Secretary, Department of Customer Service v Tricon Builders Pty Ltd [2026] NSWCATAP 271
Catchwords: APPEAL – w hether appeal on each of five grounds is on a question of law – where some purported questions of law not material to the appeal - w here some purported questions of law not identified with precision – whether the Tribunal failed to address contentions seriously advanced by the regulator – whether the regulator made substantial, clearly articulated argument s to which the Tribunal did not respond - whether the Tribunal erred by imposing an onus of proof on the regulator – whether the regulator has an obligation to prove disciplinary allegations in proceedings for administrative review of a disciplinary decision – relevance of principle in Briginshaw v Briginshaw ( 1936) 60 CLR 336 – whether leave to appeal should be granted in respect of the appeal grounds which are not on a question of law
Civil and Administrative Tribunal
New South Wales
Medium Neutral Citation:
Secretary, Department of Customer Service v Tricon Builders Pty Ltd [2026] NSWCATAP 271
Hearing dates:
29 May 2026
Date of orders:
28 August 2026
Decision date:
28 August 2026
Jurisdiction:
Appeal Panel
Before:
Dr J Lucy, Principal Member
A Lo Surdo SC, Senior Member
Decision:
(1)
Leave to appeal on ground s
1 ,
4 and 5
is refused.
(2) The appeal is otherwise dismissed.
Catchwords:
APPEAL
–
w hether appeal on each of five grounds is on a question of law –
where
some purported questions of law not material to the appeal -
w here some purported questions of law not identified with precision
–
whether the Tribunal failed to address contentions seriously advanced by the regulator
–
whether the regulator made
substantial, clearly articulated argument s to which the Tribunal did not respond - whether the Tribunal erred by imposing an onus of proof on the regulator
–
whether the
regulator has an obligation to prove disciplinary allegations
in proceedings for administrative review of a disciplinary decision – relevance of principle in
Briginshaw
v
Briginshaw
( 1936) 60 CLR 336
–
whether leave to appeal should be granted in respect of the appeal grounds which are not on a question of law
Legislation Cited:
Administrative Decisions Review Act 1997
(NSW)
Civil and Administrative Tribunal Act 2013
(NSW)
Crimes Act 1900
(NSW)
Design and Building Practitioners Act 2020
(NSW)
Design and Building Practitioners Regulation 2021
(NSW)
Environmental Planning and Assessment Act 1979
(NSW)
Home Building Act 1989
(NSW)
Cases Cited:
Bimson, Roads & Maritime Services v
Damorange
Pty Ltd [2014] NSWSC 734
Brazel v Sydney Water Corporation [2026] NSWCATAP 9
Briginshaw
v
Briginshaw
(1936) 60 CLR 336
Bronze Wing International Pty Ltd v SafeWork NSW [2017] NSWCA 41
Builders Licensing Board v
Sperway
Constructions (Syd) Pty Ltd (1976) 135 CLR 616
Collector of Customs v Pozzolanic Enterprises Pty Ltd [1993] FCA 456;
(1993) 43 FCR 280
Collins v Urban [2014] NSWCATAP 17
Commissioner of Police, NSW Police Force v Hogan [2024] NSWCATAP 77
Damico v Secretary, Department of Customer Service [2025] NSWCATAP 109
Donohoe v
Albulario
[2025] NSWSC 9
Dranichnikov
v Minister for Immigration and Multicultural Affairs
(2003) 77 ALJR 1088; [2003] HCA 26
Ferella
v Chief Commissioner of State Revenue [2014] NSWCA 378
Hermes Nominees Pty Ltd v Shepherd [2024] NSWCATAP 36
HNOE Limited v Angus & Julia Stone Pty Ltd [2024] NSWCA 271
Kudrynski
v Orange City Council [2024] NSWCA 33
Liu v Director of Public Prosecutions (NSW) [2024] NSWSC 382
Medical Council of New South Wales v Mooney [2024] NSWCA 180
Minister for Immigration and Border Protection v SZVFW
(2018) 264 CLR 541; [2018] HCA 30
Minister for Immigration and Ethnic Affairs v Wu Shan Liang (1996) 185 CLR 259
Neat Holdings Pty Ltd v Karajan Holdings Pty Ltd
(1992) 67 ALJR 170
Ng v Pharmacy Council of New South Wales
(No 2) [2026] NSWCATOD 106
Orr v Cobar Management Pty Ltd
(2020) 103 NSWLR 36; [2020] NSWCCA 220
Plaintiff M61/2010E v Commonwealth of Australia
(2010) 243 CLR 319
Schwartz Family Co Pty Ltd v Capitol Carpets Pty Ltd [2017] NSWCA 223
Schwartz v Health Care Complaints Commission [2026] NSWCA 162
Secretary, Department of Family and Community Services v Smith (2017) 95 NSWLR 597
Sharp Corp of Australia Pty Ltd v Collector of Customs (1995) 59 FCR 6
Taylor Construction Group Pty Ltd v Strata Plan 92888 t/as Owners Strata Plan 92888 [2021] NSWSC 1315
Thomas and Naaz Pty Ltd v Chief Commissioner of State Revenue [2023] NSWCA 40
Udy v Barton [2025] NSWCATAP 117
Unique Commercial Group Pty Ltd v Cusumano [2024] NSWCATAP 204
Wollondilly Shire Council v Styles [2024] NSWCATAP 104
Wonson v Comcare
(2020) 276 FCR 613; [2020] FCAFC 76
Young v Commissioner of Police, NSW Police Force [2025] NSWCATAP 83
Texts Cited:
None cited
Category:
Principal judgment
Parties:
Secretary, Department of Customer Service (Appellant)
Tricon Builders Pty Ltd (First Respondent)
Jason Nahas (Second Respondent)
Representation:
S Wright (Appellant)
T Lowe (First and Second Respondents)
Solicitors:
Enforcement Legal, Department of Customer Service (Appellant)
O’Brien Hudson Solicitors (First and Second Respondents)
File Number(s):
2025/00399661
Publication restriction:
Nil
Decision under appeal
Court or tribunal:
Civil and Administrative Tribunal
Jurisdiction:
Administrative and Equal Opportunity Division
Citation:
[2025] NSWCATOD 128
Date of Decision:
19 September 2025
Before:
J Little, Senior Member
File Number(s):
2024/00282400; 2024/00282393
REASONS FOR DECISION
The appellant (the Secretary) appealed from a decision of the Tribunal,
reviewing
the Secretary ’ s decision to take disciplinary action against
two builders (a company and an individual).
The Secretary had taken disciplinary action against
the builders
under the
Home Building Act 1989
and the
Design and Building Practitioners Act 2020
.
That action
included
reprimanding both builders , imposing conditions on their registration under the
Design and Building Practitioners Act 2020
and
imposing penalties to a total of $8 4 ,000 on the company and $ 25,000
on the individual.
The Tribunal
found that some of the disciplinary allegations against the builders were not established and
varied th e Secretary ’ s
decision, deciding not to reprimand or penalise either of
the builders ,
but
instead to caution them and
to
impose conditions on the company ’ s registration
only .
The Secretary appealed on various grounds,
including grounds
contending that the Tribunal
denied the Secretary procedural fairness, misconstrued
statutory
provisions and made a legally unreasonable decision.
We have found that three of the
five
appeal grounds are not on a question of law , either because the question is not material to the appeal, or because the question has not been identified with precision.
We have also decided that there is no proper basis to grant leave on those grounds.
In relation to the two grounds which raise a question of law, we are not satisfied that the Secretary has identified any material error.
Accordingly, we have refused leave to appeal
on the three grounds where leave
i s required and otherwise
have
dismissed the appeal.
Background
Mr
Elias
Nahas held a contractor licence issued under s 20 of the
Home Building Act
from 12 April 2018 in the class
“ Builder. ”
Mr Nahas is the sole director and secretary of
Tricon Builders Pty Ltd (Tricon).
Tricon has
held a contractor licence under s 20 of the
Home Building Act
in the class of
“ Builder ”
since 18 May 2018.
Mr Nahas
has been the nominated supervisor for Tricon since that date.
The
Design and Building Practitioners Act
came into force on 10 June 2020.
As the Tribunal below observed (at [17]), the Act
established a regime which imposed
new obligations on design and building practitioners with particular emphasis on design documentation and compliance with documented designs.
From 2020, Tricon was the developer and builder in respect of a class 2 apartment complex in Northmead
(the Development) .
On 25 February 2021,
a construction certificate was issued to Tricon (the First Construction Certificate) which allowed for demo li tion, excavation and construction of basement up to the transfer deck only.
On 29 November 2021, a second construction certificate was issued to Tricon (the Second Construction Certificate) which allowed for the approval
of
the external structure only.
Mr Nahas became a registered building practitioner from 25 May 2022 in the class of registration
“ Body Corporate Nominee ”
granted under s 45 of the
Design and Building Practitioners Act 2020
and cl 3(b) of Sch 1 to the
Design and Building Practitioners Regulation 2021 . There were no conditions attached to his registration.
On 31 May 2022,
the
Secretary commenced an audit of the Development.
On 4 July 2022,
Tricon
became
a registered building practitioner in the class of “Body Corporate” under s 45 of the
Design and Building Practitioners Act
and cl 3( a ) of Sch 1 to the
Design and Building Practitioners Regulation .
On 6 September 2022, a stop work order
(the First Stop Work Order)
was issued to Tri con under s 89 of the
Design and Building Practitioners Act
.
On 8 November 2022,
conditions were imposed on the First Stop Work Order to allow for bricklaying, tiling and aluminium work only.
The se conditions were referred to by the parties as
“ exceptions. ”
On 27 April 2023, the First Stop Work Order was revoked and a second stop work order was issued to Tricon requiring all work to stop by 5pm that day (the Second Stop Work Order).
The Second Stop Work Order was revoked on 14 June 2023.
On 5 June 2024,
the Secretary ’ s delegate
decided to take disciplinary action against Mr Nahas and Tricon pursuant to s 62 of the
Home Building Act
and s 65 of the
Design and Building Practitioners Act
on a number of grounds.
Disciplinary decisions
concerning
Tricon
The Secretary
decided to take action w ith respect to Tricon
under the
Design and Building Practitioners Act
on the following grounds :
Tricon had
contravened provisions of the
Design and Building Practitioners Act
, being ss 19, 21, 87 and 89(7) , and had contravened Sch 4, Part 2 of the
Design and Building Practitioners Regulation , namely clauses 3 and 5 of the Code of Conduct
(
Design and Building Practitioners Act
, s
64(b) ) ;
Tricon
contravened a law of the jurisdiction, namely s 307B of the
Crimes Act 1900
( giving false or misleading information to a public authority)
by providing false information in response to a notice under s
77 of the
Design and Building Practitioners Act
(
Design and Building Practitioners Act
, s 64(c)) .
In relation to the first disciplinary ground, t he Secretary ’ s delegate found that Tricon had contravened ss 19 ( Designs and design compliance declarations to be obtained),
21 ( Requirements for building elements and performance solutions ), 87 ( Failure to comply with direction )
and 89(7) (failure to comply with stop work order) of the
Design and Building Practitioners Act
.
Section 89(7)
provides that a person must not fail to comply with a stop work order .
The provision
imposes a maximum penalty , for non-compliance,
of
3,000 penalty units
for a
body corporate
and otherwise
1,000 penalty units
and in addition, in the case of a continuing offence, 300 penalty units
(for a
body corporate ) and otherwise 100 penalty units
for each day the offence continues .
In relation to the finding of a contravention of s 89(7), the Secretary ’ s delegate found that, between 6 September 2022 and 23 June 2023, Tricon engaged in building work which it was prohibited to do under the First and Second Stop Work Orders. The Secretary considered the
“ overall severity of the conduct to be Major Severity. ”
The delegate also found that the second disciplinary ground was established on the basis that Tricon had contravened s 307B of the
Crimes Act
by providing false information to the Secretary.
The disciplinary action the Secretary ’ s delegate
decided to take against Tricon under
s 66 of
the
Design and Building Practitioners Act
included reprimanding Tricon ,
requiring it to pay the Secretary, as a penalty, $80,000 ,
and imposing conditions on its registration.
The Secretary ’ s delegate
also decided to take action with respect to Tricon under the
Home Building Act
on the following grounds:
Tricon is guilty of improper conduct (
Home Building Act,
s 56(c))
in that,
in the course of doing any work that the licence or certificate authorises the holder to do,
Tricon
fail ed
to comply with the requirements applicable to the work made by
s 6.3 of the
Environmental Planning and Assessment Act 1979
(the EPA Act)
in respect of the work
(see
Home Building Act,
s 51(b)) ;
and
An officer of Tricon , namely Mr Nahas,
has
been guilty of improper conduct (
Home Building Act,
s 56(f))
in that Mr Nahas , as the controlling mind of Tricon,
was
responsible for Tricon ’ s contravention of s 6.3 of the EPA Act.
Paragraph
6.3 (1)(a)
of the EPA Act
provides, relevantly, that a person must not carry out building work
without a certificate under Part 6 of the EPA Act that is required by Part 6 for that activity.
The Secretary found that Tricon
undertook building work which was beyond the scope of
the applicable construction certificate
in contravention of
s 6.3(1)(a) of the EPA Act .
The Secretary ’ s delegate decided to repriman d Tricon and require it to pay $4,000 as a penalty, as disciplinary action under the
Home Building Act.
Disciplinary decisions
concerning
Mr Nahas
The Secretary ’ s delegate
was satisfied that a ground for disciplinary action against Mr Nahas had been established
under s 64(d) of
the
Design and Building Practitioners Act
,
being that
Mr Nahas
had failed to comply with a statutory duty imposed on him by the
Home Building Act
with respect to the carrying out of building work .
The Secretary considered
“ the overall severity of the conduct to be Major Severity. ”
The Secretary ’ s delegate decided
to
reprimand
Mr Nahas, to
require him to pay $20,000 as a penalty to the Secretary
and to impose certain conditions on
him, under the
Design and Building Practitioners Act
.
The Secretary ’ s delegate also found that
a ground for taking disciplinary action against
Mr Nahas
under
the
Home Building Act
was established, in that he
was guilty of improper conduct within s 56(c) of the
Home Building Act
.
The improper conduct
was that Tricon had contravened
ss 19, 21 and 87 of the
Design and Building Practitioners Act
,
clause 16 of the
Design and Building Practitioners Regulation
and s 6.3 of the EPA Act, and Mr Nahas had control over the works.
The delegate decided, under the
Home Building Act,
to reprimand Mr Nahas,
to require him to pay $5,000 as a penalty to the Secretary
and to im p ose conditions on his authority.
The
disciplinary
decisions were affirmed on internal review on 17 July 2024.
The
disciplinary
action taken was , in summary:
Home Building Act
DBP Act
Tricon
Reprimand
Reprimand
$4,000 penalty
$80,000 penalty
Conditions
Mr Nahas
Reprimand
Reprimand
$5,000
$20,000 penalty
Conditions
Conditions
On 1 August 2024,
Tricon and Mr Nahas applied to the Tribunal for administrative review of the disciplinary decisions.
Tribunal’s decision
The parties provided the Tribunal with written submissions and made oral submissions at a hearing. Following the hearing, the Tribunal
handed down reasons for decision.
Decision in respect of Tricon
The first disciplinary ground against Tricon , under s 64(b) of the
Design and Building Practitioners Act
,
was that Tricon had contravened
ss 19, 21, 87 and 89(7)
of
that Act .
The Tribunal found that Tricon had contravened ss 19 and 21,
but
was not satisfied
that it had contravened s 87 of that Act (failure to comply with a direction).
The Tribunal
was not
persuaded
that Tricon had breached the stop work orders and thus was not satisfied that it had breached s 89(7) of the
Design and Building Practitioners Act
.
The Tribunal
found
that the second disciplinary ground against Tricon was
not
established, under s 64(c) of the
Design and Building Practitioners Act
,
as it was not satisfied that Tricon had
provided false or misleading information to the Secretary , contrary to s 307B of the
Crimes Act
.
As to the fourth
and fifth disciplinary
ground s ,
under s 56(c) and (f) of the
Home Building Act,
being
that Tricon
and its officer were
guilty of improper conduct ,
t he Secretary contended that
Tricon
had
contravened
s
6.3 of the EPA
A ct
by undertaking work above the basement
of the Development
on or before 7 August
2021 ,
several months before the issue of
the Second Construction Certificate. Tricon said that
the only work undertaken
before the issue of the Second Construction Certificate
were those works required to prepare for the commencement of stage
two
works ,
including the
reinforcement of level 1.
T he Tribunal rejected the Secretary ’ s submission that Tricon contravened s 6.3 of the EPA Act
by carrying out work
which was not authorised by
an applicable
construction certificate.
It
reasoned (at [191]):
“…I do not
treat
the evidence of Tricon that it undertook work
during stage one that included
the reinforcement of level 1
in preparing for stage two
as an admission of contravention. This is because it was part of stage one to
prepare for stage two, for example, the
“reinforcement of level 1”
includes the
building of the basement and the
construction of the transfer deck
(a
transfer deck, by its very nature,
not only being a reinforcement for stage
two but a reinforcement for the entire structure).
Tricon admitting that they readied the
Development for stage two does not rise to an admission of contravention as each stage is inter-connected
because of the nature of a development. There is otherwise no other evidence to support that Tricon
contravened section 6.3 of the EPAA or that
its officer or Mr Nahas
is guilty of improper conduct because of such a contravention.”
The Tribunal then considered what disciplinary action was appropriate in relation to the
ground which had been established
(being only
the first disciplinary ground under the
Design and Building Practitioners Act
) .
The
Tribunal accepted, that by virtue of Tricon ’ s contraventions of ss 19 and 21 of the
Design and Building Practitioners Act
, the power to take disciplinary action against Tricon was enlivened
under s 64(b) of the
Design and Building Practitioners Act
.
The Tribunal considered that it was appropriate to treat the breaches of ss 19 and 21 of the
Design and Building Practitioners Act
as a single course of conduct. In the circumstances, including that this was the first occasion giving rise to disciplinary action, the Tribunal decided to impose a caution and the imposition of education conditions. The Tribunal considered that the conduct was of minor severity.
Decision in respect of Mr Nahas
The Tribunal found
that a ground for disciplinary action against Mr Nahas under s 56(c) of the
Home Building Act
was established, in that
Mr Nahas
was
guilty of improper conduct under s 53 of the
Home Building Act
.
That
finding
was
made
on the basis that Mr Nahas
was presumed , by operation of s 53(2),
to be guilty of improper conduct in circumstances where he was the nominated supervisor of Tricon and
where
Tricon
had
contravened ss 19 and 21 of the
Design and Building Practitioners Act
.
“ Improper conduct ”
is defined in s 51(1)(b) of the
Home Building Act
to include
(in broad terms)
fail ing
to comply with
legislative
requirements applicable
to the doing of work authorised by a licence .
Th e finding
that Mr Nahas was guilty of improper conduct
gave rise to a power to take disciplinary action against Mr Nahas under the
Home Building Act.
Th e circumstance that
Mr Nahas was guilty of improper conduct under s 53 of the
Home Building Act
also
enliven ed
the power to take disciplinary action under s 64(d) of the
Design and Building Practitioners Act
.
Section 64(d) relevantly provides that the Secretary may take disciplinary
action if a
practitioner has failed to comply with a statutory duty
imposed on the practitioner by a law of New South Wales
with respect to the carrying out of building work .
The Tribunal stated (at [199]):
“ As I have found that Mr Nahas is guilty of improper conduct pursuant to section 53 of the HBA, it follows that the power to take disciplinary action pursuant to section 64(d) of the DBPA is enlivened as Mr Nahas has failed to comply with section 53 of the HBA with respect to the carrying out of building work.
I do not accept, as contended by the Respondent however, that this enlivenment gives rise to a
finding of a separate
contravention
as against Mr Nahas
because it is reliant on the contravention under section 53 of the HBA.”
T he
Tribunal
decided to c aution
Mr Nahas under
s 62(1)(b) of
the
Home Building Act
, having regard to the finding that Tricon ’ s contraventions are of minor severity.
It took into account that Mr Nahas ’ s history was unblemished and that he was regretful.
It took no action against Mr Nahas under the
Design and Building Practitioners Act
for reasons given in the paragraph quoted above .
Tribunal’s decision in summary
The Tribunal
varied
the decisions of the Secretary ’ s delegate so as to impose reduced sanctions, which were to caution Tricon and Mr Nahas and to impose conditions on Tricon ’ s registration under the
Design and Building Practitioners Act
.
A summ ary of the action taken is shown in the following table :
Home Building Act
DBP Act
Tricon
N/A
Caution
N/A
Conditions
Mr Nahas
Caution
N/A
Grounds of appeal
By Amended Notice of Appeal lodged on 3 December 2025, the Secretary
appeals from the Tribunal ’ s decision on five grounds which take the form of
purported
questions
of law . They are, in summary:
Did the Tribunal misconstrue and misapply ss 6.1 and 6.3 of the EPA Act when it found that certain preparatory work for stage 2 was completed but that it did not constitute
“ any physical activity involved in the erection of a building ”
within
the definition of
“ building work ”
in
s 6.1 of the EPA Act?
Did the Tribunal fail to address certain of the appellant ’ s contentions of substance that would have affected the outcome?
Did the Tribunal misconstrue s 64(d) of the
Design and Building Practitioners Act
by deciding that a ground for disciplinary action did not exist if the Tribunal has decided to find a contravention under the
Home Building Act
or did it ask itself the wrong question by asking whether a discretion existed to ignore a claimed ground of disciplinary action only because a different ground was found to exist?
Did the Tribunal erroneously construe s 4 and/or 89(7) of the
Design and Building Practitioners Act
or misdirect itself as to the application of s 89(7) by misconstruing the meaning of
“ building work ”
and of
“ fail to comply with an order in force ”
or by making a decision that was legally unreasonable, in circumstances where it found that the First Stop Work Order was issued to Tri con requiring all work to stop and yet made some other specified findings
(including that a stop work order does not require work to stop).
Did the Tribunal misconstrue s 38(2) of the
Civil and Administrative Tribunal Act 2013
(NCAT Act) and/or s 63(1) of the
Administrative Decisions Review Act 1997
or fail to perform its statutory task by
deciding, despite its findings that a stop work order was in place and that the only exception applied was on 8 November 2022,
that it could not determine whether there was a breach of s 89(7) of the
Design and Building Practitioners Act
and declined to do so because it could not determine the ambit of a hypothetical further exception to the stop work order because there was a particular onus of proof on the Secretary to disprove an undocumented alleged representation.
In the Secretary ’ s
reply
submissions, the Secretary sought to reformulate the first ground by adding
to the end of the ground a further, alternative question, being whether the Tribunal misconstrued and misapplied ss 6.1 and 6.3 of the EPA Act by not asking itself
whether the relevant work constituted
“ any physical activity involved in the erection of a building ” .
Mr
Lowe, for the respondents, did not object to this reformulation at the hearing. We have, accordingly, treated the Secretary ’ s first ground of appeal as including the additional words.
The scope and nature of internal appeals
I nternal appeals from decisions of the Tribunal , other than interlocutory decisions,
may be made as of right on a question of law, and otherwise with leave of the Appeal Panel
( NCAT Act ,
s 80(2) ) .
The Secretary ’ s primary case is that
each appeal ground is on a question of law. The Secretary alternatively seeks leave to appeal.
Appeal as of right on a question of law
The identification of a question of law is of primary significance because it founds the Appeal Panel ’ s jurisdiction, unless the Appeal Panel gives leave to appeal on other grounds (
Medical Council of New South Wales v Mooney
[2024] NSWCA 180 (
Mooney
) at [9 5 ]).
The question or questions of law should form
“ the subject matter of the appeal to the Appeal Panel unless leave [is] sought and obtained for a merits review ”
(
Ferella
v Chief Commissioner of State Revenue
[2014] NSWCA 378 (
Ferella
), White J at [22]; see also
Bimson, Roads & Maritime Services v
Damorange
Pty Ltd
[2014] NSWSC 734
(
Bimson
) , Beech - Jones J at [40]-[41]).
There is a distinction between a question of law and an error of law (see, for example,
Schwartz Family Co
Pty Ltd v Capitol Carpets Pty Ltd
[2017] NSWCA 223 at [13]
(
Schwartz Family Co
) ;
Schwartz v Health Care Complaints Commission
[2026] NSWCA 162
at [3]-[5] ). It is not sufficient that the appellant identifies an error of law in order to be entitled to appeal
“ as of right ”
(see
Schwartz
Family Co
at [13] and
Taylor Construction Group Pty Ltd v Strata Plan 92888 t/as Owners Strata Plan 92888
[2021] NSWSC 1315 at [118]). The Court of Appeal has indicated that the obligation to identify a question of law
“ is not satisfied by rolled up allegations asserting error of law, still less by grounds which merely allege
‘ error ’”
(
Thomas and Naaz Pty Ltd v Chief Commissioner of State Revenue
[2023] NSWCA 40 (
Thomas and Naaz
) at [71];
Mooney
at [96]). The questions of law are not to be distilled from the grounds of appeal (
Mooney
at [95]).
The Appeal Panel has determined on many occasions that a
“ question of law ”
in s 80(2)(d) of the NCAT Act is a
“ pure question of law ”
and does not include a question of mixed fact and law (see, for example,
Unique Commercial Group Pty Ltd v Cusumano
[2024] NSWCATAP 204
at [25](3);
Young v Commissioner of Police, NSW Police Force
[2025] NSWCATAP 83 at [13],
Udy v Barton
[2025] NSWCATAP 117 (
Udy
) at [34]-[36];
Damico v Secretary, Department of Customer Service
[2025] NSWCATAP 109 (
Damico
) at [42]-[43];
Wollondilly Shire Council v Styles
[2024] NSWCATAP 104 at [23];
Commissioner of Police, NSW Police Force v Hogan
[2024] NSWCATAP 77 at [18];
Hermes Nominees Pty Ltd v Shepherd
[2024] NSWCATAP 36 at [13]).
This reflects the position taken by the NSW Court of Appeal
when considering the meaning of the term
“ question of law ”
in a variety of contexts , including as used in the NCAT Act . As Leeming JA put it in
Schwartz v Health Care Complaints Commission
[2026] NSWCA 162
at [65] (Adamson JA and Griffiths AJA agreeing):
“The
precise delineation of what is or is not an appeal on a question of law is problematic at the boundaries: see
Thomas and Naaz Pty Ltd v Chief Commissioner of State Revenue
at [53]. But some things are settled.
In this State,
there is a clear distinction between an appeal on a question of law, and one which involves a mixed question
of
fact and law. The latter is outside the scope of those appeals which lie as of right
‘on’
a question of law:
Orr v Cobar Management Pty Ltd
(2020) 103 NSWLR 36;
[2020] NSWCCA 220
at [60];
Vitality Works Australia Pty Ltd v Yelda (No 2)
(2021) 105 NSWLR 403; [2021] NSWCA 147
at [49].”
Whether a question is one of law must be approached as a matter of substance:
Kudrynski
v Orange City Council
[2024] NSWCA 33 at [50];
Brazel v Sydney Water Corporation
[2026] NSWCATAP 9
at [6].
A
question
of law
will
generally
not be a
“ pure ”
question of law if its answer
requires
the Appeal Panel to resolve disputed facts
(
Damico
at [43];
Udy
at [36]).
Each question of law has only one correct answer (
Minister for Immigration and Border Protection v SZVFW
(2018) 264 CLR 541;
[2018] HCA 30; see also
HNOE Limited v Angus & Julia Stone Pty Ltd
[2024] NSWCA 271 at [21]
and [58]).
Bathurst CJ and Bell P described a question of law
in
Orr v Cobar Management Pty
Ltd
(2020) 103 NSWLR
36; [2020] NSWCCA 220
as a question:
“whose
character as a question of law can be recognised on the face of the
question, and
not depend upon the answer given to the question. This does not include a question which may ultimately disclose an error of law depending on an analysis of the
facts
but where this cannot be known without scrutiny of the facts.”
The question of law must be articulated with precision, as it is the subject matter of the appeal:
Ferella
at [22].
Leave to appeal
If an appeal ground is not on a question of law, the appellant needs leave or permission to appeal. The principles concerning leave to appeal were set out in
Collins v Urban
[2014] NSWCATAP 17. Those principles were summarised in
Secretary, Department of Family and Community Services v Smith
(2017) 95 NSWLR 597 at [28] as follows:
"Only if the decision is attended with sufficient doubt to warrant its reconsideration on appeal will leave be granted. Ordinarily, it is only appropriate to grant leave where there is an issue of principle, a question of general public importance, or an injustice which is reasonably clear, in the sense of going beyond what is merely arguable. It is well established that it is not sufficient merely to show that the trial judge was arguably wrong."
We have applied those principles in this appeal.
Ground 1
– alleged misconstruction of EPA Act
As indicated above,
the Secretary ’ s first ground raises the question of whether
the Tribunal misconstrue d
and misappl ied
ss 6.1 and 6.3 of the EPA Act :
when it found that certain preparatory work for stage 2 was completed
before
the issue of the Second Construction Certificate
but that
that work
did not constitute
“ any physical activity involved in the erection of a building ”
within s 6.1 of the EPA Act ; or
by not asking itself whether the relevant work constituted
“ any physical activity involved in the erection of a building ” .
Is this ground on a question of law?
The respondents contend ed in written submissions
that
the
Secretary ’ s grounds of appeal invite the Appeal Panel to
recharacteri s e
the evidence and the factual matrix and to substitute a different evaluative conclusion.
Their position , as expressed in those submissions,
wa s that the
appeal grounds
do not identify questions of law.
At the hearing, Mr Lowe, for the respondents,
initially
conceded that all four grounds raised a question of law.
He then
appeared to retreat
from this position in
later
oral submissions ,
submitting that the appellant had attempted to
recharacteri s e
factual and evaluative findings as questions of law .
The
identification of a question of law founds the Appeal Panel ’ s jurisdiction (
Mooney
at [9 5 ])
so the parties cannot simply resolve the
issue of whether a ground raises a question of law by agreement .
The Appeal Panel must satisfy itself of its own jurisdiction.
To assess whether the appellant has appealed on a question of law, it is
appropriate to consider what is being asked
by the question , in substance.
In our view, t he question
posed by the
Secretary ’ s first appeal ground as originally formulated
is, in substance ,
whether
works including
scaffolding, temporary framework and
steel reinforcement of level one are
“ building work ”
within s 6.1 of the EPA Act.
As the Secretary accepted,
the question of whether material facts, as found, satisfy a statutory provision is generally a question of law, but if the statutory provision uses words according to their ordinary meaning, the
question is one of fact (
Collector of Customs v Pozzolanic Enterprises Pty Ltd
[1993] FCA 456; (1993) 43 FCR 280
at 287).
There is a further qualification to this, being that
whether facts fall within the meaning of a word, the meaning of which has been ascertained, is a question of fact, but whether undisputed facts
necessarily
fall within the description of a word or phrase in a statute is a question of law
(see
Sharp Corp of Australia Pty Ltd v Collector of Customs
(1995) 59 FCR 6
at [16]; and see
the
discussion of this case in
Ng v Pharmacy Council of New South Wales (No 2)
[2026] NSWCATOD 106
at [106]-[ 112]) .
The Secretary submitted that a question of law arises, because the EPA Act does not use words according to their common understanding , referring to the definition of
“ building work ”
in the EPA Act. However, we consider that the words used in the definition are used in their ordinary sense. The question, then, is whether
works including scaffolding, temporary framework and steel reinforcement
of level 1
are
“ any physical activity involved in the erection of a building ”
(being the definition of
“ building work ”
in s 6.1 of the EPA Act).
That is a question of fact.
The Secretary appears to have implicitly conceded this in its
reply
submission s
by
expressly accepting that
“ the Appeal Panel may elect not to determine the
factual conclusion
that arises from a proper construction of ss 6.1 and 6.3 of the EPAA i.e. whether or not certain building work occurred in the relevant
period ”
(our emphasis).
If the Secretary were asking, in substance, whether those works are necessarily
“ any physical activity involved in the erection of a building ”
that would involve a question of law.
The Secretary submitted , in the Secretary ’ s primary submissions,
that there was only one correct conclusion to the
question of whether the work undertaken was any physical activity involved in the erection of a building.
That is consistent with the question being one of law .
In
the Secretary ’ s
reply
submissions,
however,
the Secretary stated:
“The Secretary does not ask the Appeal Panel to decide if scaffolding, temporary framework and steel reinforcement of level 1 constitute ‘any physical activity
involved in the erection of a building’ to find error. Rather, the question of law raised is whether NCAT performed the statutory task which required it to ask itself the correct question and then correctly construe the definition of building work when answering the question.”
That appears to us to be inconsistent with
the first appeal ground, as originally formulated, and instead
indicates
that the Secretary is relying entirely on the alternative words added into that ground. It also appears to be inconsistent with advancing a case that
scaffolding, temporary framework and steel reinforcement of level 1 necessarily constitute
“ any physical activity involved in the erection of a building. ”
Nevertheless ,
resolving this apparent contradiction favourabl y
to the Secretary,
we
consider
that the
first appeal ground, as originally formulated, raises a pure question of law
to the extent that it asks whether , on
the facts, as found,
the
builder
necessarily
undertook
“ building work ”
as defined .
The alternative question posed by
Ground 1, as amended, is whether the Tribunal misconstrued and misapplied ss 6.1 and 6.3 of the EPA Act by not asking itself whether the relevant work constituted
“ any physical activity involved in the erection of a building ” .
In substance, the question is whether the Tribunal was
required to ask itself whether the relevant work was building work as defined, but failed to do so.
We are also satisfied that this raises a question of law.
Resolution of questions
of law
While we are satisfied that the appellant has raised questions of law
by the first ground of appeal , we are not persuaded that
the appeal is
“ on ”
each of those questions of law within s 80(2)(b) of the NCAT Act, in the sense that
each
question is material to the appeal
and not an abstract or hypothetical question
(see
Liu v Director of Public Prosecutions (NSW)
[2024] NSWSC 382
at [90],
citing
Bimson
at [41] ;
and
as
cited in
Unique
at [25](10)).
As Beech-Jones J observed in
Bimson
at
[41],
“ the consequential questions that will arise
[after having identified a pure question of law]
are whether the lower court or tribunal either answered that question or proceeded on an assumption concerning that answer, whether its answer or assumption was correct or incorrect, and whether that answer or assumption was material to the outcome, in the sense that it could have affected the outcome . ”
In this case,
adopting a beneficial approach to
reading the Tribunal ’ s reasons,
we are not satisfied that the Tribunal proceeded on the assumption that the work in question was not
“ building work , ”
as that term is defined in s 6.1 of the EPA Act .
As
is well-recognised , t he Tribunal ’ s reasons are
“ not to be construed
minutely and finely with an eye keenly
attuned
to the perception of error ”
(
Minister for Immigration and Ethnic Affairs v Wu Shan Liang
(1996) 185 CLR 259 at
[30]) .
In the context of
considering
the
alleged breach of s 6.3 of the EPA Act, t he Tribunal stated that the builders ’
position was to deny that
Stage 2 building works were commenced on or before 7 August 2021
and to say that
“ the only works at the Development were those works that were required to
prepare for the commencement of Stage 2 works and not Stage 2 work themselves ”
(at [119]) .
That comment is consistent with
the Tribunal
understanding
the builders ’
submissions
to distinguish
between
“ Stage 2 building works ”
and
“ works ”
( which, taking a beneficial construction, refers to
Stage 1 building works
or works to which the First Construction Certificate applied ).
We consider that
the better construction of the Tribunal ’ s reasons is that it understood that the work
to
which it referred as
“ preparatory work ”
(at
[21])
was
“ building work. ”
The Tribunal ’ s
language
( in [191] )
suggest s
that
the question it was asking itself was whether the
“ building work ”
of
scaffolding, temporary framework and steel reinforcement of level 1 was work to which the First Construction Certificate applied. That
would explain
why
it remarked that
“
it was part of stage one
to
prepare for stage two, for example, the
‘ reinforcement of level 1 ’
includes the
building of the basement and the
construction of the transfer deck
(a
transfer deck, by its very nature,
not only being a reinforcement for stage
two but a reinforcement for the entire structure) ”
(emphasis added).
Counsel for the Secretary , Ms Wright,
submitted, at the hearing,
that if the Tribunal were saying that the work was part of the First Construction Certificate, that would have required it to consider the scope of Part 1.
Ms Wright
submitted that it would be irrational to consider work on Level 1
of the Development
by reference to a construction certificate which did not allow for work on Level 1.
Whether or not the Tribunal erred in the way suggested orally by counsel for the Secretary
at the hearing
is not something we have to decide as it is not the subject of a n appeal
ground. Additionally, the potential errors raised orally appear to
involve
factual issues, including whether or not the work was
“ on Level 1. ”
To the extent that the
argument was
made
to suggest that the Tribunal did not, in fact,
consider the work to be
covered by
the First Construction Certificate , we are not persuaded that that is the case.
For reasons given above ,
we find that
the Secretary ’ s
appeal, on this ground,
is not
“ on ”
a question of law .
I f we are wrong about that,
and
the
appeal on
th is
ground is on a question of law,
the Secretary has not persuaded us that the Tribunal erred as alleged.
We agree with the Secretary that there is only one correct conclusion to the question of whether the work undertaken, being scaffolding, temporary framework and steel reinforcement of level 1, was
“ any physical activity involved in the erection of a building ” . It plainly was. However, we do not consider that the Tribunal erred in finding that
the work in question
was not
building work , as defined , because
the Secretary has not persuaded us that
the Tribunal
made that finding.
N or
are we persuaded
that
the Tribunal
failed to ask itself whether
th e
work
undertaken by the respondents
was
building work .
The better view of the reasons is
that the Tribunal proceeded on the assumption that the work undertaken was building work.
Leave is needed to appeal on this ground as it is not
“ on ”
a question of law. We would decline leave on the basis that the
Secretary has not established the premise of
the ground,
being
that
the Tribunal found that the work undertaken was not building work.
Ground 2:
Failure to address
seriously-advanced
contentions
The second question identified by the Secretary
as being a question of law
is whether the Tribunal fa iled to address three
seriously-advanced
contentions advanced by the Secretary that were of substance and worthy of serious consideration, which it was bound to address and which would have affected the outcome.
The
three contentions, which the Secretary says the Tribunal failed to address, are , in summary :
The works undertaken between July 2021 and 29 November 2021 , consisting of scaffolding,
temporary framework (or formwork) and steel reinforcement to part of Level 1,
were
“ building work ”
and were not covered by the First Construction Certificate;
Mr Nahas failed to comply with a duty imposed upon him by the
Home Building Act
with respect to work carried out under a relevant authorisation, thus constituting a ground for disciplinary action under s 64(d) of the
Design and Building Practitioners Act
;
Regardless that the same facts may be relied upon under ss 53 and 56 of the
Home Building Act,
a separate and distinct ground for disciplinary action arises under s 64(d) of the
Design and Building Practitioners Act
.
Is the appeal on this ground on a question of law?
We are satisfied that the question of whether the Tribunal addressed these contentions is a question of law.
To
“ fail to respond to a substantial, clearly articulated argument relying upon established facts ”
is
a breach of procedural fairness (
Dranichnikov
v Minister for Immigration and Multicultural Affairs
(2003) 77 ALJR 1088 ;
[2003] HCA 26
at [24] ;
Plaintiff M61/2010E v Commonwealth of Australia
(2010) 243 CLR 319
at [90] ).
Whether the Tribunal denied the Secretary procedural fairness is a question of law
(
Donohoe v
Albulario
[2025] NSWSC 9
at [39]) .
Did the Tribunal err in failing to respond to the first contention?
The Secretary submits
that the Tribunal was required to explain why it did not accept the contention that scaffolding, temporary framework (or formwork) or steel reinforcement
are building work as defined. As indicated above, we
do
not accept the Secretary ’ s premise that the Tribunal rejected that contention.
We accept the respondents ’
submission that
“ the Tribunal directly addressed the essence of the A p pellant ’ s contention (pre-CC2 words equated to contravening building work) by making a finding at Decision [191] that the evidence did not constitute an admission of contravention because the works were preparatory within Stage 1. ”
Further,
even if we are wrong about this,
we are not persuaded that the Secretary made a
“ substantial, clearly articulated argument ”
to which the Tribunal was required to respond. The Secretary did not point to
that argument in its submissions below, nor
did the Secretary take
the Appeal Panel
to a section of the
transcript
of the Tribunal hearing
in which that argument was developed orally.
I t is not plain to us
that any
substantial, clearly articulated argument
was
in fact
made .
The Secretary ’ s submissions, dated 14 March 2025,
refer red
(at [29](q))
to the
earlier
disciplinary findings that Tricon had contravened s 6.3 of the EPA Act by erecting scaffo l ding
preparatory to the Stage 2 works.
There is no mention
in that sub-paragraph
of temporary framework (or formwork)
or
steel reinforcement to part of Level 1 .
The Secretary
then submit ted , at paragraph 62 of those submissions, that
“ in the absence of evidence from either Mr Nahas or Mr Elias Nahas, the Tribunal would accept the respondent ’ s findings with respect to the facts, matters and circumstances giving rise to the findings as to contraventions. ”
(We note that
affidavits from both individuals were tendered at the hearing without objection). The Secretary
also submitted, at paragraph 66 of the submissions, that the Tribunal
would find the disciplinary grounds proved
“ for reasons articulated in the decisions. ”
The
Secretary ’ s
reference
in written submissions
to the
reasons for
the
decision
under review
and
the Secretary ’ s
reliance on those reasons
does not, in our view, make every thing in those reasons a n
“ argument ”
which the Tribunal is required to address.
Ms Wright
did
not take us to any particular passage in those
reasons for
decision
which was said to constitute a
substantial,
clearly articulated argument
for the purposes of the Tribunal proceedings .
Nor is there anything before us to suggest that the Secretary took the Tribunal below to any particular part of those reasons for decision.
Did the Tribunal err in failing to respond to the second contention?
The second contention which the Secretary says the
Tribunal failed to respond to its claim that
a ground for disciplinary action under s 64(d) of the
Design and Building Practitioners Act
existed
because
Mr Nahas failed to comply with a duty imposed upon him by the
Home Building Act
.
This contention relates to the Tribunal ’ s decision
not to take any disciplinary action against Mr Nahas
under the
Design and Building Practitioners Act
where it was taking action against him in respect of the same conduct under the
Home Building Act.
It found
that
there were grounds to take disciplinary action against Mr Nahas ,
as nominated supervisor of Tricon,
under s 56(c) of the
Home Building Act
,
because
Tricon had
not complied with
the requirements applicable to
certain
work
under the
Design and Building Practitioners Act
.
The Tribunal
then found that, although the power to take disciplinary action against Mr Nahas under the
Design and Building Practitioners Act
was enlivened in respect of that conduct, there was no
“ separate contravention. ”
The relevant paragraph of the Tribunal ’ s reasons
([199])
is as follows:
“As I have found that Mr Nahas is guilty of improper conduct
pursuant to section 53 of the HBA, it follows that
the power to take disciplinary action pursuant to section 64(d) of the DBPA is enlivened as Mr Nahas has failed to comply with
section 53 of the HBA with respect to the
carrying out of building work.
I do not accept, as contended by the Respondent however, that this enlivenment gives rise to a
finding of a separate
contravention
as against Mr Nahas
because it is reliant on the contravention under section 53 of the HBA.”
We are not satisfied that the Tribunal failed to respond to
the Secretary ’ s
claim that a ground for disciplinary action under s 64(d) of the
Design and Building Practitioners Act
existed . It explicitly found that such a ground existed.
The Secretary ’ s submissions to the contrary are not persuasive.
The Secretary contends, in its written submissions, that the Tribunal did not discuss why
it decided to take no action under the
Design and Building Practitioners Act
, other than in the paragraph quoted above. That may be so. However,
any inadequacy of reasons does
not
equate to a
failure to address a contention seriously advanced by the Secretary, being the alleged error identified in Ground 2.
The
Secretary
relies , in support of its inadequacy of reasons argument,
upon
the decision of the Full Federal Court in
Wonson v Comcare
(2020) 276 FCR 613; [2020] FCAFC 76
at [111].
That case does not support
the proposition that inadequacy of reasons
establishes
a failure to address a contention
seriously advanced by a party .
Paragraph 111
of the judgment ,
on which the Secretary relies ,
forms part of the Court ’ s discussion of a ground of inadequacy of reasons. It does not establish that
inadequa cy in
reasons for rejecting a submission lead s
inexorably to a conclusion that
a decision-maker did not respond to the submission.
In the absence of an inadequacy of reasons ground, it is not our role to assess whether or not the Tribunal ’ s reasons were legally adequate.
In circumstances where the Tribunal found that
the Secretary had established that there
was a
ground for disciplinary action under s 64(d) of the
Design and Building Practitioners Act
, the
argument
that the Tribunal failed to
address the Secretary ’ s contention that such a ground was available, cannot be sustained.
Did the Tribunal err in failing to respond to the third contention?
The third contention is that , even though
the same facts may be relied upon under ss 53 and 56 of the
Home Building Act,
a separate and distinct ground for disciplinary action arises under s 64(d) of the
Design and Building Practitioners Act
.
The Tribunal did not fail to respond to that contention. It accepted it. It simply decided
that the correct and preferable decision was not to take any disciplinary action against Mr Nahas under the
Design and Building Practitioners Act
, in its discretion.
Conclusion on Ground 2
For the reasons given above, this ground is not established.
Ground 3
– alleged misconstruction of
Design and Building Practitioners Act
The questions which form the third appeal ground are :
D id the Tribunal misconstrue s 64(d) of the
Design and Building Practitioners Act
by deciding that a ground for disciplinary action did not exist if the Tribunal has decided to find a contravention under the
Home Building Act
?
or
D id
the Tribunal
ask itself the wrong question by asking whether a discretion existed to ignore a claimed ground of disciplinary action only because a different ground was found to exist?
We are satisfied that th ese two questions are questions of law
raised on the appeal such that the Secretary may appeal as of right on Ground 3 .
The answers to each of the questions of law
raised by these grounds are very straightforward. The Tribunal did not decide that a ground for disciplinary action did not exist under s 64(d) of the
Design and Building Practitioners Act
. It expressly
found
(at [119])
that a ground
for taking disciplinary action did exist, when it stated:
“ the power to take disciplinary action pursuant to section 64(d) of the DBPA is enlivened . ”
Accordingly,
we reject
the premise of the first question in Ground 3.
The answer to the first question of law in
G round
3
is that the Tribunal did not misconstrue s 64(d) of the
Design and Building Practitioners Act
in the way alleged.
The
second question of law
included in this ground is whether the Tribunal asked itself the wrong question by asking whether a discretion existed to ignore a claimed ground of disciplinary action only because a different ground was found to exist.
The answer is that
the Tribunal
did not
do so .
Section 66(1) of the
Design and Building Practitioners Act
gives the Secretary
a broad discretion to take one of a number of specified courses of action (or inaction) if
“ satisfied that one or more of the grounds for taking disciplinary action against a registered practitioner has been established . ”
One option available to the Secretary is
“ to
determine to take no further action against the practitioner ”
(s 66(1)(a)).
The Tribunal, standing in the Secretary ’ s shoes, was entitled to
decide to take no further action against Mr Nahas under the
Design and Building Practitioners Act
in circumstances where the Tribunal was imposing a sanction for the same conduct under a different
statute.
Ground 4
–
alleged inconsistent findings about stop work order
This ground seeks to challenge the Tribunal ’ s decision (at [150]) that it was not satisfied that Tricon breached the Stop Work Orders and that it was therefore not satisfied that Tricon had breached s 89(7) of the
Design and Building Practitioners Act
.
As indicated above, s
89(7) provides that a
person must not fail to comply with a
stop work
order
which is
in force
and provides a penalty for non-compliance .
It is an offence provision.
The Secretary submitted
before the Tribunal at first instance
that Tricon
had
engaged in glazing work, fire safety work and the work of filling holes left when a crane was moved, contrary to the First Stop Work Order. The Tribunal dealt with those contentions at [137] to [150] of its decision deciding, in summary, that this work did not contravene the First Stop Work Order because:
The aluminium glazing fell within the exception to the Stop Work Order for
“ aluminium metal work ” ;
Tricon was told to address the fire safety issues before the Stop Work Order could be removed and there was insufficient evidence to conclude that the Secretary (or authorised representative) did not require this to be done, such that it would be inappropriate to find a breach by Tricon;
Filling the holes left by the crane is not work involved in the construction of a building, but was rather a result of the removal of a crane.
Is the appeal on this ground on a question of law?
The alleged
question
of law which forms Ground 4 is very long,
containing
a number of alternative propositions , including that the
Tribunal misconstrued a statute , misdirected itself
or that the
decision was legally unreasonable,
which are
put on the basis that the Tribunal made
various decisions .
Those decisions , it is suggested by the question, were
inconsistent with its finding that the First Stop Work Order required
all work to stop by 5pm on 6 September 2022.
The question
is formulated as follows:
“ 4. Did the Tribunal erroneously construe s 4 and/or 89(7) of the Design and Building Practitioners Act (DBPA)
or misdirect itself as to the application of s 89(7)
of the DBPA by misconstruing the meaning of
‘building work’
and of
‘fail to comply with an order in force’
or by making a decision that was legally unreasonable in circumstances where it found at [38] that
‘On 6 September 2022, a
Stop Work Order (‘SWO-1’) was issued to Tricon under s 89 of the DBPA
requiring all work to stop
by 5pm on that day.”, (and made
a finding at [40] that design elements were required to be addressed, which did not involve a finding that any building work was permitted) and yet:
4.1 Decided that
a stop work order does not require work to stop.
4.2 Decided that a failure to stop work does
not
constitute a failure to comply with a stop work order.
4.3 Found that work on the slab of the building was undertaken during the operation of the stop work order and that work on a slab is not ‘building work’ (at [146]-[147]).
4.4 Decided that fire safety works and/or filling holes in the slab did not warrant disciplinary action by reference to Tricon’s interpretation, rather than by reference to the DPBA: at [148].
4.5 Decided whether a breach of a stop work order had occurred by first deciding whether a penalty or disciplinary action was warranted: at [148].
4.6 Erroneously considered whether a claimed oral representation operated as a proven amendment to a statutory stop work order, unless the making of the oral representation was disproved by the Secretary (thus imposing an onus on the Secretary to disprove the existence of an asserted amendment): at [141]-[145].”
In its present form, we do not consider that
this
is a question of law.
If there are questions of law contained
with in this
compound
question, they are
many and various, and do not appear to us to have been articulated with precision.
The question
the subject of Ground 4
is not
in substance a question, but rather a series of propositions. It
contains, in
parts
4.1 to 4.6
of the question ,
propositions which
are essentially submissions about
the proper characterisation of
the Tribunal ’ s findings
(such as that it decided that
a stop work order does not require work to stop ) .
The Secretary ’ s contentions in
parts
4.1 and 4.2
of the question,
that
the Tribunal
“ decided that
a stop work order does not require work to stop ”
and
“ decided that a failure to stop work does
not
constitute a failure to comply with a stop work order ”
are unhelpful
ways of characterising the Tribunal ’ s decision , for the purposes of posing a question of law .
If the Secretary wished to
contend that the Tribunal erred by finding that a failure to stop work does
not
constitute a failure to comply with a stop work order, that could have been made the subject of a separate question . Bundling up a number of contentious propositions in a compendious question does not give rise to a question of law.
Doing our best to
discern the substance of this ground, it
appears
that one of the questions it is asking is whether the Tribunal misconstrued the definition of
“ building work ”
in s 4 of the
Design and Building Practitioners Act
when it found that pouring cement into a slab
(to fill holes left by a crane) was not building work.
That definition is as follows:
(1) For the purposes of this Act,
building work
means work involved in, or involved in coordinating or supervising work involved in, one or more of the following—
(a) the construction of a building of a class or type prescribed by the regulations for the purposes of this definition,
(b) the making of alterations or additions to a building of that class or type,
(c) the repair, renovation or protective treatment of a building of that class or type.
To the extent that the
Secretary is contending that, on the facts as found, pouring cement into the slab is necessarily building work, th at
raises a question of law
(albeit one which is not identified with precision, as required) .
Even if we were
to consider the appeal on this ground to
raise this
question
of law, despite the lack of precision in the question in circumstances where the
appellant
is legally represented,
the question is not material to the appeal.
That is because the Tribunal indicated that it would not exercise its discretion to impose a sanction, even if
Tricon had breached the Stop Work Orders.
Accordingly, we consider that the
appeal on this ground is not
“ on ”
that question of law in that the question is not material to the appeal.
It could not have affected the outcome
in circumstances
where the Tribunal stated that it would have made the same decision irrespective of a breach finding.
For the same reason, the question s
of whether :
the
Tribunal ’ s
finding
that
filling of holes in a concrete slab is not building work is legally unreasonable ; and
the Tribunal
erroneously
construed
s
89(7) of the
Design and Building Practitioners Act
by misconstruing the words
“ fail to comply with an order in force , ”
if properly raised by Ground 4, are
not material to the appeal, even
if
each is a question of law .
As the appeal on this ground is not
“ on ”
a question of law, leave is needed to appeal.
Should leave to appeal be granted?
One of the relevant factors when deciding whether to grant leave to appeal is
whether
the
decision is attended with sufficient doubt to warrant its reconsideration on appeal.
Having regard to
the Secretary ’ s
written
submissions,
at paragraphs 102 and 103,
we understand that
the ground
is partly directed to alleged inconsistencies in the Tribunal ’ s reasoning process.
However, the question formulated by the appellant
as an appeal ground
does not
make
the nature of the alleged inconsistency plain .
The Secretary also ma de
some submissions in support of this ground on the
premise
that the Tribunal found that
filling ho l es left in a slab is not building work.
We do not accept that premise , for reasons given in relation to Ground 1.
The Secretary also submitted that
only one conclusion was open to the Tribunal in relation to the fire safety work, being that
Tricon
failed to comply with the stop work order.
The Secretary ’ s submissions on this point
had some merit, insofar as the work was, in our view, plainly
“ building work. ”
However,
the
lack of a finding
that Tricon did not
comply with the stop work order
was not material
to the Tribunal ’ s decision.
A significant consideration against the grant of leave is that
the
Tribunal
indicated
that, even if it were wrong
to find that there was no breach
of the
stop work orders , it would not exercise its discretion to take disciplinary action. It stated
(at [148]) :
“ Even if I was satisfied that the aluminium glazing, the fire safety works and/or the filling of holes left by the crane were breaches of the SWOs, the circumstances are such that it would be inappropriate to exercise the discretion to impose a penalty or disciplinary action on Tricon: section 66(1)(a) of the of the [sic] DBPA. This is because it was reasonable for Tricon to adopt an interpretation that such work was permissible in the circumstances and therefore the case is not consistent with the objective of deterrence:
Australian Building and Construction Commissioner v Pattison
(2022) 399 ALR 599; [2022] HCA 13 at [9]. ”
It was open
to
the Tribunal to exercise its discretion in that way .
To the extent that the Secretary
implicitly
contends, in
part
4. 4 of its question, that
the Tribunal erred by d ecid ing
“ that fire safety works and/or filling holes in the slab did not warrant disciplinary action by reference to Tricon ’ s interpretation, rather than by reference to ”
the
Design and Building Practitioners Act
, we disagree.
It was open to the Tribunal to take into account subjective factors when determining whether to take disciplinary action , including any reasonable belief
on the part of Tricon
that the conduct in question was authorised
(even if that reasonable belief was misplaced) .
The Tribunal adopted
the assumption that
it
had power to impose disciplinary action (contrary to its primary position), the n
indicated that it would decline to do so.
We do not see any error in the approach taken by the Tribunal
to the exercise of its discretion .
The Secretary stated, in the Amended Notice of Appeal, that if the Tribunal
were to determine a question was not a question of law, leave was sought on the basis that the matter involves
issues of principle and questions of public importance and errors that were central to the Tribunal ’ s decision.
One of the questions said to be raised by the appeal is
whether a stop work order requires a practitioner to stop work, or whether they can exercise their own discretion.
Another is that whether practitioners can commence work that has not yet been approved under the EPA Act. We are not
persuaded that either of those questions is properly raised by the appeal.
The Secretary made some other general
submissions in support of the grant of leave in its written submissions, which we have considered.
We are not satisfied that the Secretary has identified an issue of principle, a question of general public importance, or an injustice which is reasonably clear, in the sense of going beyond what is merely arguable, which would justify a grant of leave to appeal.
Even if the Tribunal erred in finding that Tricon did not contravene the Stop Work Orders,
there was no injustice
to the Secretary , because
the Tribunal also
decided , lawfully, that it would not exercise its discretion to take disciplinary action.
We are not satisfied that the decision is attended with sufficient doubt,
in relation to
an issue raised in Ground 4,
to warrant its reconsideration on appeal .
We have therefore decided to refuse leave to appeal on this ground.
Ground 5
The question posed by Ground 5 is whether the Tribunal misconstrued s 38(2) of the NCAT Act and/or s 63(1) of the
Administrative Decisions Review Act
or failed to perform its statutory task by deciding, despite its findings that a stop work order was in place and that the only exception applied was on 8 November 2022, that it could not determine whether there was a breach of s 89(7) of the
Design and Building Practitioners Act
and declined to do so because it could not determine the ambit of a hypothetical further exception to the stop work order because there was a particular onus of proof on the Secretary to disprove an undocumented alleged representation.
This question,
like the
purported
question
of law
which constitutes Ground 4 , is convoluted .
In short, t he Secretary has
not identif ied
a question of law with precision.
Breaking
down the various issues raised by the question , we understand
the Secretary
to be asking the following:
Did the Tribunal misconstrue a statutory provision or fail to perform its statutory task,
i n circumst ances where it had found a stop work order was in place, with one specified exception,
b y deciding it could not or would not determine
whether there was a breach of s 89(7) of the
Design and Building Practitioners Act
(the prohibition on failing to comply with a stop work order) ,
because it could not determine the ambit of a
“ hypothetical further exception ”
to the stop work order,
because there was a particular onus of proof on the Secretary to disprove
“ an undocumented alleged representation. ”
There
ar e a number of questions which could be teased out from this compound question , in light of the Secretary ’ s submissions in support of this ground . They might include :
Did the Tribunal erroneously impose an onus of proof
on the Secretary
to disprove
that it had directed Tricon to
address fire safety work before the stop work orders could be removed?
Did
the Tribunal err in
declining
to
find a breach of s 89(7) of the
Design and Building Practitioners Act
in relation to Tricon ’ s undertaking the fire safety works, in circumstances where it
could not resolve
“ the ambit of the exception to the ”
stop work orders?
Can
a
direction given
on behalf of the Secretary
orally at a meeting constitute an exception to a stop work order?
Was the Tribunal required to determine whether or not Tricon breached s 89(7) of the
Design and Building Practitioners Act
by undertaking the fire safety works?
Did the Tribunal misconstrue s 38(2) of the NCAT Act,
which provides that the Tribunal is not bound by the rules of evidence, by
failing to make a finding about whether the Secretary directed Tricon to
undertake the fire safety works?
Did the Tribunal misconstrue s 63(1) of the
Administrative Decisions Review Act
( which required
the Tribunal
to
decide what the correct and preferable decision is, having regard to the material then before it ),
by reasoning that the Secretary was required to prove
that it did not give an exemption to undertake the fire safety work?
When the
(possible)
questions
raised by this ground
are broken down
like this, a further question then arises as to whether each is a question of law, or a mixed question of fact and law.
In the compendious form in which the question which constitutes Ground 5 was put, that exercise is far more challenging. Further, in the absence of
precisely-formulated
questions of law,
it is procedurally unfair to expect
the respondent to break the questions down into sub-questions and identify whether each
putative
sub-question raises a question of law for the purpose of responding to the appellant ’ s case. Moreover, it is not the role of the Tribunal to make the case for the appellant, by attempting to distil questions of law from a compendious question which is not, in itself, a question of law.
In
Wollondilly Shire Council v Styles
[2024] NSWCATAP 104 , the Appeal Panel
referred to the
desirability of a specific question of law being identified with precision. It stated (at [29]):
“Whilst it is true that simply alleging that reasons are inadequate “raises” a question of law, and that may be sufficient where the parties and the Appeal Panel correctly understand what that allegation entails (
STAR Training Academy Pty Ltd v Commissioner of Police (No 2)
[2022] NSWCATAP 98 at [14] to [22]), it is preferable that the actual and specific question of law that it raises is identified with precision. That position is reinforced where the appellant is legally represented:
Theophilas
v Chief Commissioner of State Revenue
[2016] NSWCATAP 111, at [24];
Thomas and Naaz
, above, at [72].”
Leeming JA
put it more directly in
Ferella
at [22]
,
commenting
that it is
“ necessary ”
for
a
notice of appeal
purporting to be an appeal on a question of law
“ to identify precisely the particular question or questions of law. ”
We
recognise that
the Secretary ’ s
purported appeal on a
question
of law on Ground
5
raises possible legal errors
made by the Tribunal .
However,
the appeal
must be
on a question of law
to found
jurisdictio n , not merely raise errors of law .
We are
mindful that
the form of the question matters
(see, for example,
Schwartz v Health Care Complaints Commission
[2026] NSWCA 162
at
[3]-[7]) . For example, the
hypothetical
question :
“Can a direction given on behalf of the Secretary orally at a meeting constitute an exception to a stop work order?”
is a question of law, because it
has only one answer
and asks the Appeal Panel to resolve a “pure” legal point. On the other hand,
the question:
“Did the Tribunal err by finding that it could not determine whether there was a breach of s 89(7) of the
Design and Building Practitioners Act
and declined to do so because it could not determine the ambit of a hypothetical further exception to the stop work order ?”
is
probably not
a question of law.
It follows that,
as
the Secretary
has not
identif ied
a question of law with precision, the Secretary needs leave to appeal on this ground.
Should leave to appeal be granted?
When deciding whether to grant leave to appeal,
we have had regard to the Secretary ’ s submissions to understand the arguments the Secretary is making , which are not plain from the ground itself.
The submissions indicate that the Secretary takes issue with the Tribunal ’ s
decision not to find a breach of the stop work orders in respect of the fire safety works undertaken by Tricon .
We have considered , first,
whether the decision is attended by sufficient doubt to warrant the grant of leave, by
considering whether the submissions on this ground raise an error of law
or other error, which is
referable
to the ground.
The
Secretary
contended before the Tribunal
that Tricon ’ s undertaking fire safety works while a stop work order was in force was a breach of s 89(7) of the
Design and Building Practitioners Act
.
The Tribunal recorded that
Tricon ’ s case was that
“ during a meeting between representatives of Tricon and representatives of the Respondent
… ,
Tricon was advised that fire safety work had to be addressed and found compliant before the stop work orders could be removed ”
(at [141]).
Tricon
said that
its understanding was that it had to comply with th e Secretary ’ s
“ direction ”
(to undertake the fire safety work) and also had to comply with
an
“ order ”
from
the certifier
directing it to rectify minor defects.
The Tribunal considered whether
a representation was made to Tricon on behalf of the
Secretary
requiring Tricon to undertake the fire safety work .
The Tribunal
stated that this was
“ of
obvious
significance to whether there has been a
breach
of s
89(7) of the DBPA
by Tricon
because if
[a representation]
was made,
it acted as an exception to the SWOs or permission to
Tricon to
undertake such
work to have
the SWO withdrawn
or, alternatively, it was reasonable for Tricon to
apply that understanding ”
(at [143]).
It is not plain to us
what evidence was tendered on behalf of Tricon and Mr Nahas going to this issue.
They relied on affidavits
of
Christopher Cole,
Jason Nahas and Elias Nahas sworn on 19 , 20
and
25 March 2025, but none of that evidence was before the Appeal Panel.
The Tribunal found that there was
“ scant evidence ”
from the
Secretary
about whether such a representation had been made (as claimed by Tricon).
The Tribunal then stated (at [145):
“Given the factual matter in dispute, the absence of evidence from individuals present at the alleged meeting, and the lack of cross-examination of any witnesses who did give evidence, I cannot resolve on the evidence before me the ambit of the exception to the SWOs. It would be inappropriate to make a finding of breach of s 89(7) of the DBPA against Tricon in those circumstances and I decline to do so.”
We are not persuaded that any alleged error
covered by this ground
would
constitute a misconstruction of s 38(2) of the NCAT Act or s 63(1) of the
Administrative Decisions Review Act
, as the Secretar y
claims .
Section 38(2) of the NCAT Act provides:
The Tribunal is not bound by the rules of evidence and may inquire into and inform itself on any matter in such manner as it thinks fit, subject to the rules of natural justice.
A failure to determine whether there was a breach of s 89(7) of the
Design and Building Practitioners Act
, even if that were unlawful,
would not constitute a
“ breach ”
of s
38(2) of the NCAT Act.
Similarly,
a failure to determine a matter would be
unlikely to be
a
“ breach ”
of s 63 (1) of the
Administrative Decisions Review Act
, which provides:
In determining an application for an administrative review under this Act of an administratively reviewable decision, the Tribunal is to decide what the correct and preferable decision is having regard to the material then before it,
…
The Tribunal did decide what the correct and preferable decision is, albeit that it did not make a finding of breach on a particular matter.
O n
the other hand, we
consider
that
the Secretary has an
arguable
case
that a failure to decide a n aspect of a claim
that the Tribunal is required to decide when conducting an administrative review could constitute a failure to perform its statutory task.
The question remains whether the Tribunal was required to decide whether
Tricon contravened
s
89(7) of
the
Design and Building Practitioners Act
by undertaking the fire safety works.
The Secretary
contended that there was an error in fact-finding because
the Tribunal
effectively required the Secretary to provide more (or different) evidence , including evidence elicited through cross-examination,
that the Secretary ’ s representatives had not represented to Tricon, in a meeting, that Tricon was required to undertake fire safety work.
It was said for t he Secretary that the Tribunal was required to resolve th at
factual dispute . The Secretary also submit ted
that
there was no onus of proof, but
the applicant was expected to present evidence
to enable the Tribunal to make a decision favourable to it. The Secretary ’ s position was
that, if the applicants were unable to
present sufficient evidence to prove the existence of a condition, a favourable decision to them that a condition existed could not be made.
Onus of proof
The Secretary ’ s complaint is that,
notwithstanding th e Tribunal ’ s statement (at [83]) that there was no onus of proof in the administrative review proceedings ,
the Tribunal
imposed an onus on the Secretary.
Th e
question of what a regulator is required to prove
is nuanced in
merits review
proceedings
for the review of
a
disciplinary
decision .
T hat
is because procedural fairness may require the
regulator to establish disciplinary allegations
to the Tribunal ’ s satisfaction, and the Tribunal may
require that it be
“ comfortably satisfied ”
of the facts in issue
before making any adverse disciplinary findings (see
Briginshaw
v
Briginshaw
(1936) 60 CLR 336
(
Briginshaw
)) .
Legislation
providing for
the discipline of persons holding licences or approvals generally requires the regulator to
provide the licence holder with some form of disciplinary charge, and an opportunity to respond, before a
sanction may be imposed. That is consistent with general law principles of procedural fairness.
Under the
Design and Building Practitioners Act
,
disciplinary action may only be taken on specified grounds (s 64)
and ,
unless it is in the public interest to take immediate action (s 65(7)),
the practitioner must be given a notice to show cause,
stating the
disciplinary
grounds (s 65(2) and (3))
and
the practitioner has a right to
make submissions which must be considered (s 65(4) and (6)) . Only then,
if
the Secretary is
satisfied that one or more of the grounds for taking disciplinary action has been established,
may
the Secretary take specified disciplinary action
(s 66(1)).
Similarly, under the
Home Building Act,
disciplinary action may only be taken on specified grounds (s s
56 , 57 )
and
the
holder of an authority
must be given a notice to show cause, stating the grounds (s 6 1 (2) and (3)) .
T he
holder of the authority
has a right to make submissions which must be considered (s 6 1 (4) and ( 7 )).
Only then,
if
the Secretary is
satisfied that one or more of the grounds for taking disciplinary action against
the holder of an authority
has been established,
may
the Secretary take specified disciplinary action (s 62(1)).
Both these schemes are consistent with the principle that,
when a
disciplinary
decision is being made , as a matter of procedural fairness,
the subject person is entitled to be provided with specific charges or allegations,
has a right to be heard and the
allegations must be established
to the satisfaction of the regulator .
When such a decision is reviewed or reconsidered on appeal,
it may be that
the regulator has
an onus to establish the disciplinary allegations to the satisfaction of the review or appeal body
or, if not a legal onus,
an obligation, as a matter of procedural fairness, to provide evidence in support of the allegations to the Tribunal
before the Tribunal can properly be satisfied that they are established .
In
Builders Licensing Board v
Sperway
Constructions (Syd) Pty Ltd
(1976) 135 CLR 616, a board
was responsible for issuing licences permitting persons to carry out building work and also dealt with complaints against licensees.
It could require the licensee to show cause why
he or she should not be dealt with under the disciplinary provisions of the legislation in question, providing particulars of the grounds on which the licensee was required to show cause.
The board was bound by the rules of evidence.
The licensee had a right of appeal to a District Court.
T he High Court held that
the board
had an onus to present its case afresh to the appellate court ,
which was conducting an appeal de novo.
Mason J (with whom Barwick CJ and Stephen J agreed) accepted the licensee ’ s submission that the
Board was bound to call evidence , on appeal,
in support of the grounds upon which the
licensee
had been required to show cause
and that
the board had an onus to present its case in the District Court (at 625) .
It may be , in light of the
Sperway
decision,
that the nature of the administrative review of a disciplinary decision under the
Home Building Act
and
Design and Building Practitioners Act
is such that the Secretary has
an obligation
to
establish
the disciplinary allegations in question
to the Tribunal ’ s satisfaction , notwithstanding that
the Tribunal
is conducting a merits review and it s role is to determine the correct and preferable decision under s 63(1) of the
Administrative Decisions Review Act.
This
might be conceived as an onus of proof, or
it may be better understood as an aspect of procedural fairness.
Alternatively, it may be an aspect of the
general principle that the Tribunal may
properly
require
strong evidence to establish an allegation that a party committed an offence ( in circumstances where
s 89(7)
of the
Design and Building Practitioners Act
carries
a penalty
of 3,000 penalty units
for contravention ) , or is guilty of a disciplinary charge .
The Tribunal is not bound by the rules of evidence
and in circumstances where there is no onus of proof it
is not bound to
apply the principle in
Briginshaw
. That principle is, broadly,
that
the seriousness of an allegation
made is a consideration which affects the answer to the question of whether an issue has been proved to the reasonable satisfaction of a tribunal (
Briginshaw
at
361).
However, the principle may still guide the Tribunal ’ s
fact-finding .
In
Neat Holdings Pty Ltd v Karajan Holdings Pty Ltd
(1992) 67 ALJR 170
(
Neat Holdings
) ,
Mason CJ,
Brennan, Deane and
Gaudron
JJ
observed
at 171:
"[T]he strength of the evidence necessary to establish a fact or facts on the balance of probabilities may vary according to the nature of what it is sought to prove. Thus, authoritative statements have often been made to the effect that clear or cogent or strict proof is necessary 'where so serious a matter as fraud is to be found'. Statements to that effect should not, however, be understood as directed to the standard of proof. Rather, they should be understood as merely reflecting a conventional perception that members of our society do not ordinarily engage in fraudulent or criminal conduct and a judicial approach that a court should not lightly make a finding that, on the balance of probabilities, a party to civil litigation has been guilty of such conduct." [citations omitted]
The Court of Appeal
(Leeming JA, Basten and Gleeson JJA agreeing)
cited this passage in
Bronze Wing International Pty Ltd v SafeWork NSW
[2017] NSWCA 41
at
[126] , an appeal from a decision
of the Tribunal reviewing a regulator ’ s decision
to take disciplinary action against licensees.
Leeming JA
observed
(at [127])
that
what was said in
Briginshaw
and
Neat Holdings
reflects a more general approach to fact finding, which is applicable by analogy to NCAT.
In light of these authorities , we consider that it was open to the Tribunal to
decline to make a finding of
breach of s 89(7) of the
Design and Building Practitioners Act
against Tricon
in circumstances where, it may be inferred
from its reasons , it was
not
“ comfortably satisfied ”
that
the breach was established (see
Briginshaw
at 350).
Materiality
Even if the Tribunal erred in this respect,
contrary to our view,
the error was not material. That is because
the Tribunal
stated that it would not have exercised its discretion to take disciplinary action
against Tricon
in any event
(at [148]).
That is a strong consideration against the grant of leave.
Conclusion on leave
We are not satisfied that the Secretary has identified
by Ground 5
an issue of principle, a question of general public importance, or an injustice which is reasonably clear, in the sense of going beyond what is merely arguable.
Further, we are not persuaded that the decision is attended with sufficient doubt to warrant a grant of leave.
Accordingly, we have decided to refuse leave to appeal on this ground.
Conclusion
For the reasons given above,
the Secretary needs leave to appeal on Grounds 1, 4 and 5 and has not established that leave should be granted. The
appeal on Grounds 2 and 3 is dismissed.
Orders
We make the following orders:
Leave to appeal on grounds 1, 4 and 5 is refused.
The appeal is otherwise dismissed.
**********
I hereby certify that this is a true and accurate record of the reasons for
decision of the Civil and Administrative Tribunal of New South Wales.
Registrar
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Decision last updated:
28 August 2026
Official source: https://www.caselaw.nsw.gov.au/decision/1a04055acd223bfc0084c7b7