BUILDSMART PTY LTD and BUILDING SERVICES BOARD [2026] WASAT 90
[2026] WASAT 90
Page 1
JURISDICTION : STATE ADMINISTRATIVE TRIBUNAL
ACT : BUILDING SERVICES (REGISTRATION) ACT
2011 (WA)
CITATION : BUILDSMART PTY LTD and BUILDING
SERVICES BOARD [2026] WASAT 90
MEMBER : MS N OLDFIELD, MEMBER
MR M ANDERSON, SENIOR SESSIONAL
MEMBER
MR S BURNS, SESSIONAL MEMBER
HEARD : 18-19 DECEMBER 2025 AND 23 APRIL 2026
CLOSING WRITTEN SUBMISSIONS LODGED ON
1 MAY 2026
DELIVERED : 31 JULY 2026
FILE NO/S : CC 720 of 2025
BETWEEN : BUILDSMART PTY LTD
Applicant
AND
BUILDING SERVICES BOARD
Respondent
Catchwords:
Building contractor registration - Review of decision refusing to renew
registration - Capacity to meet debts as and when they fall due - Turns on own
facts
-- 1 of 35 --
[2026] WASAT 90
Page 2
Legislation:
Building Services (Registration) Act 2011 (WA), s 18(1), s 18(1)(b), s 18(2),
s 64(1)(a), s 64(2)
Building Services (Registration) Regulations 2011 (WA), reg 18(1), reg 18(2)
State Administrative Tribunal Act 2004 (WA), s 27, s 32(2)
State Administrative Tribunal Rules 2004 (WA), r 39A
Result:
Application unsuccessful
Decision under review affirmed
Category: B
Representation:
Counsel:
Applicant : Mr J Jacobson
Respondent : Mr E Homan
Solicitors:
Applicant : Jacobson and Associates
Respondent : Industry Regulation & Consumer Protection Legal Services
Division
Case(s) referred to in decision(s):
Nil
-- 2 of 35 --
[2026] WASAT 90
Page 3
REASONS FOR DECISION OF THE TRIBUNAL:
Introduction
1 The Building Services Board (Board) refused to renew the
registration of Buildsmart WA Pty Ltd (Buildsmart) as a registered
building contractor on the basis Buildsmart did not meet the financial
requirements for registration.
2 Buildsmart disputed the Board's conclusion and applied for
a review of the decision by the Tribunal.
Issue for Determination
3 The primary issue for determination is whether the correct and
preferable decision is to grant or refuse the renewal of Buildsmart's
registration. Answering that question requires a consideration of
whether Buildsmart meets the financial requirements for registration.
Legislative framework
4 Section 18(1) of the Building Services (Registration) Act 2011
(WA) (BSR Act) provides that the Board must renew the registration of
a building service contractor if the Board is satisfied the relevant
contractor has satisfied eight specified criteria. Section 18(2) states the
Board must not renew the registration if the requirements of s 18(1)
have not been met.
5 One of the specified criteria is that that contractor must have the
capacity to meet debts as and when they fall due.1 In making an
assessment, the Board may consider a broad range of factors.2
6 If a person is aggrieved by a decision to refuse to renew
a registration, they may apply to the Tribunal for a review of that
decision.3
7 The purpose of a review by the Tribunal is not to assess the
original decision, but to determine the correct and preferable decision
as at the time of the review.4 For this reason, the Tribunal may
consider new evidence which was not before the original
decision-maker.
1 BSR Act, s 18(1)(b) and Building Services (Registration) Regulations 2011 (WA) (BSR Regs), reg 18(1).
2 BSR Regs, reg 18(2).
3 BSR Act, s 64(1)(a) and s 64(2).
4 State Administrative Tribunal Act 2004 (WA), s 27.
-- 3 of 35 --
[2026] WASAT 90
Page 4
Background facts
8 Our findings as to material facts on the balance of probabilities are
as follows. Unless indicated otherwise, they were uncontentious.
9 The Board is responsible for the registration of building service
providers. Building and Energy (BE) is part of the WA Department of
Local Government, Industry Regulation and Safety (LGIRS) and
provides services on behalf of the Board.
10 Buildsmart was incorporated on 1 October 2013. Aleksandar
Petrovski is the sole director and secretary. Mr Petrovski has
a background as a residential building scheduler and estimator. He is
not a registered building contractor or building practitioner.
11 Buildsmart was first registered as a building contractor on 14 April
2014. At present Michael Adams is the nominated supervisor for
Buildsmart. Mr Adams is a registered building practitioner and
building contractor.
12 On 16 October 2024 Buildsmart applied to BE for renewal of its
registration.
13 On 5 November 2024 BE wrote to Buildsmart to request
additional information for the purpose of the Board assessing whether
Buildsmart had the capacity to pay its debts as and when they fall due.
The information sought comprised financial statements for 30 June
2023 and 30 June 2024, a list of aged creditors and debtors, details of
work in progress, a current bank statement, evidence of lodgement
and payment of relevant taxes (or terms for payment of the same) and
details of its home indemnity insurance facility.
14 Buildsmart applied for and was granted several extensions of time
in relation to the above request for information and subsequent requests
for information by BE. The final extensions of time expired on
28 August 2025 and 4 September 2025.
15 At a meeting on 14 October 2025 the Board considered this
matter. The Board's decision was to refuse to renew the registration
because it was not satisfied Buildsmart had demonstrated it met the
financial requirements for registration as a building contractor.
This decision was based upon the following analysis:
-- 4 of 35 --
[2026] WASAT 90
Page 5
(a) After re-assessing what appeared to be an overstatement of the
value of trade debtors, it appeared the net asset position as
at 31 December 2024 was -$4,779.74.
(b) Buildsmart was facing a minimum cash flow deficit of $48,397
over the following 12 months.
(c) There was no evidence of Buildsmart having access to an
overdraft or loan facility.
(d) The declared assets of Buildsmart appeared unlikely to be
accepted as security in relation to a new loan facility.
(e) There were indicators of potential insolvency, such as overdue
taxes, cash on demand arrangements with suppliers (which may
have indicated a history of late or failed payments) and its
apparent difficulty in providing accurate and timely accounts to
BE.
Opinion evidence
16 Jodie Guppy and Vy Huynh are both employed by LGIRS.
They produced a report analysing the financial information provided by
Buildsmart, which was relied upon by the Board in its decision
to decline re-registration. Ms Guppy and Ms Huynh prepared a further
report which analysed the evidence provided by Buildsmart in the
course of these proceedings. Both reports expressed the view
Buildsmart has not demonstrated it can pay its debts as and when they
fall due.
17 Both reports state that Ms Guppy and Ms Huynh consider
themselves bound by the obligations which apply to independent expert
witnesses giving evidence in proceedings before the Tribunal.5
18 In its written closing submissions, Buildsmart suggests the
Tribunal should not rely upon these reports because Ms Guppy and
Ms Huynh as employees of LGIRS are not independent. Furthermore,
Buildsmart suggests their involvement in the Board's investigations
means they are 'hopelessly conflicted' and could be considered to be
acting as advocates for the Board.
19 In this proceeding, the Tribunal has heard many expressions
of opinion. Mr McGrath expressed opinions regarding the likely costs
5 State Administrative Tribunal Rules 2004 (WA), (SAT rules) r 39A.
-- 5 of 35 --
[2026] WASAT 90
Page 6
of construction, as did Mr Petrovski, Mr du Toit and Mr Constanzo.
Mr Petrovski, Michael Andruszkiw, Ms Guppy and Ms Huynh
expressed opinions regarding the financial records of Buildsmart and
the conclusions to be drawn from them. Each might be said to have
varying degrees of independence.
20 In court proceedings, there are restrictions on the admissibility of
opinion evidence. The Tribunal is not bound by the rules of evidence.6
Therefore the concern is not whether opinion evidence is admissible,
but whether the evidence is relevant to the issues and if so, the weight
to be given to the opinion.
21 Expert evidence is not immune from the evaluative process.
Indeed, there are countless proceedings in which the Tribunal has not
been persuaded by the view of a particular expert.
22 We have proceeded on the basis the expertise or independence of a
witness are factors to be taken into account when assessing the
relevance of, and weight to be given to, their evidence.
Evidence regarding the financial position of Buildsmart
Work in progress
23 Over the course of the Board's enquiries and the Tribunal
proceedings, Buildsmart provided four schedules of its work in
progress. The more relevant parts of those schedules are annexed to
this decision.
24 As at 31 January 2025 Buildsmart listed eight projects as being in
progress. The earliest contract dates were late December 2020 and
the most recent was September 2024. Five contracts were at the
'slab down' stage, one was at lock up and the most recent was
at the stage of preliminary documentation. In relation to the projects at
the slab down stage, Buildsmart estimated three would be completed in
early April 2025 and two in August 2025.
25 As at 16 November 2025, Buildsmart had 13 projects in progress
(November 2025 WIP). The date of the contracts varied between
March 2021 and November 2025. Seven were at 'slab down' stage and
four were at stages preliminary to construction. Of the four contracts
which remained from the January list, the estimated time for
6 SAT Act, s 32(2).
-- 6 of 35 --
[2026] WASAT 90
Page 7
completion had been significantly extended for two, and one remained
at the preliminary documents stage.
26 As at 21 January 2026, Buildsmart had 11 projects in progress
(January 2026 WIP). All were the same contracts as had been on foot
in November, save for two of the four projects at the preliminary stage
which had fallen away. The estimated date of completion had been
extended for all projects, save that located at The Vines.
27 As at 22 April 2026, Buildsmart had 12 projects in progress
(April 2026 WIP). All were the same contracts as had been in
progress in January of that year, save for the return of a project which
had been omitted from the November 2025 and January 2026 WIP.
Of the total 12 projects listed, two were at the preliminary stage, three
had been varied to cost plus contracts, two remained at slab down and
four estimated dates of completion had been extended.
28 Relevantly to the expert reports considered below, the work in
progress schedules state the total contract price (comprising the original
construction contract plus any variations) as follows:
(a) Treeby site - $305,481 including GST;
(b) Cloverdale A - $316,451 including GST; and
(c) Singleton - $491,312 including GST.
29 We note when converting contract and contract variation prices as
including or excluding GST, there is a small inconsistency between
the contract prices in the Buildsmart work in progress schedules and the
breakdowns of the amounts contained in the expert reports of
Mr du Toit. The parties agreed the total contract prices including
variations and including GST were as contained in the schedules.
In the absence of the contractual documents, we accept the accuracy of
the total contract price as contained in the Buildsmart work in progress
schedules and have taken the breakdown by Mr du Toit as being
sufficiently close for the purposes of our decision.
30 We further note there is no evidence as to whether or not
the relevant owners accept or dispute the variations to the prices of the
contract issued by Buildsmart.
-- 7 of 35 --
[2026] WASAT 90
Page 8
Construction cost overruns
The parties' evidence
31 The Board alleged Buildsmart will incur significant cost overruns
in relation to the completion of its works in progress. In November
2025, Ian McGrath, senior technical officer of BE, assessed the current
costs of the contracts. His report was based on a software estimation of
the floor area of each project and application of the lowest full brick
rate in the Rawlinsons Construction Cost Guide 2025 (Rawlinsons).
He calculated the costs of construction could exceed the contract prices
by an amount exceeding $3.18 million including GST.
32 Mr Petrovski disagreed. He produced schedules detailing his own
analysis of building costs, which estimated the amounts paid by owners
pursuant to the construction contracts would exceed construction costs
by over $540,000 including GST.
The expert evidence
33 During the course of the final hearing, the parties sought and were
granted leave to adduce expert evidence regarding construction costs.
34 Mr du Toit is a qualified quantity surveyor, principal of
BDI Quantity Surveying, with some 30 years experience in the
construction environment in Australia and overseas. He was engaged
by Buildsmart to consider the likely cost to complete projects identified
in this decision as Treeby, Cloverdale A and Singleton.
35 Mr Costanzo is a qualified quantity surveyor, director of
Sage Quantity Surveyors Pty Ltd, with some 20 years' experience in the
commercial and residential construction industries. He was engaged by
the Board to consider the likely cost to complete the Treeby, Cloverdale
A and Singleton projects.
36 The report of Mr du Toit dated 20 January 2026 estimated the
probable total construction costs as at January 2026 (excluding GST,
overheads and profit) as follows:
(a) Treeby - $287,855; and
(b) Cloverdale A - $249,961.
37 The report of Mr Costanzo dated 26 February 2026 estimated the
probable total construction costs as at the date of his report (excluding
-- 8 of 35 --
[2026] WASAT 90
Page 9
GST but including a 10% allowance for overheads and profit) as
follows:
(a) Treeby - $410,126;
(b) Cloverdale A - $322,856; and
(c) Singleton - $669,861.
38 Mr Costanzo's report also estimated the costs to complete
(excluding GST but including a 10% allowance for overheads and
profit) as follows:
(a) Treeby - $356,799;
(b) Cloverdale A - $210,569; and
(c) Singleton - $588,214.
39 In a follow-up report dated 19 March 2026, Mr Costanzo stated he
considered an allowance for overheads and profit as essential.
40 The report of Mr du Toit dated 22 April 2026 estimated the
probable total construction costs as at April 2026 in relation
to Singleton as $463,022 excluding GST, overheads and profit.
If a margin of 10% were applied on account of overheads and profit, his
figure was $509,355.66 excluding GST.7
41 The experts gave concurrent evidence during the hearing.
Mr Costanzo remained firm as to the correctness of his assessments.
Mr du Toit largely also was firm in relation to his assessments,
although he conceded some smaller items included by Mr Costanzo
should also have been included by him. Both agreed that on average,
residential construction costs increase by 0.5% per month. They also
agreed the hostilities in the Middle East (as at 23 April 2026) were
causing significant upwards pressure on costs in addition to the usual
factors.
42 In our view, some of the difference between the experts' opinions
results from differing interpretations as to the inclusions and exclusions
under the construction contracts. The most significant cause for the
disparity between their analyses arose from their methods of analysis.
7 In adding 10% we reached a slightly different figure. We do not consider the difference significant in the
context of these reasons.
-- 9 of 35 --
[2026] WASAT 90
Page 10
43 Mr du Toit had approached the task by comparing the quotes and
invoices supplied by Buildsmart to rates provided by the Cordell
Construction Cost Index (Cordell) and considered the figures
analogous. Accordingly, he used the figures contained in the quotes
and invoices where they were available, and otherwise used the
amounts provided by Cordell.
44 On the other hand, Mr Costanzo did not use those quotes and
invoices. He said he had been engaged to perform an independent
assessment and so assessed the probable costs based on his own
industry knowledge and experience. He did not use the rates provided
by Rawlinsons or Cordell.
45 Mr Costanzo said his industry experience was based upon looking
after the money in relation to projects, which included validating
material and labour quotations and costs before and after construction.
He said his relevant recent experience related to residential
developments including multi-unit developments.
Our consideration and conclusions
46 Without intending any disrespect, we prefer the expert costs
evidence over the evidence of Mr Petrovski and Mr McGrath. We do
not rely upon Mr McGrath's assessments because:
(a) Mr McGrath did not have available to him accurate information
regarding the floor areas of each of the projects;
(b) we have reservations regarding the relevance of the Rawlinsons
figures to the Buildsmart projects;
(c) the evidence does not suggest his training and experience in
relation to the estimating of costs matches that of the costs
experts; and
(d) although we accept Mr McGrath had no personal interest in the
proceedings, neither is he entirely independent.
47 We do not rely upon Mr Petrovski's schedules because:
(a) in the absence of supporting evidence, various line items
appeared to under estimate current industry rates;
-- 10 of 35 --
[2026] WASAT 90
Page 11
(b) the evidence does not suggest his training and experience in
relation to the estimating of costs matches that of the costs
experts; and
(c) as the sole director of Buildsmart, he is not independent.
48 Despite our preference for the expert reports, we have some
reservations regarding their accuracy. In relation to Mr du Toit, the
invoices and quotes upon which he relied were not in evidence. Also, it
was unclear the extent to which he had exercised his own expertise, as
opposed to simply applying the figures supplied to him.
49 Furthermore, Mr du Toit's calculations of floor areas and
construction costs (adding 10% for overheads and profit) result in the
following construction costs per square metre:8
(a) Treeby - $1,481;
(b) Cloverdale A - $1,558; and
(c) Singleton - $1,476.
50 Excluding price increases since January 2026, these rates are
surprisingly low. There is no explanation as to how Buildsmart can
achieve these rates.
51 In relation to Mr Costanzo, he said he ignored the evidence of the
costs actually incurred regarding work already performed and instead
preferred his own (higher) estimate. It was not adequately explained
why paid invoices was not a reliable indicator of costs incurred
in relation the relevant site. We consider this overly artificial.
Delay damages
52 It was uncontroversial and we therefore accept the following:
(a) Pursuant to orders of the Tribunal in unrelated proceedings
between Buildsmart and the relevant homeowners, the due date
for practical completion of construction in relation to the
Bushmead site was 17 December 2025 and in relation to Treeby
was 19 December 2025.
(b) Pursuant to the same proceedings, if the dates for practical
completion are not met, Buildsmart is liable to pay liquidated
8 Rounded to the nearest dollar.
-- 11 of 35 --
[2026] WASAT 90
Page 12
damages of $100 per day (in relation to Bushmead) and $50 per
day (in relation to Treeby) from the due date until the date of
practical completion (liquidated damages).
(c) At the close of the final hearing, neither house had reached
practical completion. Buildsmart estimates both will be
completed on 30 August 2026.
53 Mr Petrovski's evidence was that he had minimised the amount of
liquidated damages by issuing notices of extension of time on
17 November 2025. The notices in evidence were unsigned, undated
and bore no indication of having been sent to or received by the
relevant homeowners. Each notice purported to extend the deadline for
practical completion by 60 working days. Each notice stated the
following reason for the delay, 'Material & Labour Shortage - Bricks as
selected by Owner and Bricklayers and Labours'.9
54 We have reservations as to the validity of the notices extending
time. However, the parties did not lodge evidence regarding the
validity of these notices. We can therefore draw no conclusions
regarding validity.
55 Mr Petrovski claimed the liability of Buildsmart to pay liquidated
damages in relation to the Bushmead site would be approximately
$5,000 to $7,500. He did not explain the basis on which he calculated
these amounts. Mr Petrovski did not disclose any calculations of
liquidated damages in relation to the Treeby site.
56 If the notices are ineffective and if each project is completed on
30 August 2026, the Board estimates Buildsmart's liability to pay
liquidated damages as being $17,500 in relation to Bushmead and
$8,650 in relation to Treeby.
57 The calculations of the Board are based on the assumption
damages are payable in relation to business days. However the orders
of the Tribunal refer to 'day' and not to business or working days.
58 Our calculations of the liquidated damages which Buildsmart
could be liable to pay, in the various circumstances described, are
below.
9 Exhibit 1, pages 99 - 100.
-- 12 of 35 --
[2026] WASAT 90
Page 13
Bushmead Treeby
17 December 2025 - 30 August
2026 (all days)
$25,600
17 December 2025 - 30 August
2026 (working days)
$17,400
19 December 2025 - 30 August
2026 (all days)
$12,700
19 December 2025 - 30 August
2026 (working days)
$8,600
18 March 2025 - 30 August 2026
(all days)
$16,500
18 March 2025 - 30 August 2026
(working days)
$11,400
20 March 2025 - 30 August 2026
(all days)
$8,150
20 March 2025 - 30 August 2026
(working days)
$5,600
59 The Thornlie B project has not appeared in the work in progress
schedules of Buildsmart since January 2025. Mr Petrovski gave
evidence in December 2025 that there had been no progress since the
slab was laid. He intended to issue a default notice regarding
non-payment and to terminate the contract if payment was not made.
60 In its closing submissions, Buildsmart states that the contract has
not been formally terminated, but the owner had clearly repudiated the
contract by 'failing to communicate' with Buildsmart.10 There is
insufficient information for us to be satisfied of the extent (if any) of
the risk of liability this poses to Buildsmart.
Other costs
61 The financial statements of Buildsmart for the years ending 30
June 2024 (2024 financial statement) and 30 June 2025 (2025 financial
statement) provide the following breakdown of expenses:
10 Applicant's Closing Written Submissions filed 1 May 2026 (ACWS) at para 23(p).
-- 13 of 35 --
[2026] WASAT 90
Page 14
2024 2025
Cost of Sales $73,842 $130,102
Direct costs $392,157 $392,029
Expenses $82,357 $74,351
Total $548,356 $596,842
62 The 2024 and 2025 financial statements state that Buildsmart paid
the following wages:
(a) in 2023 - $2,641;
(b) in 2024 - $11,922; and
(c) in 2025 - $12,556.
63 Mr Petrovski's evidence is that:
(a) He does not draw a wage from Buildsmart. To an extent he has
been reliant upon the income of his wife, but he also draws
upon the monies he had lent to Buildsmart.
(b) The wages recorded in the financial statements were paid to
Mr Adams. The company was not very busy, and so Mr Adams
had agreed to work on a part time basis.
64 We note that the schedule of works in progress dated
16 November 2025 indicated Buildsmart had 11 sites under
construction with a further two sites at the preliminary documentation
stage. Ordinarily this would appear to be a substantial amount of work
for a building company comprised of one director and one part-time
employee. Particularly given the sites were widely situated, from
Two Rocks in the north, to Singleton in the south to The Vines in the
east.
65 At the time of the Board's decision, information supplied by
Buildsmart indicated that it had potential liabilities in relation to
superannuation and unpaid GST, PAYG and income tax. The Board
concedes that by the close of the final hearing the evidence indicated
overdue amounts had been paid.
66 In the Board's reasons for decision, one of the concerns noted was
the advice of Buildsmart that most of its suppliers were paid cash on
-- 14 of 35 --
[2026] WASAT 90
Page 15
demand. It said this suggested suppliers were unwilling to provide
Buildsmart credit facilities due to late or non-payment of previous
invoices.
67 This was not specifically addressed by Buildsmart in the final
hearing and Buildsmart did not lodge a statement of its current aged
creditors. In its closing submissions, Buildsmart stated it does not have
any aged creditors and it currently has credit facilities with six separate
suppliers to a total of $165,000.
68 We do not accept the closing submissions as evidence. We are
satisfied Buildsmart informed the Board in 2025 that most of its
suppliers were paid cash on demand. There is no evidence this has
since altered.
Net assets
69 The amended financial statements provided by Buildsmart provide
that its net asset position 2023 to 2025 was as follows:
(a) Financial year ended 30 June 2023 - $53,222;
(b) Financial year ended 30 June 2024 - $1,097;
(c) Financial year ended 30 June 2025 - $43,032.
70 In the 2025 financial statements, over 99% of the current assets are
comprised of trade debtors ($426,093) and work in progress
($126,091).
Trade debtors11
71 Buildsmart stated its trade debtors as at 30 June 2025 comprised
the following:12
Client Amount outstanding
Castiello $8,643.36
LCPL $150,000.00
The Vines $39,325.00
Beckenham $21,120.39
Treeby $42,415.64
Singleton $164,589.00
Total $426,093.39
11 We have not included details of the owners' names because they are not relevant to this decision.
12 Exhibit 1, page 63.
-- 15 of 35 --
[2026] WASAT 90
Page 16
72 Buildsmart stated its trade debtors as at 2 April 2026 (April TD
statement) comprised the following:13
Client Amount outstanding
Castiello $8,643.36
LCPL $150,000.00
The Vines $14,000.00
Beckenham $21,120.39
Treeby $42,415.64
Innaloo A & B $766.57
Thornlie A $5,000.00
Cloverdale A & B $156,316.96
Total $398,262.92
73 In relation to Castiello:
(a) Mr Petrovski stated Buildsmart was working with the owner in
relation to payment of the account.
(b) The Board considered this should be disregarded as an asset of
Buildsmart because the debt was over 10 years old and the last
part payment was made by the client on 19 November 2021.
(c) Buildsmart has not lodged evidence of receiving payment from
the client.
(d) On the basis of the April TD statement, we conclude this debt
remains outstanding. We agree with the Board the prospects of
Buildsmart now receiving payment are too slim for the debt to
be considered as an asset.
74 In relation to LCPL:
(a) Mr Petrovski stated Buildsmart issued an invoice in the amount
of $150,000 prior to 30 June 2024 before work had commenced.
The revised 2024 financial statement recategorized this sum
from contract income/sales to unearned revenue. This project is
not listed in the most recent statement of work in progress and
Buildsmart has not lodged evidence indicating if or when work
13 Exhibit 10, page 12.
-- 16 of 35 --
[2026] WASAT 90
Page 17
might be expected to commence. Accordingly, we consider it
appropriate to remove this sum as an asset of Buildsmart.
75 In relation to Beckenham:
(a) The Board considered this should be disregarded as an asset of
Buildsmart because it was likely uncollectable. The job was at
'preliminary documentation' stage, the invoice was dated
9 September 2024, the job had not advanced since it was first
included in the works in progress schedule dated 31 January
2025 and Buildsmart had acknowledged the job would likely
not proceed because finance had not been secured by the owner.
(b) Mr Petrovski said works were suspended by mutual agreement
due to the outstanding balance. On 27 November 2025 he was
informed the owner wished the project to restart. He had
arranged a meeting to take place in December 2025.
(c) Buildsmart has not lodged evidence of payments received from
the owner, the outcome of the proposed meeting, nor any other
change in circumstances.
(d) We agree with the Board the debt appears too unlikely to now
be paid to be included as an asset of Buildsmart.
76 In relation to Treeby:
(a) The Board considered this should be disregarded as an asset of
Buildsmart because the amount appeared to have been unpaid
since at least 30 September 2024.
(b) Mr Petrovski stated the owner had agreed to pay the outstanding
amount in instalments of $10,000 as each new progress claim is
rendered. There is no other evidence of the agreement, for
example, a written agreement or text messages confirming an
oral agreement. Also, despite progress in construction, the
amount outstanding appears to be unchanged.
(c) There is no information regarding how this debt arose.
The amount does not match any instalments in the progress
payment schedule.
(d) The project to which this debt relates is one to which
Buildsmart has an apparent liability to pay compensation.
Although it was not suggested by Buildsmart, we speculate the
-- 17 of 35 --
[2026] WASAT 90
Page 18
parties could arrange to set off their respective debts to each
other. Therefore it may be inaccurate to disregard this amount.
However, if the least delay damages applied, the
amount recoverable in relation to Treeby might be $36,815.64.
If the maximum amount of delay damages were payable by
Buildsmart (but still assuming practical completion on
30 August 2026) the amount recoverable may only be
$29,715.64.
77 In relation to The Vines:
(a) Mr Petrovski stated Mr and Ms Adams had paid the full amount
outstanding in July 2025. Buildsmart did not lodge evidence of
the receipt of those funds. The current debt is said to have been
outstanding for more than 90 days. The Board does not dispute
the status of this as an asset.
78 The Board does not dispute that the amounts owed in relation to
Innaloo A and B, Thornlie A and Cloverdale A and B are assets.
79 On the basis of the foregoing, our assessment of the trade debtors
of Buildsmart (as at 2 April 2026 ) is as follows:
Client Amount outstanding
Castiello $0
LCPL $0
The Vines $14,000.00
Beckenham $0
Treeby $36,815.64
Innaloo A & B $766.57
Thornlie A $5,000.00
Cloverdale A & B $156,316.96
Total $212,899.17
Work in progress
80 The April 2026 WIP anticipates the following upcoming
payments:14
Contract Next payment Estimated date of
next payment
Total payment
claims remaining
Treeby $40,504.00 23/4/2026 $202,432.00
Bushmead $72,101.00 15/5/2026 $216,432.00
14 Exhibit 17.
-- 18 of 35 --
[2026] WASAT 90
Page 19
Victoria Park A - - -
Innaloo A $53,994.00 30/4/2026 $162,111.00
Innaloo B $55,155.00 30/4/2026 $165,595.00
Singleton $98,262.00 4/5/2026 $294,788.16
Cloverdale A $63,290.00 22/5/2026 $140,002.00
Cloverdale B $63,290.00 22/5/2026 $140,002.00
The Vines $60,500.00 15/5/2026 $353,925.00
Thornlie A - - -
81 Buildsmart has not explained why Victoria Park A is listed as
a work in progress and yet no further payments are anticipated.
We observe it is said to be at lock up stage, and Mr Petrovski gave
evidence the scope of works was to construct to the lock up stage.
Our conclusion is that works at Victoria Park A are complete and it
should not have been included in the April 2026 WIP.
82 Consistent with our above conclusion, the cashflow forecast
lodged on 2 April 2026 (forecast) does not anticipate any further funds
being expended or received in relation to Victoria Park A.
83 Inconsistently with the April 2026 WIP, the forecast anticipates in
relation to Thornlie A that Buildsmart will expend $3,856 in early
April 2026 and receive $5,000 by 1 May 2026.
84 As noted above,15 estimated dates of completion had extended
significantly over the course of the schedules of works in progress
produced in evidence. The most recent (the April WIP) anticipates all
current projects will be completed in July or August 2026 (save for
those in relation to which no date is provided). The cashflow forecast
is not inconsistent, because it only extends to the end of July 2026.
Cashflow
85 Initially, Buildsmart did not provide a cash flow analysis either
during the Board's investigation or for the initial part of the final
hearing in December 2025.
86 In their report which analysed the position of Buildsmart as at
3 December 2025, Ms Guppy and Ms Huynh included 'an indicative
assessment' of Buildsmart's cash flow between 17 November 2025
to 16 November 2026.16 They considered Buildsmart was likely to
experience a shortfall at a minimum of $72,921. This assessment was
15 See paras [25] - [27].
16 Exhibit 1, page 1559.
-- 19 of 35 --
[2026] WASAT 90
Page 20
largely based upon estimated cost overruns in relation to the Treeby
and Bushmead sites, but also included the estimated cost of overheads
and liabilities in relation to tax, superannuation, credit facilities and
liquidated damages.
87 When the final hearing resumed in April 2026, Buildsmart had
filed a cash flow forecast for the period 3 April 2026 to 31 July 2026.
88 Buildsmart submits the forecast was drafted by Mr Andruszkiw's
accountancy firm and this together with the following statement of
Mr Andruszkiw demonstrates the 'high probative' value of the
forecast:17
While the level of supporting detail may be limited, this does not of
itself invalidate the usefulness of the CFF as a financial planning tool.
In real terms, the cashflow forecast for business of the Applicant's scale
is not a complex task and does not contain significant assumptions.
In my view and the way that I have guided the Applicant in its
preparation was to in detail assess the timing of his progress claims and
payment thereof along with the cost spent profile having consideration
to creditor payment terms.
89 We do not agree with Buildsmart's interpretation. In our view the
above statement by Mr Andruszkiw indicates:
(a) Buildsmart prepared the forecast, with guidance from
Mr Andruszkiw; and
(b) Mr Andruszkiw considers the forecast a planning tool.
90 A planning tool is not the same as something that is objectively
true. A planning tool may be more or less accurate, depending upon the
accuracy of the data inputs. In this regard we note Mr Andruszkiw's
evidence that, in preparing financial reports for Buildsmart and
expressing the view it satisfied the financial requirements for
registration, he had relied upon the information provided to him by
Buildsmart.
91 The forecast was not accompanied by a list of the assumptions,
inclusions and exclusions applied to the forecast. There are no
supporting documents explicitly linked to the forecast. In its written
closing submissions, Buildsmart stated that if the Board 'had requested
additional "granular" information regarding the cash flow forecast, they
17 Exhibit 20, pages 2 - 3.
-- 20 of 35 --
[2026] WASAT 90
Page 21
could have requested such information, which would have been
provided'.18 With respect, that is misconceived. In these proceedings it
was incumbent upon Buildsmart to lodge all relevant evidence in
support of its application that it meets the financial requirements for
registration.
92 The forecast provides that '[d]rawings' of $12,000 are expected
to occur on 17 April, 15 May, 19 June and 17 July 2026. There is no
further evidence regarding these amounts. The Board assumed,
consistently with Mr Petrovski's evidence,19 that these amounts
represent payments to Mr Petrovski in reduction of the sums he had
loaned to Buildsmart. However, in its closing written submissions,
Buildsmart stated these are payments to Mr Adams 'to compensate him
for his services to' Buildsmart.20 However, it has not been explained:
(a) if these payments are in the nature of wages to Mr Adams as the
nominated supervisor, why those amounts were not recorded in
the forecast as part of '[s]upervisor [w]ages' and whether this
means there has been an undercalculation of Buildsmart's
liability to pay superannuation and PAYG; and
(b) if they are not wages, then the basis upon which Buildsmart is
making payments to Mr Adams.
93 Our further observations in relation to this forecast are:
(a) Most weeks are forecast to have a net inflow of money.
Over the 18 weeks, it is forecast Buildsmart will have a total net
inflow of approximately $176,178.
(b) Buildsmart has not included a schedule linking the expected
stages of construction of each project to the expected cash
inflows and outflows.
(c) It is not clear how the date of the expected inflows has been
calculated, for example, date of expected completion of
the relevant stage of construction, within seven days of issue
of the invoice or at some other time. As observed above,21 not
every client of Buildsmart has paid or is paying in a timely
manner.
18 ACWS at para 23(a).
19 See para [63] above.
20 ACWS at para 23(k).
21 See para [71] - [79].
-- 21 of 35 --
[2026] WASAT 90
Page 22
(d) Buildsmart has not explained the basis of its calculations of the
outflows directly related to construction. We are unable to
ascertain whether the outflows are taken from Mr Petrovski's
schedules of costs,22 Mr du Toit's schedules of costs or are
calculated on some other basis.
(e) Buildsmart does not appear to have included in its expected
indirect outflows the cost of liquidated damages, nor liability to
pay interest on loans provided by Mr and Ms Petrovski or
Mr Adams.
(f) General overheads total $18,649, over a period of 119 days.
If extrapolated to a full year, the overheads are approximately
$57,200. This appears low, in comparison to the overheads in
the financial statements for the 2023 ($90,754), 2024 ($80,735)
and 2025 financial years ($70,259). Particularly so, considering
overheads in the financial statements are amounts reduced by
calculations for depreciation. There is no information as to the
basis on which the general overheads in the forecast were
calculated.
(g) 'Supervisor wages' of $14,000 are expected to be paid on 5 June
and 31 July 2026. That is not consistent with payments of
$14,449 to Mr Adams on 27 January, 6 February and
12 February 2026, recorded in a Buildsmart bank statement for
the period 2 January to 2 April 2026.
(h) Only one payment of legal fees is anticipated, on 10 April 2026.
It is unclear if that is the final amount, or if Buildsmart should
have anticipated an additional payment after the conclusion of
the hearing on 23 April 2026 and the lodging of written closing
submissions in May 2026.
(i) It is not stated whether the amounts in the forecast are inclusive
or exclusive of GST. It is unclear how the GST liability of
$21,000 for the first quarter has been calculated. Particularly
given the total net GST paid for the 2025 financial year was
$18,285.
22 See para [32] above.
-- 22 of 35 --
[2026] WASAT 90
Page 23
Capacity to raise further funds
94 It was uncontentious and we therefore accept Buildsmart does not
own assets which could generate additional funds either by sale or as
security for lending.
95 In December 2025, Mr Petrovski gave evidence that he would
have access to the following funds:
(a) $126,000 obtained through the restructure of a personal loan
secured against his home; and
(b) an inheritance of approximately $400,000 expected to be
received no earlier than the middle of 2026.
Loan restructure
96 Mr Petrovski said in his affidavit that from the restructure of the
personal loan, he intended to lend 'at least $100,000' to Buildsmart
if required.23 On 18 December 2025, Mr Petrovski said the loan would
be advanced by the relevant financial institution in the near future.
97 Buildsmart did not lodge evidence of the personal loan to Mr and
Ms Petrovski, nor an agreement for the on-lending of those funds to
Buildsmart.
98 In evidence are various bank statements, most which do not
address the relevant period. Buildsmart lodged what appears to be
a report from accounting software listing bank transactions between
21 October 2025 and 1 April 2026. That report contains the following
transactions which include in the description 'A Petrovski' or
'Aleksandar Petrovski':
Date Monies Paid Date Monies Received
27 October $13,418.04 4 November $7,000.00
17 February $3,000.00 12 November $20,000.00
10 March $500.00 19 December $20,000.00
16 March $500.00 29 December $10,000.00
16 March $10,000.00 7 January $15,000.00
19 March $500.00 9 January $50.00
12 January $5,000.00
15 January $10,000.00
19 January $5,000.00
22 January $5,000.00
22 January $5,000.00
23 Exhibit 1, page 128.
-- 23 of 35 --
[2026] WASAT 90
Page 24
27 January $10,000.00
5 February $500.00
Total $27,918.04 $112,550.00
99 There is no evidence regarding the source of the funds paid by
Mr Petrovski to Buildsmart, nor the reason for those payments.
100 It is possible the source of the funds was the restructure of the
personal loan referred to at paragraph [97] above. If so, it would appear
further advances by Mr Petrovski from the restructure are unlikely - on
the basis of his evidence regarding the loan restructure and that no
further advances were made after 5 February 2026.
101 The solicitor for Buildsmart wrote in correspondence filed with
the Tribunal on 2 April 2026 that Mr and Ms Petrovski 'do not have any
further funds available to lend' to Buildsmart.24 Whilst this
correspondence does not constitute evidence, it may be considered
consistent with the above evidence.
Inheritance
102 We place no reliance upon Buildsmart receiving funds via
Mr Petrovski's anticipated inheritance because:
(a) There is no evidence of the value of the estate, Mr Petrovski's
entitlement to an inheritance, the value of his share or the
executor's estimation of when distribution to the beneficiaries
will be effected.
(b) It is speculation to say, if or when Mr Petrovski receives an
inheritance, he will lend some or all those funds to Buildsmart.
He is under no obligation to do so. Depending on the
circumstances which then exist, it may be imprudent for him to
do so.
103 Additionally, Mr Petrovski gave evidence that Mr Adams had
provided a loan facility. This will be addressed below.25
24 Exhibit 10, page 2.
25 See paras [109] - [114].
-- 24 of 35 --
[2026] WASAT 90
Page 25
Michael Adams
Connection to Buildsmart
104 Mr Adams holds the following roles in relation to Buildsmart:
(a) nominated supervisor (Mr Petrovski is not a registered building
practitioner or registered building contractor);
(b) employee;
(c) client (Mr and Ms Adams own the site located at The Vines);
and
(d) lender.
105 Furthermore, Mr Petrovski states that he and Mr Adams have an
agreement that, assuming the company is able to renew its builder
registration, Mr Adams will be brought in as a director and shareholder
of Buildsmart.
106 Mr Petrovski stated that Mr Adams had performed more work for
Buildsmart than the wages figures indicated. He said Mr Adams had
been willing to do that in expectation of becoming a director and
shareholder of Buildsmart. Mr Adams is expected to purchase that
interest in Buildsmart, but there will be some set-off on account of the
work he had performed without payment.
107 Mr Petrovski said he had not undertaken any enquiries regarding
Mr Adams' financial capacity to purchase an interest in Buildsmart.
He understands through general conversations that Mr Adams has
substantial financial resources as a result of selling a property for
almost $1 million.
108 Mr Petrovski said these arrangements with Mr Adams are not in
writing. He said that if for any reason these plans did not eventuate,
there was no likelihood Mr Adams might want some financial
compensation in relation to his unpaid work.
Lending arrangements
109 On 8 December 2025 Mr Adams wrote a letter to Mr Petrovski
which stated he was willing to provide Buildsmart with a loan facility
to a maximum of $200,000 on the following conditions:
(a) interest of 5% per annum on amounts advanced;
-- 25 of 35 --
[2026] WASAT 90
Page 26
(b) monthly payments to be interest only for the first 12 months and
thereafter interest and principal;
(c) Mr and Ms Petrovski provide security which could be registered
against the title of their property; and
(d) a written loan agreement be prepared.
110 Mr Petrovski gave evidence that, as at 18 December 2025,
Mr Adams had advanced $35,000 to Buildsmart. Mr Petrovski stated
Mr Adams' loan would be secured by a personal guarantee and/or upon
real estate, though not by means of a second mortgage. He said there
was no written loan agreement, though that was intended.
111 On 3 April 2026 Buildsmart lodged a document described as
a loan statement which states:
(a) advances were made by Mr Adams on 12, 15 and 16 December
2025 and on 9 February 2026;
(b) the total sum borrowed from Mr Adams is $45,000;
(c) interest is payable at 10% per annum; and
(d) Buildsmart has made no repayments.
112 The author of the loan statement has not been disclosed.
113 There is no evidence of a written loan agreement or security.
The written closing submissions of Buildsmart state the existence of
a loan facility of $200,000 is proven by the loan statement.
This suggests there is no written loan agreement or security.
114 Clearly there are inconsistencies:
(a) Mr Adams' letter suggests a formal loan agreement and
registered security were a condition of providing the funds.
However, the loan statement suggests he made the first advance
only days later and has continued to make advances in the
absence of a written agreement and security.
(b) The letter states interest was to be paid at 5% per annum but
the loan statement refers to interest at 10% per annum.
-- 26 of 35 --
[2026] WASAT 90
Page 27
(c) The letter states there were to be monthly repayments, but the
loan statement indicates that between December 2025 and
April 2026 no repayments have been made.
115 Beyond Mr Adams' letter expressing a willingness to lend
$200,000, there is no evidence he had or has the funds to lend. There is
no evidence he continues to be willing to make further payments.
In the absence of a signed agreement, he appears to have no obligation
to lend further funds.
The Vines
116 A construction contract dated 10 July 2025 was signed by Mr and
Ms Adams and Mr Petrovski on behalf of Buildsmart. The works are
described as a double storey residence, and provides for ten progress
payments, from deposit to practical completion. However, the
November 2025 WIP states The Vines project is only being taken to
lock up. This is repeated in the January 2026 and April 2026 WIPs and
in Mr Petrovski's written witness statement.
117 Mr Petrovski explained this by saying that from a cost perspective,
Buildsmart is taking the construction to lock up. From that point the
owners (Mr and Ms Adams) will manage and pay the trades people.
However, Buildsmart will continue to have a supervisory role until
completion.
118 In response to the suggestion this sounded like licence lending,
Mr Petrovski said Mr Adams holds licences as a building practitioner
and building contractor. Mr Petrovski was asked why Mr Adams did
not then complete construction under his own name, but Mr Petrovski
had no answer.
Our comments
119 Mr Adams' relationship with Buildsmart is unusual and has not
been adequately explained. There is a lack of documentation and
inconsistencies in the evidence. Accordingly, we have reservations as
to the reliability of what we have been told regarding arrangements
between Mr Adams, Buildsmart and Mr Petrovski.
Consideration
120 We do not consider the forecast to be reliable. Without the
supporting documents and a list of the assumptions, inclusions and
-- 27 of 35 --
[2026] WASAT 90
Page 28
exclusions which underpin to the forecast, we are left with too many
unanswered questions.
121 The below table compares the income Buildsmart expects to
derive from completing construction on the Treeby, Cloverdale A and
Singleton sites26 with the cost to complete construction as estimated by
Mr Costanzo.
Site Total payment
claims
remaining
Costanzo estimated
cost to complete
Profit/loss
Treeby $202,432.00 $356,799.00 ($154,367.00)
Cloverdale A $140,002.00 $210,569.00 ($70,567.00)
Singleton $294,788.16 $588,214.00 ($293,425.84)
($518,359.84)
122 Mr Du Toit did not estimate the cost of completing construction.
We have considered the stage of construction of each site provided in
the January 2026 WIP and deleted those parts of his estimate which
appear to relate to completed works. Mr Du Toit's estimate in relation
to Singleton included allowances for costs, overheads and GST, whilst
his estimates for Treeby and Cloverdale A did not. For consistency
with Mr Costanzo's figures, we have ascertained Mr Du Toit's estimates
excluding costs, overheads and GST, deleted completed works and then
added 10% for costs and overheads.
Site Total payment
claims remaining
Du Toit estimated
cost to complete
Profit/loss
Treeby $202,432.00 $289,142.17 ($86,710.17)
Cloverdale A $140,002.00 $187,524.46 ($47,522.46)
Singleton $294,788.16 $475,050.69 ($180,262.53)
($314,495.16)
123 The parties selected the Treeby, Cloverdale A and Singleton sites
for assessment by the quantity surveyors on the basis these properties
were considered to be representative of the projects identified in the
lists of works in progress.
124 We therefore apply the above figures to all of the projects by
calculating the average loss per project in relation to the Treeby,
26 As stated in the April 2026 WIP.
-- 28 of 35 --
[2026] WASAT 90
Page 29
Cloverdale A and Singleton sites and then multiplying the average
figure by eight, which is the total of the sites apparently under
construction in the April 2026 WIP.27
125 Using Mr Du Toit's estimations, we calculate the average loss as
$104,831.72 per project, which means a loss of $838,653.76 across
eight projects. Using Mr Costanzo's estimations, we calculate the
average loss as $172,786.61 per project and thus a total loss of
$1,382,292.88 in relation to eight projects.
126 We note Buildsmart stated all projects would have reached
practical completion (and thus these costs would have been incurred in
full) by 30 August 2026.
127 If we were to accept the forecast as accurate, Buildsmart will incur
overheads and statutory outgoings of $169,749 over 119 days to 31 July
2026. Which could mean $212,542.86 over 149 days to 30 August
2026.
128 Buildsmart may have the following resources to meet these costs
(ignoring other likely costs):
(a) cash at bank of approximately $32,619.84, as it stood on 2 April
2026;
(b) payments by trade debtors of $212,749.17; and
(c) the remainder of the loan funds from Mr Adams, being
$155,000 (assuming the funds were advanced).
129 Therefore, on a rough calculation, Buildsmart may have financial
resources of approximately $400,370 to meet outgoings of
approximately $1,051,196 (based on Mr Du Toit's estimations and not
including other costs). The disparity between financial resources and
outgoings would be greater if Mr Costanzo's estimates were applied.
Conclusion
130 For the reasons described above, we are not satisfied Buildsmart
has the capacity to meet debts as and when they fall due.
131 Therefore, we must dismiss the application of Buildsmart and
affirm the decision of the Board.
27 See para [82] above.
-- 29 of 35 --
[2026] WASAT 90
Page 30
Orders
The Tribunal orders:
1. The decision of the respondent made on 14 October 2025 to
refuse the applicant's application for registration as a building
service practitioner under the Building Services (Registration)
Act 2011 (WA) is affirmed.
2. The stay (of the operation of the decision of the respondent
made on 14 October 2025) ordered by the Tribunal in this
proceeding on 23 October 2025 is lifted.
-- 30 of 35 --
[2026] WASAT 90
Page 31
Annexure 1
Work in progress as at 31 January 2025
Contract Contract date Time to complete
from commencement
Date of
commencement
Estimated
completion date
Current stage of
works
Contract value incl
variations
Contract amount not
yet invoiced
Thornlie A 10/12/2020 ? 6/4/2023 1/4/2025 Slab down $202,609 150,000
Thornlie B 11/12/2020 ? 6/4/2023 1/4/2025 Slab down $201.019 150,000
Treeby
(residential,
fixed price)
30/3/2021 260 working days 8/4/2023 1/8/2025 Slab down $305,481 $280,000
Scarborough 2/8/2022 ? 10/10/2022 1/5/2025 Lock up 663.520 159,245
Bushmead
(residential,
fixed price)
19/11/2023 200 working days 11/3/2024 1/8/2025 Slab down $360,503 $265,100
Victoria Park A
(commercial,
cost plus)
27/3/2024 500 working days 19/8/2024 1/8/2025 Upper floor roof
cover
$800,000 $654,302
Victoria Park B 4/7/2024 ? 10/12/2024 1/4/2025 Slab down 99,000 50,000
Beckenham
(residential)
9/9/2024 TBA TBA TBA Preliminary
documents
$58,620 $21,120
-- 31 of 35 --
[2026] WASAT 90
Page 32
Annexure 2
Work in progress as at 16 November 2025
Contract Contract date Time to complete from
commencement
Date of
commencement
Estimated
completion date
Current stage of
works
Contract value
incl variations
Contract
amount not
yet invoiced
Treeby
(residential, fixed price)
30/3/2021 260 working days 8/4/2023 30/4/2026 Slab down $305,481 $280,000
Bushmead
(residential, fixed price)
19/11/2023 200 working days 11/3/2024 30/4/2026 Slab down $360,503 $265,100
Victoria Park A
(commercial, cost plus)
27/3/2024 500 working days 19/8/2024 1/8/2025 Upper floor roof
cover
$800,000 $654,302
Beckenham
(residential)
9/9/2024 TBA TBA TBA Preliminary
documents
$58,620 $21,120
Innaloo A
(residential, fixed price)
10/11/2025 250 working days 1/8/2025 30/4/2026 Slab down $269,968 $216,105
Innaloo B
(residential, fixed price)
10/11/2025 250 working days 1/8/2025 30/4/2026 Slab down $275,773 $220,750
Mt Lawley
(residential)
28/4/2025 130 working days TBA TBA Deposit/building
permit
$10,000 $5,000
Singleton
(residential, fixed price)
7/4/2025 250 working days 10/7/2025 6/4/2026 Wall frames $491,312 $393,050
Cloverdale A
(residential, fixed price)
10/7/2025 260 working days 26/10/2025 30/6/2026 Slab down $316,451 $254,013
Cloverdale B
(residential, fixed price)
21/4/2025 260 working days 26/10/2025 30/6/2026 Slab down $316,451 $254,013
The Vines
(Residential, lock up only,
fixed price)
10/7/2025 380 working days 20/8/2025 30/6/2026 Slab down $605,000 $505,175
Cooloongup
(residential, fixed price)
21/7/2025 TBA TBA TBA Preliminary
documents
$4,000 Nil
Two Rocks
(residential, fixed price)
10/9/2025 TBA TBA TBA Preliminary
documents
$42,270 Nil
-- 32 of 35 --
[2026] WASAT 90
Page 33
Annexure 3
Work in progress as at 21 January 2026
Contract Contract date Time to complete
from commencement
Date of commencement Estimated completion date Current stage of works
Treeby
(residential, fixed price)
30/3/2021 260 working days 8/4/2023 30/7/2026 Slab down
Bushmead
(residential, fixed price)
19/11/2023 200 working days 11/3/2024 30/7/2026 Slab down
Victoria Park A
(commercial, cost plus)
27/3/2024 500 working days 19/8/2024 1/5/2026 Ground floor wall cladding
90%
Beckenham
(residential)
9/9/2024 TBA TBA TBA Preliminary documents
Innaloo A
(residential, fixed price)
10/11/2025 250 working days 1/8/2025 30/7/2026 Brickwork plate height 90%
Innaloo B
(residential, fixed price)
10/11/2025 250 working days 1/8/2025 30/7/2026 Brickwork plate height 0%
Mt Lawley
(residential)
28/4/2025 130 working days TBA TBA Deposit/building permit
Singleton
(residential, fixed price)
7/4/2025 250 working days 10/7/2025 6/7/2026 Wall frames manufacturing
Cloverdale A
(residential, fixed price)
10/7/2025 260 working days 26/10/2025 30/7/2026 Brickwork plate height
Cloverdale B
(residential, fixed price)
21/4/2025 260 working days 26/10/2025 30/7/2026 Brickwork plate height
The Vines
(Residential, lock up only,
fixed price)
10/7/2025 380 working days 20/8/2025 30/6/2026 Upper floor slab reo
-- 33 of 35 --
[2026] WASAT 90
Page 34
Annexure 4
Work in progress as at 22 April 2026
Contract Contract date Time to complete from
commencement
Date of commencement Estimated completion date Current stage of works
Treeby 30/3/2021 260 working days 8/4/2023 30/8/2026 Brick plate height – timber onsite
Bushmead 19/11/2023 200 working days 11/3/2024 30/8/2026 Brick plate height – timber onsite
Victoria Park A 27/3/2024 500 working days 19/8/2024 30/6/2026 Lock up
Beckenham 9/9/2024 TBA TBA TBA Preliminary documents
Innaloo A 10/11/2025 250 working days 1/8/2025 30/7/2026 Roof frame complete
Innaloo B 10/11/2025 250 working days 1/8/2025 30/7/2026 Roof frame complete
Mt Lawley 28/4/2025 130 working days TBA TBA Deposit/building permit
Singleton 7/4/2025 250 working days 10/7/2025 6/7/2026 Wall frames and roof frames Install
Cloverdale A 10/7/2025 260 working days 26/10/2025 30/7/2026 Roof cover complete
Cloverdale B 21/4/2025 260 working days 26/10/2025 30/7/2026 Roof cover complete
The Vines 10/7/2025 380 working days 20/8/2025 30/7/2026 Upper floor brickwork to start
Thornlie A 10/12/2020 - 20/3/2023 30/7/2026 Roof frame complete
-- 34 of 35 --
[2026] WASAT 90
Page 35
I certify that the preceding paragraph(s) comprise the reasons for decision of
the State Administrative Tribunal.
MS N Oldfield, MEMBER
31 JULY 2026
-- 35 of 35 --