Domestic Building Contracts and Tribunal (General) Regulations 1996
i
Domestic Building Contracts and Tribunal
(General) Regulations 1996
S.R. No. 32/1996
TABLE OF PROVISIONS
Regulation Page
1. Objectives 1
2. Authorising provision 1
3. Definitions 2
4. Building work to which Act does not apply 2
5. Type of cost plus contract allowed 2
6. Progress payments 3
__________________
SCHEDULE 4
FORM 1—Warning to owner—change of legal rights 4
FORM 2—Progress payments 6
-- 1 of 7 --
1
STATUTORY RULES 1996
S.R. No. 32/1996
Domestic Building Contracts and Tribunal Act 1995
Domestic Building Contracts and Tribunal
(General) Regulations 1996
The Governor in Council makes the following Regulations:
Dated: 30 April 1996
Responsible Minister:
JAN WADE
Minister for Fair Trading
A. WILTSHIRE
Clerk of the Executive Council
1. Objectives
The objectives of these Regulations are—
(a) to prescribe certain work as building work to
which the Act does not apply;
(b) to allow certain contracts to be cost plus
contracts for the purposes of section 13 of
the Act; and
(c) to prescribe, with regard to progress
payments, the manner in which parties to a
contract may agree that sections 40(2) and
(3) of the Act do not apply.
2. Authorising provision
These Regulations are made under section 135 of
the Act.
-- 2 of 7 --
S.R. No. 32/1996
Domestic Building Contracts and Tribunal (General)
Regulations 1996
2
3. Definitions
In these Regulations, "the Act" means the
Domestic Building Contracts and Tribunal Act
1995.
4. Building work to which Act does not apply
For the purposes of section 6(a) of the Act, the
Act does not apply to the following building work
if it is to be carried out under a contract that
applies to one only of the following—
(a) attaching external fixtures (including
awnings, security screens, insect screens and
balustrades);
(b) draining work as defined in section 85(1) of
the Building Control (Plumbers, Gasfitters
and Drainers) Act 1981;
(c) electrical work;
(d) glazing;
(e) installing floor coverings;
(f) insulating;
(g) painting;
(h) plastering;
(i) plumbing work as defined in section 85(1) of
the Building Control (Plumbers, Gasfitters
and Drainers) Act 1981;
(j) tiling (wall and floor).
5. Type of cost plus contract allowed
For the purposes of section 13(1)(a) of the Act,
the classes of cost plus contracts allowed are—
(a) contracts for work that it is reasonably
estimated will cost $500,000 or more; and
r. 3
-- 3 of 7 --
S.R. No. 32/1996
Domestic Building Contracts and Tribunal (General)
Regulations 1996
3
(b) domestic building contracts for public
construction as defined in section 3(1) of the
Project Development and Construction
Management Act 1994 where the Crown or
a public statutory authority is a party to the
contract.
6. Progress payments
For the purposes of section 40(4) of the Act, the
prescribed manner of agreement is to include in
the domestic building contract—
(a) a warning in the form of Form 1 of the
Schedule which is to be signed by the
building owner before the execution of the
contract; and
(b) a clause in the form of Form 2 of the
Schedule.
__________________
r. 6
-- 4 of 7 --
S.R. No. 32/1996
Domestic Building Contracts and Tribunal (General)
Regulations 1996
4
SCHEDULE
FORM 1
Regulation 6(a)
WARNING TO OWNER — CHANGE OF LEGAL RIGHTS
Section 40 of the Domestic Building Contracts and Tribunal Act 1995
provides that a builder cannot charge more than a fixed percentage of the
total contract price at the completion of each stage of building a home.
The Act also allows the parties to agree in writing to change the stages and
the percentage of the contract price to be paid at the completion of each
stage.
There are several ways in which a particular contract can vary from the
normal, and it is these exceptional cases which have caused the law to allow
for these changes.
Examples would include—
• where it is very expensive to prepare the land for building for example,
where the site is steep or rocky;
• where the house is so large that it will take a long time to complete, and
intermediate progress payments are therefore required;
• where exceptionally expensive finishes are required, meaning that the
final stage will represent a much larger proportion of the whole price;
• where an architect is engaged to independently assess the value of
completed work for progress payments.
You should not agree to progress payments different from that provided in
the Act unless your house is unusual in some way and you are SURE THAT
DIFFERENT PROGRESS PAYMENTS ARE NECESSARY and you
understand clearly why the change is needed in the case of your particular
house.
Sch.
-- 5 of 7 --
S.R. No. 32/1996
Domestic Building Contracts and Tribunal (General)
Regulations 1996
5
If you have any doubts, you could contact—
Housing Industry Association
The Master Builders' Association of Victoria
Office of Fair Trading and Business Affairs
Royal Australian Institute of Architects
....................................................
I acknowledge that I have read this warning before
signing the contract
Signature of Building Owner
__________________
Sch.
-- 6 of 7 --
S.R. No. 32/1996
Domestic Building Contracts and Tribunal (General)
Regulations 1996
6
FORM 2
Regulation 6(b)
Progress payments
The parties agree—
(i) that the progress payments fixed by section 40 of the
Domestic Building Contracts and Tribunal Act 1995 do
not apply; and
(ii) that instead the percentages of the contract price and
amounts payable are as follows—
Name of stage If this stage is not the same as a stage
defined in section 40(1) of the
Domestic Building Contracts and
Tribunal Act 1995, what does this
stage mean?
Percentage
of total
contract
price
$
═══════════════
Sch.
-- 7 of 7 --