Australia Estates Pty Ltd v Cairns City Council [2005] QCA 328
SUPREME COURT OF QUEENSLAND
CITATION: Australia Estates P/L v Cairns City Council [2005] QCA 328
PARTIES: AUSTRALIA ESTATES PTY LTD ACN 098 087 168
(applicant/appellant)
v
CAIRNS CITY COUNCIL
(respondent/respondent)
CAIRNS CITY COUNCIL
(applicant/respondent)
v
AUSTRALIA ESTATES PTY LTD ACN 098 087 168
(respondent/appellant)
FILE NO/S: Appeal No 9821 of 2004
Appeal No 9822 of 2004
SC No 9130 of 2004
SC No 503 of 2004
DIVISION: Court of Appeal
PROCEEDING: General Civil Appeal
ORIGINATING
COURT: Supreme Court at Brisbane
DELIVERED ON: 2 September 2005
DELIVERED AT: Brisbane
HEARING DATE: 18 May 2005
JUDGES: McMurdo P, Jerrard JA and Atkinson J
Separate reasons for judgment of each member of the Court,
each concurring as to the order made
ORDER: Appeal dismissed with costs
CATCHWORDS: ENVIRONMENT AND PLANNING – DEVELOPMENT
CONTROL – CONSENTS – APPROVALS AND PERMITS
– INTERPRETATION AND CONSTRUCTION –
GENERALLY – where contract for the respondent to sell
land to the appellant – where the appellant hoped to construct
commercial and residential buildings on the land – where the
appellant applied for a variation to a decision notice and
received a negotiated decision notice
CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – CONSTRUCTION AND
INTERPRETATION OF CONTRACTS – OTHER
MATTERS – where contract for the respondent to sell land to
the appellant – where the appellant hoped to construct
-- 1 of 23 --
2
commercial and residential buildings on the land – where the
contract concerned the process in the Integrated Planning Act
1997 (Qld) – whether the decision notice or the negotiated
decision notice issued by Brisbane City Council should be
characterised as “approval” within the meaning of the
contract
CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – CONSTRUCTION AND
INTERPRETATION OF CONTRACTS – OTHER
MATTERS – where contract varied by agreement – whether
the variation was void at common law for common mistake –
where performance of the contract not rendered impossible
EQUITY – GENERAL PRINCIPLES – MISTAKE –
EFFECT ON CONTRACTS – GENERAL PRINCIPLES –
where contract varied by agreement – whether the variation
was void for common mistake – where appellant unable to
show that the view it held of the facts or the legal effect of the
facts was mistaken when the agreement was made to vary the
completion date of the contract
Integrated Planning Act 1997 (Qld) s 3.5.15, s 3.5.17, s
3.5.19, s 4.1.27
Bell v Lever Bros Ltd [1932] AC 161, considered
Clasic International Pty Ltd v Legos [2002] NSWSC 1155;
(2002) 60 NSWLR 241, not followed
Cook v Cook (1986) 162 CLR 376, considered
Cooper v Phibbs (1867) LR 2 HL 149, considered
Gheko Developments Pty Ltd v Azzopardi & Anor [2005]
QCA 283; Appeal No 274 of 2005, 12 August 2005,
considered
Great Peace Shipping Ltd v Tsavliris Salvage (International)
Ltd [2003] QB 679, followed and applied
Harris v Digital Pulse Pty Ltd [2003] NSWCA 10; (2003) 56
NSWLR 298, considered
Hayes v Walker [2004] QCA 288; (2004) 134 LGERA 290,
distinguished
McRae v Commonwealth Disposals Commission (1951) 84
CLR 377, considered
Solle v Butcher [1950] 1 KB 671, not followed
Strickland v Turner [1852] 7 Exch 208, considered
Svanosio v McNamara (1956) 96 CLR 186, considered
Taylor v Johnson (1983) 151 CLR 422, considered
COUNSEL: B O’Donnell QC for the appellant
P J Lyons QC for the respondent
SOLICITORS: Bolton Cleary and Kern for the appellant
Williams Graham Carman for the respondent
-- 2 of 23 --
3
[1] McMURDO P: I agree with Atkinson J that the appeal should be dismissed with
costs. Her Honour in her reasons sets out the relevant facts, issues, portions of the
contract between the parties and sections of the Integrated Planning Act 1997 (Qld)
("the Act"). I need only repeat these as required to explain my own reasons.
[2] The parties entered into a contract for the sale of land subject to the appellant
purchaser obtaining development approval in respect of the land from the relevant
local government.1 The respondent was also the local government responsible for
approving the appellant's development application but that unusual factor does not
affect the issues in this appeal.
[3] The contract provided in special condition cl 2.9 that:
"[i]f the Approval is granted on terms that are unsatisfactory to the
Purchaser, the Purchaser may terminate this Contract by written
notice to the vendor within said period of 5 business days, failing
which the Purchaser will be deemed to have given notice that the
terms of the Approval are satisfactory."2
[4] The appellant obtained a decision notice from the local government granting the
development approval on 26 July 2004 under s 3.5.15(2) of the Act. On 2 August
2004 the appellant made representations to the Vouncil to vary conditions of the
approval contained in the decision notice under s 3.5.17 of the Act. Before a
negotiated decision notice was issued under that section, the respondent's solicitor
on 13 August 2004 faxed a letter to the appellant's solicitor stating that the local
government's decision notice of 26 July 2004 was clearly an approval for the
purposes of the special condition in the contract relating to the development
approval of the land; although the appellant had not complied with all the
requirements of that special condition the respondent proposed that the date of that
letter (13 August 2004) be taken as the date of satisfaction of the special condition
requiring development approval and that 12 October 2004 be the completion date
with time remaining of the essence. The appellant's solicitor on 18 August 2004
responded by letter confirming that the settlement date for the contract was to be
12 October 2004 and stating that the deposit (payable under the contract upon
satisfaction of special condition cl 2) had been paid.
[5] The local government issued the negotiated decision notice on 31 August 2004. On
8 October 2004 the appellant told the respondent that the negotiated decision notice,
not the decision notice, was the approval for the purposes of the special conditions
of the contract and that the completion date was 25 October 2004, not 12 October
2004 as agreed on 18 August 2004. When the appellant did not settle on 12 October
2004 the respondent elected to terminate the contract and the appellant lodged a
caveat over the land.
[6] The learned primary judge refused the appellant's application for a declaration that
the contract was not lawfully terminated by the respondent and that the date for
completion of the contract was Monday, 1 November 2004. His Honour granted the
respondent's application that the appellant's caveat be removed.
[7] The appellant contends the judge should have concluded that it only received
development approval under the contract when it received the local government's
1 Contract Special Conditions Definitions 1.1(2) provided that "Approval" means the approval of the
Application by the local government.
2 Contract cl 2.9.
-- 3 of 23 --
4
negotiated decision notice on 31 August 2004 and that in agreeing to vary the
contract on 18 August 2004 both parties were acting under a common mistake as to
the effect of the contract so that the contract as varied should be set aside and the
parties bound only by the original contract.
[8] Contracts for the sale of land are not infrequently subject to the purchaser obtaining
development approval and such contracts are sometimes interpreted by courts. See
for example, Gheko Developments Pty Ltd v Azzopardi & Anor3 and Hayes v
Walker.4 Each case will naturally turn on the provisions of the particular contract.
[9] What is of significance in the special conditions relating to the development
approval of this contract is that, under special condition cl 2.9, if the approval was
granted on terms unsatisfactory to the appellant, the appellant could terminate the
contract by written notice to the respondent within five business days, failing which
the appellant was deemed to have given notice that the terms of the approval were
satisfactory. What special condition cl 2.9 emphasises is the appellant's right to
terminate where the terms of the development approval are unsatisfactory to it, not
the effect of the Act: see Gheko Developments Pty Ltd v Azzopardi & Anor.5 The
appellant's agreement through its solicitor on 18 August 2004 that the settlement
date of the contract was to be 12 October 2004 must objectively be taken to have
been an acceptance by the appellant that the terms of the approval it then had under
the decision notice of 26 July 2004 were satisfactory to it and that it was agreeing to
this variation of the initial contract with the respondent.
[10] In any case, by contrast to the position in Hayes v Walker, the decision notice here
of 26 July 2004 not having been replaced by a negotiated decision notice remained a
valid development approval as at 18 August 2004 when the parties agreed to vary
the initial contract. The letter of 18 August 2004 to the respondent's solicitor from
the appellant's solicitor was objectively an unambiguous acceptance of the
variations suggested by the respondent; it constituted an acceptance by the
respondent that the terms of the development approval stated in the decision notice
of 26 July 2004 were not so unsatisfactory to the appellant for it to terminate the
contract. The appellant instead agreed through its solicitor to the respondent's
suggestion that the date of satisfaction of special condition cl 2 relating to
development approval be 13 August 2004.
[11] There is simply no evidence that the parties acted under any common mistake in
agreeing to vary the contract in this way. It follows that it is unnecessary to
consider the interesting question, first raised by Jerrard JA with counsel in the
course of argument during the appeal hearing, as to the effect in Australia on the
law of mistake in contract of the decision of the English Court of Appeal in Great
Peace Shipping Ltd v Tsavliris Salvage (International) Ltd.6
[12] The learned primary judge was right to refuse to make the declaration sought by the
appellants and to order that the caveat be removed.
[13] The appeal should be dismissed with costs to be assessed.
3 [2005] QCA 283; Appeal No 274 of 2005, 12 August 2005.
4 [2004] QCA 288; (2004) 134 LGERA 290.
5 [2005] QCA 283; Appeal No 274 of 2005, 12 August 2005, [1], [9], [10], [31].
6 [2003] QB 679.
-- 4 of 23 --
5
[14] JERRARD JA: In this appeal I have had the advantage of reading the reasons for
judgment of Atkinson J, and the orders proposed by Her Honour, and I respectfully
agree with those reasons and orders.
[15] The contract the parties entered into in this matter appeared to be a standard form of
contract particularly relevant when one party is selling another land upon which the
purchasing party intends, if a development application is approved, to carry out
development work. That form of contract was adapted to this matter, in which one
party was the Council, who would approve the development application; that fact
results in the agreed terms requiring the purchaser to notify the Council as vendor of
decisions the Council had made and communicated to the purchaser as applicant for
development approval.
[16] That oddity apart, the terms of the contract do not assist the appellant’s argument. I
agree with Atkinson J that there was no relevant mistake made by either party on 18
August 2004, that being the date of the letter by which the appellant’s solicitor
communicated agreement confirming the suggestion made 13 August 2004 by the
respondent’s solicitors, namely that 12 October 2004 be agreed as the completion
date. As at 18 August 2004 there had been two decision notices issued on 26 July
2004, received by the appellant on 30 July 2004, and the appellant’s solicitor had
written on 9 August 2004 accepting that the development permit received on 30
July 2004 constituted an “approval” for the purposes of clause 2 of the contract; and
agreeing to pay the balance deposit. There was no fact about which any party was
mistaken on 18 August 2004. No negotiated decision notice favourable to the
appellant had been made by that date, and of course it was possible on 18 August
that the appellant’s application to the Council for that negotiated decision could be
refused.
[17] The appellant contends that the fact a negotiated decision notice issued dated 31
August 2004 significantly changed matters, including that it once again had the
right pursuant to clause 2 to notify the Council as purchaser as to whether the
conditions of the negotiated decision notice were satisfactory to it, or alternatively,
if unsatisfactory, to terminate the contract by notice within five business days of 31
August 2004. Further, the appellant’s solicitor wrote on 8 October 2004 to the
respondent, contending that because the negotiated decision notice was issued on 26
August 2004 (it is actually dated 31 August 2004) the completion date was 60 days
from 26 August 2004, namely 25 October 2004, not the previously agreed date of
12 October 2004.
[18] There is much that can be said about that latter argument. However, even if every
other assumption in it was correct, the fact is that the parties had agreed by 18
August 2004 on the date 12 October 2004 as the completion date, at a time when
both parties knew that the purchaser had made submissions to the vendor, in which
the purchaser had sought a negotiated decision notice giving it more favourable
terms for development than those in the decision notice. The date 12 October,
agreed to, did not depend on either construing the reference to a decision notice in
clause 2 in the special conditions of the contract as meaning only the original
decision notice, or on construing it to include a negotiated decision notice later
made; the date 12 October 2004 was fixed irrespective of either potential
construction of the contract, and without reference to the result that would be
arrived at by applying either construction; it was simply a date that the respondent
suggested and to which the appellant agreed. It did not result from any view of the
-- 5 of 23 --
6
proper construction of the contract, whether mistaken or not. That much is clear
from the correspondence between the parties.
[19] The appellant nevertheless contended before the learned trial judge that there had
been a relevant mistake. This was said to arise from the fact that the appellant’s
solicitor swore that, while he was aware on 6 August 2004 and 9 August 2004, as
his correspondence with the respondent’s solicitor showed, that there were
negotiations between the appellant and the respondent in respect of some of the
conditions of the approval, he was not personally familiar with the provisions of the
Integrated Planning Act 1997 (Qld) (“the IPA”), and had not grasped that the
decision notices of 26 July 2004 might be replaced at some future time by what he
later learnt was a negotiated decision notice. Accepting that evidence, and the
learned trial judge made no finding about it, it establishes only a period of ignorance
of the relevant law, not any common or unilateral mistake of fact. Whether or not
the appellant’s solicitor grasped that a negotiated decision notice was being sought,
and that such a thing could exist, as at 18 August 2004 there was only the first
decision notice, and the possibility of any negotiated decision notice was a matter of
speculation.
[20] In any event, I also agree with Atkinson J that the proper construction of the
contract leads to the conclusion that the parties objectively intended not to include a
negotiated decision notice as a decision notice referred to in clause 2 of the special
conditions of the contract. This is because construing the contract as the appellant
wishes produces the result that the appellant purchaser could affirm the contract,
negotiate for conditions more acceptable to it, obtain those, and then rescind after it
obtained those better conditions. That would be an odd result; there was also the
point made by Mr Lyons QC for the respondent, that if the appellant was correct in
its construction, a contract would become unworkable if the appellant gave notice
that the terms were satisfactory and then made representations seeking a negotiated
decision notice, which representations had not been determined upon by the
otherwise applicable completion date. Neither party could know whether settlement
should occur on the date calculated by reference to the original decision notice, or
whether it was to be on some later date, which would only become clear if and
when a negotiated decision notice issued. (It should be appreciated that where a
Council rejects representations made to it, that rejection does not constitute a
negotiated decision notice under s 3.5.17 of the IPA; it is only when a Council
agrees with any of the representations that a negotiated decision notice is issued).
[21] The fact that the contract could readily become unworkable if the appellant’s
construction was correct adds to the probability that the parties deliberately omitted
reference to a negotiated decision notice in the contract, whereas they deliberately
provided for the possibility of there being submitters, and for an appeal by those
submitters. The latter situation could result in matters beyond the control of either
party, and accordingly by clause 2.15 the parties agreed that if one or more
submitter did appeal, then either party might terminate the contract by notice in
writing to the other. In contrast, it was within the purchaser’s power to determine
whether to seek a negotiated decision notice or not, thus improving its position,
after electing to affirm the contract on receipt of the first decision notice.
[22] Mr O’Donnell QC for the appellant contended that construing the contract to
interpret “decision notice” as meaning a decision notice excluding a negotiated
decision notice denied the appellant the opportunity of obtaining a binding contract
on more favourable terms than those in the first decision notice. He submitted that
-- 6 of 23 --
7
in reality the purchaser was entitled to simply screw up the first decision notice
received and toss it in the bin; that submission depended on the assumption that a
favourable decision notice was later received. On that assumption, his submission
was that the purchaser was entitled to ignore the time limits in clause 2 of the
special conditions, since those would only come into effect once the negotiated
decision notice was received.
[23] That argument was also based on an asserted injustice to the appellant if it was
dissatisfied with the conditions conveyed in the original decision notice, and
unwilling to commit itself to a purchase on those conditions, but confident of
obtaining better ones. Implicit in the submission was the associated contention that
the appellant had been in fact unwilling to enter into the agreement on the
conditions originally notified. But that assumption does not bear scrutiny. The
appellant’s solicitor, who says now that he was ignorant of the law then, and was
acting on the mistaken belief that the original decision notice was the relevant
decision notice for the purposes of the contract, accepted the development permit as
an “approval” for the purposes of clause 2 of the contract in that solicitor’s letter of
9 August 2004. It follows that the solicitor must have had instructions that his
clients were willing to accept the contract on those terms. If the solicitor’s opinion
then was correct, that “decision notice” in the contract meant the decision notice
which had already been received, and no other decision notice, then it was necessary
for the solicitor to affirm the contract as his correspondence of 9 August 2004 did.
That left it open to the purchaser to improve the conditions, if it could, in
subsequent negotiations, without risking loss of the contract. If the view the
appellant now has of the contract is correct, namely that a “decision notice” referred
to in the contract could include a negotiated decision notice, then where the solicitor
held instructions that the purchaser wanted to secure a binding contract even on the
originally imposed conditions, those being in fact acceptable to the purchaser, it was
an entirely appropriate commercial decision for the purchaser to have the solicitor
accept the original decision notice as a decision notice and affirm the contract.
Failing to do that would risk loss of the contract if the negotiations were
unsuccessful. When they were successful, the purchaser obtained a second
opportunity to rescind.
[24] It follows that on either view of the proper construction of the contract, whether it
be that which the solicitor originally held or that which the appellant now advances,
it was appropriate for the purchaser to take the steps that it did to confirm the
contract, and that step did not relevantly result from any mistaken view of the law.
It resulted from instructions which can confidently be inferred.
[25] Accordingly, while I agree with the analysis of the law undertaken by Atkinson J –
other than that I consider Cooper v Phibbs7 was a case of mistake (even at common
law) in which only an equitable remedy was appropriate – no relevant mistake
operated to cause the contract to be affirmed, or the date 12 October 2004 settled
upon as the completion date. I agree that the appeal should be dismissed, with
costs.
[26] ATKINSON J: By a contract dated 9 May 2003 Cairns City Council (“the
Council”) agreed to sell to Australia Estates Pty Ltd (“Australia Estates”), land in
Grafton and Lake Streets in Cairns (“the land”), some of which was to be leased
back to the Council (“the contract”). The purchase price was $3,000,000. Special
7 (1867) LR 2 HL 149
-- 7 of 23 --
8
Conditions of the contract made provision for an application for an approval from
the Council (as the local government and, therefore, assessment manager) for
development of land; and fixed the date for completion of the contract by reference
to events associated with obtaining the approval. The purchaser wished to construct
residential and commercial buildings on what was referred to as the old Council
library site.
[27] The Special Conditions of the contract which relate to the approval process refer to
the vendor and the local government. Usually the vendor and the local government
would be quite different entities but in this case because the Council was the owner
of the land, it was both the vendor and the local government and assessment
manager. Australia Estates is variously referred to herein as the applicant and the
purchaser because of its different roles as purchaser under the contract and applicant
under the approval process found in the Integrated Planning Act 1997 (Qld)
(“IPA”).
[28] The relevant terms of the Special Conditions are set out below:
“2. Development Approval
2.1 This Contract is subject to the Purchaser obtaining the Approval by
the Approval Date.
…
2.5 If:
(1) the draft Application is not provided to the Vendor in
accordance with sub-clause .3; or
(2) the application is not lodged by the Lodgement Date;
the Vendor may terminate the Contract by notice in writing to the
Purchaser.
…
2.7 The Purchaser must notify the Vendor within 2 business days of
receiving the Decision Notice and provide the Vendor with a copy
thereof.
2.8 Within 5 business days of receipt of the Decision Notice the
Purchaser must notify the Vendor in writing whether the
Application has been approved and if so whether the conditions of
the Approval are satisfactory to the Purchaser.
2.9 If the Approval is granted on terms that are unsatisfactory to the
Purchaser, the Purchaser may terminate this Contract by written
notice to the vendor within said period of 5 business days, failing
which the Purchaser will be deemed to have given notice that the
terms of the Approval are satisfactory.
…
-- 8 of 23 --
9
2.11 Following the giving of an Approval Notice the purchaser will
ascertain from Local Government whether notification is required to
be given to any Submitter in respect of the Approval, whether such
notification has been given and the date of expiry of the Submitter’s
Appeal Period and immediately give written notice thereof to the
Vendor (and in any event within 5 business days following the
giving of the Approval Notice).
2.12 If no Submitters have any rights of appeal in respect of the
Approval, subject to the Purchaser’s rights under clause 2.9, this
clause will be deemed to be satisfied in respect of the Application,
upon the giving of the Approval Notice.
2.13 If one or more Submitters have a right of appeal against the
Approval then, within 2 business days following the expiration of
the last of the Submitter’s Appeal Periods, the Purchaser will give
written notice to the Vendor as to whether any Submitter has
appealed.
…
5. Completion
5.1 The Completion Date will be 60 days after clause 2 is satisfied.
…”
[29] Clause 2.1 of the Special Conditions provided that the contract was subject to the
purchaser obtaining the approval by the approval date. The “Approval” was defined
to mean the approval of the Application by the local government and the “Approval
Date” was defined to mean 150 days after the “Lodgement Date” which in turn was
defined to mean 150 days after the “Contract Date”. The “Application” was defined
in the contract to mean the application for developmental approval to use the land.
So the contract was subject to Australia Estates receiving the approval by 4 March
2004, i.e. 300 days after the contract date of 9 May 2003. The date for the approval
was, however, extended by agreement to 31 August 2004.
[30] Clause 2.7 of the Special Conditions provided that Australia Estates was obliged to
notify the Council, as vendor, within two business days of receiving the decision
notice. The decision notice was defined in the Special Conditions to mean the
decision notice from the Council in relation to the application. In accordance with
the Janus-like role of the Council in this contract, Australia Estates was obliged to
provide the Council as vendor with a copy of the decision notice it had received
from the Council as assessment manager. Australia Estates was also obliged under
cl 2.8 to notify the Council, as vendor, in writing within five business days of
receipt of the decision notice whether the application had been approved and if so
whether the conditions of approval were satisfactory to the purchaser. If the
approval was granted on terms which were not satisfactory to the purchaser,
Australia Estates had the right under cl 2.9 to terminate the contract by giving
written notice within five business days of receipt of the decision notice. If it did
not give notice terminating within that time, it would be deemed to have given
notice that the terms of the approval were satisfactory.
-- 9 of 23 --
10
[31] “Approval Notice” was defined in cl 1.1(4) of the Special Conditions of the contract
to mean “…a notice (or deemed notice) by the Purchaser to the effect that the
Approval had been granted and that the conditions applying to such Approval are
satisfactory to the Purchaser.”
[32] Australia Estates made application for approval of a material change of use in
respect of the land on 3 October 2003. No submissions8 were received in
opposition to its application. Decision notices were issued on 26 July 2004 pursuant
to s 3.5.15 of the IPA which provides:
“3.5.15 Decision notice
(1) The assessment manager must give written notice of the decision in
the approved form (the “decision notice”) to—
(a) the applicant; and
…
(c) if the assessment manager is not the local government and the
development is in a local government area—the local
government.
(2) The decision notice must be given within 5 business days after the
day the decision is made and must state the following—
(a) the day the decision was made;
(b) the name and address of each referral agency;
(c) whether the application is approved, approved subject to
conditions or refused;
(d) if the application is approved subject to conditions—
(i) the conditions; and
(ii) whether each condition is a concurrence agency or
assessment manager condition, and if a concurrence
agency condition, the name of the concurrence agency;
(e) if the application is refused—
(i) whether the assessment manager was directed to refuse
the application and, if so, the name of the concurrence
agency directing refusal and whether the refusal is solely
because of the concurrence agency’s direction; and
(ii) the reasons for refusal;
(f) if the application is approved—whether the approval is a
preliminary approval, a development permit or a combined
preliminary approval and development permit;
8 A Submitter is a person who makes a submission against the grant of all of part of an approval: s
4.1.28
-- 10 of 23 --
11
(g) any other development permits necessary to allow the
development to be carried out;
(h) any code the applicant may need to comply with for self-
assessable development related to the development approved;
(i) whether or not there were any properly made submissions about
the application;
(j) the rights of appeal for the applicant and any submitters.
…”
Australia Estates received a copy of the decision notices on 30 July 2004. The first
decision notice was for preliminary approval with conditions showing that the
applicant needed a development permit. The second decision notice was the
approval of the development permit subject to the conditions contained therein.
Such decision notices constituted development approval as defined in Schedule 10
of the IPA:
“development approval means a decision notice or a negotiated
decision notice that—
a) approves, wholly or partially, development applied for in a
development application (whether or not the approval has conditions
attached to it); and
b) is in the form of a preliminary approval, a development permit or an
approval combining both a preliminary approval and a development
permit in the one approval.”
[33] On the receipt of the decision notice Australia Estates had rights and duties under
the contract as purchaser as well as rights and duties provided by statute to it as
applicant. The statute, the IPA, gave Australia Estates a right of appeal to the
Planning and Environment Court pursuant to s 4.1.27. It did not exercise that right.
The applicant had the right to make representations about a matter in the decision
notice to the assessment manager. If it did so, the assessment manager had duties
pursuant to s 3.5.17 of the IPA. Section 3.7.17 provides:
“3.5.17 Changing conditions and other matters during the
applicant’s appeal period
(1) This section applies if the applicant makes representations to the
assessment manager about a matter stated in the decision notice…
(2) If the assessment manager agrees with any of the representations, the
assessment manager must give a new decision notice (the
“negotiated decision notice”) to—
(a) the applicant; and
(b) each principal submitter; and
…
(3) Only 1 negotiated decision notice may be given.
-- 11 of 23 --
12
(4) The negotiated decision notice—
(a) must be given within 5 business days after the day the
assessment manager agrees with the representations; and
(b) must be in the same form as the decision notice previously
given; and
(c) must state the nature of the changes; and
(d) replaces the decision notice previously given.
(5) If the assessment manager does not agree with any of the
representations, the assessment manager must, within 5 business days
after the day the assessment manager decides not to agree with any of
the representations, give a written notice to the applicant stating the
decision about the representations.
(6) Before the assessment manager agrees to a change under this section,
the assessment manager must reconsider the matters considered when
the original decision was made, to the extent the matters are relevant.
…”
If the assessment manager agreed with any of the representations then it was
obliged to give a new decision notice, the negotiated decision notice, to the
applicant. Only one negotiated decision notice might be given. If the assessment
manager did not agree with any of the representations, then he or she was obliged to
give written notice to the applicant stating the decision about the representations.
[34] On 2 August 2004, Australia Estates made representations to the Council under
s 3.5.17 of the IPA to vary conditions contained in the decision notice, with regard
to the amount of car parking space required. The Council made its determination on
those representations on 26 August 2004, and on 31 August 2004 issued a
negotiated decision notice which made slight changes to the decision notices of 26
July 2004. The negotiated decision notice was then taken to be the development
approval which took effect from the time the negotiated decision notice was given:
IPA s 3.5.19 which provides:
“3.5.19 When approval takes effect
If the application is approved, or approved subject to conditions, the decision
notice, or if a negotiated decision notice is given, the negotiated
decision notice, is taken to be the development approval and has
effect—
(a) if there is no submitter and the applicant does not appeal the
decision to the court—from the time the decision notice is given;
(or if a negotiated decision notice is given, from the time the
negotiated decision notice is given); or
(b) if there is a submitter and the applicant does not appeal the
decision to the court—when the submitter’s appeal period ends;
or
(c) if an appeal is made to the court—subject to the decision
of the court, when the appeal is finally decided.
-- 12 of 23 --
13
It then replaced the decision notice which was previously given: IPA s 3.5.17(4)(d).
[35] With regard to its contractual rights and duties, no notice was given by Australia
Estates pursuant to cl 2.9 terminating the contract by 6 August 2004 (ie within five
business days of receiving the decision notice). However, on that date, solicitors for
the purchaser sent a letter by facsimile transmission to the solicitors for the Council
saying that there were still some outstanding issues being negotiated and asking for
confirmation that the decision notice for preliminary approval was not the
“Approval Notice” referred to in cl 2 of the Special Conditions. If it were
considered the “Approval Notice”, then the purchaser said it would make
arrangements to comply with cl 2. The Council’s solicitors replied on the same day
pointing out that Australia Estates had been given two decision notices and saying
that whilst the preliminary approval might not be approval for the purposes of the
contract, the development permit clearly was, and asking what their client’s position
was in relation to cl 2. At this point, Australia Estates had an approval which it
could not lose. It knew that the conditions of approval might be made more
favourable to it but could not be made more onerous or lost. It was not surprising in
those circumstances that the decision notice was the triggering event for the
appellant to elect whether or not to terminate the contract.
[36] On 9 August 2004, the solicitors for Australia Estates accepted that the development
permit was an “approval” for the purposes of cl 2 but asked, in view of the ongoing
negotiations about the conditions of approval, that the five day notification period
pursuant to cl 2.11 of the Special Conditions be extended to 10 September 2004
with both parties agreeing that the notices received by Australia Estates constituted
approval in terms of the contract. Clause 2.11 referred to the requirement on the
purchaser to give notice to the vendor within five business days of the giving of the
approval notice of whether any notification was required to be given to any
submitter, whether such notice had been given and the date of expiry of the
submitter’s appeal period.
[37] As there were no submitters, cl 2.12, rather than cl 2.11, applied to ascertain the
time when cl 2 was satisfied or deemed to be satisfied. That date was significant
because cl 5 provided that the completion date was 60 days after cl 2 was satisfied.
Clause 2.12 provided that, subject to the purchaser’s rights to terminate under cl 2.9,
cl 2 was deemed to be satisfied upon the giving of the approval notice, i.e. the
notice (or deemed notice) by the Purchaser to the effect that the approval had been
granted on satisfactory terms. Under the contract, that was deemed to have occurred
pursuant to cl 2.9 when the five business days had expired, i.e. on 3 August 2004,
unless the purchaser had exercised its right to terminate.
[38] In this case, as no right to terminate had been exercised, the completion date under
the contract was to be 3 October 2004, 60 days after 3 August 2004.
[39] On 13 August 2004, the Council’s solicitors replied to the letters of the purchaser’s
solicitors of 6 and 9 August 2004. They reiterated that the decision notice dated 26
July 2004 approving a development permit was an approval for the purposes of cl 2
of the Special Conditions. They referred to the fact that no notifications had been
received pursuant to cl 2.7, cl 2.8 or cl 2.9 and therefore cl 2 had been satisfied.
Clause 5.1 provided that the completion date was 60 days after cl 2 was satisfied.
However the Council proposed that the date of their solicitors’ letter be taken to be
the date of satisfaction of cl 2 and that 12 October 2004 be the completion date with
-- 13 of 23 --
14
time to be and remain of the essence. This was an offer to vary the contract with
regard to the completion date.
[40] On 18 August 2004, the Council and Australia Estates, through their solicitors,
reached agreement that the completion date for the contract would be 12 October
2004. On that date, the solicitor for Australia Estates wrote to the Council’s
solicitors saying, “I confirm the settlement date as 12 October 2004”. This was a
variation to the contract binding on both parties. At that time, Australia Estates paid
the balance of the deposit, which under the contract was payable on satisfaction of
cl 2 of the Special Conditions.
[41] On 8 October 2004, four days before the agreed completion date, Australia Estates
raised for the first time the contention that the negotiated decision notice, and not
the decision notice, was the approval for the purposes of the Special Conditions of
the contract; and that accordingly the completion date under the contract was 25
October 2004.
[42] Settlement did not occur on 12 October 2004, and on 13 October 2004 the Council
elected to terminate the contract. The learned trial judge found that the Council was
entitled so to terminate the contract.
Should the agreement be set aside for mistake?
[43] In order to succeed on appeal the applicant must succeed in having the agreement in
which the date for settlement was arranged for 12 October 2004 set aside. The
applicant says that that agreement should be set aside because it was vitiated by
common mistake. The applicant submitted that when the contract for the sale of
land was varied to provide for a settlement date of 12 October 2004, both parties
were operating under a mistake of mixed fact and law. The mistake was said to be
that approval was obtained by the decision notice on 26 July 2004, as the Council
contended, rather than the negotiated decision notice of 31 August 2004, as
Australia Estates subsequently contended.
[44] The applicant relied on the principles derived from Solle v Butcher,9 a decision of
the Court of Appeal in England. These principles were conveniently set out in the
judgment of Palmer J in the New South Wales Supreme Court in Clasic
International Pty Ltd v Legos10 where his Honour held:
“The defendants invoke the principle that equity may set aside a
contract if both parties were induced to enter into it by a common
mistake as to a fundamental matter, provided that the party seeking
to set aside the contract was not at fault.
The principle is expressed thus by Denning LJ in Solle v Butcher
[1950] 1 KB 671 at 693:
‘A contract is also liable in equity to be set aside if the parties
were under a common misapprehension either as to the facts or
to their respective rights, provided that the misapprehension was
fundamental and that the party seeking to set it aside was not
himself at fault …’.”
9 [1950] 1 KB 671 at 693.
10 (2002) 60 NSWLR 241 at 249; [2002] NSWSC 1155 at [39]-[40]
-- 14 of 23 --
15
[45] The problem with reliance on this decision is that Solle v Butcher has itself been
overruled by the Court of Appeal in England in Great Peace Shipping Ltd v
Tsavliris Salvage (International) Ltd.11 The parties to this appeal were unaware of
that decision but were given leave to file further submissions. There is no
suggestion that it would have required any findings of fact or evidence that was not
traversed at the trial.
[46] There was no appeal from the decision in Clasic International Pty Ltd v Legos.
However reliance on the authority of Solle v Butcher was touched upon in an appeal
from another judgment of the same trial judge to the Court of Appeal in New South
Wales, Harris v Digital Pulse Pty Ltd,12 where exemplary damages had been
awarded for breach of fiduciary duties by an employee. On appeal, the respondent
submitted that although exemplary damages had never been granted for equitable
wrongs in England or Australia, neither was there any case in which exemplary
damages had been sought and refused.13 Relying on the proposition stated by the
learned author of Hanbury and Martin Modern Equity14 that “the principles of
equity have constantly developed and found new fields of application”, the
respondent submitted that those developments could extend to the awarding of
exemplary damages in equity.
[47] Heydon JA (as his Honour then was), in dismissing an argument that equity was
sufficiently creative and dynamic to expand so as to create a power to award
exemplary damages for breach of fiduciary duties by an employee when no such
power had previously been held to exist, said:15
“So far as the plaintiff’s argument relied on what Hanbury and
Maudsley said, it must be remembered that most of the various
examples which that work provides of equity’s ‘creativity’ and
‘dynamism’ fall into the following classes: they are decisions of the
House of Lords, not lower courts (eg Barclays Bank Ltd v Quistclose
Investments Ltd16; they have since been overruled or damagingly
criticised by the House of Lords (eg the reasoning in Chase
Manhattan Bank NA v Israel-British Bank (London) Ltd [1981] Ch
105, was not accepted in Westdeutsche Landesbank Girozentrale v
Islington London Borough Council [1996] AC 669 at 714-715); they
have since been overruled by other courts in England (eg Solle v
Butcher [1950] 1 KB 671, was overruled in Great Peace Shipping
Ltd v Tsavliris Salvage (International) Ltd [2002] 3 WLR 1617;
[2002] 4 All ER 689); they have been held by this Court and the
High Court not to be law in Australia (eg Lord Denning MR’s “new
model constructive trust”); they are said by Hanbury & Martin
Modern Equity, 14th ed itself to be problematical or wrong; or they
are not really novel.”
In other words, the apparent adventurousness of some of the developments in equity
should not be replaced with adventurism.
11 [2003] QB 679.
12 (2003) 56 NSWLR 298; [2003] NSWCA 10.
13 The learned authors of R P Meagher, W M C Gummow, and J R F Lehane, Equity, Doctrines and
Remedies, 3rd ed, Butterworths, Sydney, 1992 at 3 [102] have described equity’s progress as being
“haphazard” and “ad hoc”.
14 J E Martin (ed) 14th ed, Sweet & Maxwell Ltd, London, 1993 at 44.
15 at [455].
16 [1970] AC 567.
-- 15 of 23 --
16
[48] In Great Peace Shipping Ltd v Tsavliris Salvage (International) Ltd, the Court of
Appeal, in a judgment of conspicuous clarity, examined the common law of mistake
and the equitable doctrine of rescission for mistake. The court held that the
following elements must be present if common mistake is to avoid a contract at
common law:17
“(i) there must be a common assumption as to the existence of a state
of affairs;
(ii) there must be no warranty by either party that that state of affairs
exists;
(iii) the non-existence of the state of affairs must not be attributable
to the fault of either party;
(iv) the non-existence of the state of affairs must render performance
of the contract impossible;
(v) the state of affairs may be the existence, or a vital attribute, of the
consideration to be provided or circumstances which must subsist if
performance of the contractual adventure is to be possible.”
[49] The common law doctrine of common mistake, as the Court of Appeal held,18 fills a
gap in the contract where it transpires that it is impossible of performance without
the fault of either party and the parties have not, expressly or by implication, dealt
with their rights and obligations in that eventuality. A common mistake at common
law makes a contract void ab initio. For example in Strickland v Turner19 neither
the vendor nor the purchaser of an annuity realised that the annuitant had died when
the bargain was completed. In such a case there was no annuity in existence, and
the contract was void ab initio. A common mistake in equity on the other hand
rendered a contract voidable. An example is found in Cooper v Phibbs20 when a
contract whereby a purchaser bought property which neither he nor the seller
realised already belonged to the purchaser was liable to be set aside in equity for
that common mistake. However the Court of Appeal observed that cases of
common mistake were likely to be rare because where parties agree that something
shall be done which is impossible at the time of making the agreement, it is more
likely that, on a true construction of the agreement, one or the other will have
undertaken responsibility for the mistaken state of affairs.21
[50] After the discussion of Bell v Lever Bros Ltd22 in Solle v Butcher, it was assumed in
later cases that the common law of mistake was different from the equitable
jurisdiction to set aside a contract for mistake. In Great Peace Shipping v Tsavliris
Salvage, the Court of Appeal held that this had led to incoherence and confusion in
this area of the law. The only way of resolving that confusion was to declare, as the
court did, that there was no jurisdiction in equity to grant rescission of a contract on
the ground of common mistake where that contract was valid and enforceable in
common law on ordinary principles of contract law. In doing so, the court
overruled Solle v Butcher, as well as many English decisions which had followed it.
17 (supra) at 703.
18 Great Peace Shipping Ltd v Tsavliris Salvage Ltd (supra) at 704.
19 [1852] 7 Exch 208.
20 (1867) LR 2 HL 149.
21 (supra) at 706.
22 [1932] AC 161.
-- 16 of 23 --
17
Should Great Peace Shipping v Tsavliris Salvage be followed by this Court?
[51] Prior to the High Court’s decision in Cook v Cook23 it was considered that the
Supreme Court of a State, even when sitting on appeal, should as a general rule
follow decisions of the English Court of Appeal if there was no other controlling
authority. However, this rule was abandoned in that case. Mason, Wilson, Deane
and Dawson JJ observed:24
“The history of this country and of the common law makes it
inevitable and desirable that the courts of this country will continue
to obtain assistance and guidance from the learning and reasoning of
United Kingdom courts just as Australian courts benefit from the
learning and reasoning of other great common law courts. Subject,
perhaps, to the special position of decisions of the House of Lords
given in the period in which appeals lay from this country to the
Privy Council, the precedents of other legal systems are not binding
and are useful only to the degree of the persuasiveness of their
reasoning.”
Brennan J (as his Honour then was) specifically concurred with that observation.25
[52] In this case, the persuasiveness of the court’s reasoning in Great Peace Shipping v
Tsavliris Salvage, together with the negative reference to Solle v Butcher by
Heydon JA in Harris v Digital Pulse and the somewhat qualified approach taken to
Solle v Butcher by the High Court, the history of which is detailed below, suggests
that the law as stated in Great Peace Shipping should be applied by this Court in
preference to the law as stated in Solle v Butcher and the cases which have followed
it.26
[53] Solle v Butcher had, even before its overruling in the House of Lords, a cautious
reception in the High Court. The first case in which it was referred to was McRae v
Commonwealth Disposals Commission27 where the court held that the contract in
question was not voidable in equity for mistake. The case concerned the sale of an
oil tanker by the respondent to the appellant. It was apparently one of many vessels
which were wrecked or stranded off the coast of Australia during the Second World
War and which were sold for salvage. However, there was no oil tanker lying at the
location specified by the Commission in its agreement with McRae.
[54] Referring to the judgment of Denning LJ in Solle v Butcher, Dixon and Fullagar JJ
agreed with an observation made by his Lordship about the inapplicability of the
French law as to mistake to the common law but, in doing so, their Honours
expressed a reservation about the remainder of his Lordship’s reasons by saying that
they “would not be prepared to assent to everything that is said by Denning L.J. in
the course of this judgment”. 28 As to the doctrine of mistake their Honours said:
23 (1986) 162 CLR 376.
24 (supra) at 390.
25 (supra) at 394.
26 Great Peace Shipping has been followed in England in Brennan v Bolt Burdon [2005] QB 303;
Champion Investments Ltd v Ahmed [2004] EWHC 1956; referred to in EIC Services Ltd v Phipps
[2005] 1 WLR 1377; and cited with approval at first instance in the Supreme Court of Queensland in
Donkin v Official Trustee in Bankruptcy [2003] QSC 401; 251 of 2002, 26 November 2003 at [52].
27 (1951) 84 CLR 377.
28 McRae v Commonwealth Disposals Commission (supra) at 407.
-- 17 of 23 --
18
“Denning L.J. indeed says in Solle v Butcher,29 at p. 692:-- 'Neither
party can rely on his own mistake to say it was a nullity from the
beginning, no matter that it was a mistake which to his mind was
fundamental, and no matter that the other party knew he was under a
mistake. A fortiori if the other party did not know of the mistake, but
shared it'. But, even if this be not wholly and strictly correct, yet at
least it must be true to say that a party cannot rely on mutual mistake
where the mistake consists of a belief which is, on the one hand,
entertained by him without any reasonable ground, and, on the other
hand, deliberately induced by him in the mind of the other party.” 30
[55] Dixon and Fullagar JJ rejected the proposition that the contract in question could be
avoided because of mistake, mistake being defined as “a common assumption of
fact so as to justify the conclusion that the correctness of the assumption was
intended by both parties to be a condition precedent to the creation of contractual
relations.”31 Rather their Honours held that the appellant was entitled to damages
for breach of contract because the contract included, on its proper construction, a
promise by the Commission that the tanker existed in the position specified. If the
doctrine of mistake were to be considered, their Honours held:32
“…then the Commission cannot in this case rely on any mistake as
avoiding the contract, because any mistake was induced by the
serious fault of their own servants, who asserted the existence of a
tanker recklessly and without any reasonable ground.”
McRae was referred to with approval in Great Peace Shipping Ltd v Tsavliris
Salvage (International) Ltd,33 as an example of the second and third of the elements
to which it referred which must be present for a contract to be void for common
mistake.
[56] The next time Solle v Butcher was considered by the High Court was in Svanosio v
McNamara,34 where the respondents had agreed to sell to the appellant land,
together with the licensed premises known as the Bullshead Hotel erected thereon,
the victualler’s licence in respect of the hotel and the goodwill. After completion it
was discovered that the hotel stood partly only on the land conveyed and partly on
adjoining Crown land. The appellant sought a declaration that the transactions were
void and an order setting aside the agreements and the conveyance. He sought a
declaration that the agreement was entered into and executed by the appellant and
the respondents under a common mistake as to the existence of a fact accepted by
all parties as a basis or condition fundamental to the transactions, namely that the
defendants were the owners of the whole of the land upon which the hotel was
erected or which was used or occupied in conjunction with the hotel.
[57] After referring to their discussion of Solle v Butcher in McRae v Commonwealth
Disposals Commission, Dixon CJ and Fullagar J contemplated that mistake might
afford a ground on which equity would refuse specific performance of a contract
and even that there might be cases of “mistake” in which it would be so inequitable
29 [1950] 1 KB.
30 (supra) at 408
31 McRae v Commonwealth Disposals Commission (supra) at 409.
32 (supra) at 410.
33 (supra) at 703-704.
34 (1956) 96 CLR 186.
-- 18 of 23 --
19
that a party should be held to his or her contract that equity would set it aside.
However their Honours went on to say:35
“…it is difficult to conceive any circumstances in which equity could
properly give relief by setting aside the contract unless there has
been fraud or misrepresentation or a condition can be found
expressed or implied in the contract.”
In other words their Honours were saying that the contract could only be set aside
either on traditional grounds in equity or under the common law of mistake.
[58] The High Court held that the contract was not void and it should not be set aside.
Importantly their Honours held that in the absence of fraud or misrepresentation, the
plaintiff was not entitled to the equitable relief he sought. It would not therefore be
set aside in equity for mistake alone although that might be a ground to refuse
specific performance.36
[59] The high water mark for Solle v Butcher in the High Court was found in Taylor v
Johnson.37 In that case, the respondent, Mrs Johnson, granted an option to
Laurence Taylor or his nominee to purchase land for a purchase price of $15,000.
The option was exercised by Mr Taylor within three weeks and less than a month
later, Mrs Johnson and Mr Taylor’s children, as his nominee, entered into a contract
for the sale of land with the purchase price being $15,000 as provided by the option.
However Mrs Johnson declined to perform the contract in accordance with its terms
saying that at the time she granted the option and executed the contract, she believed
that the document she was signing provided for a consideration of $15,000 per acre
which would have made the consideration $150,000, rather than the $15,000 which
both documents specified. The High Court held that it could be inferred that Mr
Taylor and Mrs Johnson each believed that the other was acting under a mistake or
misapprehension, either as to price or value, when each agreed to a sale at the
purchase price which each believed the other had accepted. The court found that Mr
Taylor deliberately set out to ensure that Mrs Johnson was not disabused of the
mistake or misapprehension under which he believed her to be acting.
[60] Mason ACJ, Murphy and Deane JJ in their joint judgment referred to the line of
authority discussed above. With regard to the caution expressed by Dixon CJ and
Fullagar J, their Honours said:
"Dixon C.J. and Fullagar J. referred … to a difficulty in conceiving
circumstances in which equity could properly give relief by setting
aside the contract unless there had been fraud or misrepresentation or
a condition could be found expressed or implied in the contract.
Presumably, their Honours were referring to ‘fraud’ in the wide
equitable sense which includes unconscionable dealing. If they were
not, we do not share the difficulty to which they referred. To the
contrary, it seems to us that the reported cases, including Solle v.
Butcher itself, readily provide concrete examples of such
circumstances." 38
35 at 196.
36 cf Tanwar Enterprises Pty Limited v Cauchi [2003] HCA 57 at [58], [64], [106]; 217 CLR 315 at
335, 336, 351.
37 (1983) 151 CLR 422.
38 Taylor v Johnson (supra) at 431
-- 19 of 23 --
20
[61] However, their Honours also expressed the view that Lord Denning had, in Solle v
Butcher, formulated a more general proposition than the speech of Lord Atkin in
Bell v Lever Brothers Ltd,39 on which it was based, would warrant. Bell v Lever
Brothers was an authoritative declaration of the common law of mistake.
[62] Taylor v Johnson was itself a case of unilateral mistake where the other party, while
not inducing the mistake, stood by knowing the vendor was labouring under a
fundamental error as to the terms of the contract. The ratio of the case was narrowly
stated:40
"It is that a party who has entered into a written contract under a
serious mistake about its contents in relation to a fundamental term
will be entitled in equity to an order rescinding the contact if the
other party is aware that circumstances exist which indicate that the
first party is entering the contract under some serious mistake or
misapprehension about either the content or subject matter of that
term and deliberately sets out to ensure that the first party does not
become aware of the existence of his mistake or misapprehension."
Application of the law to this case
[63] The appellant in this case argued that the parties were mistaken about a fundamental
matter and that Australia Estates, the party seeking to set aside the contract, was
without fault. That is the test from Solle v Butcher. However for the reasons
already given, that is no longer the appropriate test. Even if it were the test, for the
reasons given below, the appellant would fail.
[64] In my view, the correct question to be posed on this appeal is whether the agreement
is void at common law for common mistake. The test that should be applied is that
found in the five elements set out in Great Peace Shipping v Tsavliris. It is
abundantly clear in applying those elements to this case that the common law of
mistake could not be used to declare the agreement void. For the reasons discussed
below, there was no mistake. Even if there had been, the mistake (or non-existence
of a state of affairs) alleged by the appellant did not render the performance of the
agreement impossible. There is no equitable jurisdiction to set aside, on the ground
of common mistake, an agreement, which is valid and enforceable at common law.
[65] If, contrary to my view, the test to be posed is that found in Taylor v Johnson, the
appellant must show that when it entered into the agreement to vary the completion
date of the contract, the Council was aware that circumstances existed which
showed that Australia Estates entered into that agreement under a serious mistake or
misapprehension about the content or subject matter of a fundamental term and that
the Council deliberately set out to ensure that Australia Estates did not become
aware of the existence of its mistake or misapprehension.
[66] The serious mistake or misapprehension about the content or subject matter of a
fundamental term was said to be that Australia Estates was unaware that the effect
of s 3.5.19 of the IPA was that the application could not be taken to be approved for
the purposes of cl 2 of the Special Conditions of the Contract until the negotiated
decision notice issued on 31 August 2005. The appellant also has to show that the
Council was aware that circumstances existed which showed that Australia Estates
laboured under that mistake or misapprehension and deliberately set out to ensure
39 [1932] AC 161.
40 (supra) at 432.
-- 20 of 23 --
21
that Australia Estates did not become aware of the existence of its mistake or
misapprehension. All of these elements are based on the proposition that there was
a mistake. Australia Estates would first have to show that the view it held of the
facts or the legal effect of the facts was mistaken when the agreement was made to
vary the completion date of the contract. This it has been unable to do.
[67] Section 3.5.19(1) of the IPA provides that if the application is approved, or
approved subject to conditions, the decision notice, or if a negotiated decision notice
is given, the negotiated decision notice, is taken to be the development approval and
has effect, if there is no submitter and the applicant does not appeal the decision to
the court, from the time the decision notice was given, or if a negotiated decision
notice was given, from the time the negotiated decision notice was given. The
operative date is important for statutory purposes because time starts to run from
that date and it governs when the approval will lapse.
[68] However the appellant argued that s 3.5.19 of the IPA should be used to construe
the contract so that the effect of the negotiated decision notice issuing is that only
the negotiated decision notice of 31 August 2004 took effect as the development
approval and that the decision notice of 26 July 2004 did not take effect even at the
time it issued as the development approval. That argument is wrong both as a
matter of statutory interpretation and construction of the contract.
[69] As to the statute, the IPA provides that when it issues, a negotiated decision notice
replaces the decision notice. As a matter of statutory construction, the negotiated
decision notice becomes the development approval from the time it issues and not
before. It does not mean that the decision notice never had effect but rather that
from the time of issue of the negotiated decision notice, it replaces the decision
notice as development approval.
[70] The contract itself makes no mention of the possibility of a negotiated decision
notice although it does contain detailed provisions to cover various other
contingencies. If the appellant’s argument were correct, grave difficulties of
interpretation would arise. A number of sub-clauses in cl 2 of the Special
Conditions require the purchaser to send notifications of various types to the
vendor. Each of them uses the receipt of the decision notice as the trigger for the
sending of that notification. If notification is not sent in accordance with cl 2.9
within five days of receipt of the decision notice, then cl 2 is deemed to be satisfied
and the contract becomes unconditional as to cl 2. The contract would become
hopelessly ambiguous and uncertain if either the vendor or the purchaser was not
sure whether the satisfaction of cl 2 had occurred because there might or might not
come into existence some time after the decision notice, a negotiated decision
notice. The uncertainty would arise because there is no duty on a purchaser to apply
for a negotiated decision notice; and if such an application be made, it may or may
not be granted. There might never be a negotiated decision notice. The contract is
drafted on the basis that when a decision notice is received, the time for the contract
becoming unconditional starts to run.
[71] Indeed at the time the parties entered into the agreement to vary the date for
completion the only approval was the decision notices issued on 26 July 2004.
There was no operative mistake on that date.
-- 21 of 23 --
22
[72] The appellant relied on the decision of this Court in Hayes v Walker.41 However
analysis of the contract in that case, shows that reliance is misplaced. Hayes v
Walker concerned a contract for the sale of land subject to development approval.
Condition 1 of the contract provided:
“This contract is subject to the seller obtaining from the Brisbane
City Council approval to develop the land and to construct:
5x3 bedroom townhouses and
2x2 bedroom townhouses
The contract is conditional upon the buyer being satisfied with all the
terms, condition and requirements as set down by the Brisbane City
in relation to the said D.A.”
Submissions were made objecting to the development application. In that case, a
decision notice was received which specifically said that it had no effect until either
the submitters’ appeal period had ended or, if an appeal were made to the court or a
tribunal, the decision of the court or tribunal was made in favour of the proposed
development. In those circumstances the decision notice could not constitute a
development approval so as to satisfy the condition in the contract. As the Chief
Justice observed:42
“It is not a case where an ‘approval’, though inchoate or incipient, is
nevertheless an approval.”
The contract referred to “development approval” being obtained, not the receipt of a
“decision notice”. Where, as in that case, there were submissions in opposition, the
decision notice was not effective of itself to grant development approval.
[73] The present case is quite different. The receipt of the ‘decision notice’ was the
triggering event; and it was effective in granting development approval. At that
point, the notification requirements in cl 2 were activated. If no negotiated decision
notice were applied for or issued, the decision notice would remain the development
approval. The appellant had development approval when it received the decision
notice. It was, as the learned trial judge held, effective until, and as I would add,
unless, replaced. The agreement to vary the date for completion of the contract was
entered into at a time when the decision notice was the development approval.
[74] The parties were very careful to spell out when the right to terminate under cl 2
arose and when it was satisfied or deemed satisfied. The contract specified in detail,
for instance, what happened if there were submitters with a right to appeal.
Importantly, even then, the contract did not contemplate that the parties had to await
the outcome of any appeal. If a submitter had a right of appeal against the approval
then the purchaser was obliged to give notice to the vendor within 2 business days
of the expiration of the time for appeal, if any submitter had appealed (cl 2.13). If
there were no such appeal, then cl 2 was deemed satisfied on the giving of the notice
referred to in cl 2.13. Again it did not await any negotiated decision notice. If there
were an appeal, then either party might terminate the contract by notice in writing to
the other party within the period referred to in cl 2.13. If neither party terminated,
then cl 2 was deemed satisfied.
41 (2004) 134 LGERA 290; [2004] QCA 288.
42 (supra) at 295, [15].
-- 22 of 23 --
23
[75] In any event, the question of when the approval could be said to have been given
was not a fundamental term of the agreement to vary the completion date. If there
were any mistake, it was not as to a fundamental term of the agreement under
consideration ie the agreement to vary the date for settlement of the contract. If it
were a mistake, it was a mistake that motivated the agreement to vary the contract
not a mistake as to a fundamental term.43
[76] Even if the appellant had been successful in its argument that it was labouring under
a serious mistake or misapprehension about the content or subject matter of a
fundamental term, it could not succeed on the other elements of the test in Taylor v
Johnson i.e. that the Council knew that this was a mistake and deliberately set out to
ensure that Australia Estates did not become aware of its mistake or
misapprehension. The Council did not believe that Australia Estates was labouring
under any such error or deliberately set out to ensure that Australia Estates did not
become aware of its error.
[77] The appeal should be dismissed with costs.
43 cf Baird v BCE Holdings Pty Ltd (1996) 40 NSWLR 374 at 384.
-- 23 of 23 --
Official source: https://www.sclqld.org.au/caselaw/QCA/2005/328