Genuity Pty Ltd v IG Power (Callide) Ltd [2026] QSC 194
SUPREME COURT OF QUEENSLAND
CITATION: Genuity Pty Ltd v IG Power (Callide) Ltd [2026] QSC 194
PARTIES: GENUITY PTY LTD
ACN 128 655 096
(applicant)
v
IG POWER (CALLIDE) LTD
ACN 082 413 885
(respondent)
FILE NO: 3050 of 2025
DIVISION: Trial Division
PROCEEDING: Hearing
ORIGINATING
COURT:
Supreme Court at Brisbane
DELIVERED ON: 28 August 2026
DELIVERED AT: Brisbane
HEARING DATE: 8 June 2026, 9 June 2026, 10 June 2026
JUDGE: Muir J
ORDER: 1. The answer to question one is “no”: clause 5 of the
Loan Agreement does not oblige IGPC to reimburse
Genuity for the amounts of interest paid by Genuity
pursuant to the OUK/Genuity Loan Agreements.
2. If I am wrong and the answer to question one is “yes”,
then the answer to question two is also “no”: the
amount sought to be recovered by Genuity from IGPC
as Interest Charges are not “necessary and
reasonable” within the terms of clause 5 of the Loan
Agreement.
3. It is unnecessary to answer questions three and four.
4. I will hear from the parties as to the appropriate
directions to be made for the determination of
question five, the second tranche trial listed on 7 and 8
December 2026 and as to costs.
CATCHWORDS: CONTRACTS – GENERAL CONTRACTUAL
PRINCIPLES – CONSTRUCTION AND
INTERPRETATION OF CONTRACTS – CUSTOM AND
USAGE – INCORPORATION INTO CONTRACT –
CONSISTENCY WITH EXPRESS TERMS – where the
applicant advanced money to the respondent pursuant to two
-- 1 of 20 --
2
loan agreements – where the applicant submits that the
respondent is liable for the interest charges incurred for the
maintaining of the first loan agreement – whether, on the
proper construction of the first loan agreement, the respondent
is liable to pay the interest charges claimed by the applicant –
where evidence of the objective factual background known to
the parties at the time of contracting may be considered in
construing the loan agreement – where the factual background
includes the complex corporate structure of the entities
associated with the project and the circumstances under which
the loan agreement was made
INTEREST – RECOVERABILITY OF INTEREST – IN
GENERAL – where the applicant seeks to recover from the
respondent approximately $24 million in interest charges –
whether, on the proper construction of clause 5 of the first loan
agreement, the interest charged sought to be recovered are
“necessary and reasonable” within the meaning of that clause
– where determination of that question requires consideration
of factual findings and an assessment of whether it was
necessary and reasonable for the applicant to incur the interest
charges
INTERPRETATION – GENERAL RULES OF
CONSTRUCTION OF INSTRUMENTS – GIVING EFFECT
TO MANIFEST INTENTION – where the applicant submits
that the loan agreement permits the interest charges to be
passed on to the respondent – whether that construction is
consistent with the express language and clear intention of the
loan agreement
Civil Proceedings Act 2011 (Qld), s 58
Income Tax Assessment Act 1997 (Cth), s815-B, s 815-C,
s 815-D
Aurizon Network Pty Ltd v Glencore Coal Queensland Pty
Ltd (2019) 1 QR 392
Australian Broadcasting Commission v Australasian
Performing Right Association Ltd (1973) 129 CLR 99
Cherry v Steele-Park (2017) 96 NSWLR 548
Colquhoun v Brooks (1888) 21 QBD 52
Consolidated Fertilisers v DCT (1992) 36 FCR 1
Electricity Generation Corporation (trading as Verve
Energy) v Woodside Energy Ltd (2014) 251 CLR 640
HNA Irish Nominee Ltd v Kinghorn (No 2) (2012) 290 ALR
372
Houssein v Under Secretary, Department of Industrial
Relations & Technology (NSW) (1982) 148 CLR 88
Jireh International Pty Ltd v Western Exports Services Inc
[2011] NSWCA 137
-- 2 of 20 --
3
LCA Marrickville Pty Ltd v Swiss Re International SE (2022)
290 FCR 435
Masterton Homes Pty Ltd v Palm Assets Pty Ltd (2009) 261
ALR 382
Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd
(2015) 256 CLR 104
Plenary Research Pty Ltd v Biosciences Research Centre Pty
Ltd [2013] VSCA 217
PMT Partners Pty Ltd v Australian National Park & Wildlife
Service (1995) 184 CLR 301
S.C.N. Pty Ltd v Smith [2006] QCA 360
Santos Ltd v Fluor Australia Pty Ltd [2025] QSC 184
Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd (2004) 219 CLR
165
Vision Super Pty Ltd v Poulter (2006) 154 FCR 185
Wilkie v Gordian Runoff Ltd (2005) 221 CLR 522
Yume Group Holdings Pty Ltd v Ashthorn CA Pty Ltd [2024]
VSCA 134
COUNSEL: B W Wacker for the applicant
N M Bender SC, with W LeMass, for the respondent
SOLICITORS: Johnson Winter Slattery for the applicant
Quinn Emanuel Urquhart & Sullivan for the respondent
Introduction
[1] The Callide Power Station is a coal-powered electricity generator located near Biloela
in central Queensland. This power station is comprised of the Callide B and Callide
C power plants, each with two generating units. Until October 2024, Callide C was
operated by an unincorporated joint venture between the respondent, IG Power
(Callide) Ltd (IGPC); a subsidiary of the applicant Genuity, and Callide Energy Pty
Ltd (CEPL), with each of IGPC and CEPL having a 50 per cent interest (Callide
Power Project). CEPL is owned by CS Energy Limited (CSE), a Queensland
Government State-owned enterprise.
[2] In May 2021, an explosion tripped the C3 and C4 generating units at Callide C,
impairing the production of electricity to the grid and causing critical damage to the
C4 unit. Approximately $70 million in remedial work was required to return the
power plant to service (the Callide C4 Rebuild Project), but a dispute arose between
IGPC and its insurer, so the process was delayed.
[3] In the meantime, Genuity and IGPC were unable to raise sufficient external funds to
pay for the rebuild with the looming potential that the value of Callide C would be
significantly reduced. So, by a written Loan Agreement dated 1 April 2022, Genuity
(formerly OzGen Holdings Australia Pty Ltd (sometimes referred to as (OHA))
agreed to lend IGPC $60 million. Clause 4 of the Loan Agreement provided that
“The Loan shall not bear interest”. To fund the Loan to IGPC, Genuity borrowed $60
million from its parent company, OzGen (UK) Limited (OUK) pursuant to three loan
-- 3 of 20 --
4
agreements (together, the OUK/Genuity Loan Agreements). OUK obtained the
funds to lend to Genuity by way of equity contributions from shareholders. Under the
OUK/Genuity Loan Agreements, Genuity was required to repay the $60 million,
together with interest at 10 per cent per annum, by 15 June 2026. The principal
balance was repaid by Genuity to OUK on 5 June 2026, and the interest of about
$24,395,890.42 (Interest Charges) was repaid in full on 10 June 2026.
[4] Between April and June 2022, IGPC drew down $59,285,888 pursuant to the Loan
Agreement. But IGPC was unable to repay the funds advanced under the Loan
Agreement and was placed into administration by its directors on 24 March 2023. By
transactions on 16 October 2024 and 24 March 2025, Sev.en Global Investments a.s
(7GI) acquired 100 per cent of the shares in in IGPC’s immediate parent company,
IG Power Holdings Ltd (IGPH) and so, from around March 2025, 7GI has controlled
IGPC. The result is that IGPC is no longer a subsidiary of Genuity and the Callide
Power Project is effectively now a joint venture between CSE and 7GI.
[5] By proceedings commenced in July 2025, Genuity claims that IGPC is liable for the
Interest Charges under clause 5 of the Loan Agreement as “necessary and reasonable
fees, costs, charges and expenses” it incurred to OUK in funding the Loan to IGPC.
There is also an offsetting debt claim by IGPC, but that issue is listed for trial before
me later in the year.
Questions for determination
[6] The following five separate questions were identified for determination:
Question one: Whether on its proper construction, clause 5 of the Loan
Agreement obliges IGPC to reimburse Genuity for the
amounts of interest paid by Genuity pursuant to the
OUK/Genuity Loan Agreements. The answer to this question
turns on the construction of that clause as it appears in the
Loan Agreement.
Question two: If the answer to question one is yes, whether the amount
sought to be recovered by Genuity from IGPC are “necessary
and reasonable” within the terms of clause 5 of the Loan
Agreement. The answer turns not only on the proper
construction of clause 5, but on the factual findings and an
objective assessment as to whether it was necessary and
reasonable for Genuity to have incurred the Interest Charges.
Question three: If the answer to question two is yes, whether “necessary and
reasonable” fees, costs, charges and expenses are only
recoverable on demand (that is, is a demand a necessary
condition to reimbursement)? It is unnecessary to answer this
question as, despite a denial in the pleading, IGPC now
accepts that a demand for payment of the Interest Charges has
been made both by letter and the commencement of the
proceeding.
Question four: Whether interest incurred but not paid under the OUK/
Genuity Loan Agreements is recoverable. It is unnecessary to
answer this question as all of the Interest Charges have now
-- 4 of 20 --
5
been paid to OUK, with the last tranche of about $8 million
paid by Genuity on 10 June 2026.
Question five: The calculation of the amount due by IGPC to Genuity
pursuant to the Loan Agreement. The parties agreed that the
answer should be deferred until questions one and two have
been answered with the parties to be given the opportunity to
make further submissions.
[7] These reasons address questions one and two. As the answers to both turn on the
proper construction of the Loan Agreement, it is convenient to start by setting out that
document in full.
The terms of the Loan Agreement
[8] The Loan Agreement defines Genuity as the “Lender” and IGPC as the “Borrower”
and otherwise states:
“…
This agreement records the terms of an agreement between the Lender
and the Borrower where the Lender agrees to lend an amount of up to
A$60,000,000.00 to the Borrower on the terms set out in this
agreement.
1. Timing
At the discretion of the Lender, and upon receipt of a written request
from the Borrower, the Lender will lend to the Borrower an amount of
up to A$60,000,000.00 (“the Loan”). The Loan may be drawn down
in a single draw down request or over multiple draw down requests as
requested at the Borrower’s discretion provided always that the
aggregate of all draw down requests made by the Borrower do not
exceed A$60,000,000.00.
2. Purpose
The purpose of this Loan is to enable the Borrower to provide liquidity
support to the Borrower to enable the Borrower to pay costs and other
obligations approved in the Callide Rebuild Commitment Agreement
dated 28 December 2021 between Union Star Development Limited,
InterGen Australian Holdings (UK) Limited and OzGen (UK)
Limited. The Borrower must apply the proceeds of the Loan for this
purpose.
3. Repayment
This Loan is repayable on demand by the Lender and in any event
within 12 months from the date of this Loan Agreement unless
otherwise agreed between the Lender and the Borrower in writing. The
Borrower must repay any amount so demanded by the Lender
forthwith after receipt of the demand.
-- 5 of 20 --
6
4. Interest
The Loan shall not bear interest.
5. Fees and Costs
The Borrower must reimburse the Lender on demand for all necessary
and reasonable fees, costs, charges and expenses which the Lender
may incur in funding and maintaining the Loan.
6. Governing Law
This agreement is governed by the laws of Queensland and the Lender
and the Borrower submit to the non-exclusive jurisdiction of the
Courts of Queensland.
…”
[9] The parties contend for alternative constructions of clause 5. Genuity submitted that
the Interest Charges amount to “necessary and reasonable fees, costs, charges and
expenses which Genuity…incur[red] in funding and maintaining the Loan to [IGPC]”
but IGPC submitted that the express provisions of clause 4 provide for an interest-
free Loan and are otherwise not necessary or reasonable.
[10] How then should the Court approach the construction of the Loan Agreement?
How are commercial agreements to be construed?
[11] The proper construction of a commercial contract is to be determined from the text
and the commercial context at the time in which the agreement was made; Toll
(FGCT) Pty Ltd v Alphapharm Pty Ltd (2004) 219 CLR 165 at [40]. That context
includes construing the terms as a reasonable businessperson would have understood
them to mean; Electricity Generation Corporation (t/as Verve Energy) v Woodside
Energy Ltd (2014) 251 CLR 640 at [35]. In doing so, it is necessary to consider the
language used, the surrounding circumstances known to the parties at the time of the
contract and the commercial purpose or objects to be secured by the contract;
Electricity Generation at [35].
[12] Ordinarily, a commercial contract is to be construed on the assumption that the parties
intended to produce a commercial result unless a contrary intention appears;
Electricity Generation at [35].
[13] The commercial purpose or objects of the agreement may be informed by an
understanding of the background to the transaction and the context and market in
which the parties are operating; Mount Bruce Mining Pty Ltd v Wright Prospecting
Pty Ltd (2015) 256 CLR 104 at [49]. This is the case despite how clear the “ordinary
words” of the agreement may be; Yume Group Holdings Pty Ltd v Ashthorn CA Pty
Ltd [2024] VSCA 134 at [53]. There is no requirement to establish ambiguity before
the surrounding circumstances can be considered; Masterton Homes Pty Ltd v Palm
Assets Pty Ltd (2009) 261 ALR 382 at [3].
[14] The necessary analysis of the objective facts and circumstances relevant to the
construction of the Loan Agreement is informed firstly by a more detailed
-- 6 of 20 --
7
understanding of the complex corporate structure of the entities associated with the
Callide Power Project.
Detail of the corporate structure of the Callide Power Project
[15] At the time of the various loan agreements the subject of these proceedings:
(a) Genuity was the head of the Australian OUK subsidiaries; collectively referred to
as Genuity Group. It controlled joint-venture interests in Callide C (50 per cent)
and another power station at Millmerran (65 per cent). As stated earlier, IGPC
held the interest in Callide C with the other 50 per cent in Callide C owned by an
entity associated with CSE;
(b) Genuity was owned by OUK, a company registered in England and Wales;
(c) OUK was owned by two companies: InterGen Australian Holdings (UK) Limited
(IAHUKL) and Union Star Development Limited (USDL) in equal shares (the
OUK Shareholders);
(d) USDL was effectively controlled by China Hua Neng Group Hong Kong Limited
(CHG); and
(e) IAHUKL was owned by interests related to 7GI (50 per cent) with the balance
held by entities controlled by CHG and others.
[16] Mr Tengdahl is the chief financial officer of the Genuity Group. He has over 35
years’ experience in tax and finance and has worked at Genuity since 2002. He has
been the CFO of the Genuity Group since 2008 and has been and remains since
2010, a director of all the Genuity Group companies. Mr Tengdahl resigned as a
director of IGPC (and the other companies sold to 7GI) in April 2025. He was
therefore a director of both Genuity and IGPC at the time of the Loan Agreement
and the OUK/Genuity Loan Agreements. Mr Tengdahl swore several affidavits and
was cross-examined before me. I found Mr Tengdahl to be an honest witness but for
the reasons stated below (at [94]) he was not a particularly reliable historian and his
evidence as it concerned the issue of the Interest Charges being necessary and
reasonable was unconvincing and unreliable.
[17] Mr Tengdahl and Mr d’Emden were the main individuals involved (for both Genuity
and IGPC) in the execution of the Loan Agreement. Mr d’Emden is the head of
treasury and financial planning and analysis of Genuity. He reports to Mr Tengdahl
and has over 12 years’ experience as a financial analyst at Genuity. Mr d’Emden
drafted the Loan Agreement and has prepared various reconciliations of the amounts
due under the various loans.
[18] The subjective intentions of these witnesses as the relevant minds of both sides of the
agreement are of course irrelevant. The objective purpose of the Loan Agreement is
to be determined by the Court in the light of what was known to the parties at the
time; HNA Irish Nominee Ltd v Kinghorn (No 2) (2012) 290 ALR 372 at [261]–[264].
[19] What then were the circumstances in which the Loan Agreement came about?
-- 7 of 20 --
8
Objective factual background at the time the Loan Agreement was executed
[20] Following the explosion in May 2021, IGPC made a claim on its insurance, with the
proceeds expected to be received in September 2021. But that did not occur. So, in
September 2021, Mr Tengdahl started exploring options for IGPC to obtain funding
for the Callide C4 Rebuild Project. Mr Tengdahl also asked Mr d’Emden and an
external consultant (Mr Livingston) to explore IGPC’s options.
[21] On 14 September 2021, Mr Livingston sent an email to Mr Tengdahl and Mr d’Emden
estimating that C4 would be returned to service in February 2022 and that IGPC
would require funding of about $117 million to meet the rebuild costs and other
cashflow requirements to November 2022. Mr Livingston proposed various options
involving “‘external’ liquidity support” through a third-party financier.
[22] Mr Tengdahl did not consider IGPC would be successful in obtaining funding from a
third party such as a bank, and together with Mr d’Emden, decided to seek funding
from OUK Shareholders. I accept (as both logical and reasonable), Mr Tengdahl and
Mr d’Emden’s evidence about the difficulties in obtaining funding from a third party.
[23] First, in 2017 and 2018, IGPC had approached around 36 banks for external bank
funding. This process was slow and not particularly fruitful. Over 18 months, only
two banks provided funding and for much lower amounts than had been sought.
[24] Second, there was urgency in obtaining the funding. Mr Tengdahl considered that
the process to obtain external bank funding would take many months. Time that IGPC
did not have.
[25] Third, the banks had developed environmental, social and governance policies which
discouraged financing projects in the coal industry or those associated with the coal
industry.
[26] Fourth, the financial position of IGPC was worse in late 2021 than it was in 2018.
The C4 explosion had reduced IGPC’s revenue.
[27] Fifth, the fact of the C4 explosion was likely to dissuade third party lenders from
providing finance to IGPC.
[28] The most suitable option was therefore to raise funds directly from OUK
Shareholders.
November 2021 – Genuity request to OUK Shareholders for funding approval
[29] On 1 November 2021, the managing director of Genuity, Mr Gunther sent a “liquidity
update and request” for OUK Shareholder approval:
(a) for the Callide C4 Rebuild Project at an estimated cost of $70 million (excluding
the contingency); and
(b) for the rebuild to be funded by insurance proceeds (if received), available Callide
Project cashflow and from Millmerran distributions or other equity provided by
shareholders (at shareholders’ election), which was forecast to be required from
December 2021.
-- 8 of 20 --
9
[30] On 10 November 2021, Mr Gunther sent a “Shareholder Liquidity Support”
memorandum to OUK Shareholders. The memorandum noted that Callide C had
funded margin calls of $19 million in September and October 2021 which had
“changed Callide’s liquidity” such that additional funding would be required in
January 2022.
[31] The memorandum further noted:
(a) that if the insurance proceeds were not received by 31 December 2021, the Callide
Project required additional liquidity support to continue its operations and return
to service;
(b) without insurance, the Callide Project required funds totalling $117 million to
meet operating costs, rebuild costs, debt payments and, for the period November
2021 to March 2023, cash support for the project to operate;
(c) Genuity had sought potential options about finance with its financial advisers and
consultants, but for various reasons there was no solution identified that would
attract liquidity to support Callide, so this was not a viable option;
(d) Callide could draw $20 million from an existing working capital facility to meet
margin calls that had been paid, but a draw on that facility would not be possible
without the provision of liquidity support from the OUK Shareholders; and
(e) the directors were seeking approval from the OUK Shareholders “to provide the
necessary liquidity support to the Callide project...over the next 9 months...”.
December 2021: Callide Rebuild Commitment Agreement
[32] On 28 December 2021, OUK and the OUK Shareholders executed the Callide
Rebuild Commitment Agreement (CRCA). Genuity was not a party to this agreement
nor was it involved in its negotiation. Although Mr Tengdahl was provided a copy of
the agreement on 29 December 2021.
[33] Pursuant to the CRCA:
(a) (clause 2.1) the OUK Shareholders acknowledged that the Callide C4 Rebuild
Project was expected to be completed within the budget of $117 million and
would be funded “to the extent possible by any combination of funds” from:
(i) the proceeds of insurance;
(ii) the current or future cash reserves of the Callide Project; and
(iii) the available proceeds of any debt financing of the Callide Project;
(b) (clause 2.2) to the extent funding was not available from those sources, OUK
undertook to the OUK Shareholders to contribute, and procure its subsidiaries to
contribute, any available cash reserves to the C4 rebuild;
(c) (clauses 2.3 and 2.4) the OUK Shareholders undertook to each other to each
support 50 per cent of any shortfall between the sources in clauses 2.1 and 2.2 and
the C4 rebuild costs (the Funding Gap), up to $30 million each; and
-- 9 of 20 --
10
(d) (clause 2.5) the funding provided by the OUK Shareholders to OUK “shall be
provided by way of equity subscription or loan as agreed” between the OUK
Shareholders and, absent agreement, by equity.
March 2022 – funding is required
[34] In late March 2022, there were significant increases in forward market electricity
prices. This resulted in Mr d’Emden preparing a cashflow forecast for the Callide
Project. It showed that IGPC required immediate funding of $20 million to meet
anticipated margin calls.
[35] On 28 March 2022, Mr Tengdahl sent an email to Mr Teague (a director of OUK)
with the subject line “Callide Liquidity—Shareholder Funding”. It stated:
“Hi Paul
Fyi, the forward curve has continued to increase over the past few
weeks with the largest increase coming today (see below email). This
is just a heads up to let you know I expect to send an email to you, Di
[Zhang] and 7E, tomorrow with a general Callide liquidity update and
a request for $20m (IG share GBP 5.7m) of the $60m shareholder
funding to be provided asap but no later than Monday April 11, with
another $20m in May. We are still working through a few issues that
I will discuss with Brent [Gunther] but I believe that is where we will
end up so wanted to give you some advance notice...”
[36] In response, Mr Teague stated:
“Thanks Brett - will need a cash update (inc forecast summary).
Propose going in as debt or equity? Ease of return of insurance
proceeds a factor?”
(emphasis added)
[37] In response, on 30 March 2022, Mr Tengdahl wrote: “We would inject the funds as a
loan from OzUK to OHA...”
[38] On 31 March 2022, Mr Tengdahl sent a request to OUK Shareholders for $20 million
of funding in April 2022, with a further $23 million in May 2022. The email further
stated:
“Accordingly, OzGen management requests that as soon as possible
but no later than April 15, OzGen shareholders each transfer A$10m
(total of A$20m) to OHA of the A$60m funds which has been
previously approved as part of the Shareholder funding in the Equity
Commitment Deed,1 for the following purposes...”
Many balls in the air on 1 April 2022
[39] In an exchange of emails between Mr Tengdahl and Mr Graves and Mr Teague (from
OUK) on 1 April 2022:
1 This appears to be a reference to the CRCA.
-- 10 of 20 --
11
(a) Mr Graves asked: “I was wondering if you have heard from CHG regarding form
of funding into OzGen UK - equity or utilising the existing loan structure that was
used to fund Millmerran?”;
(b) Mr Tengdahl responded: “No I have not discussed this directly with Di [Zhang]
but I would expect it would follow the existing loan structure used for
Millmerran”.
[40] Mr Zhang is a representative of CHG. He was a director of OUK and USDL. He was
not called, nor did he give evidence at the hearing. Nothing turns on this.
[41] On 1 April 2022, Mr d’Emden prepared a draft loan agreement between OUK and
Genuity. The draft provided for interest to be paid by Genuity to OUK at 10 per cent
per annum. This agreement was based on a template Mr d’Emden obtained from a
prior loan between OUK and Genuity for Millmerran (required due to a shortfall in
the debt provided to Millmerran) (the Millmerran Loan). The rate of 10 per cent in
the Millmerran Loan took into account that OUK had borrowed the funds at 8.75 per
cent from the OUK Shareholders and “grossing up” that amount for Australian
withholding tax (or 10 per cent). It was also based on advice Genuity received from
Mr Bona, a partner of PwC Global Tax. That advice, dated 29 June 2021, was that an
arm’s length range would be 8.5 per cent to 12.9 per cent, with the median in the order
of 10 per cent.
[42] At the time, Mr Tengdahl was conscious that any interest payable by Genuity to OUK
had to comply with the transfer pricing requirements of the Income Tax Assessment
Act 1997 (Cth). Mr Tengdahl explained those obligations require cross-border loans
to comply with arm’s length principles (that is, a loan that would be expected between
independent entities dealing at arm’s length).
[43] As things transpired, the OUK Shareholders elected not to lend moneys to OUK
(which was a departure from the Millmerran funding structure).
[44] On 1 April 2022, shareholders of 7GI and other related shareholders resolved to
provide $30 million of funding to IAHUK “to allow for the contribution of funds to
OzGen to meet IAHUK’s obligations under the Callide Commitment Agreement” and
“that such funds may be provided and contributed by any combination of (i) loans
and (ii) subscription for new shares of the Company and/or in OzGen”. Mr Tengdahl
was not aware by 1 April 2022 it had been agreed that the funds under the CCRA
were to be provided to OUK through an equity injection by the OUK Shareholders.
He initially thought he became aware of this fact by March 2023. But as discussed in
more detail below (at [94]), Mr Tengdahl belatedly accepted that he knew of that
much earlier. Indeed, Mr Tengdahl realised that he was told on 14 April 2022 that the
funding from the OUK Shareholders was by way of equity in return for shares.
[45] It is within this factual construct that the Loan Agreement (drafted by Mr d’Emden)
providing for Genuity to lend $60 million to IGPC was executed by Mr Tengdahl on
1 April 2022.
What happened after the Loan Agreement was executed on 1 April 2022
[46] The following factual matrix is not relevant to the first issue of whether the Interest
Charges fall within the definition of fees and costs under clause 5. But it forms part
-- 11 of 20 --
12
of the ongoing narrative and is otherwise relevant to the second issue as to whether
Interest Charges (as may be captured by clause 5) are necessary and reasonable.
[47] By early April 2022, IGPC was clearly in urgent need of funding. In April 2022,
Genuity advanced $12.88 million to IGPC by way of a Gap Loan. This amount was
sourced by Genuity from its own cash resources and those of its Australian
subsidiaries. The Gap Loan was repaid by IGPC to Genuity once the loan from OUK
to Genuity became available.
April 2022: The drawdown on the Working Capital Facility Agreement is denied
[48] On 5 April 2022, IGPC gave notice to its banker, Bank of China, seeking to draw
down $20 million from the WC Facility Agreement. But on 6 April 2022, Bank of
China gave notice to IGPC that the financiers under the WC Facility Agreement were
“not comfortable” proceeding with the request and IGPC subsequently withdrew the
drawdown request.
Subsequent preparation of the Loan Agreements between OUK and Genuity
[49] On 4 April 2022, Mr Svoboda, the Chairman of the board of 7GI, sent an email to the
OUK Shareholders’ representatives, OUK directors and Mr Gunther and Mr
Tengdahl stating that:
“…At the same time OzGen Shareholders should provide the $60m of
liquidity to Callide as part of the Equity Commitment Deed in order
to fund the reconstruction of C4. I also understand from Brett
[Tengdahl] that this should be done ASAP. Again, we are ready to do
so and will ask Jim and Paul [of OUK] to prepare the appropriate
loan agreements.”
(emphasis added)
[50] On 8 April 2022:
(a) Mr Slechta of 7GI asked Mr Teague: “In which form will IGNV/IAHUK be
providing the funding to OzGen [OUK]? Simple loan, right?”;
(b) in response, Mr Slechta was informed by Mr Teague that the form of funding
from the OUK Shareholders to OUK would “more likely” be equity and OUK to
Genuity “is likely debt” and then “equity down to project”; and
(c) following that email, Mr Slechta sent an email to Mr Tengdahl confirming that
debt from OUK to Genuity “sounds good”.
[51] On 13 April 2022, Mr Zhang advised that CHG was “ready to review and approve
the loan docs...before contributing cash under CRCA. We understand that this need[s]
both OZGEN and IG board approval and ask IG and OZGEN to provide us the Docs
this week”.
19 April 2022: First OUK/Genuity Loan Agreement
[52] On 19 April 2022, the OUK Shareholders resolved that OUK and Genuity could enter
into the First OUK/Genuity Loan Agreement and that Genuity may draw down funds
up to the Commitment amount under the OUK/Genuity Loan Facility.
-- 12 of 20 --
13
[53] The First OUK/Genuity Loan Agreement was executed by Mr Tengdahl on behalf of
Genuity and provided:
(a) (clause 2.1) for OUK to make an advance to Genuity of up to $20 million;
(b) (clause 3) for Genuity to pay interest at the rate of 10 per cent per annum, which
accrues daily and is payable in arrears every six months;
(c) (clause 4) for the advance and all accrued and outstanding interest to be paid by
15 June 2026 (the “Final Maturity Date”); and
(d) (clause 5) that Genuity could elect to defer the payment of interest and could elect
to pay amounts of deferred interest.
[54] The commitment of $20 million was advanced to Genuity by payments made of
$10 million each directly by the two OUK Shareholders on 19 and 20 April 2022,
respectively.
May 2022: Second OUK/Genuity Loan Agreement
[55] On 6 May 2022, Mr Tengdahl sent an email to the OUK directors and OUK
Shareholders seeking further funding of $25 million. Each of the OUK Shareholders
was requested to contribute $12.5 million each to OUK by 15 May 2022.
[56] On 17 May 2022, OUK and Genuity entered into the Second OUK/Genuity Loan
Agreement. Again, this agreement was executed by Mr Tengdahl and is in the same
terms as the first agreement, except the commitment was $25 million.
[57] The commitment of $25 million was advanced to Genuity by payments made of
$12.5 million each directly by the two OUK Shareholders on 17 and 18 May 2022.
respectively.
June 2022: Third OUK/Genuity Loan Agreement
[58] On 1 June 2022, Mr Tengdahl sent an email to the OUK directors and OUK
Shareholders seeking further funding of $15 million. Each of the OUK Shareholders
was requested to contribute $7.5 million each to OUK by 8 June 2022.
[59] On 7 June 2022, the directors of OUK and the OUK Shareholders resolved that OUK
would lend $15 million to Genuity on the same terms of the Second OUK/Genuity
Loan Agreement. The Third OUK/Genuity Loan Agreement was in the same terms
as the earlier two agreement except that the commitment was $15 million.
[60] IGPC submitted that the Third OUK/Genuity Loan Agreement was “backdated” by
Mr Tengdahl. Genuity accepted that the agreement was executed by Mr Tengdahl
“albeit belatedly” but argued that this was due to a simple administrative oversight.
It is unnecessary to resolve what exactly happened. The real issue is one of the proper
construction of clause 5 of the Loan Agreement. Regardless, what is clear is that
Genuity:
(a) confirmed its assent to the terms of this third agreement by sending a draft to OUK
and OUK Shareholders for execution;
(b) performed its terms, including obtaining the benefit of the loan and in repaying
interest and, most recently, the whole of the principal due; and
-- 13 of 20 --
14
(c) is bound by its terms.
[61] The commitment of $15 million was advanced to Genuity by payments made of
$7.5 million each directly by the two OUK Shareholders on 9 and 10 June 2022,
respectively.
The advances by Genuity to IGPC under the Loan Agreement
[62] Between 20 April 2022 and 21 June 2022, Genuity advanced $59,285,888 over
11 payments to IGPC pursuant to the Loan agreement.
[63] The moneys were “drip fed” to IGPC as IGPC required funding to meet its payment
obligations and to ensure there was not a significant cash balance in IGPC which may
have been a catalyst for lenders to act more aggressively to the detriment of IGPC
and its shareholders. The consequence of the drip feeding of money was that Genuity
incurred interest on the whole of the $60 million advanced to it, but which was not
necessarily advanced to IGPC at the same time (or at all). However, the $60 million
advanced to Genuity was held in an interest-bearing account pending it being on-lent
to IGPC. In calculating its costs of providing the funding, Genuity has deducted the
interest received by it in respect of the $60 million (or so much of it as was not on-
lent) held in that interest-bearing account.
The Second Loan Agreement
[64] On 20 December 2022, Genuity and IGPC entered into a Second Loan Agreement in
relatively the same terms as the first one between them. That same day, Genuity
advanced $11.4 million to IGPC pursuant to the Second Loan Agreement. As those
moneys were not “on lent” from moneys borrowed by Genuity from OUK, Genuity
does not claim in respect of the costs of funding or maintaining the second loan. The
claim is simply for the recovery of the principal, which is part of question 5; to be
determined after these reasons have been delivered.
Question one: does clause 5 of the Loan Agreement oblige IGPC to reimburse
Genuity for the Interest Charges
[65] The Court is entitled to look at evidence of the objective factual background known
to the parties at the time of the contract to assist in the interpretation of a written
agreement if the language is ambiguous or susceptible of more than one meaning –
as has been submitted in this case. As stated earlier, the meaning of a commercial
contract is to be determined objectively according to what a reasonable
businessperson would have understood its term to mean. This approach proceeds on
the assumption that the parties intended to produce a commercial result and to avoid
the contract making commercial nonsense or working commercial inconvenience.
Commercial context
[66] At the time of the Loan Agreement, both lender and borrower were members of the
same corporate group. Mr Tengdahl was a director of both (with other common
directors). In late November 2021, and in the time leading up to the Loan Agreement
being signed on 1 April 2022, IGPC was facing intense liquidity issues arising from
margin calls and the C4 rebuild costs. Mr Tengdahl and Mr d’Emden were working
quickly to sure up finance for IGPC. That context at the time was that Genuity and
-- 14 of 20 --
15
IGPC were unable to raise sufficient external funding to fund the cost of Callide C.
To address the funding gap, Genuity looked to the shareholders of its parent company,
OUK, to supply the necessary funds. Unless Callide C was repaired, its value was
estimated to reduce from $300 million to $30 million.
[67] On 28 December 2021, OUK’s Shareholders entered into the CRCA each agreeing to
provide to OUK the sum of $30 million, for a total of
$60 million, in order to assist in financing the cost of the Callide C4 Rebuild Project.
Under the CRCA, in return for the $60 million in funding, the OUK Shareholders
were to receive further shares in OUK. The CRCA provides that, unless agreed
otherwise, the funds provided under the CRCA would be provided in return for shares
in OUK. There was no other agreement, and as things transpired, the funds advanced
under the CRCA were provided as equity, not debt.
[68] The purpose of the funding from OUK, which was to be on-lent to IGPC, was for the
costs of rebuilding the C4 unit following the incident. That is evident from the
November 2021 emails and the terms of the CRCA itself. It is also evident from the
purpose of the loan as recorded in clause 2 of the Loan Agreement was to provide
liquidity support to IGPC to enable IGPC to pay costs and other obligations approved
in the CRCA. The parties anticipated at the time that the insurance proceeds would
be up to $138 million but there was uncertainty as to the timing of payment. The
repayment of the Loan (due on 1 April 2023, 12 months from the date of the Loan
Agreement) was anticipated to align with repayment of the insurance proceeds and
C4 being returned to service.
[69] Genuity submitted that the fact the parties were members of the same corporate group
explains why $60 million was lent on the back of such a short agreement. I accept
that. But this submission cuts both ways. The parties are part of a sophisticated
corporate structure in a highly complex industry. Those behind the corporate face are
very experienced businessmen who, at the time, had been involved in the industry
and in the formulation of loan agreements for some time. Objectively speaking, the
drafting of such a short concise document is also consistent with the objective
likelihood that the parties wanted to record what was to be a simple and speedy
transaction to fill a gap pending the receipt of insurance monies. This was done
through a short-term loan which, by clause 3, was repayable on demand and, in any
event, within 12 months.
[70] Genuity submitted that the construction for which IGPC contends produces “a
commercial nonsense or [works] a commercial inconvenience” because it “traps” the
liability to pay interest within Genuity where Genuity:
(a) did not derive any meaningful revenue and had no means to pay the interest,
absent support from other companies in the group;
(b) was not the ultimate beneficiary of the funding, which was for IGPC to meet its
obligations towards the C4 rebuild; and
(c) did not derive the revenue from the Callide Power Project, or stand to receive the
insurance proceeds, to which the funding was directed to filling a “gap” pending
receipt of those moneys.
[71] I do not accept the above submission. Rather, I am satisfied that it was objectively in
the mutual interests of IGPC, Genuity, OUK and OUK Shareholders that the funding
-- 15 of 20 --
16
gap was met. In this context, whether IGPC repaid the Loan with or without interest
was of no commercial significance, particularly given that all relevant transactions
occurred within a single corporate group. In these circumstances, there was nothing
commercially unsurprising about Genuity incurring interest on funding which it
provided to its ailing subsidiary (IGPC) on an interest-free basis during a time of
crisis. Mr Teague did not propose an interest obligation on IGPC down the line (at
[50(b]) above). This is unsurprising, given the fact that in contrast to IGPC’s dire
financial predicament, Genuity’s other asset was a 65 per cent interest in the
Millmerran Power Station which had earned a profit for the year ending December
2021 of about $104 million. It is also instructive that clause 2.2 of the CCRA
provided that OUK and OUK Shareholders committed to procuring their subsidiaries
to contribute any available cash reserves to the C4 rebuild, with Genuity being one of
those subsidiaries.
What language was used?
[72] While a court will have regard to the commercial context, the start and end point, of
course, is the language chosen by the parties to record their agreement: Cherry v
Steele-Park (2017) 96 NSWLR 548 at [72].
[73] The court must give effect to the language of the contract, unless to do so would give
the contract an absurd operation: Jireh International Pty Ltd v Western Exports
Services Inc [2011] NSWCA 137 at [55]. There is nothing absurd or uncommercial
in giving effect to the clear terms of the Loan Agreement.
[74] The Loan Agreement is only two pages long. Clauses 4 and 5 appear immediately
after one another as set out (again) below:
“…
4 Interest
The Loan shall not bear interest.
5 Fees and Costs
The Borrower must reimburse the Lender on demand for all necessary
and reasonable fees, costs, charges and expenses which the Lender
may incur in funding and maintaining the Loan.
…”
[75] The plain meaning of the words “the loan shall not bear interest” in clause 4 are clear.
They mean that IGPC is not liable to pay interest on the Loan. The commercial object
of this Loan (concerning interest) is that it was to be interest-free.
[76] The clauses of a contract are to be construed in a way that is harmonious and achieves
congruency to the various parts: Wilkie v Gordian Runoff Ltd (2005) 221 CLR 522 at
[16]; Australian Broadcasting Commission v Australasian Performing Right
Association Ltd (1973) 129 CLR 99, 109.
[77] Under clause 5 of the Loan Agreement, IGPC is required to reimburse Genuity on
demand for all necessary and reasonable “fees, costs, charges and expenses”. Clause
5 does not refer to “interest”, notwithstanding that interest is expressly referred to
-- 16 of 20 --
17
immediately above in clause 4. This strongly suggests that the objective intention
underlying clause 5 was that it would not permit Genuity to pass interest on to IGPC.
The fact that the issue of interest is expressly and specifically mentioned in one clause
rationally tends to exclude the implication of it arising in another clause; Expressio
unius est exclusio alterius; S.C.N. Pty Ltd v Smith [2006] QCA 360 at [7].
[78] I am not satisfied that the omission of a reference in clause 5 to interest is the result
of inadvertence; Houssein v Under Secretary, Department of Industrial Relations &
Technology (NSW) (1982) 148 CLR 88, 94. Rather, the intention of the parties is
plainly discoverable on the face of the Loan Agreement; PMT Partners Pty Ltd v
Australian National Park & Wildlife Service (1995) 184 CLR 301, 320.
[79] Genuity submitted that a construction that finds that clause 5 does not permit the
recovery of interest it incurred is to render that clause redundant or surplusage
because the only “fees, costs, charges and expenses” in the contemplation of the
parties that Genuity might incur in funding and maintaining the loan was interest
under the OUK/Genuity loan agreements. But this submission overlooks two things.
[80] First, that clause 5 is not expressed in mandatory terms and, by its use of “may” rather
than “will”, contemplates that such items may not be incurred.
[81] Second, IGPC’s ailing financial position and the difficult circumstances facing the
Callide C Rebuild Project. In those circumstances, the expression “necessary and
reasonable fees, costs, charges and expenses” in clause 5 when construed objectively
may be seen to contemplate any relatively modest transactional expenses such as bank
fees, legal and accounting fees that might arise in funding and maintaining the loan.
But having regard to the mutually known factual background to the Loan (including
that it was repayable within 12 months), it would be uncommercial for “costs” and
“expenses” to include some $24 million in Interest Charges.
[82] Genuity sought to distinguish between interest by way of “return or compensation”;
Vision Super Pty Ltd v Poulter (2006) 154 FCR 185 at [71], and the interest incurred
by Genuity in borrowing the monies from OUK. The first being interest as a method
of making profit (covered by clause 4) and the other as the mere recovery of interest
paid (said to be included in clause 5). Assuming that such a distinction exists and
makes a difference, this submission overlooks that at the time of entering into the
Loan Agreement, it was objectively known to the parties, through Mr Tengdahl and
Mr d’Emden, that the OUK/Genuity Loan Agreements were going to include a
provision for interest to be paid by Genuity to OUK at the rate of 10 per cent. Such a
rate was expressly specified in the draft agreement prepared by Mr d’Emden on 1
April 2021. That is, the actual “cost” was known.
[83] If the parties had intended that a considerable amount of interest incurred by Genuity
was to be passed on to IGPC as a “cost” or “expense” of funding and maintaining the
Loan, it is reasonable to expect that they would have expressed this in clear and
unambiguous terms in the Loan Agreement. It would have been very easy to do so,
as the notion that interest at a rate of 10 per cent was being contemplated and was
known to parties at the time. But the parties chose not to include any reference to the
passing on of interest in clause 5 or anywhere else in the Loan Agreement.
[84] What Genuity claims as a cost or expense under clause 5 is the interest on the money
that it was lent by OUK. The passing on of this type of “cost” to IGPC falls squarely
-- 17 of 20 --
18
within the various definitions of “interest” discussed in Consolidated Fertilisers v
DCT (1992) 36 FCR 1 at page 6, including an obligation to pay money as a charge
for the use of borrowed money expressed as a percentage per time unit of the sum
used.
[85] Viewed in context, the omission of “interest” from the phrase “fees, costs, charges
and expenses” in clause 5 cannot be regarded as an omission or oversight by the
parties. The parties expressly turned their mind to the issue of interest and addressed
it in clause 4. If it had been intended that, notwithstanding the clear effect of clause
4, Genuity could nonetheless pass on Interest Charges (it was liable to OUK for) to
IGPC under clause 5, the parties would have made some reference to that (for
instance, by adding the words “fees, costs, charges, interest incurred, and expenses”).
[86] In the absence of a reference to interest in clause 5, and in the context of interest being
addressed specifically in clause 4, the proper construction of clause 5 is that the
Interest Charges are not contemplated as “fees, costs, charges and expenses” that may
be passed on from Genuity to IGPC. Such a finding is consistent with the maxim of
contractual interpretation that a specific provision within a contract is to prevail over
a general provision covering the same subject matter in the same contract; generalia
specialibus non derogant: LCA Marrickville Pty Ltd v Swiss Re International SE
(2022) 290 FCR 435 at [58].
[87] I find that on a proper construction of the Loan Agreement, IGPC is not obliged to
reimburse Genuity for Interest Charges incurred (and now paid) by Genuity pursuant
to the OUK/Genuity Loan Agreements.
[88] The answer to the first question for determination is therefore: “no”.
Question two: are the Interest Charges “necessary and reasonable” within the
terms of clause 5
[89] In case I am wrong about my answer to the first question, I will answer question two.
[90] The onus is on Genuity to establish that the Interest Charges were necessary and costs
(or expenses) it incurred were reasonable in funding and maintaining the Loan.
[91] The Interest Charges were incurred by Genuity pursuant to the OUK/ Genuity Loan
Agreements. IGPC does not quibble with the rate of 10 per cent as being necessary
and reasonable. But rather submitted that Genuity has not established that the Interest
Charges of themselves necessary and reasonable costs.
[92] The starting point is that at the time that each of the OUK/ Genuity Loan Agreements
were entered into, Genuity (through Mr Tengdahl) knew that the funding under the
CCRA was coming from the OUK Shareholders by way of equity in return for shares.
This, of course, was a very different situation to the Millmerran Loan, where OUK
had borrowed the funds at 8.75 per cent from the OUK Shareholders and then on-lent
those monies to Genuity at an interest rate of 10 per cent.
[93] Mr Tengdahl only realised he knew of the equity funding from OUK on 14 April
2022 after he had been cross-examined (and re-examined) at the hearing. The
correction to his initial evidence (that he did not know about the equity injection until
sometime later) only came about after Mr Slechta apparently emailed Mr Tengdahl
-- 18 of 20 --
19
the night he finished giving his evidence, warning him that he may have perjured
himself because there was documentary evidence by way of an email dated 14 April
2022 that revealed that Mr Tengdahl knew that the funds were coming from OUK
by way of equity and not debt. I accept Mr Tengdahl’s frank and immediate
acknowledgment about this as expressed in the form of a further affidavit. But the
difficulty with this late and otherwise unexplained concession is that it infects all of
Mr Tengdahl’s evidence on this issue, making it both confusing and unreliable. For
example, his earlier evidence was that when he found out (much later) he was
surprised “that they did that” because it “introduces an inefficiency” in the structure,
and for an internal transaction that created a “UK tax liability which is completely
unnecessary” is difficult to understand in light of his actual knowledge of the true
position prior to entering into the OUK/Genuity Loan Agreements.
[94] The difficulty is that Genuity knew that the funds it was receiving to be on lent to
IGPC for the Callide C4 Rebuild Project were not coming from a debt incurred by
OUK; yet chose to enter into an agreement to pay 10 per cent interest on those equity
funds. The fact it had done this for the Millmerran Loan is irrelevant, as it was a
different funding circumstance.
[95] Genuity pointed to it being a decision by OUK to charge interest and appeared to
contend that, even though it was a party to the OUK/Genuity Loan Agreements, it
effectively had no say in the matter of interest. I found this submission unconvincing
and raised more questions than answers. I accept that there is evidence from OUK
Shareholders that approved the notion of debt from OUK to Genuity, but none of
those emails make any reference to interest being charged. Although the draft loan
agreement of 1 April 2022 includes interest, that is on the basis that it was an
arrangement like the Millmerran Loan – which Mr Tengdahl now accepts he knew it
was not.
[96] On the evidence, there is no cogent or reasonable explanation as to why it was
necessary for the equity injected funds to be on lent to Genuity with interest. It follows
that Genuity has not satisfactorily established why the incurring of Interest Charges
were necessary and reasonable costs.
[97] That is particularly so in circumstances where Mr Tengdahl accepted that none of the
reasons he had identified in his affidavits which favoured the funds being provided
by OUK to Genuity as a loan would have prevented those funds from being advanced
to Genuity as equity. That is, there was nothing preventing the funds that were the
subject of the Loan Agreement being provided to Genuity as a non-interest-bearing
capital contribution.
[98] Genuity have not proved why it was necessary and reasonable for the Interest Charges
to have been incurred in funding and maintaining the Loan to IGPC
[99] The answer to question two is therefore: “no”.
Answers to the questions stated
[100] The answer to question one is “no”: clause 5 of the Loan Agreement does not oblige
IGPC to reimburse Genuity for the amounts of interest paid by Genuity pursuant to
the OUK/Genuity Loan Agreements.
-- 19 of 20 --
20
[101] If I am wrong and the answer to question one is “yes”, then the answer to question
two is also “no”. The amount sought to be recovered by Genuity from IGPC as
Interest Charges are not “necessary and reasonable” within the terms of clause 5 of
the Loan Agreement.
[102] It is unnecessary to answer questions three and four.
[103] I will hear from the parties as to the appropriate directions to be made for the
determination of question five, the second tranche trial listed on 7 and 8 December
2026 and as to costs.
-- 20 of 20 --
Official source: https://www.sclqld.org.au/caselaw/QSC/2026/194