Council of the City of Caloundra v Beerwah Pine Pty Ltd [1991] QSC 97
I
i
I
{
!
I I
)
10
30
!~R·, i=•-:-11
"'=O r.--:;;,n, ·
r_:-;:-,: ''t.:~:,
- 1
,_
,Ur~-
..._, ..
_,
•
-•'' •,.,.
• _;
I C:.:it!d Repcrt::1: ~·:~1rt:;au
i Dc:te,
:J..,/
S-
I 9t
__
....__
_______
,.,
IN THE SUPREME COURT OF QUEENSLAND
CIVIL JURISDICTION No. 385
of
1991
BEFORE MR. JUSTICE LEE
BRISBANE,
11
APRIL
1991
(Copyright
in this transcript is
vested
in
the
Crown.
Copies
thereof
must
not be
made
or sold without the written authority of the
Chief Court Reporter,Court Reporting Bureau.)
BETWEEN:
COUNCIL
OF THE
CITY OF
CALOUNDRA
-and-
BEERWAH
PINE PTY
LTD
JUDGMENT
Plaintiff
Defendant
HIS
HONOUR:
On
the question of the application
by
counsel
for the
defendant
to
read
and
file
an
affidavit
before
me
before
I
hand
down
judgment, an
affidavit
which
apparently
has
only
just
been
prepared,
this
was
objected
to
by
counsel
for
the
plaintiff
on
the basis
that
it
deals
with matters
argued
before
me
on
the
hearing,
and
also
on
the basis
that
depending
upon
the decision
which
I am
about
to deliver,
it
may
be
that
10
20
30
40 40
50
60
the
defendant could
bring
a
further application
consequent
upon
that
decision,
if
that
was
thought necessary
by
it.
In
the
circumstances,
I
decline
to
receive the further
affidavit
material
at this late
stage,
and
particularly
having
regard
to
the
fact that
the
proceedings
are
interlocutory in
nature.
For
the
reasons
which
I am
about
to
publish,
and
in
the
exercise of
my
discretion,
I
have
decided
on
balance
that
the
injunction
as
sought should
now
be
declined
and
the
matter
allowed
to
go
to
trial
as
speedily
as
possible.
Govt. Printer, Qld.
1
50
60
-- 1 of 33 --
10
20
30
40
50
60
----~- -----
-------------
---
Accordingly, the application is dismissed.
Costs of and
incidental to the motion are reserved.
The
action
is certified
as one which should be
tried
speedily. Further order as follows: defence and
counterclaim
within seven days;
reply
and answer
within three
days
10
of
delivery of the
defence
and
counterclaim; each
party to
serve
and
file
an
affidavit
of
documents
within three
days
after
delivery of the reply
and answer;
inspection within three
days
thereafter;
leave to either
party to deliver interrogatories
for
examination
of the other within
three
days
after
20
n.
inspection;
answers
by
affidavit
within
seven days
of delivery;
abridge the
time
for the
·
return of
a
duly tendered signed
certificate
of readiness
to three
days
after
delivery.
Order
accordingly.
I
publish
my
reasons.
Govt. Printer, Old.
2
(~_)
30
0
40
(J'
\.
50
60
I
-- 2 of 33 --
l
1.
1.
I,
t
I
[
1.
I,
ll
t
l
1,
II
1:
n
C)
()
IN THE SUPREME COURT
OF QUEENSLAND
Writ
No. 385
of
1991
Before
Mr.
Justice
Lee
BETWEEN:
COUNCIL OF THE CITY OF CALOUNDRA
Plaintiff
AND:
BEERWAH
PINE PTY. LTD.
Defendant
JUDGMENT
- LEE
J.
Delivered the 11th
day
of April,
1991
CATCHWORDS:
Q
Counsel:
Mr. G.H.
Brandis
for
applicant/plaintiff
Mr.
R.J.
Douglas
Q.C.
respondent/defendant
and
J.D.
Batch
for
Solicitors:
Watkins
Stokes,
town
agents
for
Heiner
&
Doyle
for
applicant/plaintiff
Carberry
&
McGuire
for
resp_ondent/defendant
Hearing
date:
12th
March,
1991
-- 3 of 33 --
I .
[
l
l
l
1.
I.
I,
I.
r
),
I.
1.
1.
I
f
r
t
n
0
IN THE SUPREME COURT
OF QUEENSLAND
Writ
No. 385
of
1991
BETWEEN:
COUNCIL
OF THE CITY
OF CALOUNDRA
Plaintiff
AND:
BEERWAH
PINE PTY. LTD.
Defendant
JUDGMENT
- LEE
J.
Delivered the 11th
day
of April,
1991
The
plaintiff,
the
Council
of
the City of
Caloundra,
by
notice of
motion
filed
4th
March, 1991,
seeks
an
order
that
the
defendant,
Beerwah
Pine
Pty.
Ltd. (Receiver
and Manager
appointed)
by
itself,
its
servants or agents,
be
restrained
until
the
trial
of
this
action or further
earlier
order
from
causing
nuisance
by
reason
of
the
emission
from
its
property
at
Back
Creek
Road, Beerwah
in
the
State of
Queensland,
of
levels
of
noise
in
excess
of
maximum
levels set
out
in the
schedule
to
the
statement
of
claim served with the
notice of
motion.
The
schedule
to
the statement
of
claim
shows
three
different
maximum
levels of
noise
depending
upon
the
time
of
day
or night
or
on
Sundays and
public holidays
when
the defendant
operates
its
timber
mill
on
the
above
property.
By
the
writ (also
issued
on
4th
March,
1991)
and
the
statement
of
claim,
the
plaintiff
claimed
two
types
of
injunctions:-
-- 4 of 33 --
2
(1) an injunction to restrain the defendant from
carrying
out
activities in
and about the property so as to
cause noise levels to
exceed the levels set out in the
schedule to the statement of claim;
and
(2)
a
mandatory
injunction requiring the defendant
to take
all
such
steps as are necessary
and
suitable to
ensure
that
the level of noise
does not exceed
the
above
levels,
including undertaking the noise
abatement
measures.
Some
dispute
occurred over
what
precisely the
plaintiff
was
claiming
in
this particular
notice of
motion. Counsel
for the
plaintiff
submitted
that
care
had been
taken
to
seek
in
the
notice of
motion, only
an
injunction prohibiting
excessive noise,
and
not
a
mandatory
injunction
compelling
the defendant
to
abate
the noise as
also
claimed
in
the
writ
and
statement
of
claim.
He
further
submitted
that
the
plaintiff's
claim
for interlocutory
relief
was
based
upon
nuisance,
a
breach
of the
by-laws
of the
Council,
and
a
breach
of
a
deed between
the
parties
dated
1st
June,
1989.
0
CJ
0
It
was
also
submitted
that
this
case involved
a
public
()
nuisance
so
that
the
principles referred to in
the
judgment
of
the
Privy
Council
in
Associated Minerals Consolidated Ltd. v.
Wyong
Shire
Council
(1974)
48
A.L.J.R.
464
at
470
applied
viz.
that
by
reason
of
s.
52(8)
of the
Local
Government
Act 1966-1984,
the
plaintiff
was
seeking
relief
in
the public
interest
so
that
it
is
necessary
to
base
the granting
or
denial of equitable
relief
on
broader
grounds
than
would
normally apply
as
between
private
citizens.
This
means
a
weighing
of
injury to
the public
-- 5 of 33 --
l
I
(
1.
1.
L
L
t
1.
1.
I
f
f
I,
t
I
f
C)
0
3
interest
by
denial of relief, its
extent
and degree of
irre·mediabili ty, against
any
loss
which
the defendant
may
have
sustained
by
the
plaintiff
standing by.
Counsel
further relied
on
the statement in
Doherty v.
Allman
and
Dowden
(1878)
3
A.C. 709 by Lord
Cairns
at
719-80
to the
effect that
when
a
negative
covenant
is
broken (as
opposed
to
an
affirmative covenant), there
was
a
well-settled practice that
a
Court
of
Equity
had no
discretion to exercise
because
an
injunction
does
nothing
more
than give sanction of the process
of the
Court
to
that
which
is
already in the
contract
between
the
parties,
subject to
the
subsequent
development
of the
law
on
the
notion
of the balance
of
convenience.
He
further
submitted
that
the
jurisdiction to
award
damages
ought
to
be
exercised
only
in
very
exceptional circumstances
where an
actionable
nuisance
was
continuing: see
Shelfer
v. City of
London
Electric
Lighting
Co.
(1895]
1
Ch.
287;
Kennaway
v.
Thompson
(1981]
1
Q.B. 88
at
92-93.
According
to
the
submission,
it
follows
from
these cases
that
the
plaintiff
was
entitled
to
the
interlocutory
relief
sought.
Senior counsel
for
the
defendant submitted
that
even
if
the
plaintiff
could
rely in
this
motion
on
an
alleged
breach
of
covenant,
the
covenant
in
question
was
a
positive
one
and
not
to
refrain
from
doing something, so
that
Doherty
v.
Allman
was
inapplicable.
However,
he
submitted
that
the
application
was
framed
only
a
nuisance
which
was
the
only claim
the
defendant
was
required
to
meet on
this
application
and
that,
regardless
of the
way
the
plaintiff
advanced
its
application,
it
was
in fact
seeking
a
mandatory
injunction
which,
he
submitted,
required
a
much
more
stringent
test
referred
to in
the decision of
Gibbs
-- 6 of 33 --
4
C.
J. in State of Queensland v. Australian Telecommunications
Commission (1985)
59
A.L.J.R.
562
at
563 where His Honour
referred to the
House
of
Lords
decision in
Redland
Bricks Ltd.
v. Morris [1970] A.C. 652
and
a
passage
in Halsbury's
Laws
of
England
vol.
24
para.
948
to the
effect that whilst
a
mandatory
injunction
can be
granted
on an
interlocutory application as well
as
at
the hearing, in the
absence
of special
circumstances
it
will
not
normally be
granted.
See
also the
passage
cited
by His
Honour from
the
judgment
of
Megarry
J.
in
Shepherd
Homes
Ltd. v.
Sandham
[1971]
1
Ch. 340
at
351
as
follows:-
"
on
motion,
as
contrasted
with the
trial,
the
Court
is
far
more
reluctant to grant
a
mandatory
injunction
than
it
would be
to grant
a
comparable
prohibitory injunction.
In
a
normal
case the
Court
must,
inter alia,
feel
a
high degree
of
assurance
thatat
the
trial
it
will
appear
that
the injunction
was
rightly
granted;
and
this is
a
higher standard than
is
required for
a
prohibitory injunction."
Counsel
for the
plaintiff
in reply referred to the decision
of Carter
J.
in Gillespie
v.
Whiteoak [1989]
1 Qd.
R.
284
where
His
Honour
followed
State
of
Queensland v.
Australian
0
0
0
Telecommunications
Commission
(supra)
and
Shepherd
Homes
Ltd. v.
Sandham
(supra)
in his
·
conclusion
that
"a high degree
of
(J
persuasion"
had been
satisfied
on
the
facts
before
him.
Counsel
also
submitted
that
various
decisions of the
Federal
Court
had
held
that
no
different
test
applies to
each
type
of
injunction
and
that
even
if
a
mandatory
injunction
was
in fact
sought,
the
test
of
a
"high degree
of persuasion"
was
satisfied
in
this
case.
His fundamental
submission
however
was
that
a
mandatory
injunction
was
not being
sought
but only
a
prohibitory injunction
in
accordance with
the
terms
of the
notice of
motion which
in
substance
follows
the
first
claim
in
the
writ
and
statement of
f,
-- 7 of 33 --
1.
I_
I~
1.
L
1.
l
l
l
l
I.
l
5
claim.
No
application
was made
to
amend
the notice of motion
to
allege
a
breach of the by-laws or
a
breach of the deed of 1st
June, 1989.
It is
necessary to refer to the history of the matter.
For
some
years
prior to
26th
May,
1988,
a
substantial
saw
mill
had been conducted on
the subject land and
that
use
was
an
existing
lawful
non-conforming use under
the
plaintiff's
town
planning
scheme.
On
the
above
date, the defendant applied to the
,'~ plaintiff
for rezoning
of the land
consisting of
1.103 ha.
from
the "rural"
zone
to the "special
purposes
-
timber
mill,
timber
Q
products
and
associated
facilities
zone".
The
reason
for the
application
was
that
the defendant wished
to
expand
its
operations, construct
new
buildings
and
install
new
machinery.
This
also
involved
building
and
ancillary applications to the
plaintiff.
For
some
time
prior
to the
above
date,
complaints
had
been
made
by
local residents
concerning
noise, dust
etc.
emanating
from
the land.
It
appears
from
the
affidavit
of
Barry William
Sands,
consulting engineer
filed
12th
March,
1991
that
the
mill
had
operated
on
the land
for
a
considerable
period
when
the
adjoining
Old
Bruce
Highway was
the
main
North Coast
highway
carrying
a
constant
and
considerable
volume
of
heavy and
noisy
traffic
which
tended
to
overshadow any
noise
produced
by
the
mill.
It
appears
from
his
affidavit,
although
the
timing
is
not
precise,
that
after
the
new
Caloundra By-pass
Highway was
opened
a
few
years
ago,
thus
leaving the
former
Old
Bruce
Highway
as
a
substantially quieter local
scenic
road,
the noise
level
of the
highway
dropped
substantially
with
the
practical
result
that
to
-- 8 of 33 --
6
local listeners the noise of the mill then seemed
to
be more
acute
and excessive, hence the complaints in recent years, an
unfortunate result
not only for the residents but also for the
defendant.
As a
result, there
has been
a
long period of
negotiation
between
the
plaintiff,
the defendant
and
the
Department
of
Environment and
Heritage ("the
Department")
followed
by
confrontation including prosecutions
launched
by
the
plaintiff
against the defendant
in the Magistrates
Court
and
now
this
proceeding.
The
complaints
from
residents
were
apparently
made
to the
defendant
who
appears
to
have
taken
certain
action
and
incurred
expense
since
1987
in
an
attempt
to
abate the noise, but
unfortunately
not
to
the apparent
satisfaction
of
some
local
residents.
The
plaintiff
commenced
receiving
complaints
early
in
1988.
So
also
did the
Department
as appears
from
the
affidavit
of Peter
Charles
Justin
Overton,
the
Senior
Environmental
Officer of
that
Department,
filed
4th
March, 1991.
Mr.
Overton took
noise readings
in
March 1988
followed
by
discussions
with
management
of the
defendant
in
March/
April
1988.
By
letter
19th
May
1988
the
Department wrote
to
the
defendant
recommending
maximum
noise
levels,
the
same
as those
which
appear
in
the
first
column
of the
schedule
to
the
writ
and
statement
of
claim. Further
readings
on
21st
June,
1988 showed
that
the noise
level
was
no
lower
than those
revealed
earlier.
On
8th July,
1988,
the
Department
by
letter
provided
to
the
plaintiff
the
table
of
maximum
noise
levels
which
are
those
adopted
by
the
plaintiff
as
one
of
the conditions
for granting
its
approval
to
0
C)
0
(J
-- 9 of 33 --
1.
I~
I.
1.
1.
1.
l
ll
l
1,
t
7
the defendant's application for rezoning (see below
-
and para.
6
of
Mr.
Overton's affidavit).
Soon
thereafter the
plaintiff
approved
the defendant's
application for rezoning, subject to certain conditions including
conditions as to
air
pollution
and
noise levels.
By
letter
dated
13th October,
1988,
the
plaintiff
wrote
to the
Department
advising
that
the rezoning
was
recently
approved
by
the
plaintiff,
one
of the conditions being
maximum
levels relating
·~
to
air
pollution
and
noise emission.
The
letter
also referred
to "significant
number
of complaints"
relating to the foregoing,
indicating the
fact that
it
had
co-operated with the defendant
in granting building
approval
for
sound
amelioration
measures,
and
requested the
Department
to investigate
the
problem
as
early
as
possible
with
any
intended
action
consequent thereon~
The
letter
indicated
that this
matter
had
been an ongoing
source
of
complaint
and
was
"still
...
of
grave concern
to joining
owners".
The
plaintiff
not unreasonably
was
then
content
to
let
the matter
be
resolved
by
the
Department
with
appropriate
action
pursuant
to that
Department's
statutory
powers
under
the
Noise
Abatement
()
Act.
On
25th October,
1988
(ex.
C
to
the
affidavit
of
John
Raymond
Smith,
town
clerk to
the
plaintiff
filed
4th
March,
1991),
the
plaintiff
wrote
to
the
defendant
after
expiry
of the
objector
appeal
period,
no
objector
having appealed
against
the
application
for
rezoning.
The
letter
at
p.
5
indicates
that
there
had been
some
10
objections to
the
initial
application.
The
letter
in
its
terms
advised
that
the
plaintiff
had
confirmed
its
previously
deemed
decision
to
support the
application to
the
-- 10 of 33 --
8
Minister for amendment to the scheme as proposed, subject to the
previously nominated conditions as listed in the letter. These
included the entry into a binding agreement with the plaintiff
before submission of the application for rezoning for ministerial
approval.
The agreement was to bind the defendant to development
conditions including - development in accordance with drawing no.
2496; submission of a cash bond or bank guarantee to secure the
performance "of all works external to the subject site", the Q
actual amount to be determined by the plaintiff upon preparation
of detail estimates of required works; completion of specified
road works; provision of ingress and egress to Back Creek Road
in accordance with the plaintiff's minimum requirements;
provision of a 1.8 metre high solid timber, a.c or concrete fence
along Back Creek Road; application to be made to the appropriate
authorities to obtain permission to occupy that part of the road
0
reserve over which buildings had been partially erected; a Q
condition regarding parking of vehicles in the road reserve;
provision of a sealed parking area; maintenance of noise levels
measured on FAST response at any affected residence so as not to
exceed the levels specified in the letter (being identical with
those contained in the writ and statement of claim and as
furnished to the plaintiff by Mr. Overton on 8th July 1988) . The
following then appeared after condition (i) as to noise levels:-
"To achieve these levels, the following measures are
to be taken:-
( i) dri-ers and wood chippers are to be
acoustically treated Q!: adequately enclosed.
(ii) the debarking machine and circular saws are to be
adequately enclosed.
CJ
-- 11 of 33 --
I
[
l
1.
I.
l
I.
l
lt
l
l
I
[
with
9
(iii)
endloaders on
the site are to be modified using
high insertion loss modifiers".
A
further condition required
air
emission levels to
comply
the requirements of the
Department. Also
building
approvals
were
to
be
obtained for
all
unauthorised
and proposed
work
with
a
building application for unauthorised
work
to
be
lodged
prior to the application being forwarded
to the
Department
on
Local
Government
for Ministerial
approval.
Compliance
with
the
above
conditions necessarily
involved the lapse of
a
considerable period of time,
the incurring of considerable
expenditure
by
the defendant, compliance with
local authority
and
(J
other
statutory
requirements
and
consents,
and
a
degree
of
co-operation
between
the
plaintiff
and
the defendant with regard
to
approvals
etc.
The
letter
further
advised
the
defendant
of
its
right
of
appeal
to
the
Local
Government
Court
against
the
plaint.:i,.ff'
s
decision in
relation
to
the conditions
nominated
in
the
letter.
The
letter
also
acknowledged
receipt
of
a
submission
on
behalf
of the
defendant
by
Chris
Schamburgk
Consul
ting
Pty.
Ltd. seeking
Q
amendments
to
the conditions regarding
completion
of
road
works
and
maintenance
of
noise
levels.
The
letter
indicated
that
these
matters
were
receiving consideration
and
that
the
defendant
would
be
advised
of
the
plaintiff's
decision
at
the
earliest
convenience.
The
material
does
not
disclose
the
extent of
the
plaintiff's
consideration
of
and
its
decision
on
those matters
or
whether
and
by
what
means
or
when
its
decision
(if
any)
was
conveyed
to
the
defendant.
It
must be
taken,
however,
from
what
follows,
that
the
plaintiff
did not
amend
or
vary
the
specified
noise
levels.
Further
discussions
were
held
between
Mr.
Overton
and
the
defendant
and on
14th
November,
1988
the
Department
wrote
again
-- 12 of 33 --
10
to the defendant (ex.
B
to
Mr.
Overton'
s
affidavit),
acknowledging
that certain noise abatement work had been
carried
out
by
the defendant but pointing out that this
work was
not
sufficient or satisfactory for residents during the day.
A
programme
of
abatement measures and
its
timetable
was
requested
by
30th
November, 1988,
failing
which
it
was
pointed out
that
a
reference
would be
made
to the
Noise Abatement
Authority for
consideration
under
the
Noise
Abatement
Act.
By
letter
24th
November, 1988
(ex.
C
to
Mr.
Overton'
s
affidavit)
the defendant wrote
to
the
Department
referring to
its
efforts
to
satisfy
noise
complaints
from
residents.
It
pointed
0
out
that
"The
company
does
not
have
unlimited
funds
available,
()
however
each
month
we
have
spent
many
dollars in
an
effort
to
reduce
noise
to
the
very
low
levels
set
for
our
Sawmill."
On
25th
November,
1988,
the
defendant appealed
to
the
Local
Government
Court
in respect of
certain
conditions in
the
conditional
approval
letter
of
25th October
1988
and
in
particular
in respect of the contribution
to
roadworks,
erection
of
a 1
.8 metre high fence,
and
the noise
levels,
on
the
grounds
()
set
out
in
the notice of
appeal,
ex.
D
to
the
affidavit
of
(J
Mr.
Smith.
follows:-
Grounds
9
and
10
dealing
with
noise
levels
are
as
"9. Condition
1(i)
is
not reasonably
required
by
the
rezoning
of the subject
land having
regard
to
thenature of the
surrounding
area, the location
of
the
subject
land adjacent
to
a
major
tourist
and
local
thoroughfare
and
in
close
proximity
to
a
railway
line,
and
the
ambient background
noise
levels in
the
surrounding
area.
10.
Condition
1(i)
ought
to
be
amended
by
deleting
all
reference
to stipulated
noise
levels
and
insubstitution
therefore, requiring the
appellantto
satisfy
the
requirements
of
the
Noise
,.
-- 13 of 33 --
1.
I~
1.
l
l
I.
ll
I
i:
1 1
Abatement Authority
M.A.A.
with respect to noise
emissions from
the subject land."
On 2nd December, 1988,
the Department
replied to the
plaintiff's letter
of 13th October, 1988,
advising
that the
defendant's response
to the Department's request for
a
programme
of
abatement measures and
the timetable for
completion
indicated
that "sufficient
measures
are unlikely to
be implemented
to
achieve
a
satisfactory situation for residents".
The
letter
indicated
that
the
Department
would
be
obliged
to refer
the
matter
to the
Noise Abatement
Authority
for consideration
under
the relevant
Act.
(,,,-----)
On
15th
December, 1988
a
letter
signed
by
some 57
residents
\
.•
C)
was
received
by
the
plaintiff
(ex.
"A"
to
the
affidavit
of
John
Joseph Hession,
the
plaintiff's
Deputy
Town
Planner
filed
8th
March,
1991). That
was
an
objection to
the
planned
rezoning.
On
8th
February,
1989,
the
plaintiff
applied for
and
was
given
a
date for
hearing of the
defendant's
appeal
to
the
Local
Government
Court.
On
7th
April,
1989,
the
defendant
withdrew
its
appeal.
The
reasons
for
this
withdrawal
are
not
stated
in
the
Q
evidence
before
me.
In
the
meantime on
15th
and
16th
March,
1989,
the
Department
conducted
further
noise
surveys.
These
again
indicated
excessive noise
levels
i.e.
that
is
levels in
excess
of the
maximum
specified in
the
plaintiff's letter
of
conditional
approval
dated
25th October,
1988.
On
6th
May,
1989
a
further
letter
signed
by numerous
residents
was
sent
to
the
plaintiff
for the
attention
of
the
Health
Department.
It
demanded
that
proceedings
be
taken
against
the
defendant
under
s.
86
of
the
Health
Act
1937
(complaint
of
-- 14 of 33 --
12
nuisance).
The
plaintiff after receipt of legal advice did not
proceed under
that
Act.
Notwithstanding the foregoing,
on
1st
June, 1989,
the
plaintiff
and
the defendant entered into the
deed (ex.
"E"
to
Mr.
Smith's
affidavit), in
accordance with the
letter
of
approval
of
25th October,
1988
(ex.
"C"
to
Mr.
Smith's
affidavit).
The
conditions in
Schedule
2
thereof are the
same
as those in the
letter
of
25th October, 1988. Clause
9
of that
schedule deals
with noise
abatement
levels in similar
terms,
and
with the
same
words
following the
table
commencing
with
the
words "To
achieve
these
levels,
the following
measures are'
to
be
taken".
Clause
2
of the
deed
provides
that in
the
event
of the
Governor-in-Council
approving the
application referred to in
cl.
1
(for
rezoning) the
defendant
shall
"undertake,
carry
out; provide
and do
or
cause
to
be
undertaken,
carried out,
provided
and done
the
works and
make
or
pay
the
payments
of contribution
set
out
and
specified
in
the
~econd
Schedule which,
on
its
face,
includes the
abatement
measures
in
order
to
achieve
the
maximum
noise
emissions
referred
to.
Clause
3
of
Schedule
2
refers
to the provision
by
the
defendant of
a
bond
to
secure the defendant's
due
performance
of
its
obligations
under
the
deed
with
respect
to
"payments
or
contributions
required
to
be
made
and
the
works,
matters
and
things required
to
be
undertaken,
carried out,
provided
and done
by
the applicant
as
set
out
and
specified
in
the
Second
Schedule
hereto".
Prima
facie,
this
bond
covers
all
works
including the
noise
abatement measures.
Yet
the
bond
to
be
provided
in
cl.
2
of the
Second
Schedule
is
(as
is
also
provided
for
by
the
letter
0
0
0
CJ
-- 15 of 33 --
(
f,
1.
r'
I.
I
13
of 25th October, 1988),
a
bond
to secure performance of all
works
external to the
site. It is
obvious
that the noise abatement
measures
at least are
works
to
be performed on
the
site
and
are
not external to the
site.
The
above
provisions
were
relied
upon by
senior counsel for
the defendant as imposing
a
positive obligation
on
the defendant
to undertake
and
carry out
works,
i.e.
a
positive
covenant
and
not
merely
a
negative
covenant
to abate noise.
It
was
further
)
submitted
that
a
substantial issue
would
have
to
be
tried
in
due
course as
to
the
true construction of the
deed
when
viewed
in the
proper context of
all
surrounding circumstances.
0
On
26th June,
1989,
the defendant duly lodged with the
plaintiff
a
bond
of
$90,000.00
in
accordance with
one
of the
conditions of approval.
On
12th
July,
1989
the
plaintiff
issued
a
complaint under
the
Justices
Act
1886
as
amended
(ex.
"H"
to
Mr.
Smith's
affidavit)
alleging
a
breach
by
the defendant
in
about
December
1988
of the
plaintiff's
town
planning
scheme,
cl.
10(5).
It
was
alleged
that
the
defendant executed
or carried
out
certain
additions
to
its
premises without
obtaining the
prior
consent
of
the
plaintiff
as
required
by
the
Town
Planning
Scheme.
These
additions
included
various
structures.
On
17th
August,
1989,
the
defendant
was
convicted
of the offence
at
the
Caloundra
i
Magistrates
Court
and
fined
$150.00.
On
18th
September,
1989,
the
rezoning
of
the land
after
approval
by
the
Governor-in-Council
was
duly
gazetted.
Thus
the
rezoning
had
become
law.
It
was
submitted
by
counsel
for the
plaintiff
that
the conditions
imposed by
the
Council
by
virtue
-- 16 of 33 --
14
of the letter dated 25th October, 1988 and in particular by the
deed of 1 st June, 1989, must be taken to be "reasonable and
relevant conditions to which the approval of the rezoning was
subject".
Further noise tests were conducted by the Department on and
in the region of the defendant's land and in particular on 3rd
April, 1990. On 22nd March, 1990 the plaintiff issued a further
complaint (ex. "I" to Mr. Smith's affidavit) alleging inter alia
a breach of the conditions of approval to the rezoning in that
it stored scrap timber within the road reserve adjoining the land 0
and noise levels generated upon the subject land exceeded those
permitted by the Conditions of Approval. On 19th April, 1990, Q
the defendant was convicted of the offence in the Caloundra
Magistrates Court and fined $200.00. It was said on behalf of
the defendant that this prosecution was invalid because it was
based on an alleged breach of the deed of 1st June, 1989. The
defendant did not appear at that hearing. Counsel for the
plaintiff on the other hand drew attention to cl. 5 of Part IV
of the Town Plan ( Queensland Government Gazette No. 68,
December, 1987) as follows:-
" 5. Where in respect of any applications to rezone
whether approved by the Council before or after the
coming into force of this part and which is approved
by the Council subject to reasonable and relevant
conditions, any person who ·in any respect fails to
comply with any one or more of the conditions imposed
by the Council in granting the approval within the
time specified or if no time is specified then after
the use of the land commences whether in whole or in
part shall be guilty of an offence under this
Chapter."
19th
On 3rd April, 1990, the Department carried out more tests
(see ex. "F" to Mr. Overton's affidavit). This resulted in a
0
0
-- 17 of 33 --
n
C)
0
j
15
noise abatement notice being issued against the defendant,
calling
on
the defendant to
show
cause
why
an
order should not
be made.
On
1st
May, 1990
a
"show
cause" hearing
was
held
by
the
Noise Abatement
Authority
and on 23rd
July,
1990
a
noise
abatement
order
was
issued against the defendant (ex.
11
0
11
to
Mr.
Overton's
affidavit
of 4th
March,
1991),
stating that
the noise
emitted
was
excessive.
The
order required the defendant
to
commission
a
recognised acoustics
consul
ting expert
and
to
submit
to
the
Department by
10th August,
1990
a
report
on
identifiable
noise sources
and
available noise control techniques
and
by
that
date also
a
draft
timetable for the
implementation
of noise
control
measures
recommended by
the acoustic consultant.
On
22nd
May,
1990
Mr.
Overton
inspected the
site
with
the defendant's
manager and
seven
areas
were
identified
which
contributed to
noise
levels.
It
appears
from
the
minutes
dated 13th June,
1990
(ex.
"H"
to
the
affidavit
of
John
Joseph
Hession
sworn
4th
March,
1991
-
the
plaintiff's
Deputy
Town
Planner)
that
a
site
inspection
was
undertaken
on
11
th
May,
1990 by him
and
another
officer
in
company
with
a
representative of
the defendant.
A
further
site
inspection
was
undertaken
on
31st
May,
1990 by
Mr.
Hession,
the
Building
Inspector, the
Health
Inspector,
and
two
Local Council
Aldermen
together
with
the
manager
of
the defendant
company.
A
review
of
all
of the conditions of
.
the
rezoning
apparently
occurred
and
these
are referred to in
those minutes.
Certain
conditions
which had
not
been complied
with
were
noted.
It
was
noted
that
noise
levels often
exceeded
the
nominated
maximum
levels
imposed
and
that
no
acoustic
treatment
had
been
undertaken
-- 18 of 33 --
16
on site with regard to the drier and other machines. It was
stated that there had not been full compliance with this
condition of approval. The recommendation of that meeting was
that the proprietor of the defendant should be given the
opportunity to show cause why the Council should not proceed with
action for the defendant's failure to satisfy the rezoning
conditions relating to noise levels and with respect to the
alleged unlawful installation of a drier and proposed
installation of a second drier in a storage shed not indicated
in the original application.
The defendant submitted a report from Consulting Structural
and Mechanical Engineers, Stewart and Thiris Pty. Ltd. following
tests conducted at the site on 30th July, 1990. By letter dated
8th August, 1990 (part of ex. "E" to Mr. Overton's affidavit),
that engineer congratulated the defendant for a "very low noise
level" which had been achieved. The letter stated that the noise
generated was considerably less than that generated by some
stockfeed mills, furniture and joinery works and continued:-
"From our inspection of the mill noise, generated
during operationi and the background noise with mill
shut down, a much lesser noise generation is indicated
than the figures obtained by the Department of
Environment and Heri~age."
The letter questioned some of the readings obtained by
Mr. Overton but went on to refer to three noise sources about
which "something can be done". He referred to the "recommended"
limits recognised in the Department's environment guidance
leaflet which he said were strictly only guidelines and stated
to be "desirable objectives". He did not refer to the levels in
fact approved by the plaintiff and which had been incorporated
0
C)
C)
(j
-- 19 of 33 --
0
17
as conditions of the plaintiff's
approval to the rezoning.
He
concluded
that the mill operated within an acceptable level of
noise
when
compared
with the noise generated
from
other mills.
It
was
submitted
that this
evidence
also indicated that there
was
a
substantial issue to
be
tried
namely
whether
or not there
was
in fact
a
nuisance, being the only
basis
claimed by
the
plaintiff
in the notice of
motion.
On
8th
August, 1990,
the defendant wrote
to
the
Council
(ex.
11
J
11
to the
affidavit
of
Mr.
Hession)
enclosing
a
copy
of the
above
consultant's reports, referring also to
money
spent over
the previous
18
months and
giving
specific
answers
to
Mr.
Hession's
letter
of
10th
July,
1990
to the defendant.
The
defendant
was
making
some
effort
to
abate the noise
and
was
not
ignoring the
problem.
It
appears
however
that
the
expertise of
this
consultant
commissioned
by
the defendant,
was
not accepted
by
the
plaintiff.
On
5th
September,
1990
the
plaintiff
issued
two
further
complaints (exs. "J"
and
"K"
to
Mr.
Smith's
affidavit).
The
first
alleged
a
breach
of
the conditions
of
approval
to
the
rezoning
and
in
particular
alleged
failures in
relation
to
the
erection of
a
drier,
the
non-completion
of
a 1
.8 metre high fence
and
the non-provision
of
a
sealed car-parking
area.
Exhibit
"K"
consisted of
an
alleged
breach
of
the
rezoning
conditions
in
that
the
noise
levels
measured
at
an
effected residence
exceeded
the
permissible noise
level
set
out
in
the
said conditions.
On
2nd November,
1990,
a
receiver
and manager
was
appointed
to
the
defendant
company
by
a
major
creditor,
the
ANZ
Banking
Group.
On
23rd
November,
1990,
the
solicitors
for
Mr.
Max
-- 20 of 33 --
18
Prentice, the receiver
and manager, wrote to the solicitors for
the
plaintiff
seeking
a
commercial
solution to the
problem which
existed
between
the
plaintiff
and
the defendant
and
seeking an
adjournment
of the hearing of the aforesaid complaints
which were
due
to
come
before the Magistrate's
Court on
28th
November,
1990.
It
appears
that
the
plaintiff's solicitors
refused
an adjournment
and proceeded
on
28th
November, 1990 when
the
first
of the
above
two summonses was
dismissed with
a
costs order of
$6,500.00
awarded
against the
plaintiff.
Senior counsel
for the defendant
informed
me
that
the Magistrate
had acceded
to
submissions
on
behalf of the defendant
to the
effect that
there
could
be
no
quasi criminal prosecution for
a
breach
of
a
deed between
the
parties,
even
if
a
breach
had
in fact
occurred.
The
noise
prosecution
summons
was
adjourned
to
10th
December, 1990
and
subsequently
by
consent
to
4th April,
1991.
The
Council has
appealed
to
the
District
Court
against
the decision of the
Magistrates
Court
on
28th
November, 1990
dismissing the
complaint.
It
appears
that
a
conference arranged
to
be
held
at
the
plaintiff's
premises
on
29th
November, 1990
(i.e.
the
day
after
the
Court
hearing)
was
cancelled.
According
to
submissions
of
senior
counsel
for the
defendant,
this
was
cancelled
by
the
plaintiff.
By
letter
dated 4th
December, 1990
(ex.
"B"
to
the
affidavit
of
Christopher
Michael
Carbery,
solicitor
for the
receivers
filed
12th
March, 1991)
the
receiver's
solicitors
wrote
again
to
the
solicitors
for the
plaintiff
again
referring to
the
fact that
the
receiver
had been
only
recently
appointed
and
was
now
in control of the
company
without
a
thorough
knowledge
of the
0
C)
C)
0
-- 21 of 33 --
I ·
'[
I
\
I
[
I
i:
I
'
't
L
I
f
r
1
J
r
l
n
19
issues but
was
anxious to obtain that
knowledge from the
plaintiff.
The
receiver expressed anxiety in preserving the
asset
value of the land and business as
a
going concern and again
entreated the
plaintiff's solicitors to attempt to arrive at
a
commercial
solution in order to
keep
the business going.
It
was
stated that
the receiver
and
the
ANZ
Banking Group were most
anxious
to
ensure
that there
were no
unnecessary retrenchments
from
the defendant's mill.
The
letter
entreated the
Council
to
reconvene
a
conference
in order
that
the matter could
be amicably
discussed.
That
letter
was
acknowledged
by
letter
dated 7th
December,
1990 from
the
plaintiff's
solicitors
which
referred to the
fact
that
a
meeting
was
convened on
5th
December,
1990. By
letter
dated 12th
December, 1990
(ex.
"D"
to
Mr.
Carbery's
affidavit),
the
solicitors
for the
plaintiff
paid
$6,500.00
to
the
solicitors
for
the
defendant
and
expressed disagreement with
some
of
the
()
matters
referred to in
the
receiver's
solicitors'
letter
of
4th
December,
1990.
0
In the
meantime
Mr.
Overton conducted
further
noise
level
tests at
or
near
the
site
on
3rd
April,
1990,
28th
September,
1990 and
8th January,
1991.
See
exs.
"F",
"G"
and
"H"
to his
affidavit.
All
tests
showed
readings
above
the
approved
limits.
His
reports also indicate
that
these
tests
showed
no
significant
reduction
in
noise
levels
and
indeed,
he
said
that
the
tests
in
September
1990 showed
a
higher
reading than
that
recorded
in his
previous
tests.
In
para.
13
of
that affidavit,
Mr.
Overton
suggested
various
measures
which
could
be
taken,
many
of
which
did not
in his
opinion
require
the
approval
of
the
plaintiff
but
-- 22 of 33 --
20
were
matters for the
management
at
the defendant's mill.
His
recommendations
also included the replacement of galvanised iron
sheds which
contributed to the noise level
by
reverberant build-
up, with an
acoustically designed building, but
he
recognised
that this
required
funding by
the defendant,
and
approval
from
the
plaintiff.
Mr.
Overton expressed the opinion
that
from
a
practical
point of
view,
the noise
levels
emanating
from
the mill
were
greater
than twice as loud as
that
permitted
by
the
approval
conditions.
He
further said that this
was
a
practical
consequence
to
a
listener.
It
appears
from
the
affidavits
of
Mr.
Lovewell and
Mrs.
Neilson
who
live
close to
the mill that
noise, dust
and
other
activity
caused
them
annoyance and
concern.
It
appears
that
the
plaintiff
proposed
to
proceed with
the
roadworks
referred to in para.
(c)
of the
rezoning approval
and
to that
end,
the
plaintiff
had
previously resolved
to
draw
down
on
the
funds
deposited
by
the
defendant
by
way
of the
bond
on·
26th June,
1989.
By
his
affidavit filed
4th
March,
1991,
Mr.
Hession
said that
the
plaintiff
was
presently
undertaking
some
of
those
works.
In
that affidavit
he
referred to
what he
termed
"various
breaches"
by
the
defendant
of
rezoning
conditions.
On
5th
March,
1991
Mr.
Overton
took
further
readings
of
noise
emanating
from
the
defendant's
mill in
the
garden
of the
residence
of
Mr.
Lovewell.
This recorded
a
reading
well
in
excess
of
tlle
maximum
specified
levels.
On
5th
March,
1991
he,
in
the
company
of
Mr.
Hession,
and
the
manager
of
the
mill
inspected the
mill.
The
manager
indicated to
them
three
items
0
0
()
(j
-- 23 of 33 --
f
21
of
work undertaken by
the defendant to
implement the
recommendation
of Stewart
&
Thiris Pty. Ltd. which Mr.
Overton
described as minor.
Mr.
Overton
said that noise levels
from
the
mill
had
not reduced
significantly since the
measurements taken
in
September 1990.
On 7
th
March,
1 9 91 , Mr.
Overton took
a
further
reading
from
Mr.
Lovewell's premises
at
8.13 a.m. which
showed
a
reading of
72.1
LA.Max
Adj.
15
min.
David Spence
Irvine,
company
secretary
and
internal
accountant
for the defendant
swore an
affidavit filed
12th
March,
1991
on
behalf of the defendant.
He
referred to
expenditure
incurred
by
the defendant
since
October
1987 on
noise
abatement.
r'
1
\_~)
He
said
that
in
September
1990
the defendant
had
submitted plans
C)
to the
plaintiff
for
approval
of construction of
a
building to
enclose the
southern-most
chipper as well as
to
erect
a
roof over
the debarker
and
lining for the
drier
shed.
He
swore
that
the
defendant
was
still
awaiting approval
from
the
plaintiff
before
being
able
to carry out the
major
part
of
this
work.
He
said
that
the
defendant
had on
6th
March,
1991
given
instructions to
a
firm
of
engineers
to
prepare plans
for the
erection of
a
50
Q
metre long, four
metre
high
solid
fill
wall along
the
western
side of the
plant building
thereby enclosing the debarker,
saw
mill
and
veneer
mill
and
providing
for
openings
for the
feeding
of
logs
into
the
plant
with rubber screens over
these
openings.
Mr.
Irvine also said
that
on
a
number
of
occasions
since
February
1991
he had
personally
performed
sound
tests
or
had
caused
the
mine manager
to carry
out noise
emission
tests.
He
referred to
a
list
of
noise
levels
which
in
general did not
exceed
the
maximum
contained
in
the conditions of
approval
for the
rezoning.
-- 24 of 33 --
22
It
was
submitted that this
was a
further basis for ordering
a
trial
of the action because such disputed questions of fact could
not be determined on an
interlocutory application.
On
or about 10th January 1991, Barry William Sands,
Consulting Engineer,
was
retained
by
the receiver
and manager
of
the defendant
to report
on
the
feasibility
of reducing noise
levels.
Mr.
Sands
knew
of the
site,
having
travelled that
road
which
was
the
Old Bruce
Highway
on numerous
occasions during the
past
30
years.
He
formed
the
view
that
the noise
levels
caused
Qby
traffic
alone
in that
area before the
new
Caloundra by-pass
was
built
so
that
all
of the constant
heavy
traffic
then
flowed
past the
mill,
was
about
67-75 db,
i.e.
well
above
the noise
limits
now
permitted
by
the conditions of
approval,
and
quite
apart
from
the noise generated
by
the
mill.
Mr.
Sands
conducted
several inspections in
January
and
stated that
all
of the
houses
situated
adjacent to
the
highway and
near the mill
would
have
been
affected
by heavy
traffic
volumes and
noises before the
construction of the
by-pass so
that
from
a
practical
point of
view,
the
opening
of
the
Caloundra
by-pass
had
the unfortunate
effect that local
residents
then
noticed the
major remaining
noise
which
they
had
not
particularly
observed
previously.
He
concluded
by
saying
that
he
doubted whether
the
combined
level
of
road
and
mill
and
background
noise
at
present
is
any
greater
than
it
was
in
previous years
when
the
road
was
then
the
main
highway.
Nevertheless,
Mr.
Sands
said
that
it
was
possible to
undertake
various
works
required
by
the
plaintiff
and
that
such
works would
probably
effect
a
reduction of noise
levels.
He
said
0
0
0
-- 25 of 33 --
r
r.
n
0
23
that the main
inhibiting factors
and
constraints
were the
question of costs
and
the co-operation of the
plaintiff in
approval of building plans.
He
also said that his
tests
and
inspections
were
substantially in
agreement with those of
Mr.
Overton with
some
areas of
divergence
which he
set
out.
He
said that since
Mr.
Overton'
s
inspection the chains
of the debarking
machine had been
tightened
and
the
machine
was
now
running
much
more
quietly
so
that the
machine
may
not
in fact
need
enclosure as provided
for
in the conditions of
rezoning.
From
this
it
was
argued on
behalf
of the defendant
that at least
one
of the conditions
set
out in
the conditions of
approval
was
no
longer necessary as noise
abatement
was
achieved
by
a
different
process. Whilst not
commenting
on
Mr.
Overton's "permitted
level"
which
resulted in
Mr.
Overton's
view
that
to
the
average
listener
sounds emanated
were
more
than twice as loud as the permitted
level,
Mr.
Sands
agreed
that
the
levels
recorded
would
be
regarded
by
an
average
listener
as
excessively
noisy, although
no
noisier
than
was
the
position
when
the
highway
was
in fact
the
main
North
Coast
U
highway
before the
Caloundra
by-pass
was
constructed.
It
appears
from
the
affidavit
of Peter
Kenneth
Lowcock
(employee
in
the
firm
of Prentice
Parbery
and
Briller,
Chartered
Accountants,
who
are
engaged
on
behalf
of
the
receiver)
filed
12th
March,
1981,
that
the
plaintiff
was
asked
to
advise
when
it
intended
to
commence
roadworks and he
sought
an
accounting
of
how
the
$90,000.00
bond which
the
plaintiff
proposed
to
use
would be
spent.
The
plaintiff's
reply
on
15th February,
1991
was
to
the
effect that
as
the
guarantee
was
unconditional,
it
would
"be
-- 26 of 33 --
24
spent
how
Council sees
fit".
Mr. Lowcock
contacted the plaintiff
expressing concern
at this
response
but. was
told "that's
the only
explanation the Council's going
to give you".
Graham
Max
Squire, Queensland Manager
of the firm of
Chartered Accountants
acting for the receiver
and manager swore
an
affidavit filed
12th
March,
1991
referring to his
involvement
and
that
of the receiver since his
appointment.
He
endeavoured
to
arrange conferences with the
plaintiff,
one
of
which
was
held
on
5th
December, 1990
at
the
plaintiff's
premises. Present
was
the
Mayor,
Mr.
Smith,
Mr.
Hession
and
four
other City
Aldermen
representing the
ward.
He
said that
the
Mayor
informed
him
that
the
plaintiff
insisted that
the noise
level
be
in
conformity with
the
schedule
of the rezoning
agreement.
On
7th
December,
1990
Mr.
Squire
wrote
to
the
plaintiff
expressing the
desire
of the
receiver
and manager
to carry
out
works
to
minimise
the excessive
noise
as
much
as
is
practicable
and
that
it
intended
to
obtain
a
further report
from
an
acoustics engineer.
He
sought
assistance
from
the
Council
as
to
names
of
suitable
engineers but
as
no
advice
was
forthcoming,
he engaged
Mr.
Sands.
On
21st January,
1991,
Mr.
Squire
and
Mr.
Lowcock
attended
a
further
meeting
at
the
.plaintiff's
chambers.
They
were
advised
that
the
plaintiff
proposed
to
seek
an
injunction
and
asked
what
were
the
receiver's
plans
for
rectifying
the noise
problem.
Mr.
Squire
advised
that
Mr.
Sands had
been engaged and
the
Town
Clerk
said
that
the
plaintiff
required
an immediate
curtailment
of
operating
hours
to
7.00 a.m.
to
6.00
p.m.
with
the
drier
and
fans
to
be
shut
down
at
6.00
p.m.
A
reply to
that
request
was
to
be
given within
24
hours.
On
22nd
January,
1991,
Mr.
Squire
wrote
0
C)
CJ
-- 27 of 33 --
25
to the plaintiff
undertaking to curtail the operating hours as
requested
by
the
plaintiff whilst reserving the right to
review
these hours
when
the noise being emitted
by
the mill
is
within
the acceptable level specified
by
the
Department
of
Environment
and
Heritage (ex.
"A"
to
Mr.
Squire's
affidavit).
Following
a
letter
from
the
plaintiff
on
25th January,
1991,
Mr.
Squire
sent
a
report to
the Council which
addressed noise
attenuation proposals in
two
stages.
He
confirmed
that
the
n
operating
hours
were
restricted
to
7.30 a.m.
to
6.00 p.m.
Monday
to
Friday only
and
that
it
was
the
receiver's intention to
pursue
n "
,,
(J
the
rectification
of the rezoning breaches
in the
most
practical
manner and
to
make
all
reasonable
efforts
to
meet
Council
requirements.
He
invited
the
plaintiff's
officers
to contact
him
at
any
time should
further
information
be
required.
Having no
response
to
the lastmentioned
report,
Mr.
Squire
made
attempts through
staff
to contact
Mr.
Hession
and
Mr.
Smith
but
both
were
unavailable.
The
only information
available
was
that
an
injunction
was
to
be
sought
by
the
plaintiff.
He
expressed concern
at
the
response
to
Mr.
Lowcock's
letter
requesting
an
accounting
by
the
Council
as
to
how
it
would expend
the
$90,000.00
bond
provided
by
the defendant.
He
again
asked
for
co-operation
and
sought
a
resolution
by
negotiation.
Mr.
Squire
referred
to
difficulties
in
complying
with
all
rezoning requirements
and
in
particular,
the
defendant
had
made
application to the
Land
Administration
Commission
for the
purchase
of adjoining
Crown
land
and
that
the
Land
Administration
Commission
had
proposed
certain
pre-conditions.
This
required
a
bond
of
$8,400.00
with regard
to
mains
water
supply
and
certain
-- 28 of 33 --
26
other departmental requirements including those of Telecom
Australia and the Department of Transport regarding access. He
indicated that the receiver would need to take a commercial
decision in relation to the viability of acquiring adjacent Crown
land having regard to the cost of complying with the Department
of Transport' s requirements. He said that he was unable to
ascertain the costs of satisfying the Department of Transport's
requirements because of the plaintiff's continual refusal to give
details of engineering works commenced by the Council on or about
15th February, 1991 without his knowledge or to account to him
for the sum of $90,000.00 bond money confiscated by the
plaintiff.
Since the appointment of the receiver, the defendant has
traded at a loss. The receiver must consider the interests of
creditors and particularly those of the major secured creditor,
the ANZ Banking Group. He must fully investigate all options
with respect to the marketing for sale of the assets of the
company including the marketing of the entire land administered
as a going concern. It is obvious that the receiver needed to
obtain full information and has acted promptly in an endeavour
to do so. One option to be considered was whether or not the
entire plant should be closed down and the assets sold piecemeal
at a substantially lower figure than if the operation was sold
as a going concern. He said that if an injunction was sought the
receiver would have no choice but to close the mill down
immediately.
Peter Kenneth Lowcock, accountant employed by the receivers,
by affidavit filed 12th March, 1991, said that the defendant
0
C)
C)
C)
-- 29 of 33 --
n
(~)
27
employed 23
full-time
permanent employees and
a
further
11
employees on
a
casual basis but
who
are
engaged
full-time.
Approximately $800,000.00 per
annum
is
paid to local contractors
and
approximately $748,000.00
in
wages
annually.
He
was
informed
by
the Caloundra branch
of the
Commonwealth Employment
Service
that
the
Caloundra and Sunshine Coast
areas rank
amongst
the
highest areas of
unemployment
in Australia
and
that
it
would be
extremely
difficult
to find
employment
for
an
additional
34 men
should they
be
put out of
work. Eleven
of the
employees
are
single
without dependents
and
the balance
of
employees have
a
total
of
45
dependents.
The company
pays approximately
$720,000.00
per
annum
to
C.S.R.
for the supply
of
raw
materials
of
which
approximately $300,000.00
is
paid
to local
contractors
by
C.S.R.
It
was
submitted
by
senior
counsel
for the
defendant
that
if
the defendant
were
to
be
forced
to close
down,
it
would
involve not only
the
unemployment
problem
referred to
but
a
(J
withdrawal
of
approximately $2,000,000.00
per
annum
from
the
local
community
at
Beerwah
with
substantial
economic
effects
to
that
small
community.
0
There can be
little
doubt
that
the
receiver
and
manager
since
his
appointment
on
2nd November,
1990,
has
acted
in
a
reasonable
manner
in
endeavouring
to
ascertain
all
details
applicable
to
the
problem and
in
endeavouring
to
meet
the
plaintiff's
requirements with
a
view
to resolving the dispute in
a
commercial
manner
without
litigation.
On
the
other
hand,
there
has
been
noticeable
noise
emanating
from
the
defendant's
land
at
least
since the
new
Caloundra
by-pass
was
opened, and
this
noise,
according
to
the
evidence
of
some
deponents
to affidavits,
-- 30 of 33 --
28
exceeds the limits specified in the conditions of approval
although there is
some
evidence to the contrary.
It
must
also
be recognised
that the
plaintiff
has
a
public duty
to
perform
in
ensuring
that
its
conditions of approval are not broken.
It
has
a
duty
to represent the
interests of the
whole community and
it
has endeavoured
to
do
so as
it
saw
fit.
The
circumstances under which an
injunction
is
granted are
well-known.
The remedy
)is
discretionary in nature.
The
first
requirement
is
that
there
must be
a
substantial
question to
be
tried
in the action
between
the
parties.
If
this
condition
is
satisfied,
as
it
clearly
is
in
this
case, then
the balance
of
convenience
must
be
considered,
i.e.
the position
not only with
regard
to
both
plaintiff
and
the
defendant
pending
trial,
but
also to
the
positions of affected
third parties:
Clarke v. Japan
Machines
(Australia)
Pty. Ltd.
[1984]
1
Qd. R. 404
per
Thomas
J.
at
419.
For
the
purposes
submissions
of senior
of
this
application,
I
accept
counsel
for
the
defendant
that
the
the
plaintiff's
claim
is
based
only
on
nuisance, with
no
claim
based
upon
an
alleged
breach
of the
by-laws
or of the
deed.
The
notice
of
motion
is
based only
on
common
law
nuisance
even though
a
breach
of
conditions contained
in
the
deed
or of conditions of
approval
may
provide
some
evidence
that
a
nuisance
otherwise
in
fact exists.
Notwithstanding
that
this
point
was
taken during
the
proceedings
by
senior
counsel
for
the
defendant,
no
application
was made
on
behalf of the
plaintiff
to
amend
the
notice
of
motion.
C)
C)
C)
C)
-- 31 of 33 --
(;' /
29
I
also accept the submissions of senior counsel for the
defendant that
if
this
claim
is in fact based upon
a
breach of
the deed,
there
is
a
question to
be determined as to the true
meaning and
effect of the nature of the covenant
referred to
therein.
This
document must be
construed
in the
light
of
all
the
surrounding circumstances
and
it
is
not convenient
to construe
this
document on an
interlocutory application in the Practice
Court.
Furthermore, notwithstanding the opinions expressed
by
Mr.
Overton,
there
is
some
dispute
as
to the actual noise
levels
and
their
causes
and
as
to
the extent
to
which
the
defendant has
complied
with the
plaintiff's
requirements
either
by
performance
of
any
necessary
work
or
whether
or
not
some
of the requirements
are
no
longer necessary
by
reason
of
alternative
action
taken.
It
is
not necessary
for the
purposes
of
this
application to
go
into
the disputed question of
whether
or
not the
defendant
is
()
still
awaiting
for
approvals
from
the
plaintiff
in
order to
[)
undertake
certain
work.
Nor
is
it
the
Court's
function
on an
interlocutory application to finally
resolve
other
disputed areas
- .
of
fact.
This
must
be
left
for
trial.
Having
regard
to
the defendant's
financial
situation,
it
may
be
wondered
whether
the
defendant
will in fact
·
be
able
to
undertake
this
work
without
the infusion of
further
funds
which
the
receiver
indicated
that
he
might
seek
once he
is
in
possession
of
all
information.
Alternatively, there
is
a
real
possibility,
as appears
from
the
evidence,
that
a
decision
may
very
soon be
made
to
shut the
mill
down
completely
in
any
event.
-- 32 of 33 --
30
If this occurs, then the noise problem will disappear without the
need for protracted and costly litigation.
Having carefully considered all of the material in detail
and all of the submissions and arguments before me, as well as
the number of years during which this dispute has continued, it
seems to me that on balance, the injunction sought should now be
declined and the matter allowed to go to trial as speedily as
possible. Relatively speaking, the further delay should not be
considerable.
Accordingly, the application is dismissed. Costs of and
incidental to the motion are reserved. The action is certified
as one which should be tried speedily.
' .
C)
0
C).
-- 33 of 33 --
Official source: https://www.sclqld.org.au/caselaw/QSC/1991/097