Blue Wren Holdings Pty Ltd t/as Civic Showers Screens and Wardrobes v Serenity Constructions Qld Pty Ltd [2026] QCAT 359
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Blue Wren Holdings Pty Ltd t/as Civic Showers Screens
and Wardrobes v Serenity Constructions Qld Pty Ltd
[2026] QCAT 359
PARTIES: BLUE WREN HOLDINGS PTY LTD TRADING AS
CIVIC SHOWER SCREENS AND WARDROBES
(applicant)
v
SERENITY CONSTRUCTIONS QLD PTY LTD
(respondent)
APPLICATION NO/S: BDL294-24
MATTER TYPE: Building matters
DELIVERED ON: 30 July 2026
HEARING DATE: On the Papers
HEARD AT: Brisbane
DECISION OF: Member S M Burke
ORDERS: The Respondent is to make payment to the Applicant in
the sum of $6,583.14 on or before 3 September 2026.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – REMEDIES FOR BREACH
OF CONTRACT – MEASURE OF DAMAGES – where
subcontractor performed building work – where allegation
of defective works – failure of party to comply with
directions – failure of party to deliver any evidence before
the Tribunal
Queensland Building and Construction Commission Act
1991 (Qld), s 77(2)
APPEARANCES &
REPRESENTATION:
This matter was heard and determined on the papers
pursuant to s 32 of the Queensland Civil and Administrative
Tribunal Act 2009 (Qld)
REASONS FOR DECISION
[1] On 23 August 2024, the Applicant filed an application for a commercial building
dispute, claiming the sum of $8,357.14 for unpaid invoices for works performed at
Lot 135, 2 Sunset Place Jacobs Well, Queensland (‘the property’).
[2] The Respondent was the contractor engaged by the owners to carry out the renovation
and extension of a three-storey dwelling at the property.
-- 1 of 4 --
2
[3] The Applicant was the subcontractor engaged by the contractor to carry out the
installation of a number of shower screens and other related works at the property.
[4] On or about 28 September 2023, a purchase order No. 00034004 was raised by the
contractor for the following works:
(a) Shower screens, mirrors, robe shelving/Civic shr screens/As per quote
[5] The subcontractor carried out the subcontract works between 27 September 2023 and
31 October 2023.
The Directions and Compliance
[6] In compliance with the Tribunal’s directions of 8 September 2024, the Applicant filed
a copy of a letter from the Queensland Building and Construction Commission
(‘QBCC’) on 11 September 2024 confirming compliance with s 77(2) of the
Queensland Building and Construction Commission Act 1991 (Qld) regarding the
process established to resolve the dispute between the parties.
[7] By directions on 2 December 2024, the Respondent was required to file in the Tribunal
a response to the application for a commercial building dispute by 16 December 2024.
[8] The Respondent’s response stated:
(a) the Applicant has refused and/or failed to rectify defective workmanship carried
out by the Applicant despite numerous requests from the Respondent;
(b) the Respondent requests the Applicant:
(i) to rectify the defective workmanship as advised by the Respondent
including the rectification of any damage caused whilst carrying out the
work at its own cost; or
(ii) the Respondent is to rectify the works and deduct the cost to rectify the
work from monies claimed to be owed to the Applicant.
[9] On 17 January 2025, the Tribunal delivered directions addressing the obligations of
the parties to file statements of evidence and any documents relied upon by the
Applicant and the Respondent on 27 February 2025 and 10 April 2025, respectively.
[10] Further, the parties were required to produce a Scott Schedule addressing the alleged
defective and incomplete work. Neither party provided details in the form of a Scott
Schedule.
[11] Further directions were made by the Tribunal on 24 July 2025 addressing the delivery
of evidence from both parties, including the required common form Scott Schedule.
[12] Once again there was no response from the Respondent.
[13] On 20 October 2025, the Tribunal directed that in the event of non-compliance by the
Respondent by 17 November 2025, the Respondent would not be permitted to file and
rely upon any statements of evidence unless the Tribunal otherwise ordered.
[14] On 12 December 2025, the Tribunal directed that the matter would proceed on the
papers unless the parties advised that an oral hearing was required. No request for an
oral hearing was made.
-- 2 of 4 --
3
[15] The Tribunal has proceeded on the basis of the material filed by both parties by
January 2026.
The Claim
[16] The Applicant claims the following amounts for payment pursuant to the agreement
between the parties:
(a) Invoice #79046 dated 23 October 2023 – $3,969.90;
(b) Invoice #79711 dated 26 October 2023 – $2,834.70; and
(c) Invoice #80529 dated 31 October 2023 – $1,552.54.
[17] Between 7 November 2023 and June 2024, Mr Keith Mellor, on behalf of the
Applicant, and Mr Bill Woolley, on behalf of the Respondent, engaged in continued
debate about the outstanding invoices and defects alleged to have been caused by the
Applicant during installation of the shower screens.
[18] The statement filed 4 March 2025 by the managing director of the Applicant, Mr
Stefan Styles, sets out all the correspondence between the parties regarding the
outstanding invoices and the allegations regarding the defective works.
[19] A further statement has been provided by the Applicant’s field supervisor, Mr Keith
Mellor, who was involved in all the negotiations with the Respondent’s representative,
Mr Bill Woolley.
[20] There is no necessity for the Tribunal to traverse every item of written and oral
correspondence.
[21] It is obvious that by June 2024, there was an agreement between the parties that the
defective works were to be attended to by the Applicant and payment was to be made
for the outstanding tax invoices supplied.
[22] The issue which remained was the extent of rectification work and the associated cost.
[23] The rectification of defective works included replacement of a mirror that was
measured wrongly, rectification of a scratched panel in the 2-way bathroom and
replacement of a linen cupboard.
[24] The parties had agreed that the cost of the alleged defective works would be in the
sum of $1,607.00 plus GST.
[25] On 24 June 2024, the Applicant outlined that after taking into account the costs for
rectification works, the sum outstanding which the Applicant was prepared to accept
was $6,000.00.
[26] No reply from the Respondent was received until an acknowledgement of the
outstanding amount and necessity for rectification works on 12 August 2024. Further
complaints of works requiring rectification were added to the list.
[27] On 13 August 2024, the Applicant advised that it would not be completing any further
works until the agreed amount of $6,000.00 outstanding was paid by the Respondent.
-- 3 of 4 --
4
[28] The Respondent confirmed that due to the Applicant’s refusal to rectify the defective
works, it would proceed to have the rectification works carried out and deduct all cost
from the monies held.
[29] There was no follow-up by the Respondent to this proposal.
[30] No material has been delivered by the Respondent identifying any costs incurred for
further rectification works.
[31] I am satisfied on the material provided that it was agreed at the meeting between Mr
Mellor and Mr Woolley on 21 June 2024, as confirmed by email on 24 June 2024,
that the amount of $1,607.00 plus GST would be deducted from the invoices
submitted for the rectification of defective works.
[32] On 24 June 2024, the Applicant made an offer to accept $6,000.00 as payment for the
outstanding invoices after deduction of $2,357.14 for rectification costs.
[33] After this date, it is the case that the Respondent did not confirm this agreement and
later raised the issue of additional defects and the right to withhold monies until the
defects were rectified.
[34] Given there is no evidence from the Respondent regarding the cost of rectification
works incurred by it, the Tribunal is unable to assess whether the Respondent is
entitled to deduct any other amounts from the outstanding amount owing to the
Applicant.
[35] The Applicant does not deny that there were works which required rectification to the
value of $1,607.00 (plus GST).
[36] I am satisfied that the amount outstanding to the Applicant is the amount of the
outstanding invoices, being $8,357.14 less the amount of $1,774.00 (being the amount
of $1,607.00 plus GST). Such outstanding sum totals $6,583.14.
Orders
[37] The Respondent is to make payment to the Applicant in the sum of $6,583.14 being
the amount owed by the Respondent to the Applicant for the outstanding invoices less
the cost of rectification works.
-- 4 of 4 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2026/359