Akhavan v Queensland Building and Construction Commission and Anor [2026] QCAT 361
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Akhavan v Queensland Building and Construction
Commission and Anor [2026] QCAT 361
PARTIES: ARTIN AKHAVAN
(applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION
COMMISSION
(first respondent)
ICONIC LINE CONSTRUCTIONS PTY LTD
(second respondent)
APPLICATION NO/S: GAR239-24
MATTER TYPE: General administrative review matters
DELIVERED ON: 5 August 2026
HEARING DATE: 13 March 2026
HEARD AT: Brisbane
DECISION OF: Member Lambie
ORDERS: The first respondent’s decision of 4 March 2024 is set
aside and substituted with a decision that its decision of
10 January 2024 is confirmed.
CATCHWORDS: GENERAL ADMINISTRATIVE REVIEW –
PROFESSIONS AND TRADES – BUILDERS –
INTERNAL REVIEW OF DECISION A DOMESTIC
BUILDING CONTRACT HAS BEEN VALIDLY
TERMINATED – CONTRACTS – DISCHARGE,
BREACH AND DEFENCES TO ACTION FOR BREACH
– where initial decision that contract was terminated at the
default of the builder – where internal review finds mutual
termination or abandonment – where the applicant brings an
application to review the decision
Queensland Building and Construction Commission Act
1991 (Qld), ss 67WA, 85A, 86, 87, Schedule 6
Queensland Civil and Administrative Tribunal Act 2009
(Qld) ss 17, 20
Agropolou v Shkolyar (Domestic Building) [2011] VCAT
2213
Cedar Meats (Aust) Pty Ltd v Five Star Lamb Pty Ltd
[2013] VSC 164
CGM Investments Pty Ltd v Chelliah [2003] FCA 79
-- 1 of 18 --
2
Imam v Life (China) Company Limited [2023] QCA 19
Mareva Building Consultants v Zevon and Zevon [2013]
ACTACA 28
Ryder v Frohlich [2004] NSWCA 472
Torua v Sariklis (Domestic Building) [2012] VCAT 144
Yan v Brown Bros Cabinet Work Pty Ltd (Domestic
Building) [2013] VCAT 1623
APPEARANCES &
REPRESENTATION:
Applicant: Y Furgan, instructed by Gibbs Wright Litigation Lawyers
First Respondent:
Second Respondent:
N Congram, instructed by K Steward, Queensland Building
and Construction Commission
Self-represented
REASONS FOR DECISION
[1] This is an application for review of a decision of the first respondent (‘the QBCC’ or
‘the Commission’) of 4 March 2024 (‘the Decision’), which set aside its decision of
10 January 2024 (‘the Original Decision’) that a contract between the applicant and
the second respondent had been validly terminated at the default of the second
respondent. The Decision was that the contract had been mutually terminated or
abandoned and that, therefore, the applicant’s claim against the statutory insurance
scheme was disallowed.
[2] The applicant seeks an order that the decision be set aside and replaced with a decision
that he validly terminated the contract.
Background
[3] The applicant, Mr Akhavan, is a joint owner of the property located at 16 Page Street,
Everton Park. On 21 June 2022, he and the second respondent (‘the Builder’) entered
into a contract for the construction of a new home at the property for a price of
$951,966.
[4] The deposit amount under the contract was $47,598, which was paid in four
instalments between July and October 2022.
[5] On 9 May 2023, the Builder obtained building approval for the works.
[6] On 15 May 2023, the Builder issued a variation (referred to the evidence as Variation
4) to Mr Akhavan, purporting to increase the contract price by $253,265.
[7] Mr Akhavan and the Builder met on 11 July 2023 to discuss the variation and
corresponded on the issue until about 29 August 2023.
[8] On 8 August 2023, Mr Akhavan submitted a complaint to the QBCC seeking
assistance for the return of the deposit on the basis that work had not started at the
property. This commenced a claim under the statutory insurance scheme under the
Queensland Building and Construction Commission Act 1991 (Qld) (‘the QBCC
Act’).
-- 2 of 18 --
3
[9] Mr Akhavan’s solicitors wrote to the Builder between 13 September 2023 and 1
November 2023. These letters were:
(a) a demand of 13 September 2023 that the Builder commence the works within
20 business days, to which the builder did not respond;
(b) a notice to remedy breach dated 13 October 2023, requiring the builder to rectify
its substantial breach of the contract by commencing the works within 10
business days; and
(c) a letter of 1 November 2023 terminating the contract with immediate effect.
[10] On 10 January 2024, the QBCC made the Original Decision and the deposit amount
was paid to Mr Akhavan.
[11] On 4 March 2024, the QBCC made the Decision, which set aside the Original
Decision.
Issues for determination
[12] The parties have agreed that the issues for determination are:
(a) Is Mr Akhavan a ‘consumer’ as defined in s 67WA of the QBCC Act?
(b) If so, is the contract between Mr Akhavan and the Builder a ‘fixed price
residential contract’ as defined in ss 2 and 3 of the terms of cover in Schedule 6
of the Queensland Building and Construction Commission Regulation 2018
(Qld) (‘the QBCC Regulation’)?
(c) If so, did Mr Akhavan and the Builder terminate the contract on or about 13 July
2023 by mutual agreement or abandonment?
(d) If not, did Mr Akhavan validly terminate the contract on or about 1 November
2023 on the default of the Builder?
(e) As a consequence of (a) to (d) above, should Mr Akhavan’s claim under the
statutory insurance scheme in the QBCC Act and Regulation be allowed or
disallowed?
[13] At the hearing, the parties agreed that it was not in issue between them that Mr
Akhavan was a ‘consumer’ and that the contract was a ‘fixed price residential
contract’. The issue for determination, therefore, is when and how the contract ended.
The Commission conceded that, if the contract was not mutually terminated or
abandoned at some time between 11 July 2023 and the end of August 2023, the
contract was validly terminated under the process described in paragraph [9] above
and the Original Decision should stand.
Evidence
The factual basis for the Decision
[14] The Builder’s letter to the commission seeking internal review, dated 7 February
2023, made the following claims:
(a) it was confirmed that no work had commenced on the property prior to the
mutual termination of the contract;
-- 3 of 18 --
4
(b) Mr Akhavan requested 27 variations to the original drawings and specifications
which resulted in increased costs associated with the construction of the
property;
(c) the Builder issued the proposed variation document in accordance with the
contract due to the changes made in the design process, which Mr Akhavan
refused;
(d) on or about 11 July 2023, Mr Akhavan met with the Builder and at the meeting
the parties agreed to mutually terminate the contract;
(e) Mr Akhavan requested the CAD files and the ‘Revit files’ to engage with
another Builder or, alternatively, to sell the land to another person with the
designs available to be used by a subsequent owner;
(f) on or around 13 July 2023, in reliance on the claimed mutual termination
agreement, the Builder released all the CAD files associated with the property
to Mr Akhavan;
(g) on 17 July 2023, Mr Akhavan requested the Revit files and confirmed that the
copyright associated with the construction plans had been transferred to him;
(h) on 26 July 2023, Mr Akhavan wrote to the Builder confirming the transfer of
the copyright of the plans and specifications;
(i) on or about 3 August 2023, the Builder attempted to confirm that the contract
had been mutually terminated and that it was no longer completing the
construction of the property; and
(j) following this communication, Mr Akhavan issued the notice to remedy breach
and termination notice.
[15] The Commission cited the following summary of facts as material to the Decision:
(a) Mr Akhavan had made the appropriate payments under the contract.
(b) On 15 May 2023, the builder issued the variation proposal to Mr Akhavan citing
increased costs to building supplies and materials due to increased demand as a
result of market changes as the basis for the variation1.
(c) On or around 11 July 2023, Mr Akhavan met with the Builder’s representative.
At the meeting, the parties allegedly agreed to mutually terminate the contract.
At the meeting, Mr Akhavan requested the CAD files and the Revit files be
released for use by him to engage in new builder or, alternatively, for a
subsequent purchaser of the property to undertake the works.
(d) On or around 13 July 2023 “in accordance with the mutual termination
agreement” the Builder released the CAD files to Mr Akhavan.
(e) On 17 July 2023, Mr Akhavan requested the Revit files and confirmation that
“copyright associated with construction plans had been transferred” to him,
1 Note that the QBCC did not accept the Builder’s claim that the proposed variation was occasioned by
Mr Akhavan’s requests for variations to the drawings and specifications. See paragraphs 83 – 88 of
the QBCC’s Decision Notice, HB 16 – 17.
-- 4 of 18 --
5
stating “as discussed, these drawings and associated files may be used by either
[Mr Akhavan] or another owner to build at Page St.”
(f) there was a disagreement between the parties with respect to the “costs
associated with the project to date”.
(g) On 3 August 2023, the Builder sent correspondence to Mr Akhavan stating that
the contract had been mutually terminated and, further, that the Builder was no
longer completing the construction of the dwelling at the property.
(h) On 13 September 2023, Mr Akhavan, though his solicitors, advised the Builder
that:
(i) the variation proposal had been rejected;
(ii) he was seeking a refund of the unused portion of the deposit;
(iii) he was ready, willing and able to comply with his obligations under the
contract;
(iv) in circumstances where the Builder was “unable or unwilling to proceed
with the contract for the contract price, then [Mr Akhavan] may consider
a mutual termination of the contract, on the condition that [the Builder]
agrees to grant a licence to [Mr Akhavan] to use the plans”; and
(v) there was never a mutual termination or abandonment of the contract and
that Mr Akhavan’s request was that the Builder “withdrew their price
increase and commit to [their] contractual obligations within the specified
timeframe.”
The Decision
[16] The Commission gave weight to the Builder’s submission that:
(a) by the “mutual termination” agreement, it was agreed that the Builder would
release the CAD and Revit files; and
(b) in accordance with that agreement, the files were subsequently released to Mr
Akhavan, which amounted to confirmation that the contract had been mutually
abandoned prior to Mr Akhavan issuing the notice to remedy breach and,
subsequently, the termination notice.
[17] The Commission was satisfied that there were sufficient reasons on the evidence to
find that the Builder’s and Mr Akhavan’s “external manifestations evince an intention
to abandon” the contract.
[18] The Commission found that the conduct of the parties was categorically inconsistent
with each of the parties performing their outstanding requirements under the contract,
because of:
(a) the statements made by Mr Akhavan (on around 11 July 2023) when he
requested the drawing plans from the Builder, which objectively raised the
possibility that he would either be continuing the build with another contractor,
or provide to a subsequent purchaser of the property; and
(b) the statements made by the Builder (on around 3 August 2023) in relation to the
proposed variation, namely that at that time any costings previously submitted
-- 5 of 18 --
6
had become irrelevant given that the Builder was no longer performing the
works under the contract for Mr Akhavan.
[19] The Commission also considered that, objectively, the parties intended for an entity
other than the builder to undertake the works.
[20] Accordingly, the Commission was satisfied that the notice to remedy breach and
termination notice were invalidly issued because the contract had already been
mutually abandoned through the parties’ conduct on or around 11 July 2023.
[21] Section 4 of the QBCC Regulation provides that a valid termination for a fixed price
residential contract does not include mutual abandonment of the contract by the parties
to the contract. Therefore, the Commission determined that the contract was not
validly terminated at the default of the Builder and that Mr Akhavan’s claim under
the statutory insurance scheme be disallowed.
Mutual termination or abandonment: Mr Akhavan’s evidence
[22] Mr Akhavan’s statement of 11 October 2024, in relation to the events of 13 July 2024
and following, is:
(a) He attended the meeting with the Builder on 11 July 2023, accompanied by
Leila Aria. The representatives of the Builder in attendance were Mr Suyatno,
Mr Joliffe and Ms O’Brien.
(b) He demanded that the Builder withdraw Variation 4 and commence construction
of the works as soon as possible.
(c) Mr Suyatno said that the Builder would not withdraw the variation and could
not proceed with construction for the contract price because it would cause the
Builder to suffer a substantial loss on the project.
(d) Mr Suyatno said that Mr Akhavan should attempt to sell the property with the
approved plans so that a prospective purchaser could construct the works with
the builder for the contract price plus Variation 4.
(e) Mr Akhavan recalls that he was not interested in this proposal and wished to
proceed with the works. He said that he would only consider a mutual
termination of the contract if the Builder:
(i) refunded the entire amount of the deposit to him; and
(ii) provided express permission for him to use the plans so that he could
either engage a new builder or sell the property with the approved plans
included as part of the sale.
(f) Mr Suyatno replied:
(i) the Builder could not refund the entire deposit, and would only consider a
partial refund;
(ii) he would provide Mr Akhavan with an update in about five days as to the
Builder’s costs to date and any partial refund that might be offered, and
whether the builder would permit him to use the plans.
(g) Mr Akhavan left the meeting after this exchange. He claims that, upon leaving
the meeting:
-- 6 of 18 --
7
(i) the belief the contract was still on foot;
(ii) he had not agreed to any final terms with the Builder to mutually terminate
the contract; and
(iii) the only item that was agreed at the meeting was that the Builder would
provide him with their costs incurred to date.
(h) On 13 July 2023, following the meeting, he received an email from the builder
which contained a copy of the drawings for the works.
(i) On 17 July 2023, he sent an email to the builder in which he requested
confirmation from the builder as to whether he was permitted to use the plans
in future. He received no response.
(j) On 20 July 2023, he sent an email to the Builder requesting an update as to its
costs to date for the works.
(k) On 26 July 2023, having received no response he sent a further email to the
builder in which he stated that he considered the actual costs of the works to
date were approximately $13,205.
(l) On 29 July 2023, he received an email from the Builder which included a list of
additional expenses it claimed to have incurred for the works.
(m) On 31 July 2023, he sent an email to the Builder in which he stated that he
required:
(i) a refund of at least $27,128;
(ii) the Builder to pay any fees for the building approval for the works;
(iii) the Builder to transfer the building approval to him; and
(iv) a response by close of business on 2 August 2023.
(n) On 3 August 2023, there was an exchange of emails, as previously described.
(o) On 27 August 2023, he received an email from the Builder which enclosed a
bundle of invoices the Builder claimed to have paid towards the works.
(p) On 28 August 2023, he sent an email to the Builder which disputed his liability
to pay for the invoices and reiterated his demand for refund of the deposit and
release of the building approval to him.
(q) On 29 August 2023 at 11:55 AM, he sent an email to the Builder stating that he
would require a refund of the deposit and release of the building approval to
him.
(r) On 29 August 2023 at 12:37 PM he sent a further email to the Builder and
requested a meeting to discuss a possible settlement of the dispute. There was
no response to this email.
[23] At the hearing, Mr Akhavan stated that no agreement was reached at the meeting of
11 July 2023 that the contract should be terminated. His evidence was that the purpose
of the meeting was to have the builder withdraw Variation 4. He said that, when it
became clear to him that the builder had no intention of withdrawing the variation, he
was prepared to discuss termination on two conditions: a full refund of the deposit and
-- 7 of 18 --
8
release of the drawings. He said that those conditions were never met. It was put to
him in cross-examination that he was given express verbal permission at the meeting
to use the drawings. He said that that would never have been sufficient and that
express permission would need to be in writing. It was suggested to him that the
builder’s agreement to release the drawings to him is in accordance with his proposal.
He said that the drawings were of no use to him without written permission.
[24] Mr Akhavan accepted that he received the drawings on 13 July 2023 but that they
came without any written permission to use them.
[25] He was taken to his email of 17 July 20232 , in which he said:
Thank you for releasing the drawings as it was agreed in our last week’s
meeting.
May you please release the Revit files as well, in case the buyer wants to make
any change to the current plan.
As discussed, these drawings and associated files, may be used by either by me
or another owner to build at Page St. If you oppose this, please let me know by
COB 19 th July 2023. Otherwise, it will be taken and understood that Iconic Line
Construction acknowledge the transfer of the copyright to me and any third
party to build at this address.
[26] He said that the paragraph as to the use of the drawings was to prompt the Builder to
provide the written permission he was seeking, or to confirm the Builder’s
understanding use to which the drawing could be put.
[27] He was taken to his email of 26 July 20233 , in which he wrote, “I confirm again that
I received the drawings and BA for the dwelling and since I received no objection by
the due date given about the release of the copyright, it is considered that the copyright
has been transferred to us (the client).” He told the Tribunal that this was a further
attempt to “put the words into [the Builder’s] mouth, but they never confirmed it.” It
was put to him that the email confirmed that at least one of his conditions had been
met. He said that he did not agree and that his attempts to secure agreement on the
two conditions went nowhere. He said that it was not his understanding that the
copyright in the drawings had been transferred.
[28] Mr Akhavan was asked why, in that email, he had made no reference of any
continuation of the works. He said that, at the meeting, the Builder had made it clear
that it did not intend to start work within the terms of the contract as written. He said
that he was not prepared to walk away from the contract without satisfaction of the
two conditions he had proposed.
[29] It was put to Mr Akhavan that, in his email of 31 July 20234, he had provided a
breakdown of the amount of the deposit he was seeking to have returned but, having
not mentioned the permitted use of the drawings, had accepted that his condition in
that respect had been met. He did not agree and stated that he had already tried twice
without receiving a response.
[30] Mr Akhavan was taken to his email of 3 August 2023, and which he wrote:
2 HB 464.
3 HB 113.
4 HB 111.
-- 8 of 18 --
9
Since I have not received any objection to my below email and calculation of
the actuals and refundable by the due date of yesterday 2nd August, it is
considered that it is all accepted by Iconic.
To show the goodwill again, I expect to receive the refunds of $27,178 in my
account by COB 11th August.
[31] Mr Akhavan told the Tribunal that, as with the copyright in the drawings, he was
attempting to hasten the Builder’s response to his proposals and, he hoped, to secure
an agreement. However, his proposals were never accepted by the Builder.
[32] Mr Akhavan was taken back to his email of 17 July 2023 (see [25] above) and was
asked about his reference to “the buyer”. He said that the reference was hypothetical
because the property had not been put on the market. He said he was considering all
options at that time, given that he could not afford the amount claimed in Variation 4.
He was therefore casting around for a way to proceed.
[33] Mr Akhavan was asked when he had decided to engage a different builder. He said it
was after he had given the notice of termination. He said that he had not landed on an
option before then because his principal concern was obtaining finance for the project.
Before the notice of termination, he had only gone as far as making enquiries and
could not go further because the position with his finance was not settled. Taken to
the letter from his solicitors of 19 October 20235, which, in relation to the drawings,
states: “You may wish to … provide them to your new builder to confirm you are able
to use them,” he told the Tribunal that a builder had not been engaged at that point
and that the advice referred to a future situation. Similarly, he said, his solicitor’s letter
of 1 November 20236 which stated,” our clients intend to engage another builder to
carry out the Works” reflected the fact that he had, at that time, received proposals
from builders but his finance was still not settled and so any intention to engage
another builder was a contingent one.
Mutual termination or abandonment: the Builder’s evidence
[34] Mr Roy Suyatno, the Builder’s project manager, gave evidence for the Builder. In his
statement of 22 November 2024, he claimed:
(a) Despite the contract being executed by the parties on 18 June 2022, final plans
were not issued until 13 March 2023 because of the numerous design changes
requested by Mr Akhavan.
(b) The final certified construction plans and engineering were approved on 9 May
2023.
(c) On 15 May 2023, the builder wrote to Mr Akhavan to advise of the cost
increases. Mr Akhavan responded by email on 16 May 2023 requesting an
urgent meeting to discuss the matter.
(d) The meeting took place on 11 July 2023. Present were Mr Akhavan and, for the
Builder, Mr Suyatno, Alan Joliffe (salesperson) and Ebony O’Brien (contract
administrator).
(e) Mr Suyatno’s account of the meeting was:
5 HB 278.
6 HB 282.
-- 9 of 18 --
10
(i) The Builder’s representatives explained that the reason for the price
increase was due to building design changes made by Mr Akhavan, the
requirements to enable approval, and the time it took for the approval to
be provided.
(ii) Mr Akhavan advised that he would potentially need to sell the property.
(iii) Mr Akhavan said that he was not satisfied with the price increase.
(iv) Mr Akhavan threatened to sue the Builder for loss of rent.
(v) The Builder’s representatives explained that the contract was subject to
Council approval to commence construction.
(vi) Mr Suyatno explained to Mr Akhavan that it had been Mr Akhavan’s
decision to demolish the existing dwelling, and that it had been Mr
Akhavan’s decision to make continual amendments to the design which
were responsible for significant delays, including additional requests for
information from the Council,
(vii) Mr Suyatno’s understanding was that Mr Akhavan left the meeting
intending to engage a different builder, or possibly to sell the property
with the approved plans.
(viii) The only matter left to be arranged was for Mr Akhavan to request a
breakdown of the costs that the Builder had incurred to date.
(f) On or around 13 July 2023, in accordance with the builder’s understanding of
the situation Alan Joliffe released the CAD files to Mr Akhavan.
(g) Following receipt of the CAD files, Mr Akhavan emailed Mr Suyatno to request
the Revit files, “in case the buyer wants to make any changes to the current
plans.”
(h) That email further stated:
As discussed, these drawings and associated files, may be used by me or
another owner to build at Page St. if you oppose this, please let me know
by COB 19 th July 2023. Otherwise, it will be taken and understood that
Iconic Line Construction acknowledge the transfer of the copyright to me
and any third party to build at this address.
(i) The Builder did not oppose the transfer of the copyright to Mr Akhavan because
it is understood that it would no longer be completing the works. Mr Suyatno
understood that Mr Akhavan intended to either complete the works with another
builder or to sell the property with the approved plans.
(j) On or around 26 July 2023, Mr Suyatno received an email from Mr Akhavan
requesting the costs that the Builder had incurred to date. It also contained words
to the effect that Mr Akhavan confirmed receipt of the drawings and building
approval and that he considered the copyright of the plan is to have been
transferred to him.
(k) On 29 July 2023, Mr Suyatno sent an email to Mr Akhavan detailing a list of
additional expenses incurred by the Builder for the work.
-- 10 of 18 --
11
(l) On 31 July 2023, Mr Suyatno received an email from Mr Akhavan proposing to
except only part of the costs the builder had claimed to have incurred.
(m) On 3 August 2023, there were a series of emails between Mr Suyatno and Mr
Akhavan relating to these claims and other matters in dispute. At about 2:17
PM, Mr Suyatno sent an email to Mr Akhavan stating that some of Mr
Akhavan’s cost calculations were not relevant because the Builder was no
longer engaged by Mr Akhavan on the project.
[35] At the hearing, Mr Suyatno was asked if the purpose of the meeting was to discuss
Variation 4. He agreed that it was. He was asked if Mr Akhavan had asked for work
on the dwelling to start. He said that work would not start until the price increase was
agreed. He was asked again if Mr Akhavan had asked for work to start. Mr Suyatno
said that that he knew that Mr Akhavan did not like the price increase but could not
recall if he had asked for work to start because he was in and out of the meeting on
several occasions. He agreed that Mr Akhavan asked that Variation 4 be withdrawn.
[36] Mr Suyatno agreed that Mr Akhavan had asked for the drawings because he could not
afford the Builder’s new price for the dwelling. Asked if Mr Akhavan had expressed
an intention to sell the property, he said he could not remember.
[37] It was put to Mr Suyatno that he did not give Mr Akhavan express permission to use
the drawings. He said he had been happy to provide the drawings to him. It was further
put to him that this was not the same as permission to use the drawings and that, on
that issue, he had told Mr Akhavan that he would need to think about it. Mr Suyatno
said he could not remember. It was suggested to him that he never provided
permission. He said that he did provide written submission in November 2023. He
agreed that this was after the notice of termination had been given. Asked if he agreed
that no written permission was given before November 2023, he said he was not clear
about that but had been happy, in principle, to provide the drawings.
[38] Mr Suyatno agreed that Mr Akhavan had also asked for a full refund of his deposit.
He said that he had explained to Mr Akhavan that a full refund could not be made
because of the expenses incurred by the Builder. He agreed that he had told Mr
Akhavan that he would get back to him on that. He further agreed that the meeting
had not resulted in any agreement.
[39] Mr Suyatno was taken to a series of emails between himself and Mr Akhavan of 3
August 20237. He agreed that he did not accept any of Mr Akhavan’s proposals and
that the parties never agreed on an amount to be refunded.
[40] Mr Suyatno was asked about his authority to contract on behalf of the Builder. He
said that he had no express authority to enter or alter contracts. His responsibility in
that regard was to provide input into costings. He agreed that contracts were executed
by one or more of the directors.
Principles
[41] A decision of the QBCC that a building contract has, or has not, been validly
terminated for the purposes of determining whether a claim for non-completion under
the statutory insurance scheme should be allowed is a reviewable decision. A
7 HB 106 – 100.
-- 11 of 18 --
12
reviewable decision is defined in s 86 of the QBCC Act to include an internal review
decision (itself defined in s 85A of that Act).
[42] By s 87 of the QBCC Act, a person affected by a reviewable decision may apply to
the Tribunal for a review of the decision. The Tribunal’s review jurisdiction is the
jurisdiction conferred on the Tribunal by an enabling Act to review a decision made
or taken to have been made by another entity under that Act.8 I am satisfied that the
Tribunal has jurisdiction to review the Decision.
[43] This matter turns on the question as to whether the meeting of 11 July 2023 evidenced,
or can reasonably be interpreted to show, that the contract had been brought to an end
by mutual termination or abandonment.
[44] The Court of Appeal in Imam v Life (China) Company Limited9 held:
Whether a contract has been abandoned is a question of fact to be inferred from
an objective assessment of conduct of the parties…[O]ne must have regard to
the conduct of the parties, and what might be inferred from that conduct. The
authorities establish that the court looks at an objective assessment of the
conduct of the parties, and as to whether that conduct result in an inference that
neither party maintains an intention to perform the contract. The assessment
does not call for an examination of whether a party actually has this objective
intention of abandoning, but considers “whether there conduct, when
objectively viewed, manifested that intention”.
[45] In Cedar Meats (Aust) Pty Ltd v Five Star Lamb Pty Ltd10 (‘Cedar Meats’) the
Supreme Court of Victoria held:
The critical question is whether the parties conducted themselves mutually in
such a way so as to convey to the other that they did not intend that the
Agreement should be further performed or that such party did not regard the
agreement as being in force. In other words did the parties by their external
manifestations evince an intention to abandon or abrogate the Agreement. If
they did the Agreement will be discharged.
In Australia, several appellate decisions have concluded that whether there is
abandonment or abrogation of a contract is a matter of fact to be inferred from
an objective assessment of the conduct of each party as evinced to the other and
acted upon. The court is not required to examine whether the party actually had
the intention of abandoning the agreement.
The inference of abandonment will be drawn more readily where “an inordinate
length of time has been allowed to elapse, during which neither party has
attempted to perform, or called upon the other to perform, a contract made
between them…”. What is really inferred in such a case is that the contract has
been discharged by agreement, each party being entitled to assume from a long
continued ignoring of the contract on both sides that “the matter is off
altogether”.
As the New South Wales Court of Appeal stated in Ryder v Frohlich:
The underlying premise of the abandonment cases is that a period of time
lapses during which neither party to the contract manifests any intention
8 Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 17(1).
9 [2023] QCA 19, [107] (citations omitted).
10 [2013] VSC 164, [43] – [46].
-- 12 of 18 --
13
to perform the contract, leading to the inference that the contract has been
abandoned.
It is clear that the question whether an “inordinate length of time has been
allowed to elapse” is relative. In DTR Nominees Pty Limited v Mona
Homes Pty Limited the High Court was prepared to infer abandonment
after a period of less than five months had elapsed during which neither
party took any steps to perform the contract. In Fitzgerald v Masters it
was held that a contract for the sale of land had not been abandoned even
though proceedings for its specific performance were not commenced
until 26 years after its execution. [Citations omitted.]
[46] This case has been cited with approval in the Appeal Tribunal.11
[47] In CGM Investments Pty Ltd v Chelliah12, Finkelstein J held:
[A] contract “can be extracted from circumstances where no acceptance of an
offer can be established or inferred and where the most that can be said is that
a manifestation of mutual assent must be implied from circumstances”. So it
must be with an implied agreement to abandon a contract.
In my opinion to show that a contract has been abandoned by inactivity on both
sides it is necessary to establish that the inactivity (which may sometimes
amount to no more than silence on one side) produces the clear inference that
one party does not wish to proceed with the contract and the other party
consented to that situation.
[48] The passage from Ryder v Frohlich13 quoted in Cedar Meats above is to the effect
that what constitutes the lapse of an inordinate amount of time is relative. In that case,
an abandonment of the contract was held to have taken place more less immediately
when the parties’ conduct was considered.
[49] An example where a significant lapse of time was not relevant was provided in
Mareva Building Consultants v Zevon and Zevon14, in which a contract for a house in
one location was agreed but put on hold by the owner just was work was to commence.
The owners sought to build instead in a second location but the parties were
subsequently unable to agree on a price. The builder had not pressed for payment for
the work referable to the first location. The Court held:
Considered together [the] facts are inconsistent with [the builder’s] claim that
the contract to build the [first] house remained on foot despite [the builder]
being offered the [second] project.
…
Objectively, the facts of the meetings between [the builder] and [the owner]
confirm such a factual circumstances and the primary judge’s finding. [The
builders]’s conduct is wholly consistent with the finding of the primary judge
that the contract to build the [first] house had been mutually abandoned.
[50] The Commission also brought to the Tribunal’s attention several VCAT decisions
concerning abandonment of residential construction contracts:
11 See Stuart v Queensland Building and Construction Commission [2015] QCATA 81.
12 [2003] FCA 79, [21] – [22].
13 [2004] NSWCA 472, [136].
14 [2013] ACTACA 28, [29], [31].
-- 13 of 18 --
14
(a) Torua v Sariklis (Domestic Building)15: “Had the builder intended to perform
the contract, it would have taken some steps following its suspension of the
works to bring matters to a head. However nothing occurred, with the result that
the owner then took over the works herself. Again the builder did nothing in
response to that action, apart from making a claim for the value of the work
completed by it as at the date it ceased work. Viewed objectively, I find that the
contract was abandoned by the parties …”
(b) In Yan v Brown Bros Cabinet Work Pty Ltd (Domestic Building)16, the parties
had several meetings about the scope and price of the works, and the parties
disagreed as to whether a contract had been formalised or a price agreed,
although the owner had made payments to the builder. A new contract was
prepared by the builder but further variations were sought by the owner and no
agreement was reached. The builder subsequently wrote to the owner offering
the option of a cancellation of any contract with a refund of monies paid less
expenses, or a new contract encompassing the further changes. The first option
would be deemed accepted unless the owner advised otherwise. The owner
sought specific performance of the original contract. The Tribunal held:
“[W]hen the parties’ conduct is objectively viewed, it is clear that neither
wanted to proceed with the contract in its original form. The fact that [the owner]
originally sought specific performance of the contract does not detract from that
conclusion because her insistence on specific performance relates to a scope of
work which is different to what was originally contemplated by the contract.
Accordingly, I find that the contract between the parties has been mutually
abandoned. In my view, that occurred at the conclusion of the meetings… At
which point it became clear that the parties could not agree on the changes to be
made to the scope of joinery works under the contract or agree on the terms of
a substituted contract.”
(c) Agropolou v Shkolyar (Domestic Building)17, where the builder advised the
owner that no more work would be undertaken until outstanding progress claims
were made, to which the owner replied that he would not make any further
payments. Following this conversation, the builder did not undertake any further
work and the owner did not make any payments. The contract was held to be
abandoned from the date of the conversation.
Was the contract mutually terminated or abandoned?
[51] The Commission submitted that the relevant events were:
(a) Mr Akhavan had made the appropriate payments under the contract;
(b) On 15 May 2023, the Builder issued Variation 4 citing increased costs in
building supplies and materials;
(c) at the meeting of 11 July 2023, the parties agreed to mutually terminate the
contract. At the meeting, Mr Akhavan requested that the CAD files and the Revit
files be released for his use to engage a new contractor or, alternatively, for a
subsequent purchaser of the property to undertake the works;
15 [2012] VCAT 144, [158].
16 [2013] VCAT 1623, [46] – [49].
17 [2011] VCAT 2213
-- 14 of 18 --
15
(d) on 13 July 2023, the Builder released the CAD files in accordance with the
mutual termination of the contract;
(e) on 17 July 2023, Mr Akhavan requested the Revit files and confirmation that
any “associated with construction’s plans had been transferred” to him and
stating quotes as discussed, these drawings and associated files may be used by
either [him] or another owner to build at Page St.”
(f) there was a disagreement between the parties with respect to “the costs
associated with the project to date”;
(g) on 3 August 2023, the builder sent correspondence to the applicant stating that
the contract had been mutually terminated and, further, that the builder was no
longer completing the construction of the dwelling;
(h) on 13 September 2023, Mr Akhavan’s lawyers asserted that Mr Akhavan
considered that the contract remained on foot and he required the withdrawal of
Variation 4, but that he would consider a mutual termination of the contract on
the condition that the Builder would grant a licence to him use the plans.
[52] The Commission submitted that the conduct of the Builder and Mr Akhavan was
categorically inconsistent with each of the parties performing their outstanding
requirements under the contract because:
(a) the statements made by Mr Akhavan at the time of requesting the drawings
objectively raised the possibility that that he would either be continuing the
build with another contractor or a subsequent purchaser of the property to build;
and
(b) the statements made by the Builder in light of the disagreement regarding costs,
namely that at that time any costings previously submitted had become
irrelevant given the builder was no longer performing the works under the
contract.
[53] The Commission submitted that, objectively, the parties intended for a different entity
other than the builder to undertake the works and that this amounted to the threshold
set out in Cedar Meats, allowing the inference of abandonment to be drawn.
[54] The Commission had, therefore, determined that the notice to remedy breach and the
termination notice were invalidly issued because the contract had been mutually
abandoned through the parties’ conduct on or around 11 July 2023.
[55] For Mr Akhavan, it was submitted that, objectively viewed, the parties did not
mutually terminate or abandon the contract in circumstances where:
(a) no such agreement or understanding was reached during the parties’ meeting in
July 2023;
(b) a mutual termination or abandonment is inconsistent with the party’s written
communications over the two months immediately following the meeting; and
(c) there was no inordinate length of time during which neither party attempted to
perform or call for the performance of the contract.
[56] It was submitted that the evidence of the meeting of 11 July 2023 showed:
-- 15 of 18 --
16
(a) Mr Akhavan demanded that the Builder withdraw Variation 4 and commence
the works under the contract;
(b) Mr Suyatno said that the Builder would not withdraw Variation 4 and would not
commence works without Mr Akhavan’s acceptance of the variation because
otherwise the Builder would suffer a loss;
(c) Mr Akhavan said that he would only consider a mutual termination if he was
refunded the entire deposit and given express permission to use the plans;
(d) Mr Suyatno said the Builder could not refund the entire deposit consider a partial
refund, and would provide an update in the next five days on the Builder’s costs
to date and whether it would allow Mr Akhavan to use the plans.
[57] On an objective assessment, it was submitted:
(a) Mr Akhavan’s statements to the builder evinced an intention for the works to
commence without the price increase in Variation 4, which was an invalid
variation;
(b) The Builder’s statements to Mr Akhavan evinced an intention to uphold
Variation 4, despite it being invalid, for commercial reasons, and to refuse to
commence the works unless Variation 4 was paid.
[58] Accordingly, there was no mutual abandonment: only the Builder evinced an
unwillingness to be bound by the contract. At this time, Mr Akhavan had paid the
deposit in full and still needed to build a house on the property. His request for a
refund was rejected and his request for express permission to use the plans was not
accepted.
[59] It was submitted that, if any agreement or understanding was reached during the
meeting, it was that the builder would simply update Mr Akhavan on its position
regarding its costs to date and whether it would permit him to use the plans. The
subsequent discussions between the parties indicate that neither of the conditions
sought by Mr Akhavan were agreed to by the Builder.
[60] It was submitted that the Builder’s communication of 3 August 2023, that Mr
Akhavan’s proposed refund was “not relevant anymore since we are not building for
you,” was a unilateral communication by the Builder as to its unwillingness to comply
with the contract rather than evidence of any mutual intention of the parties to abandon
the contract. There was no corresponding evidence of such conduct on the part of Mr
Akhavan.
[61] Finally, it was submitted that there was no inordinate length of time that had been
allowed to elapse, such that an inference of abandonment could be more readily
drawn. Mr Akhavan took immediate steps to arrange a meeting to discuss Variation
4. A period of failed negotiations followed, after which he instructed his lawyers to
require commencement of the works. This period encompassed a period of only two
months.
[62] I prefer Mr Akhavan’s account of the meeting of 11 July 2023 and the subsequent
negotiations to that of Mr Suyatno. Mr Suyatno’s account suffered from his lack of
recall of key elements of the meeting and was not assisted by his periodic absences
from it. It is clear from the evidence that the purpose of the meeting was to discuss
Variation 4, rather than to bring the contract to an end. However, if the course of the
-- 16 of 18 --
17
events at the meeting and subsequently was inconsistent with the parties performing
their outstanding requirements under the contract, the inference of mutual termination
or abandonment can be drawn.
[63] I consider that the evidence presents a course of events materially different to the
examples cited at paragraph [50] above:
(a) Unlike the situation in Torua18, there was no inactivity on the part of Mr
Akhavan to any conduct of the Builder inconsistent with the continued existence
of contract (viz, its issuing the invalid variation and purporting to declare the
contract to be at an end on its non-acceptance). Rather, Mr Akhavan nominated
two conditions under which he would release the builder from the contract, to
one of which it repeatedly declined to respond and the other to which it would
not agree. Following this, Mr Akhavan sought to exercise his remedies under
the contract.
(b) Unlike the situation in Yan19, there was no lack of certainty about the terms of
any contract into which the parties had entered.
(c) Unlike the situation in Agropolou20, there was no simple mutual abandonment
of the contract. The evidence is that Mr Akhavan was energetic in seeking either
performance of the contract or satisfaction of the two conditions he had
proposed for the Builder’s release from it.
[64] I do not accept the submission that Mr Akhavan’s statements as to his purpose of
seeking the drawings give rise to any inference that his conduct was “categorically
inconsistent” with each of the parties performing their obligations under the contract.
Rather, the request for the drawings was a rational demonstration that Mr Akhavan
was prepared to terminate construction if the variation was not withdrawn: the only
use to which the drawings could be put were with a new builder at the site or a new
buyer of the property. I do not accept the Commission’s submission that conduct that
“objectively raised the possibility” of other options is the correct or appropriate test
for mutual termination. For abandonment or mutual termination, there must be an
objective assessment of the parties’ conduct which results in an inference that neither
party maintains an intention to perform the contract21.
[65] I have two further observations in relation to Mr Akhavan’s request for the drawings:
(a) I accept his evidence that his claimed assumptions that the assignment or
licensing of the copyright in the drawings would be effected if the builder did
not deny it was an attempt on his part to force the issue. Further, I consider the
Builder’s continuing silence on the topic to constitute an attempt to escape the
contract without giving anything further away. The drawings, of course, would
be of limited value to a new builder or a purchaser of the site without a clear
licence.
(b) I reject the Commission’s assertions that the release of the drawings was “in
accordance with the mutual termination agreement” as a characterisation that is
not available on the evidence. The Builder never provided express written
18 Supra, n 15.
19 Supra, n 16.
20 Supra, n 17.
21 Imam v Life (China) Company Limited, supra, n 9
-- 17 of 18 --
18
permission for the use of the plans (as required by clause 12 of the contract)
before the notice of termination, despite repeated requests. On the issue of the
request for express permission, I prefer Mr Akhavan’s evidence over that of Mr
Suyatno, who could not recall the relevant discussion and was vague about the
matter generally. I find that express permission was requested but not provided
at the meeting or at any time prior to the notice of termination.
[66] I accept that the Builder’s assertion that it was no longer Mr Akhavan’s builder does
give rise to the relevant inference in respect of the Builder’s view of its contractual
obligations. However, by itself it does not give rise to the essential element of
mutuality. There is no evidence that Mr Akhavan was prepared to accept the assertion
without satisfaction of the conditions he had offered.
[67] On the evidence, I am satisfied that, objectively viewed, the meeting of 11 July 2023
and the subsequent negotiations were not inconsistent with both parties performing
their outstanding requirements under the contract. To the contrary, I am satisfied that
Mr Akhavan’s conduct was entirely consistent with his seeking to either have
Variation 4 withdrawn and for work to proceed, or for the Builder to provide him with
an appropriate remedy for its conduct in respect of the variation. It therefore follows
that the contract was not abandoned or ended by mutual termination.
[68] In these circumstances the Decision of 4 March 2024 should be set aside. The correct
and preferable decision is the Original Decision of 10 January 2024.
-- 18 of 18 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2026/361