subject it to the new
methodology. As to the second category, they argue that there was simply no power
in the Authority to revisit the calculation of the 2008 BRCI (except in the situations
governed by s 107 and s 111). Within this second category is the adjustment of
network charges by $4.9m which I have discussed.24
[94] As to that first category, the applicants’ argument is persuasive. The effect of
s 107(2) and s 111(2) is to require the pricing entity in those circumstances to
24 At [80].
-- 32 of 35 --
33
recalculate the BRCI for the previous tariff year. But these regulations are not in
terms which simply require some recalculation of the BRCI. More particularly,
they require the calculation of what the BRCI would have been based on the new
methodology. This confines the price entity in its recalculation, in that it is not
permitted to use the opportunity of a changed methodology to use data not
employed last time around. If the “old” data could be reused under the new
methodology, in my view that is what these provisions required. That is indicated
not only by the language but also by the desirability, in general, of not recalculating
By as it becomes By-1, because of the potential to distort the outcome as I have
discussed. But where there is a change in methodology, there could be a need for
new data in that the old data might not be all that the new methodology requires.
[95] The Authority says that these regulations are ambiguous but that the preferable
construction is that they have no effect upon the data which should be used in the
recalculation. Their only purpose, it is said, is to require a recalculation of the
previous year’s BRCI with the new methodology. Further, the Authority points to
the absence of any other regulation which restricts the use of new data in the
recalculation of the previous year’s BRCI. It argues that it would be curious if the
pricing entity were free to use new data except where there was a change in
methodology.
[96] That last point raises the validity of the Authority’s use of new data in the
recalculation where that had no connection with a change in methodology. As I
have concluded, the Act does not preclude a recalculation of the previous year’s By
for the purposes of deriving this year’s By-1. But by necessary implication, that
exercise would have to be for a purpose which is consistent with the objects of the
legislation. In particular it would have to be directed to arriving at new notified
prices, so that they involved an increase from the prices originally fixed under s 90
which was commensurate with increases in the relevant costs over that same period
of years. But within those limitations, the pricing entity has a broad discretion. I
am not persuaded that, outside the ambit of s 107 and s 111, it could never be valid
for the pricing entity to use different data in its recalculation when the old data
could have been employed. What I have said as to the desirability of a
self-correcting index means that it would not usually accord with the purpose of this
regime to use new data simply because it is “actual” data rather than what had been
forecast at the time of the original calculation. But there may be particular
situations in which some new data could be legitimately used.
[97] I return then to the respondents’ submission about s 107 and s 111. It is not the case
then that the pricing entity’s power to recalculate the previous year’s BRCI is
unconfined. Accordingly, to accept the applicants’ argument as to those provisions
would not lead to the curious result which they suggest. In my conclusion the terms
of s 107 and s 111 are clear enough, and they should be understood in the manner I
have described above at [94]. At least to this extent then, the applicants have
established that the recalculation of the 2008 BRCI was not according to the
regulations.
Conclusions
[98] The decision was not made in accordance with the Act because:
-- 33 of 35 --
34
(1) in working out the benchmark retail cost both for the relevant tariff year
and the preceding tariff year, the Authority did not form a view of the
likely total of the costs to be incurred during that year to purchase energy to
supply the NEM load of the State for that year, as required by s 92(1) of the
Act;
(2) in working out the total benchmark retail cost for the preceding year, the
Authority used data which had not been used in working out that cost when
the year to 30 June 2008 had been the relevant tariff year, and which the
Authority was not otherwise entitled to use in this decision.
[99] That second conclusion is expressed in general terms, because I am not persuaded
that all of the new data was invalidly used. Some data was invalidly used in
instances where the Authority did not act as required by s 107 and s 111 of the
Regulation.
Relief
[100] By its Originating Application, AGL sought orders under both Part 3 and Part 5 of
the Judicial Review Act 1991 (Qld). The Authority pleaded in response to the Part 3
claim that the decision was not a “decision to which this Act applies” as defined in
s 4 of that Act. Without conceding the point at the hearing AGL limited its claim to
Part 5 and to declaratory relief. That was also Origin’s position.
[101] Neither applicant seeks any order which would affect the notified prices for the year
to 30 June 2009. Nor would my conclusions that the decision was not made
according to the Act affect those prices. This is because of s 91AA which provides:
“91AA Provision for compliance with decisions about notified
prices
(1) This section applies if –
(a) the pricing entity decides or purports to
decide notified prices (the decided prices);
and
(b) the decided prices are, for whatever reason,
quashed, set aside or declared or ordered to
be of no effect in a proceeding.
(2) Despite any matter mentioned in subsection (1)(b),
for section 90A and any other provision of this Act,
the decided prices –
(a) are taken to have, since the making of the
decision or purported decision, always been
notified prices; and
(b) continue in force as if they were notified
prices until the pricing entity decides new
notified prices.”
-- 34 of 35 --
35
[102] The applicants’ concern is for the year from 1 July 2009 and subsequent years. At
the conclusion of the hearing, all parties seemed to agree that if I upheld all or some
of the applicants’ arguments, I should make declarations and stand the matter over
so that any further relief warranted by these reasons for judgment could be sought.
[103] Clearly the Authority will have to recalculate the benchmark retail cost index for the
year to 30 June 2009. The declarations made by this judgment, read with the
reasons, ought to guide the Authority in that recalculation. There will be
declarations in terms of my conclusions set out above at [98]. I will hear the parties
as to further orders and as to costs.
-- 35 of 35 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2009/090