Allco Steel (Queensland) Pty Ltd v Torres Strait Gold Pty Ltd & Ors [1990] QSC 37
10
20
30
40
50
60
IN THE SUPREME COURT OF QUEENSLAND
CIVIL JURISDICTION
BEFORE SENIOR MASTER HORTON Q.C.
BRISBANE, _12 MARCH 1990
SC
No. 2742 of 1989
(Copyright in this transcript is vested in
the Crown. Copies thereof must not be made
or sold without the written authority of the
Chief Court Reporter,Court Reporting Bureau.)
BETWEEN:
ALLCO STEEL (QUE~NSLAND) PTY. LIMITED
-and-
Plaintiff
TORRES STRAIT GOLD PTY. LTD.
-and-
POLBURY PTY. LTD.
-and-
AUGOLD N.L.
-and-
GIANT RESOURCES LIMITED
JUDGMENT
First Defendant
Second Defendant
Third Defendant
Fourth Defendant
SENIOR MASTER: I dismiss the summons for a stay.
I publish my reasons.
-Govt. Printer, Old.
-1-
10
20
30
40
50
60
-- 1 of 9 --
IN THE SUPREME COURT
OF QUEENSLAND
No. 2742 of 1989
Before Master Horton Q.C.
BETWEEN:
AND:
AND:
AND:
AND:
ALLCO STEEL (QUEENSLAND) PTY LIMITED
Plaintiff
TORRES STRAIT GOLD PTY LTD
First Defendant
POLBURY PTY LTD
Second Defendant
AUGOLD N.L.
Third Defendant
GIANT RESOURCES LIMITED
Fourth Defendant
JUDGMENT REASONS: MASTER HORTON Q.C.
This is an application brought by the First, Second, Third
and Fourth defendants against the plaintiff in action 2742 of
1989 in which the applicant defendants seek an order that the
action be stayed pursuant to the provision of Order 60 Rule 2 of
the Rules of the Supreme Court.
Before dealing with the respective merits of the
application, I feel it is necessary to briefly outline the nature
of the relief sought by the plaintiff in the subject writ. The
endorsement on the writ is as follows:
1. Monies owing pursuant to contract.
2. Damages for breach of contract.
3. Damages for negligence.
4. Interest pursuant to the Common Law Practice Act
of 1867 and 1981.
-- 2 of 9 --
A
statement of claim has been delivered on the 15th August,
1989 wherein
it is alleged inter alia that
by
written contract
made
between the plaintiff
and the
first
defendant on
or about
2nd
February, 1988,
the
plaintiff
agreed to carry out detailed
design, supply and
erection of
steel
work and
specified
equipment
for
a
crushing plant
and
C.I.L. floatation
and
grinding plant for
a
goldmine
at
Hall Island.
It
emerges from
the material exhibited to the
affidavit of
Inoke
that
the
first
defendant
was
the operator of
an
unincorporated
joint
venture
known
as the Hall Island Joint
Venture
and
the
nominees
of the
two
joint-venturers
Augold N.L.
and
Polbury
Pty. Ltd.
a
wholly
owned
subsidiary of
Giant
Resources Limited.
Further,
it
is
clear that
pursuant
to
an
agreement
the
first
defendant
was
appointed
to
manage
the
joint
venture
and
to act
as the agent
for
a
nominee
of the
joint-
venturers
to
the
purpose
of the
joint-venturers.
The
contract
originally
envisaged
that
the
plaintiff
would
commence
work on
site
in early
January
and
completion under
the
contract
would
be
achieved
by
8th
March, 1988.
Initially,
there
was
a
fourteen
week
delay
by
the
plaintiff
in the
completion
of
their
portion of the
work
(as
deposed
to
by
the
Solicitor
for
the defendants)
and
eventually matters
proceeded
to
a
stage
where
the
first
defendant
formed
a
view
that
the
plaintiff
would
be
unable
to
meet
its
contractual
obligations.
The
terms
of the
contract for
the
limited
purposes
of
the
application
today
are
relatively brief.
By
paragraph
4.5.3
(i)
the
contract
provided:
"Torres
Strait
Gold
reserves the
right
to inspect
and
to
copy
at
any
time
any
record
in
their
original
form
held
by
the
contractor in
relating
to
the
contract for
auditing or for
any
other
purpose."
-- 3 of 9 --
l
Further the contract provides under the heading "Disputes"
by paragraph 4.5.6:
"a. In
any
case,
any
dispute or difference shall arise
between the Torres
Strait
Gold and
the contractoreither
during the progress of the
work
under thecontract or after
determination,
abandonment
or breachof this contract as to the construction of the
same
or
as to
any
matter or thing whatsoever
arising
thereunder or in connection therewith then the
aggrieved party shall
give to the other notice in
writing setting
out in
full
the detailed particulars
of the dispute or difference.
Upon
receipt or issue
of the notice,
Torres
Strait
Gold
shall
give written
notice to the contractor, appointing
a
date,
time and
venue
for
a
conciliation
meeting
to
be
held
to discussin
detail
the dispute or difference
and
may
appoint
such
further
time as
may
be
necessary for the
continuation thereof.
The
parties shall
not
be
legally
represented
at
said
meeting
but
shall
present,
in
their
own
manner,
with the assistance of witnesses
and documentary
evidence, the
details
of
their
respective cases.
b.
If at
the conclusion of the
conciliation
meeting
the
parties
fail
to resolve the dispute or differenceeither
party
may
give
to
the other, within fourteen
days
a
notice
stating that
at
the
expiration of
thirty
days
it
will
proceed
to
have
the dispute or differencereferred to
a
Court
of
competent
jurisdiction in
the
province,
state,
or
territory
and
country
stated in
the
project
data section
1 . 7
and
at
the
expiration
therefore
may
so
proceed."
Matters
proceeded
to
litigation
between
the
first
defendant
as
plaintiff
and
the present
plaintiff
as defendant
by
Writ
No.
3438
of
1988.
An
application
was made
to the
Court
and an
order
made
by
the
Honourable
Mr.
Justice
Ambrose
on
the
16th
September,
1988
provided
that
the
two abovenamed
parties
proceed
to
conciliation.
A
conciliation
meeting
was
held
on
27th September,
1988
attended
by
representatives
of the
present
plaintiff
and
the
present
first
defendant.
It
was
then
apparently
adjourned.
A
further
meeting
was
held
on
9th
February,
1989. Each
was
to
no
avail
and
following
the
second
meeting,
the
plaintiff,
by
its
servant Cahill
wrote
the
letter
of
16th February,
1989
to
the
first
defendant,
foreshadowing
the
commencement
of
litigation.
-- 4 of 9 --
There then emerges a
substantial body of factual dispute.
What
is clear is that certain
documents were requested by the
first
defendant of the present plaintiff
pursuant to clause
4.5.3
(i).
A
particularly unilluminating
body
of correspondence
then ensued between
the present
first
defendant
and
the
plaintiff
and
if
any
spirit
of conciliation
and
cooperation
existed prior to this
course of correspondence such
spirit
had
certainly
evaporated
by
its
conclusion.
By way
of
illustration,
the
letter
of Allco signed
by one
Cahill,
Finance and Commercial
Manager
to the
first
defendant reads:
"In respect of
your
request for access
to
ourtimesheets,
we
reiterate that
they
are of limited
assistance in
developing
a
full
picture of events
and
circumstances
which
form
the basis of our claims.
Factual analysis
and
further
information
which
we
are
providing
to
you
is
derived
from
several sources,
particularly
our
site staff
...
In
any
event
we
confirm
your
verbal
advice
that
any
such
issues
relating to
clause
4.5.3(i)
of the contract are not
relevant toeither
the
immediate
progress
and
conciliation or
the
formulation
of
your foreshadowed
cross-claim.
In
light
of the
above,
we now
suggest
a
suitable
datefor the
further
meeting
would
be
1st
December,
1988."
Mr.
Cahill
continued
in
the
same
belligerent
fashion
by
letter
of
11th January,
1989
to
the
now
Brisbane
solicitors
for
the
first
defendant.
The
letter
concludes:
"Notwithstanding
this
position
we
do
not
wish
to
be
unhelpful
or to
prejudice the
conciliation
meeting
to
be
held
on
9th
February,
1989.
Your
client
has
been
recently
insisting that
he
requires
access
to
ourlabour timesheets
in order
to
sufficiently
document
his
cross-claim
to
allow
its
proper
consideration
in
the
conciliation
proceedings.
If
your
client
would
specify, in
clear
terms,
the relevance
of the
timesheets
to
either
the
liability
or
quantum
of
his
cross-claim,
we
would
give
consideration
to
acceding
to
as
much
of
your
client's
request as
was
reasonable."
The same
theme
was
repeated
by
the
same
author
in
the
letter
to
Chambers,
McNab
of the
27th
January,
1988
which
concludes
"III.
Our
offer
in
the
last
paragraph
of
our
letter
of
11th January,
1989
remains.
If
your
client
has
any
-- 5 of 9 --
genuine and relevant reasons
timesheets to properly detail
should state
them."
for access to
his cross-claim, the
you
In other words,
Mr.
Cahill, in
no doubt what he saw
as
a
tactical
manoeuvre sought to reserve to himself the right to
decide
when
he would
make
proper discovery.
He
then sought
to
put himself in the position of both prospective
litigant
and
prospective judge
in
determining the relevance of
documents
which were
clearly relevant
and
discoverable in
any
process
by
which
a
party
might seek
to
avoid
litigation.
This complete
lack of conciliatory
spirit
also stands in
particular contrast to
what
I
regard are,
upon
a
proper
construction of clause 4.5.3
(i),
the
contractual obligations of
the
parties.
It
was
faintly
argued
by
Mr.
Gore
of
Queen's
Counsel
who
appeared
for the
plaintiff
before
me
that
the
subject clause
only
creates
a
right
during the
life
of the
contract
i.e.
where
the
contract
is
proceeding normally along
its
path.
He
asserted that
it
had no
application
when
a
dispute
is
on
foot
and
hence
the
first
defendants could
not
insist
upon
any
rights
conferred
by
such
clause
save
and
except during
the
execution
of the construction
work
provided
for
in
the
contract.
This
contention
flies
in
the face
of the
clear
meaning
of
the
words
themselves
and
in
my
view
the
contract
provides
a
clear
obligation
on
the
present
plaintiff
to
comply
both during
the
course
of construction
and
in
the event
of
a
dispute.
I
turn
now
to
the
argument
of the
applicant.
Mr.
Keane
of
Queen's
Counsel
argued
that
clause 4.5.6
is
a
valid
"postponement
of the
right
of
access
to
the
Court"
and
referred
me
to
a
long
line
of
authorities collected
by
the
learned authors
Mustill
and
Void
in
the
textbook
"Commercial
Arbitration"
at
page 111.
He
argued
that
the clause
was
a
valid
"postponement
of the
-- 6 of 9 --
Q
right of access to the Court" and referred
me
to the authorities
of Freshwater v. Western Australian Assurance Co. Limited [1933]
1 K.B. 515
at
523
Spurrier v. La Cloch [1902] A.C. 446
at
451
and
Heyman
v. Darwins Limited [1942] A.C. 356
at
377.
Alternatively,
he argued
that the procedure required
by
clause
4.5.6
was
a
condition precedent to action
and
in as
much
that
the claim presented
by
the statement of claim has not
been
the
subject of
submission
bona
fide to the
conciliation
process the
plaintiff's
claim
a
cause
of action
has not accrued.
It
is
clear,
however,
that
all
of the
authorities referred
to
by
Mr.
Keane
are in fact, authorities relating to
arbitration
clauses or
an
obligation to
arbitrate
imposed
pursuant
to
statute.
His argument
was
that parallel
considerations
apply
in the
present circumstances
and
by
the
plaintiff's
failure to
give the
first
defendant access
to
its
documents
as
was
required
by
the
clause 4.5.3
(i)
of the
contract
the
plaintiff
has
frustrated
the
mandatory
processes of clause 4.5.6.
As I
have
indicated
earlier
it
is
my
view
that certainly
the
plaintiff
has
made
no bona
fide
attempt
to
conciliate
in
this
case
and any
conciliation
meeting
that
has been
called
and
attended
was
one which
did
not
comply
with
4.5.6 of
the
contract
the
obligations
imposed
by
4.5.3
(i)
of the
contract
having
been
breached
by
the
plaintiff.
However,
that
is
not the
end
of the
matter.
Mr.
Gore
of
Queen's
Counsel
submits
that
Clause
4.5.6
is
not
an
agreement
to
arbitrate
within the provision of
s.
10
of
the
Arbitration
Act
1973
and
hence
the cases
which
deal
with
Scott
v.
Avery
clauses
have
no
relevance
in
the present
situation.
In
my
view
such
a
submission
must
succeed
for
in
all
cases
-- 7 of 9 --
l
involving arbitration the parties envisage a binding and final
decision of a mutually agreed independent third party not merely
the obligation to conciliate between themselves with the
likelihood of no result.
Here clause 4.5.6 merely provides an agreement to
conciliate (as distinct from one to arbitrate) and as such is
severable from the binding agreement in which it is located.
See Anderson v. G.H. Mitchell & Sons Ltd. 65 C.L.R. 543.
In other words, notwithstanding what I perceive to be a
clear breach of the obligations to conciliate on the part of the
plaintiff, the doctrine that the jurisdiction of the Court
cannot be ousted dominates any other principle that would
require the plaintiff to honour its contractual obligations that
might arise under clause 4.5.6.
In some ways, the situation is similar to the pre
Arbitration Act instances dealt with by the High Court in
Anderson's case at p. 448:
"An agreement to refer disputes, whether existing or
future, to arbitration could, apart from statute be
enforced only by an action for damages against the party
who refused to carry it out ...
Apart from the statutory power of staying an action, the
most express agreement to refer to arbitration and not to
litigate could not prevent recourse to the Courts or
exclude their jurisdiction, that is where the liabilities
in question are absolute."
An appeal was made to the inherent jurisdiction of the
Court to grant a stay the condition precedent to the accruing of
a cause of action not having been met, namely bona fide
conciliation. In my view even if such relief was open this
discretionary relief must be refused as it is abundantly clear
that the parties have taken up positions which effectively rule
out the possibility of compromise and conciliation, the
plaintiff by its assertion that "discovery" does not lie
-- 8 of 9 --
~
pursuant to clause 4.5.3. and the defendants by
their insistence
of such process as
a
precondition of negotiations.
Accordingly, therefore,
I
dismiss the
summons
for
a
stay
with costs including reserved costs to
be taxed.
-- 9 of 9 --
Official source: https://www.sclqld.org.au/caselaw/QSC/1990/037