Pointon v Holstein [2026] QCAT 386
QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION: Pointon v Holstein [2026] QCAT 386
PARTIES: DANNY POINTON AND SUZANNE POINTON
(applicants)
v
NATHAN PAUL HOLSTEIN
(respondent)
APPLICATION NO/S: BDL285-25
MATTER TYPE: Domestic Dispute
DELIVERED ON: 10 August 2026
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member S M Burke
ORDERS: The Respondent, Nathan Paul Holstein, is to make
payment to the Applicants in the sum of $64,350.00 on
or before 21 September 2026.
CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING AND
RELATED CONTRACTS – REMEDIES FOR BREACH
OF CONTRACT – MEASURE OF DAMAGES – where
builder performed unlicensed building work – where builder
did not complete the works – where defective works – where
home-owner entitled to recover money paid under
agreement and damages to rectify and complete works –
failure of party to comply with Tribunal directions – failure
of party to deliver any evidence before the Tribunal
Queensland Building and Construction Commission Act
1991 (Qld), s 42, s 77
Bellgrove v Eldridge (1954) 90 CLR 613
Cook’s Construction Pty Ltd v SFS 007.298.633 Pty Ltd
[2009] QCA 75
Marshall v Marshall [1999] 1 Qd R 173
Robinson v Harman [1848] Eng R 135
APPEARANCES &
REPRESENTATION:
This matter was heard and determined on the papers
pursuant to s 32 of the Queensland Civil and Administrative
Tribunal Act 2009 (Qld)
REASONS FOR DECISION
[1] The Applicants, Danny and Suzanne Pointon, are the registered owners of a property
at 3 Miriam Court, Woolmar Queensland (‘the property’).
-- 1 of 6 --
2
[2] The Respondent, Nathan Holstein, carries on a business called NPH Concrete at 17
Cradle Court, Daguilar.
[3] On or about 17 January 2025, the Respondent provided to the Applicants a quotation
number 000388 for the installation of a plain grey concrete driveway including the
following works (‘the concrete works’):-
(a) Minor earthworks;
(b) F72 steel mesh sheets;
(c) 32MPA concrete;
(d) Ableflex expansion foam; and
(e) Concrete expansion cuts (if needed).
[4] The quotation for the works was $19,250.00.
[5] The Respondent confirmed the agreement was reached between the parties for the
concrete works requesting a deposit of 50% and the balance on completion.
[6] On 21 January 2025, the Applicants paid the deposit in the sum of $9,625.00. The
balance of $9,625.00 was to be paid on completion of the concrete works on 8
February 2025.
[7] Works were to commence on 3 February 2025.
[8] The works were completed by the Respondent on or about 22 February 2025.
[9] After a complaint on 19 March 2025 by the Applicants to the Queensland Building
and Construction Commission (‘QBCC’), the QBCC advised the Applicants on 28
April 2025 that the Respondent did not hold a QBCC licence for the work performed
and that the Respondent had been provided with the complete list of complaints filed
by the Applicants. The QBCC advised that the Respondent was aware of the items
which would be assessed at an inspection of the property on 19 May 2025. The
Respondent had been invited to attend the inspection.
[10] On 20 May 2025, a decision by QBCC inspector Mr Ferguson was made to issue a
direction to rectify in relation to 25 of the 26 complaints which were itemised in a
document headed ‘List of Complaint Items’.
[11] Mr Ferguson had carried out an inspection of the property in relation to the items in
the complaint on 19 May 2025.
[12] On 21 May 2025, the QBCC issued to the Respondent Direction to Rectify or Remedy
No. 0114174 (‘the Direction to Rectify’) requiring that the Respondent immediately
action the rectification work to be carried out by a licensed contractor.
[13] Attached to the Direction to Rectify was a Defective Work List which itemised 6
defects with the installation of the concrete driveway which were required to be
rectified and comply with Australian Standard AS 3727.
[14] On 21 May 2025, the QBCC advised the Applicants that their complaint had
progressed and that the Respondent had been issued with a Direction to Rectify with
the works to be completed by 25 June 2025.
-- 2 of 6 --
3
[15] On 21 July 2025, the QBCC confirmed that the Respondent had not complied with
the Direction to Rectify and listed the items of the Direction which had not been
rectified. This list related to all the items in the original Direction to Rectify.
[16] The Applicants have provided two quotations addressing the rectification of the
defective works:
(a) a quotation no.1113 dated 16 January 2026 from JuddCrete in the sum of
$45,100.00 for the rectification of the defective concrete driveway; and
(b) a quotation dated 23 January 2026 from JC Tech air-conditioning/electrical for
the decommissioning and reconnecting of an outdoor air-conditioning unit in
the sum of $900.00.
Directions
[17] The application for a domestic building dispute was filed 7 August 2025 in which the
Applicants sought recompense for the defective works allegedly carried out at the
property by the Respondent which involved a defective concrete driveway and
surrounding area.
[18] Directions were made by the Tribunal in relation to the filing of material and evidence
required by the Applicants and the Respondent on 27 August 2025.
[19] The Tribunal made further directions that in the event the Applicants complied with
the directions and the Respondent failed to comply with the directions, including not
filing a claim pursuant to s 42(4) of the Queensland Building and Construction
Commission Act 1991 (Qld) (‘QBCC Act’) by 24 September 2025, then the Applicants
would be entitled to a final decision in the proceeding.
[20] By direction dated 22 October 2025, the parties were advised that the application
would be determined on the papers regardless of compliance with the directions dated
27 August 2025.
[21] The Applicants have complied with the directions of the Tribunal dated 27 August
2025. No material has been filed by the Respondent and in particular no claim has
been made by the Respondent regarding any entitlement to payment pursuant to s
42(4) of the QBCC Act.
[22] As no material has been submitted by the Respondent, in accordance with the
directions of the Tribunal on 27 August 2025, the Tribunal proceeds to assess the
Applicants’ claim based on the material on which the Applicants rely.
[23] The Applicants’ evidence is uncontested despite the Respondent receiving all the
material delivered by the Applicants to the Tribunal.
[24] In the circumstances, it is necessary for the Tribunal to assess the damages claimed
by the Applicants.
Damages
[25] From the outset, in assessing the damages to which the Applicants are entitled it is
necessary to ensure that the Applicants are put into the same position they would have
been had the contract been properly performed. The starting point therefore is that the
Applicants would have incurred the sum of $19,250.00 had the works been completed
by a licensed contractor in a satisfactory manner in accordance with the contract.
-- 3 of 6 --
4
[26] The Applicants’ claim for the refund of this amount is not warranted merely on the
basis that the Respondent was unlicensed.
[27] The statutory framework of s 42(1) of the QBCC Act specifies that an unlicensed
person is prohibited from either entering into a contract to perform building work or
actually performing building work.
[28] Section 42(3) is said to sterilise any claim which might otherwise be made under the
contract or under common law by an unlicensed builder. It provides that a person who
carries out building work in contravention of s 42 is not entitled to any monetary or
other consideration for doing so.
[29] The prohibition in subsection (3) is subject to subsection (4) of s 42 which provides
that a person is not prevented from claiming a reasonable remuneration for carrying
out the building work, but only if the amount claimed is no more than the amount paid
by the person in supplying material and labour for carrying out the building work and
does not include an allowance for the supply of the person’s own labour and the
making of a profit.
[30] Section 42(4) imposes a limitation upon the right of action at common law which it
preserves against the sterilising effect of s 42(3). Without subsection (4), an
unlicensed builder’s right to payment of any amount is defeated by sections 42(1) and
42(3).
[31] The onus of proving any entitlement rests solely on the unlicensed builder.
[32] The rights and liabilities of the parties to a contract which involves the performance
of building work carried out whilst a builder is unlicensed have been addressed fully
in Cook’s Construction Pty Ltd v SFS 007.298.633 Pty Ltd [2009] QCA 75. Whilst
the burden of proving any entitlement to payment rests on the builder, s 42(4) of the
QBCC Act does provide an unlicensed builder with an avenue to claim some
compensation for works performed under the contract.
[33] Keane J further says at paragraphs [40] and [42]:
[40] …Rather, s 42(4) assumes the existence of a common law right to
remuneration which it preserves against the operation of s 42(3) while at
the same time imposing conditions upon the availability and extent of
that right. Unless the builder has a good claim conforming to these
conditions, the builder’s right to reasonable remuneration cannot avail
the builder against the operation of s 42(3).
[41] It is true that, as the appellant argues, the operation of s 42(3) of the Act
is qualified by s 42(4). But it is also clear that s 42(4) permits an
unlicensed builder to claim “reasonable remuneration for carrying out
building work, but only if the amount claimed” satisfied the criteria in
paragraphs (a) to (d). It is only the amount of the claim so quantified that
the builder may recover despite s 42(3). Absent a good claim so
quantified, the operation of s 42(3) is, for practical purposes, unqualified
by s 42(4). If the legislature had intended that s 42(3) as amended should
read “Subject to the absence of any claim under subsection (4), so as to
cast the burden of disproof of any claim for reasonable remuneration on
the other party to the contract, it could easily have said so.
[42] In my respectful opinion, it is important that the concern of the courts to
avoid an unjust outcome in a particular case should not distort the
operation of a statute intended to encourage the licensing of builders by
-- 4 of 6 --
5
disadvantaging unlicensed builders and advantaging consumers of
building services at their expense. It is hardly surprising that the
legislature should have left the burden of proving a claim for reasonable
remuneration on the builder. What would have been surprising would
have been a provision which cast the burden of proof of an unlicensed
builder’s claim on the consumer of building services. What is most
surprising, of course, is the failure of the builder in this case to adduce
evidence capable of proving a claim for an amount of reasonable
remuneration in conformity with s 42(4) of the Act.
[34] I am satisfied that the Respondent was not licensed to perform the works the subject
of the agreement. Thus, the Tribunal is satisfied that the work undertaken was carried
out by an unlicensed contractor.
[35] The Respondent has only a statutory entitlement to make a claim for works carried
out within the parameters of s 42(4) of the QBCC Act. The onus is on the Respondent
to not only make such a claim but to prove any, or the extent of, such entitlement.
[36] Absent any claim by the unlicensed builder, the operation of s 42(3) is unaffected.
[37] No statutory claim has been made by the Respondent. The Respondent has taken no
part in the proceeding and has failed to comply with any Tribunal directions. In the
circumstances, the Respondent is not entitled to any remuneration for the building
work carried out.
[38] The entitlement of the Applicants to recover monies paid to an unlicensed builder is
the reciprocal of the builder’s disentitlement to receive payment.1
[39] The Applicants are entitled to recover from the Respondent the sum of $19,250.00
[40] In relation to the Applicants’ claim for damages arising from the defective works
performed by the Respondent, I am satisfied that it was necessary for the Applicants
to engage another contractor to rectify the defective work performed by the
Respondent.
[41] The principles in relation to the assessment of damages in building disputes are clearly
set out in Bellgrove v Eldridge (1954) 90 CLR 613 at 617:
The measure of damages recoverable by the building owner for the breach of
the building contract is …the difference between the contract price of the work
or building contracted for and the cost of making the work or building conform
to the contract, with the addition, in most cases, of the amount of profits or
earnings lost by the breach.
[42] Damages for defective work are generally the amount necessary to make the work
conform with what the contractor was required to provide under the contract and thus
in accordance with the plans and specifications which formed part of it.2 The basic
purpose of an award of damages is to restore the aggrieved party to the position which
would have been obtained had the wrongful act not occurred. In the case of incomplete
and defective work the usual remedy will be the cost of rectifying and completing the
building works in accordance with the building contract.
1 Marshall v Marshall [1999] 1 Qd R 173, 176 (McPherson J).
2 Robinson v Harman [1848] Eng R 135.
-- 5 of 6 --
6
[43] The qualification outlined by the High Court in Bellgrove v Eldridge is that, not only
must the work undertaken be necessary to produce conformity, but that also it must
be a reasonable course to adopt.
[44] I am satisfied that it was necessary for the Applicants to demolish and re-build the
works performed by the Respondent in order to gain conformity with the agreement.
I accept the quotation provided by JuddCrete dated 16 January 2026 in the sum of
$45,100 including GST.
[45] I am unable to decipher the relevance of the quotation from JCTech dated 23 January
2026, in the absence of evidence from the Applicants for the necessity for the works.
Orders
[46] The Respondent is to make payment to the Applicants in the sum of $45,100.00
including GST as rectification costs incurred by the Applicants resulting from the
unsatisfactory and incomplete work provided by the Respondent.
[47] The Respondent is to make payment to the Applicants in the sum of $19,250.00 being
the refund of the amount paid to the Respondent for works carried out whilst the
Respondent was unlicensed and with respect to which the Respondent has failed to
prove any entitlement in whole or in part pursuant to s 42 of the QBCC Act.
-- 6 of 6 --
Official source: https://www.sclqld.org.au/caselaw/QCAT/2026/386