Bieto & Ors v Triline Australia Pty Ltd (No 2) [2003] QDC 307
DISTRICT COURT OF QUEENSLAND
CITATION: Bieto & Ors v Triline Australia Pty Ltd (No 2) [2003] QDC
307
PARTIES: JOSE BIETO, JOSIANE BIETO, FRANCOIS BIETO,
LOUIS BIETO and MICHEL BIETO
Appellants
v
TRILINE AUSTRALIA PTY LTD
Respondent
FILE NO/S: Appeal 1901 of 2001
DIVISION:
PROCEEDING: Appeal
ORIGINATING
COURT: Queensland Building Tribunal
DELIVERED ON: 22 September 2003
DELIVERED AT: Brisbane
HEARING DATE: 20 August 2003
JUDGE: McGill DCJ
ORDER: Appeal allowed; decision of the Queensland Building
Tribunal of 28 March 2001 in Application number C095-
99 be varied by: (a) substituting $43,890 for the sum of
$3,375 which the applicant before the tribunal was
ordered to pay the respondents before the tribunal; (b)
substituting “22 September 2003” for “the date
hereunder” in paragraph 1 of that decision; (c)
substituting, for paragraph 2 of that decision, an order
that the applicant pay three-quarters of the respondents’
costs of the proceeding in the tribunal, including reserved
costs, to be assessed if not agreed on the District Court
scale appropriate where the amount recovered exceeds
$50,000; assessment of the costs payable under the order
of the Tribunal as varied be delegated to a Deputy
Registrar of the District Court; appellants’ costs of and
incidental to this appeal be paid by the respondent;
respondent granted an indemnity certificate in respect of
the appeal under s 15(3) of the Appeal Costs Fund Act
1973.
CATCHWORDS: APPEAL AND NEW TRIAL – Costs – appeal from
Queensland Building Tribunal – whether jurisdiction to grant
respondent certificate under Appeal Costs Fund Act 1973.
DAMAGES – Interest – breach of contract causing
diminution in value of land – whether available – basis of
-- 1 of 15 --
2
award – appropriate rate and date of commencement.
INFERIOR TRIBUNALS – Building Tribunal – whether
power to award interest by statute or as damages – basis of
award where breach of contract causing diminution in value
of land.
INTEREST – Damages – breach of contract causing
diminution in value of land – basis of award – appropriate
rate and date of commencement.
PRACTICE – Costs – Building Tribunal – whether separate
issues – whether costs for party successful overall to be
limited because of separate issues on which party failed.
Queensland Building Tribunal Act 2000 ss 92, 93(2)(c).
Appeal Costs Fund Act 1973 s 4.
Anderton v Parkes Horticultural Services Pty Ltd (Appeal
2790/96, McGill DCJ, 15.11.96, unreported) – not followed.
Colburt v Beard [1992] 2 Qd R 67 – applied.
Hungerford v Walker (1989) 171 CLR 125 – applied.
Queensland Building Services Authority v Morris (Appeal
3319/97, Robin DCJ, 24.10.97, unreported) – followed.
Thiess v TCN Channel 9 Pty Ltd (No 5) [1994] 1 Qd R 156 –
applied.
COUNSEL: L Boccabella for the appellants
M D Ambrose for the respondent
SOLICITORS: A J Torbey & Associates for the appellants
Clarke & Kann for the respondent
[1] This is an appeal from a decision of the Queensland Building Tribunal which on
28 March 2001 ordered that the respondent pay the appellants $3,375 within a
particular time, after which interest was to accrue. The appeal is under the
Queensland Building Tribunal Act 2000 (“the Act”) s 92. For reasons delivered on
26 March 2003, I ordered that the appeal be allowed, and the matter listed for
further consideration. In essence I held that the tribunal had erred because, having
rejected a claim for damages advanced on a particular basis by the appellants, the
tribunal member ought to have gone on and allowed damages on the correct basis
for breaches of contract which had been proved, if necessary giving the parties the
opportunity to lead further evidence. I allowed the appeal but stood over for further
consideration, after the parties had had the opportunity to consider the detail of my
reasons, the question of whether I would remit the matter to the tribunal or deal with
the remaining issue, which was whether and to what extent the value of the
appellants’ premises had been reduced by the breaches of contract of the
respondent.
[2] I was subsequently advised that the parties had reached agreement about the amount
to be taken into account in that way, and that the only matters remaining in issue
-- 2 of 15 --
3
were interest and costs. The parties agreed that the diminution in value of the
appellants’ premises was $37,500, and, as this replaces the amount of $7,000
allowed by the tribunal for loss of amenity, effect is to be given to their agreement
by increasing the amount payable by the respondent to the appellants to $33,875.
That amount reflects the balance after the total amount payable on the appellants’
claim against the respondent was set-off against the amount found by the tribunal to
have been payable on the respondent’s claim against the appellants.
Interest
[3] In relation to the question of interest, the appellants sought interest from October
1998, when the house was due for completion under the contract. The respondent
however submitted that interest should not be awarded, as most of the final amount
payable was in respect of the change in value of the property which had been
assessed as at the current value.1
[4] The power of this court on appeal is to confirm, annul, vary or reverse the tribunal’s
decision: the Act s 92(6)(a), and to make consequential or ancillary orders or
directions: (c). It seems to follow that the court’s power to award interest depends
on whether this is something which could have been included by the tribunal in its
order; if so, the order of the tribunal which is the subject of the appeal may be
varied so as to include it. The tribunal had by s 93(2)(c) of the Act power in
circumstances of this nature to “award damages, including damages in the nature of
interest”.
Interest under Supreme Court Act 1995 s 47
[5] On the other hand, in my opinion the tribunal did not have any power under s 47 of
the Supreme Court Act 1995 to award interest. By subsection (1) of that section
there is a power to include interest in a judgment given to “the court” in respect of
any proceedings “in a court of record”. In my opinion the reference to “the court” is
a reference to the expression “court of record” that appears earlier in the subsection,
and the Queensland Building Tribunal was not a “court of record” for the purposes
of this section.2
[6] Apart from the fact that the tribunal was not made a court by the Act, it is not a
court of record. That was traditionally a court the acts and judicial proceedings of
which were enrolled for perpetual memory and testimony, and which had authority
to fine and imprison for contempt: Osborne “A Concise Law Dictionary” (5th Ed
1964) p.96. In Australia the test generally accepted has been the existence of a
power to fine or imprison for contempt or another offence: Ex parte Power; Re
Devereaux (1956) 57 SR (NSW) 253 at 260. The Queensland Building Tribunal did
not have that power; it had only a power to exclude a person from the tribunal
(s 79) or to certify a contempt in writing to the Supreme Court for punishment
(s 80). Assuming therefore that the expression “court of record” in s 47 is to be
given its technical meaning, the Queensland Building Tribunal was not a court of
1 The tribunal made an order for interest but only post-judgment interest. There was no challenge by
either party to that order, but it should be varied to substitute the date of my judgment.
2 Heaven Building Contractors Pty Ltd v Jokarta Pty Ltd [1998] QBT 159.
-- 3 of 15 --
4
record, and I know of no reason to depart from that meaning in the interpretation of
that section.
[7] Subsection (2) permits the power also to be exercised by an arbitrator or umpire;
those terms also have clearly recognised meanings. An arbitrator is normally a
person appointed under a contract to adjudicate on a dispute between the parties to a
contract, although in some circumstances an arbitrator may be appointed by order of
a court. An umpire is a person who is appointed by the arbitrators when there are an
even number of arbitrators, in order to resolve the dispute if the arbitrators disagree
on the appropriate outcome: Commercial Arbitration Act 1996 s 12. In my opinion
this also does not apply to the Queensland Building Tribunal. It may be that the
tribunal had functions which were analogous to those of arbitrators under an
arbitration agreement, in that both are concerned to resolve the dispute between the
parties, but there is a fundamental difference between the basic nature of the two
systems.
[8] Arbitration is essentially based on the contract between the parties, where the parties
have agreed to adopt a particular mechanism to settle disputes between them arising
out of the contract. The tribunal however was a creation of statute, being
established by the legislature for the purpose of resolving disputes within a
particular category of cases which are brought before it by anyone who has the sort
of dispute in respect of which the tribunal has jurisdiction. In my opinion the
position is simply that s 47 of the 1995 Act does not apply. This is unsurprising;
that section was taken from the Common Law Practice Act 1867, s 72. The 1995
Act was simply a consolidation act, and did not take into account recent inventions
such as the tribunal. In my opinion the tribunal had no power to award interest
under s 47 of the Supreme Court Act 1995.
Interest in the nature of damages
[9] It did however clearly have the power to award damages in the nature of interest.
Such damages were discussed by the High Court in Hungerford v Walker (1989)
171 CLR 125, where Mason CJ and Wilson J said at p.143 that a plaintiff should in
principle be awarded compensation which would restore him to the position he
would have been in but for the defendant’s breach of contract or negligence, and
that the plaintiff sustains an economic loss if his damages are not paid promptly.
“The loss may arise in the form of the investment cost of being deprived of money
which could have been invested at interest or used to reduce an existing
indebtedness. Or the loss may arise in the form of the borrowing cost, ie, interest
payable on borrowed money or interest foregone because an existing investment is
realised or reduced.” Their Honours rejected any distinction between a liquidated
claim and an unliquidated claim at p.146. See also p.149.
[10] This is similar in outcome to a mechanism for awarding interest on the amount
payable, although as pointed out by Brennan and Deane JJ at p.152 there is an
important difference in principle between these two situations. The awarding of
damages by way of interest makes it necessary to focus on the particular loss that
the party entitled to be paid money has suffered as a result of the non-payment, and
for that reason it may well be of particular value to a party who can prove some
specific loss (for example, where money has been borrowed to pay for rectification
-- 4 of 15 --
5
works which ought not to have been necessary but for the other party’s breach,
where the interest actually paid on the money borrowed may well be recoverable
under the principle in this case). Because of the reference to the investment cost in
relation to money which does not reimburse specific borrowings, consideration
needs to be given to how the successful party might have deployed the money had it
been paid when it ought to have been paid, that is to say, if the obligation to pay it
was not unjustifiably disputed.
From when interest runs
[11] In the present case relevantly the loss suffered by the appellants was in the form of
diminution of value. It was therefore not a situation where they incurred actual
expenditure, so there can be no question of reimbursement of the consequential
costs of borrowing to reimburse actual expenditure. Rather the position is simply
that they have been deprived of the opportunity cost to invest the damages payable.
In principle damages payable for breach of contract are to place the party in the
same position as if the contract had been performed properly.3 In the present case,
if the contract had been performed properly the appellants on completion would
have been provided with a house with foundations which were not defective.
Because the contract was not performed properly, the appellants received a house
with defective foundations, which was as a result less valuable. In my opinion, that
was a loss which they suffered at the time of practical completion, when as the
tribunal found they ought to have taken possession of the house.4
[12] Strictly speaking the valuation evidence should have been directed to any
diminution in value in the premises at that time. This is different from a situation
where it is appropriate to measure the loss by reference to the cost of rectification
work; in such circumstances, if rectification work is reasonably delayed it will
often be appropriate to assess the damages as at the date when rectification ought
reasonably to have been undertaken, or if it has not yet been undertaken, as at the
date of trial.5 In such circumstances, it may well be appropriate to assess damages
by reference to the cost of rectification as at the date of trial, and then not award
interest.
[13] That however is not the present case. The appellants are essentially receiving
compensation for diminution in value, which was suffered at that time. In principle
therefore they are entitled to interest from the time when they suffered that loss,
although a question arises as to the effect of any change in values between that time
and the time the subject of the agreement as to valuation. The parties proceeded on
the basis that the written agreement was as to the loss in current value; I think that
the written agreement is ambiguous on this, but will assume that it reflects current
values.
[14] Insofar as there is any difference in value between the time when the premises ought
to have been handed over to the plaintiff, and now, as to which there is no evidence,
it is very likely that that is attributable to changes in land value during the relevant
period. The value of improvements is affected by both changes in replacement cost
3 The Commonwealth v Amann Aviation Pty Ltd (1991) 174 CLR 64 at 116.
4 Miliangos v George Frank (Textiles) Ltd [1976] AC 443 at 468.
5 Dodd Properties Ltd v Canterbury City Council [1980] 1 WLR 433.
-- 5 of 15 --
6
(which tends to increase over time) and the increasing effect of a “new for old”
factor, which justifies some deduction from the replacement cost as the premises are
not new, which also tends to increase over time. In these circumstances, it is
tempting to assume that increases in value over time will be attributable to changes
in the value of land rather than improvements, which have not changed (at least for
the better) during that period.
[15] In this case however what is in issue is not the value of the improvements, but the
extent of the diminution in that value because of the deficiencies in the foundations.
That I suspect will be even less susceptible to change over time than the value of
improvements overall. It is in effect what would have to be taken off the price to
make it equally saleable, bearing in mind that the purchaser would be faced with
these problems, which to some extent affected the way in which the house can be
used.6 It may even be the case that a bigger discount would be necessary for this
purpose with a new house than with one which is four years old.
[16] In these circumstances, I am comforted in applying a presumption of continuance,
and on that basis conclude that the diminution in value as agreed, assuming it is a
current diminution in value, reflects the diminution in value at the earlier relevant
date, and on that basis reflects the loss suffered at that time. Putting the appellants
in the same position as if the contract had not been breached, in circumstances
where damages are assessed on this basis, notionally involves giving them
compensation for the reduced value of the premises at the time when the premises
are handed to them.
[17] In these circumstances, it is I think correct to say that the damages are not
reimbursing expenditure which has been incurred in the past, or indeed which will
be incurred in the future. Nor is it the case that the loss will only be suffered in the
future when the house is sold. A person whose property has been devalued has
suffered a loss, even if the loss has not been realised in money.7 The damages are
compensating for a loss which has been suffered in the past, and the damages by
way of interest reflect the loss which the appellants have suffered because of the
delay in payment of the damages. This is the loss that was referred to in
Hungerford v Walker (supra) as opportunity cost, that is to say the effect of being
deprived of money which could have been used to repay borrowings, or invested at
interest: p.143.
[18] Interest should run from the date of breach, that is the date on which the respondent
ought to have provided a house properly built in accordance with the contract but
did not. Although the contractual date of completion was in October 1998 the
tribunal found that practical completion was achieved in accordance with the
contract on 4 March 1999: p.52. The tribunal dealt separately with the question of
damages for delay, and in my opinion therefore it is appropriate to allow interest in
relation to diminution in value by reference to the date of practical completion.
6 It emerged in the course of the evidence before the tribunal that the damages had to take into account
that it would be desirable to avoid landscaping which tended to increase the moisture content of the
soil near the house, the prospect of some minor damage which will have to be repaired from time to
time, a small risk of more serious damage, and any other factor which adversely impacts on the value
as a result of this defect in the foundations.
7 Francis v Wharton [1994] 2 Qd R 584 at 589, 590.
-- 6 of 15 --
7
Assuming that the money has not yet been paid, it follows that the appellants are
entitled to interest for four and a half years at 6.57 percent, an amount of $10,015.
That sum should be added to the amount otherwise payable by the respondent, to
produce a total of $43,890.
Rate of interest
[19] The appellants borrowed money from the Commonwealth Bank to pay for the house
which was being built by the respondent,8 and, having obtained a less valuable
house from the respondent than ought to have been obtained, in my opinion it would
have been reasonable to have used the money, had it been paid as compensation for
diminution of value at the date of practical completion, to reduce the amount of the
housing loan. Accordingly it is appropriate to assess interest by way of damages in
this case in my opinion on the basis of the interest rate charged to the appellants on
the housing loan. The evidence that I have is that that rate was, at least at some
stage, 6.57 percent, and I will allow interest at that rate to reflect the additional
interest the appellants have paid on the housing loan which otherwise would have
been avoided if compensation for the diminution in value had been paid promptly
and at the date of completion.
[20] Had I not considered that this was an appropriate case in which to assess damages
by way of interest by reference to the cost of borrowing money which would to that
extent have been repaid had the damages been paid when the cause of action arose,
but rather assessed damages by reference to the rate of interest at which that money
could have been invested in a secure investment, the appropriate rate would have
been the rate of interest payable on a bank term deposit, and in accordance with the
approach indicated in GPS Power v Gardiner Willis Associates [2001] QSC 35, I
would have adopted six percent for that rate.
Costs
[21] The tribunal never dealt with the question of costs, the appeal being instituted
before that issue had been resolved. The appellants seek the costs of the appeal and
the costs before the tribunal. They submit that the agreed diminution in value is
substantial by comparison with the contract price of the house, being in excess of
60 percent.9 By the date of practical completion the appellants had paid the
respondent under the contract much more than the value of the house delivered. It
was submitted that the issue about the foundations and their inadequacy was the
major issue before the Queensland Building Tribunal, and that it was necessary to
go through a lengthy hearing before the tribunal and a substantial appeal before the
appellants obtained justice in relation to the deficiency in the foundations. It was
noted that the first appellant had pointed out to the respondent that there was a
problem with the foundations even before the slab was laid, in August 1998.10
[22] The appellants also relied on evidence that they were in very modest financial
circumstances, with no significant assets other than this house and land in which
8 Affidavit of Bieto sworn 20 August 2003 para 9: for the rate of interest on this loan, see Exhibit JB4.
9 The contract price was $58,620.
10 Exhibit 56 before the tribunal.
-- 7 of 15 --
8
they were living, and with the first and second appellants (the parents) receiving the
aged pension.11 The house is substantially encumbered in respect of a housing loan
and they have two other loans, money borrowed to pay part of the substantial cost of
pursuing this claim.
[23] On the other hand, the respondent submitted that there had been a number of issues
in the tribunal. So far as the respondent’s claim in the tribunal was concerned, that
was successful and an issue raised by the appellants as to the terms of the contract
was resolved against the appellants. There were a number of other issues where the
appellants were either entirely unsuccessful, or received substantially less than the
amount claimed, and even in relation to the deficiency of the foundations the
appellants claim throughout was that they were entitled to the cost of substantial
rectification works, in effect the cost of demolishing and reconstructing the house
on proper foundations, and they had not succeeded to that extent. There were seven
issues pursued in the appeal, in respect of which the appellants had at best
succeeded on two.
Proceeding in the tribunal
[24] The matter had a substantial history in the tribunal. There had been separate
applications made in the tribunal by the appellants and by the respondent; on
11 June 1999 the applications were joined, with the present respondent having the
carriage of the joined application in the tribunal.12 It was originally listed for
hearing on 15 November 1999 for four days, but on the second day of the hearing
the respondent applied for the appointment of an independent expert which
application was successful, and the hearing was adjourned. The costs of the
adjournment were reserved.13 The tribunal appointed Mr Beale as an independent
expert, and he subsequently gave evidence in respect to his report on 5 September
2000. There were also directions hearings on 6 April 2000, 24 August 2000 and
6 October 2000 before the matter was set down to commence on 16 October 2000.
It then ran for seven days.
[25] The tribunal member who conducted the hearing delivered reasons on 28 March
2001 which ran to 55 pages. The respondent before me was pursuing a claim for
$9,610 as the balance owing under the contract. In relation to that claim, the
appellants asserted that certain extras claimed ought to have been included in the
contract price. It appears that the extras in question came to $1,447,14 and the
tribunal after consideration of the evidence resolved this issue in favour of the
respondent. This issue occupied about nine pages of the tribunal’s reasons, so that it
was not a trivial aspect of the dispute.
[26] The remaining matters in issue before the tribunal were those raised in the
appellants’ cross-claim. Undoubtedly the dispute about the foundations was the
11 Affidavit of Bieto sworn 20 August 2003.
12 Order of the chair of the tribunal 11 June 1999.
13 Order of Member White 17 November 1999 at para 2. It does not appear that on any other occasion
the tribunal made any specific order as to costs of any of the various directions hearings or other
interlocutory steps. Presumably the costs of all those hearings and orders are treated as costs in the
cause.
14 Reasons of the tribunal p.4.
-- 8 of 15 --
9
most substantial issue. Because of the appointment of the independent expert, and
the acceptance by the tribunal of the evidence of that expert, the tribunal member
focused in his reasons on the evidence of that expert and what flowed from it. This
occupied 32½ pages of the tribunal’s reasons.
[27] The tribunal then over the next 10½ pages dealt with the other issues as follows:
(i) Cornices wrong size – this complaint was justified but rectification
involving replastering the house was held to be unreasonable, and $500 for
loss of amenity was allowed.
(ii) Septic tank – cost of supply delivery and installation - claim failed.
(iii) Connection of storm water – claim failed.
(iv) Credit difference in local authority fees – claim failed.
(v) Area surcharge refund – claim failed.
(vi) Connection of power supply – claim succeeded - $425 allowed.
(vii) Credit for variation in garage – claim failed.
(viii) Rent to November 1999 – claim succeeded in part, $2,520 allowed to
March 1999.
(ix) Petrol costs to November 1999 – claim succeeded in part, $2,540 allowed
to March 1999.
(x) Rent and petrol costs for the future – claimed failed.
(xi) Damages for time and inconvenience visiting site to attend to animals and
trees – claim failed.
(xii) Loss of amenity expectation and enjoyment – claim succeeded - $7,000
allowed.
(xiii) Damages for anxiety and distress – claimed failed.
[28] Overall therefore a total of $12,985 was allowed in respect of the five claims which
succeeded in whole or in part. These were set off against the respondent’s claim,
which produced the balance of $3,375 in favour of the appellants.
The appeal
[29] The appeal was argued on 5 February 2002. I delivered reasons for judgment
extending to about 28 pages. After some introductory remarks I dealt, on just over
-- 9 of 15 --
10
two pages, with the question of responsibility for the design of the foundations, in
respect of which the appellants were successful on the appeal. I then dealt with the
suitability of the design, essentially by way of background; this aspect was found in
favour of the appellants by the tribunal and that was not disputed. I then noted that
the findings of defective construction were not disputed before me, before passing
to the question of damages which then occupied 15 pages. On this issue the
appellants failed to persuade me that they were entitled to damages measured by
reference to the cost of demolition and reconstruction of the house, or the (greater)
cost of engineering works to rectify the deficiencies in the foundations of the
existing house, but did persuade me that they were entitled to damages based on
reduction in value of the house because of the defects in the foundations. I was not
able to assess that reduction at the time, but suspected then that it would be
substantial, and the subsequent agreement (based on expert valuation evidence, I
understand) vindicates my suspicion and also demonstrates that in respect of this
issue the appellants have ultimately succeeded in obtaining substantial
compensation.
[30] I then turned to other matters argued on the appeal, in respect of all of which the
appellants failed; this occupied just under eight pages of my reasons, although I
think it is fair to say that only one of these, involving an issue of construction of the
terms of the contract between the parties, was a matter which required any detailed
analysis or presented any great difficulty in the context of an appeal of this nature.
That particular point required some careful consideration; resolution of the other
issues raised on the appeal I found essentially straightforward.
[31] There were no relevant offers, and at the end of the day the appellants have obtained
substantial relief in relation to serious deficiencies in the design and construction of
the home. The deficiency in design of the foundations, although a matter for which
the respondent is contractually responsible, did not involve any moral fault on the
part of the respondent, given the finding of the tribunal that the soil testing
undertaken before construction commenced (and before the foundations were
designed) was reasonable in extent and in fact failed to identify the particular
problems the site posed. But the significant deficiencies in the construction of the
foundations identified by the tribunal were certainly the fault of the respondent,
through its subcontractors and because of the failure to exercise proper supervision,
even though its attention had been drawn to the matter specifically by Mr Bieto, and
this aspect of the respondent’s position does not excite any sympathy.
[32] Certainly the claim in relation to the foundations was the substantial matter argued,
involving much more evidence and difficulty, and much more money, than any of
the other issues. On the other hand there were a number of other separate issues
pursued, in respect of most of which the appellants were unsuccessful. To some
extent this would have made the proceedings longer and more complicated than
they needed to be, both the proceedings in the tribunal and on the appeal. Given
that the appeal was argued over only one day, however, it is difficult to see that the
inclusion of these additional issues on the appeal would have had any real effect on
the costs of the appeal, even though they certainly had some effect on the amount of
work that it was necessary for me to do in order to prepare a judgment on the
-- 10 of 15 --
11
appeal.15 It is however more difficult for me to assess the extent to which the costs
in the tribunal would have been increased by the inclusion of issues on which the
appellants were unsuccessful, but I would be surprised if it did not lead to some not
insignificant increase in the costs before the tribunal.
[33] The respondent relied on two propositions. The first was the general approach in
relation to the taxation of costs where there was a claim and a counter-claim laid
down in Smith v Madden (1946) 73 CLR 129 at 133-4, that the costs of the counter-
claim were only those associated with the extra issues raised by the counter-claim.
The other was that it was reasonable to require that a litigant who had succeeded
only upon a portion of his or her claim should bear the expense of litigating the
other portion or portions: X & Y v Pal (1991) 23 NSWLR 26 per Clarke JA. On
this basis the respondent submitted that it should receive the costs of the claim and
should pay a proportion of the costs of the cross-claim, bearing in mind that on a
number of issues the cross-claim of the appellant were unsuccessful. In relation to
the appeal, it was submitted that the appellant succeeded only in two of the seven
grounds argued, so the appellant should not receive all its costs of the appeal.
[34] In my opinion the respondent’s approach is unduly technical, and does not take
sufficient account of the extent to which the issues in relation to the foundations
dominated the proceeding before the tribunal, and the appeal, both in terms of the
amounts involved, the technical complexity of the issues raised, the time taken, and
the dominance of these issues within the judgments of the tribunal and this court of
appeal. It also seems to me that the traditional approach to apportioning costs
between a claim and a cross-claim is not appropriate in this case, partly because two
separate claims were originally consolidated by the tribunal, and the outcome as to
costs should not in my opinion be significantly affected by the fact that the tribunal
chose to give carriage to the consolidated proceeding to the respondent rather than
to the appellants. In addition, the statute encouraged the tribunal to resolve issues
without formality and technicality.16 It is also necessary to have regard in relation
to costs to the specific provisions of s 61 of the Act, particularly subsections (4) and
(5).
[35] The approach of a court to questions of costs in circumstances where there are a
number of issues in a trial and each party succeeds on some of them was discussed
by the Full Court in Colburt v Beard [1992] 2 Qd R 67, where there was a
preference for assessing costs by reference to heads of controversy, and in a way
which avoided complicated forms of taxation which would follow if costs were
awarded in respect of particular issues in a technical sense. That approach was
endorsed by the court in Thiess v TCN Channel 9 Pty Ltd (No 5) [1994] 1 Qd R 156
at 208, and applied by the court in that case where consideration was given to the
identification of substantial issues in controversy, taking into account the time and
effort devoted to them, their importance in the context of the overall litigation, and
the extent to which controversy in relation to them was resolved in favour of one or
the other party, before finally formulating a practical and simple order, that one
party pay one third of the costs of the trial of the other party: p.210. The court also
noted that in circumstances of this nature it was important to be cognisant of the
15 Fortunately for the parties, they are not charged court fees by reference to the time that I spent
preparing reasons for judgment.
16 Queensland Building Tribunal Act 2000 s 41(3), (4).
-- 11 of 15 --
12
way in which the costs of each party had to be borne as a result of the order made. I
am not aware of any later decisions which authoritatively reject this approach. It
seems to me that, in view of the essentially practical approach of the Full Court in
Thiess and Colburt, these authorities provide useful guidance in the context of a
proceeding under the Act.
[36] Approaching the matter in that way, I consider that the appellants ought to have
been successful before the tribunal in relation to the matter which was the major
matter in controversy between the parties before the tribunal, albeit not the only
matter. Although the appellants ought not to have succeeded on their claims as
formulated before the tribunal, they ought to have received substantial damages for
breach of contract, and in this respect it is significant to note that the respondent’s
position was not that the appellants were entitled only to damages on the basis of
diminished value, but that the appellants were not entitled to any significant
damages in respect of the state of the foundations. Had the issue about the
foundations been the only matter in contention the appellants would have certainly
succeeded in relation to that issue to a sufficient extent to justify their receiving all
of their costs. There was in addition some success in relation to some of the other
issues raised, although in respect of most of them the appellants were
unsuccessful.17
[37] In my opinion in the context of this case it is correct to identify the dispute about the
foundations as the central, dominant issue of the litigation, and to treat the outcome
in relation to that issue as the starting point in relation to the question of costs. This
is in contradistinction to using the outcome in the respondent’s claim as the starting
point in relation to costs, the approach adopted in Smith v Madden. I do not
consider however that the other issues which the appellants pursued, on which they
were unsuccessful before the tribunal, were so insignificant or so closely connected
with the central issue that no regard should be had to them.18 I think that in all the
circumstances of the case it is appropriate to have some regard in the costs order to
the fact that there were a number of issues run in respect of which the respondent
was forced to incur costs, and in respect of which the appellants were unsuccessful.
I consider it unjust to the respondent simply to order that the respondent pay all of
the appellants’ costs of the proceedings before the tribunal.
[38] Bearing in mind the approach adopted in Thiess, I consider that it is appropriate to
make allowance for this factor by reducing the costs payable to the appellants in the
tribunal. On that basis I will order the respondent to pay three quarters of the
appellants’ costs of the proceedings in the tribunal. Consistent with what I
understand the practice of the tribunal ordinarily was, those costs are to be assessed
on the District Court scale where the amount recovered was in excess of $50,000
(bearing in mind the difficulty and technical complexity of the issues raised in
relation to the foundations).
[39] With regard to the reserved costs, I have not been able to find any expression of
reasons for the costs being reserved.19 It appears that the application for the
17 These were separate issues, lacking a common substratum of fact: cf Inn Leisure Industries Pty Ltd
v D F McCloy Pty Ltd (1991) 28 FCR 172.
18 The exception was claim (xiii) in [27], which was consequential on the central claim.
19 This issue was not addressed specifically in argument.
-- 12 of 15 --
13
appointment of an independent expert was only made after the hearing had
commenced, and was made by the respondent, and as a result of the success of that
application the balance of the hearing had to be aborted. That circumstance
suggests that the respondent should pay those reserved costs. It is not clear to me
whether in the long run the appointment of an independent expert saved costs
overall, or increased them. However, I really do not know very much about the
circumstances under which the order came to be made on 17 November 1999, and it
may well be that the costs of the adjournment as such will not be very great. In all
the circumstances I will not deal with the reserved costs differently from the costs of
the proceeding before the tribunal generally, so the costs order in relation to the
tribunal in favour of the appellants will apply to the reserved costs as well.
[40] There is one matter I should specifically mention. The appellants relied on their
financial circumstances as a factor favouring an order for costs in their favour. I
have not been able to find any authority to support the proposition that this is a
relevant consideration in relation to the discretion as to costs. The closest I can find
is one case20 where the court apparently took into account in relation to costs that a
party was disabled by poverty from bringing forward witnesses to support a case.
Nothing of that kind occurred here, or at least, nothing of that kind was relied on on
behalf of the appellants. In my opinion this is not a relevant consideration, and I
have not taken it into account in relation to the question of costs.
[41] With regard to the costs of the appeal, I am not persuaded that those costs were
significantly increased by the inclusion of issues in respect of which the appellants
were unsuccessful, and I am not persuaded to apportion the costs of the appeal.
Relatively little attention was given to the other issues either in oral argument or
written submissions. I order the respondent to pay the appellant’s costs of the
appeal to be assessed.
[42] Ordinarily the costs if not agreed would have been assessed, as to the proceedings in
the tribunal, by the tribunal, and as to the proceedings in the court, by a deputy
registrar. The tribunal however has since been abolished,21 and it does not appear to
me to be open to remit the question of the assessment of costs to the tribunal.
Bearing in mind that the costs are to be assessed as if the matter was a proceeding in
the District Court, the practical way to deal with the matter is for this court to assess
those costs, and for that purpose I will delegate the assessment to a deputy registrar.
For practical purposes therefore both assessments if not agreed will be undertaken
by a deputy registrar in the usual way. I hope however that the parties can reach
some agreement in the matter to avoid incurring further legal costs on this issue.
Respondent’s application under the Appeal Costs Fund Act
[43] The respondent sought an indemnity certificate in respect of the appeal, on the basis
that the appeal succeeded on a question of law, and it was appropriate to grant the
certificate because the appeal had succeeded in relation to an approach adopted by
the tribunal, or rather the failure of the tribunal to go on and deal with the damages
on the correct basis. The respondent’s case was that the appellants were not entitled
20 Hasker v Summers (1884) 10 VLR (E) 204.
21 Commercial and Consumer Tribunal Act 2003.
-- 13 of 15 --
14
to damages at all, but it was not a case where the respondent had been contending
for a position which the tribunal adopted but the court concluded was wrong. This
position was supported by counsel for the appellants, and I think there is some
justification in it.
[44] I have previously expressed the view however that it is not open to this court to
issue a certificate under s 15(2) of the Appeal Costs Fund Act, because the
Queensland Building Tribunal is not a “court” as defined in s 4 of that Act. That
definition is wide enough to include something like the tribunal but only if “there is
an appeal to a superior court of law or which may state a case for the opinion or
determination of the superior court on a question of law …” There was an appeal
from the tribunal to the District Court under s 92, and the tribunal had power to state
a case on a question of law for the opinion of the District Court under s 91 of the
Act. In Anderton v Parkes Horticultural Services Pty Ltd (Appeal 2790/96,
15.11.96, unreported)22 I held that the term “superior court” was used in its
technical sense, which did not include the District Court: Stevens v Trewin [1968]
Qd R 401 at 417. I was concerned that, unless the expression “superior court” was
given its technical sense, the word “superior” was unnecessary, since, if the issue is
simply where the court sits in the hierarchy of appeals, any court to which there was
a right of appeal from a board or other body would be regarded as “superior” to that
body in the terms of that hierarchy. I was also concerned that there might be
difficulties with the definition in s 4 if the term “court” in the definition of “court”
in that section was itself to be defined in accordance with that definition.
[45] Subsequently his Honour Judge Robin, in Queensland Building Services Authority v
Morris (Appeal 3319/97, 24.10.97, unreported) also considered the question and,
with some misgivings, concluded that the expression “superior court” was not used
in s 4 in the technical sense, but was used in a more informal sense, which would
include the District Court. Accordingly his Honour allowed a certificate under s 15
in relation to an appeal to the District Court from the Queensland Building Tribunal.
I understand that Judge Robin’s decision has subsequently been followed on other
occasions. I concede that his construction is one which may produce the result that
the legislation will be thought to work better than it otherwise would, as I
recognised in Anderton. His Honour also pointed out a number of other Queensland
statutes where the term “superior court” was used other than in its technical sense,
and drew attention to the interpretation of “superior contractor” adopted in Hewitt
Nominees v Commissioner for Railways [1978] Qd R 256.
[46] One consideration which I think favours the interpretation adopted by Judge Robin
is that, if the term “court” is interpreted as I had interpreted it previously, it seems a
little curious that s 15 gives a power both to the Supreme Court and to the District
Court to issue an indemnity certificate in respect of an appeal to that court “against
the decision of a court,” which the provision in subsection (1) dealing with the
Supreme Court would take full advantage of the definition of “court” (the Supreme
Court being of course a superior court) but the provision in subsection (3) dealing
with the District Court, although using the same term “court”, would have little
scope for the operation of the extended definition of that term in s 4, because, apart
from appeals to the District Court from a Magistrates Court, there would not be
many other occasions when the District Court would deal with an appeal from a
22 My decision on the merits of that appeal appears at (1996) 17 Qld Lawyer R 48.
-- 14 of 15 --
15
board or other body or person within the extended definition of “court”. If there
was an appeal from a board or other body or person to a superior court in the
technical sense, that is the Supreme Court, it is unlikely that the appeal would be
brought (or even could be brought) to the District Court.23 The use of the same term
in subsection (3) suggests that the legislature had in mind that the extended
definition of that term in s 4 would apply to appeals to the District Court as well as
to appeals to the Supreme Court, and that in turn suggests that the legislature was
not using the expression “superior court” in a technical sense.
[47] It may be, as well, that in my decision in Anderton I was assuming a greater degree
of technical precision in the drafting of statutes than my experience since that time
would lead me to attribute to the legislature of Queensland.
[48] In the light of these considerations, the persuasive exposition of his Honour Judge
Robin in Morris, and the desirability of judicial comity on this issue, I will no
longer follow my earlier decision in Anderton, and prefer to follow the decision in
Morris. On that basis, I am now persuaded that there is jurisdiction to give a
certificate under s 15(3) of the Appeal Costs Fund Act where an appeal against a
decision of the Queensland Building Tribunal to the District Court on a question of
law succeeds. That is what has occurred in the present case; I concluded that it was
an error of law for the tribunal to fail to go on to award damages on the proper
basis. I consider that, in accordance with the ordinary approach to the exercise of
the discretion under s 15, it is appropriate in the circumstances of this case to grant a
certificate to the respondent in relation to the costs of the appeal, and I do so. This
of course will not affect the costs of the proceeding in the tribunal.
23 At one time it was possible to have an appeal under the Justices Act from the decision of a magistrate
either to the District Court under s 222, or the Supreme Court under s 209, but that choice has for
some time been removed, and in any case the Magistrates Court is clearly a court.
-- 15 of 15 --
Official source: https://www.sclqld.org.au/caselaw/QDC/2003/307