National Electricity (Victoria) Further Amendment Act 2016
Authorised by the Chief Parliamentary Counsel
Authorised Version
i
National Electricity (Victoria) Further Amendment
Act 2016
No. 24 of 2016
TABLE OF PROVISIONS
Section Page
Part 1—Preliminary 1
1 Purpose 1
2 Commencement 2
Part 2—Amendments to the National Electricity (Victoria) Act
2005 3
3 New section 11A and 11B inserted 3
4 New section 12A inserted 4
5 New Division 5 inserted in Part 3 7
6 New Schedules 2 and 3 inserted 10
Part 3—Repeal of amending Act 85
7 Repeal of amending Act 85
═══════════════
Endnotes 86
1 General information 86
-- 1 of 87 --
Authorised by the Chief Parliamentary Counsel
Authorised Version
1
National Electricity (Victoria) Further
Amendment Act 2016†
No. 24 of 2016
[Assented to 10 May 2016]
The Parliament of Victoria enacts:
Part 1—Preliminary
1 Purpose
The main purpose of this Act is to amend the
National Electricity (Victoria) Act 2005 to apply
in Victoria certain provisions of the National
Electricity Law and to amend the National
Electricity Rules as in force in Victoria to
implement certain retail customer connection
arrangements.
Victoria
-- 2 of 87 --
Part 1—Preliminary
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
2
Authorised by the Chief Parliamentary Counsel
2 Commencement
(1) Subject to subsection (2), this Act comes into
operation on a day or days to be proclaimed.
(2) If a provision of this Act does not come into
operation before 1 January 2017, it comes into
operation on that day.
-- 3 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
3
Authorised by the Chief Parliamentary Counsel
Part 2—Amendments to the National
Electricity (Victoria) Act 2005
3 New section 11A and 11B inserted
After section 11 of the National Electricity
(Victoria) Act 2005 insert—
"11A Extension of AER functions and powers
Without limiting section 6, the following
provisions of the National Electricity
(Victoria) Law apply as laws of Victoria as if
a reference in any such provision to the Law
included a reference to regulations made
under this Act—
(a) Parts 3 and 6 and Schedule 2;
(b) any other provision of the National
Electricity (Victoria) Law, the National
Electricity (Victoria) Regulations or the
National Electricity Rules prescribed by
the regulations for the purposes of this
section.
11B Prescription of provisions of the
regulations as civil penalty provisions
(1) The regulations may prescribe a provision of
the regulations as a civil penalty provision.
(2) A reference in the National Electricity
(Victoria) Law or the National Electricity
(Victoria) Regulations to a civil penalty
provision is taken to include a reference to a
provision prescribed under subsection (1).
(3) Subsection (2) applies despite anything to
the contrary in the National Electricity
(Victoria) Law.".
-- 4 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
4
Authorised by the Chief Parliamentary Counsel
4 New section 12A inserted
After section 12 of the National Electricity
(Victoria) Act 2005 insert—
"12A Regulations
(1) The Governor in Council may make
regulations for or with respect to any matter
required or permitted by this Act to be
prescribed or necessary or convenient to be
prescribed to give effect to this Act.
(2) Without limiting subsection (1), regulations
may be made under that subsection for or
with respect to—
(a) the undergrounding, relocation,
modification, replacement or removal
of distribution systems, including—
(i) proposals for the undergrounding,
relocation, modification,
replacement or removal of
distribution systems; and
(ii) requiring a distribution company
which receives a proposal for the
undergrounding, relocation,
modification, replacement or
removal of a distribution system
to make an offer to underground,
relocate, modify, replace or
remove a distribution system;
(b) the content of proposals referred to in
paragraph (a)(i) or offers referred to in
paragraph (a)(ii), including the price of,
or an estimate of costs to be incurred
for, the undergrounding, relocation,
modification, replacement or removal
of a distribution system;
-- 5 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
5
Authorised by the Chief Parliamentary Counsel
(c) the determination, calculation,
allocation or breakdown of a price or
costs referred to in paragraph (b) or
allocation or apportionment of costs
referred to in that paragraph;
(d) requiring a distribution company to call
for tenders for the performance of—
(i) works to augment or extend a
distribution system for the
purpose of connecting generating
units or customer premises to the
system and associated works;
(ii) works arising out of an offer to
underground, relocate, modify,
replace or remove a distribution
system and associated works;
(e) the development or adoption of tender
policies, or compliance with tender
policies, by a distribution company, for
the performance of works referred to in
paragraph (d);
(f) the content of tender policies referred to
in paragraph (e) including—
(i) the price, or the estimated costs, of
the works; and
(ii) procedures for dealing with and
resolving disputes that may arise
in relation to the performance of
the works;
(g) the public availability of tender policies
referred to in paragraph (e).
-- 6 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
6
Authorised by the Chief Parliamentary Counsel
(3) Regulations made under this section may—
(a) be of general or limited application;
(b) differ according to differences in time,
place or circumstance;
(c) apply, adopt or incorporate any matter
contained in any document, code,
standard, rule, specification, or method,
formulated, issued, prescribed or
published by any person or body
whether—
(i) wholly or partially or as amended
by the regulations; or
(ii) as formulated, issued, prescribed
or published at the time the
regulations are made or at any
time before then; or
(iii) as formulated, issued, prescribed
or published or amended from
time to time;
(d) confer a function, power or
discretionary authority or impose a duty
on the Minister or the AER;
(e) leave any matter or thing to be from
time to time determined, applied,
dispensed with or regulated by the
Minister or the AER;
(f) provide in a specified case or class of
cases for the exemption of persons or
things or a class of persons or things
from any of the provisions of the
regulations—
(i) whether unconditionally or on
specified conditions; or
-- 7 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
7
Authorised by the Chief Parliamentary Counsel
(ii) either wholly or to such an extent
as is specified.
(4) Regulations made for or in relation to the
content of proposals for the undergrounding,
relocation, modification, replacement or
removal of distribution systems, or the
content of tenders for the performance of
works referred to in subsection (2)(d), have
effect according to their tenor despite
anything to the contrary in any agreement or
contract.
(5) In this section—
costs includes avoided costs;
distribution company has the same meaning
as in the Electricity Industry
Act 2000.".
5 New Division 5 inserted in Part 3
After Division 4 of Part 3 of the National
Electricity (Victoria) Act 2005 insert—
'Division 5—Distribution network connections
and retail customer connection arrangements
16Q Application of certain provisions of the
National Electricity (South Australia)
Act 1996
Despite section 6—
(a) section 34(1)(a)(iv) and (aa) and (3)(fa)
of the NEL applies as a law of Victoria
as if it were included in the National
Electricity (Victoria) Law; and
(b) section 34(3)(h)(i) of the National
Electricity (Victoria) Law applies as if
for "or (f)" there were substituted
", (f) or (fa)"; and
-- 8 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
8
Authorised by the Chief Parliamentary Counsel
(c) Schedule 1 to the National Electricity
(Victoria) Law applies as if after
item 26K there were inserted—
"Sale and supply of electricity to
retail customers
26M Charges for the provision of connection
services.".
Note
Until the commencement of this section, amendments made
to the NEL by the Statutes Amendment (National Energy
Retail Law) Act 2011 of South Australia did not apply as
laws of Victoria: see clause 24 of Schedule 3 to the NEL.
The effect of this section is to apply some of those
amendments as laws of Victoria.
16R Amendment of the National Electricity
Rules
(1) The National Electricity Rules as in force as
a law of Victoria are amended as set out in
Schedule 2.
(2) To avoid doubt, the amendments made by
Schedule 2 (other than punctuation included
in those amendments) form part of the
National Electricity Rules and may be
amended in accordance with the National
Electricity (Victoria) Law.
Note
The National Electricity Rules have the force of law in this
jurisdiction: see section 9 of the National Electricity
(Victoria) Law. Until the commencement of this section,
amendments made to the National Electricity Rules by the
National Electricity (National Energy Retail Law)
Amendment Rule 2012 did not apply as laws of Victoria:
see clause 24 of Schedule 3 to the NEL. The effect of this
section and Schedule 2 is that some of those amendments
have the force of law in Victoria.
-- 9 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
9
Authorised by the Chief Parliamentary Counsel
16S Further modification of the amended
National Electricity Rules
Despite section 6, the National Electricity
Rules have the force of law in Victoria as
if—
(a) in clause 5A.A.1 the definition of
customer connection contract were
revoked; and
(b) clause 5A.C.1(c) and (d) were revoked;
and
(c) the note to clause 5A.E.4(c) were
revoked; and
(d) clause 5A.F.5(b)(2) were revoked; and
(e) for the definition of energy laws in
Chapter 10 there were substituted—
"energy laws
Includes:
(a) legislation of Victoria that
regulates electricity in
Victoria, or any instrument
made or issued under or for
the purposes of that
legislation;
(b) national electricity
legislation within the
meaning of the National
Electricity (Victoria) Law;
(c) the Rules;
(d) any instrument made or
issued under or for the
purposes of the Rules."; and
-- 10 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
10
Authorised by the Chief Parliamentary Counsel
(f) for the definition of energy
ombudsman in Chapter 10 there were
substituted—
"energy ombudsman
Is a person administering a
customer dispute resolution
scheme approved by the Essential
Services Commission that is
referred to in section 28 of the
Electricity Industry Act 2000
(VIC).".
16T Transitional provisions for retail customer
connection arrangements
Schedule 3 has effect.'.
6 New Schedules 2 and 3 inserted
After Schedule 1 to the National Electricity
(Victoria) Act 2005 insert—
'Schedule 2—Amendment of
National Electricity Rules
Section 16R
1 Clause 5.1.3—Principles
1.1 In clause 5.1.3(d)(2) of the National
Electricity Rules, after "Network Users;"
insert "and".
1.2 For clause 5.1.3(e) and (f) of the National
Electricity Rules substitute—
"(e) the operation of the Rules should result
in the achievement of:
(1) long term benefits to Registered
Participants in terms of cost and
reliability of the national grid;
and
-- 11 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
11
Authorised by the Chief Parliamentary Counsel
(2) open communication and
information flows relating to
connections between Registered
Participants themselves, and
between Registered Participants
and AEMO, while ensuring the
security of confidential
information belonging to
competitors in the market.".
2 Clause 5.3.1—Process and procedures
2.1 For clause 5.3.1 of the National Electricity
Rules substitute—
"5.3.1 Process and procedures
(a) For the purposes of this rule 5.3:
establish a connection includes modify
an existing connection or alter plant but
does not include alterations to
generating plant in the circumstances
set out in clause 5.3.9.
(b) A Registered Participant or person
intending to become a Registered
Participant who wishes to establish a
connection to a network must follow
the procedures in this rule 5.3.
(c) A Generator wishing to alter connected
generating plant must comply with
clause 5.3.9.
(d) AEMO must comply with clause 5.3.11
in relation to requests to change normal
voltage.".
3 Clause 5.3.2—Connection enquiry
3.1 In clause 5.3.2(a) of the National Electricity
Rules omit "or (c)".
-- 12 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
12
Authorised by the Chief Parliamentary Counsel
4 Insertion of new Chapter 5A
4.1 After Chapter 5 of the National Electricity
Rules insert—
"Chapter 5A—Electricity
connection for retail customers
Part A—Preliminary
5A.A.1 Definitions
In this Chapter:
basic connection service
means a connection service related to a
connection (or a proposed connection)
between a distribution system and a
retail customer's premises (excluding a
non-registered embedded generator's
premises) in the following
circumstances:
(a) either:
(1) the retail customer is typical
of a significant class of retail
customers who have sought,
or are likely to seek, the
service; or
(2) the retail customer is, or
proposes to become, a micro-
embedded generator; and
(b) the provision of the service
involves minimal or no
augmentation of the distribution
network; and
-- 13 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
13
Authorised by the Chief Parliamentary Counsel
(c) a model standing offer has been
approved by the AER for
providing that service as a basic
connection service.
basic micro EG connection service
means a basic connection service for a
retail customer who is a micro
embedded generator.
confidential information
means, in relation to a Registered
Participant, AEMO or a connection
applicant, information which is or has
been provided to that Registered
Participant, AEMO or connection
applicant under or in connection with
the Rules and which is stated under the
Rules, or by AEMO, the AER or the
AEMC, to be confidential information
or is otherwise confidential or
commercially sensitive. It also includes
any information which is derived from
such information.
connection
means a physical link between a
distribution system and a retail
customer's premises to allow the flow
of electricity.
connection alteration
means an alteration to an existing
connection including an addition,
upgrade, extension, expansion,
augmentation or any other kind of
alteration.
-- 14 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
14
Authorised by the Chief Parliamentary Counsel
connection applicant
means an applicant for a connection
service of 1 of the following categories:
(a) retail customer;
(b) retailer or other person acting on
behalf of a retail customer;
(c) real estate developer.
connection application
means an application under
clause 5A.D.3.
connection charge
means a charge imposed by a
Distribution Network Service Provider
for a connection service.
connection charge guidelines
– see clause 5A.E.3.
connection charge principles
– see clause 5A.E.1.
connection contract
means a contract formed by the making
and acceptance of a connection offer.
connection offer
means an offer by a Distribution
Network Service Provider to enter into
a connection contract with:
(a) a retail customer; or
(b) a real estate developer.
-- 15 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
15
Authorised by the Chief Parliamentary Counsel
connection policy
means a document, approved as a
connection policy by the AER under
Chapter 6, Part E, setting out the
circumstances in which connection
charges are payable and the basis for
determining the amount of such
charges.
connection service
means either or both of the following:
(a) a service relating to a new
connection for premises;
(b) a service relating to a connection
alteration for premises.
contestable
– a service is contestable if the laws of
the participating jurisdiction in which
the service is to be provided permit the
service to be provided by more than
one supplier as a contestable service or
on a competitive basis.
customer connection contract
– see section 67 of the NERL.
embedded generator
means a person that owns, controls or
operates an embedded generating unit.
enquiry
means a preliminary enquiry under
clause 5A.D.2.
-- 16 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
16
Authorised by the Chief Parliamentary Counsel
micro EG connection
means a connection between an
embedded generating unit and a
distribution network of the kind
contemplated by Australian Standard
AS 4777 (Grid connection of energy
systems via inverters).
micro embedded generator
means a retail customer who operates,
or proposes to operate, an embedded
generating unit for which a micro EG
connection is appropriate.
model standing offer
means a document approved by the
AER as a model standing offer to
provide basic connection services (see
clause 5A.B.3) or as a model standing
offer to provide standard connection
services (see clause 5A.B.5).
negotiated connection contract
– see clause 5A.C.1.
new connection
means a connection established or to be
established, in accordance with this
Chapter and applicable energy laws,
where there is no existing connection.
non-registered embedded generator
means an embedded generator that is
neither a micro embedded generator
nor a Registered Participant.
-- 17 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
17
Authorised by the Chief Parliamentary Counsel
premises connection assets
means the components of a distribution
system used to provide connection
services.
real estate developer
means a person who carries out a real
estate development.
real estate development
means the commercial development of
land including its development in 1 or
more of the following ways:
(a) subdivision;
(b) the construction of commercial or
industrial premises (or both);
(c) the construction of multiple new
residential premises.
retail customer
includes a non-registered embedded
generator and a micro embedded
generator.
standard connection service
means a connection service (other than
a basic connection service) for a
particular class (or sub-class) of
connection applicant and for which a
model standing offer has been approved
by the AER.
supply service
means a service (other than a
connection service) relating to the
supply of electricity.
-- 18 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
18
Authorised by the Chief Parliamentary Counsel
5A.A.2 Application of this Chapter
(a) This Chapter does not apply to, or in
relation to, a connection applicant that
is a Registered Participant or an
Intending Participant unless the
Registered Participant or Intending
Participant is acting as the agent of a
retail customer.
(b) Where a non-registered embedded
generator wishing to connect an
embedded generating unit to a
Distribution Network Service
Provider's network:
(1) falls within a particular class
(or subclass) of connection
applicant for which that
Distribution Network Service
Provider provides a standard
connection service, this Chapter
will apply;
(2) does not fall within a particular
class (or subclass) of connection
applicant for which that
Distribution Network Service
Provider provides a standard
connection service, paragraph (c)
will apply.
(c) A non-registered embedded generator
that meets the requirements in
paragraph (b)(2) may elect to seek
connection of the relevant embedded
generating unit under rule 5.3A instead
of this Chapter.
-- 19 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
19
Authorised by the Chief Parliamentary Counsel
(d) Any election made by a non-registered
embedded generator under
paragraph (c) must be:
(1) made before an enquiry is made or
if no enquiry is made, before a
connection application is lodged
with the relevant Distribution
Network Service Provider;
(2) in writing; and
(3) delivered to the relevant
Distribution Network Service
Provider at the same time as
lodging an enquiry under
clause 5.3A.5.
(e) For the avoidance of doubt,
clause 5A.C.1(a)(2) is still applicable
when a non-registered embedded
generator meets the requirements in
paragraph (b)(1).
5A.A.3 Small Generation Aggregator deemed to
be agent of a retail customer
A Market Small Generation Aggregator is
deemed to be the agent of a retail customer,
where there is an agreement between the
Market Small Generation Aggregator and
the retail customer relating to the retail
customer's small generating unit under
which the Market Small Generation
Aggregator is financially responsible for the
market connection point at which the small
generating unit is connected to the national
grid.
-- 20 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
20
Authorised by the Chief Parliamentary Counsel
Part B—Standardised offers to
provide basic and standard
connection services
Division 1—Basic connection services
5A.B.1 Obligation to have model standing offer to
provide basic connection services
(a) Subject to paragraph (b), a Distribution
Network Service Provider must have a
model standing offer to provide basic
connection services to retail customers.
(b) Basic connection services are of
2 classes:
(1) basic connection services for
retail customers who are not
embedded generators; and
(2) basic connection services for
retail customers who are
micro-embedded generators.
Note
Basic connection services are not available to
non-registered embedded generators.
(c) A model standing offer may relate to
each class of basic connection services
(or a subclass for which there is
significant demand) within the area
served by the relevant distribution
network.
-- 21 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
21
Authorised by the Chief Parliamentary Counsel
5A.B.2 Proposed model standing offer for basic
connection services
(a) A Distribution Network Service
Provider must submit for the AER's
approval a proposed model standing
offer to provide basic connection
services for each class (or subclass) of
basic connection services on specified
terms and conditions.
(b) The terms and conditions of the
proposed model standing offer must
cover:
(1) a description of the connection
(and the premises connection
assets of which it is to be
comprised) including a statement
of its maximum capacity; and
(2) timeframes for commencing and
completing the work; and
(3) the qualifications required for
carrying out the work involved in
providing a contestable service
(including reference to the
jurisdictional or other legislation
and statutory instruments under
which the qualifications are
required); and
(4) the safety and technical
requirements (including reference
to the jurisdictional or other
legislation and statutory
instruments under which the
requirements are imposed) to be
complied with by the provider of a
contestable service or the retail
customer (or both); and
-- 22 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
22
Authorised by the Chief Parliamentary Counsel
(5) details of the connection charges
(or the basis on which they will be
calculated) including details of the
following (so far as applicable):
(i) the cost of any necessary
extension to the distribution
system for which provision
has not already been made
through existing distribution
use of system charges or a
tariff applicable to the
connection;
(ii) meter type and cost;
(iii) the cost of any other relevant
premises connection assets;
(iv) the costs of common
components of minor
variations from the standard
specifications;
(v) any other incidental costs;
and
(6) the manner in which connection
charges are to be paid by the
retail customer; and
(7) if the service is a basic micro EG
connection service, the particular
requirements with regard to the
export of electricity into the
distribution system including:
(i) the special requirements for
metering and other
equipment for the export of
electricity; and
-- 23 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
23
Authorised by the Chief Parliamentary Counsel
(ii) the required qualification for
installers of relevant
equipment (including
reference to the jurisdictional
or other legislation and
statutory instruments under
which the qualifications are
required); and
(iii) the special safety and
technical requirements
(including reference to the
jurisdictional or other
legislation and statutory
instruments under which
they are imposed) to be
complied with by the
provider of a contestable
service or the retail customer
(or both).
5A.B.3 Approval of terms and conditions of
model standing offer to provide basic
connection services
(a) The AER may approve a proposed
model standing offer to provide basic
connection services of a particular class
(or subclass) on specified terms and
conditions if satisfied that:
(1) the services are likely to be sought
by:
(i) a significant number of retail
customers in the area served
by the distribution network
(excluding embedded
generators); or
(ii) micro-embedded generators;
and
-- 24 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
24
Authorised by the Chief Parliamentary Counsel
(2) the connection charges are
consistent with the Distribution
Network Service Provider's
distribution determination
including the connection policy;
and
(3) the terms and conditions are fair
and reasonable; and
(4) the terms and conditions comply
with applicable requirements of
the energy laws.
(b) In deciding whether to approve a
proposed model standing offer to
provide basic connection services on
specified terms and conditions, the AER
must have regard to:
(1) the national electricity objective;
and
(2) the basis on which the
Distribution Network Service
Provider has provided the relevant
services in the past; and
(3) the geographical characteristics of
the area served by the relevant
distribution network.
(c) If the AER does not approve a proposed
model standing offer to provide basic
connection services of a particular class
on specified terms and conditions:
(1) the AER must give the
Distribution Network Service
Provider written reasons for its
decision; and
-- 25 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
25
Authorised by the Chief Parliamentary Counsel
(2) the Distribution Network Service
Provider must re-submit the
proposed model standing offer
with appropriate amendments as
soon as reasonably practicable.
(d) The AER must deal expeditiously with
a proposed model standing offer to
provide basic connection services.
Division 2—Standard connection
services
5A.B.4 Standard connection services
(a) A Distribution Network Service
Provider may submit for the AER's
approval a proposed model standing
offer to provide standard connection
services on specified terms and
conditions.
(b) Different sets of terms and conditions
may be submitted under this rule for
different classes of connection services
or different classes of retail customer.
(c) The terms and conditions must cover:
(1) a description of the connection
(and the premises connection
assets of which it is to be
comprised) including a statement
of its maximum capacity; and
(2) timeframes for commencing and
completing the work; and
(3) the qualifications required for
carrying out the work involved in
providing a contestable service
(including reference to the
jurisdictional or other legislation
-- 26 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
26
Authorised by the Chief Parliamentary Counsel
and statutory instruments under
which the qualifications are
required); and
(4) the safety and technical
requirements (including reference
to the jurisdictional or other
legislation and statutory
instruments under which the
requirements are imposed) to be
complied with by the provider of a
contestable service or the retail
customer (or both); and
(5) details of the connection charges
(or the basis on which they will be
calculated) including details of the
following (so far as applicable):
(i) the cost of premises
connection assets to which
the connection charges
relate;
(ii) the cost of any necessary
augmentation of the
distribution system for which
provision has not already
been made through existing
distribution use of system
charges or a tariff applicable
to the connection;
(iii) the costs of common
components of minor
variations from the standard
specifications;
(iv) any other incidental costs;
and
-- 27 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
27
Authorised by the Chief Parliamentary Counsel
(6) the manner in which connection
charges are to be paid by the
retail customer.
5A.B.5 Approval of model standing offer to
provide standard connection services
(a) The AER may approve a proposed
model standing offer to provide a
particular class of standard connection
services on specified terms and
conditions if satisfied that:
(1) the terms and conditions are fair
and reasonable; and
(2) the connection charges are
consistent with the Distribution
Network Service Provider's
distribution determination
including the connection policy;
and
(3) the terms and conditions comply
with applicable requirements of
the energy laws.
(b) In deciding whether to approve the
proposed model standing offer, the AER
must have regard to the national
electricity objective.
(c) If the AER does not approve a proposed
model standing offer to provide
standard connection services:
(1) the AER must give the
Distribution Network Service
Provider written reasons for its
decision; and
-- 28 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
28
Authorised by the Chief Parliamentary Counsel
(2) the Distribution Network Service
Provider may re-submit the
proposed model standing offer
with appropriate amendments.
(d) The AER must deal expeditiously with
a proposed model standing offer to
provide standard connection services.
Division 3—Miscellaneous
5A.B.6 Amendment etc of model standing offer
(a) A Distribution Network Service
Provider may submit, for the AER's
approval, a proposal:
(1) for the amendment or substitution
of a model standing offer to
provide basic connection services;
or
(2) for the amendment, substitution or
revocation of a model standing
offer to provide standard
connection services.
(b) In deciding whether to approve a
proposal submitted for its approval
under this clause, the AER must, so far
as relevant, apply the same principles
and have regard to the same matters as
are relevant to the approval of a
proposed model standing offer to
provide basic connection services or
standard connection services.
(c) The amendment, substitution or
revocation of a model standing offer
takes effect on the date of the AER's
approval or a later date fixed by the
AER in its approval.
-- 29 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
29
Authorised by the Chief Parliamentary Counsel
(d) If the AER does not approve a proposal
submitted under paragraph (a):
(1) the AER must give the
Distribution Network Service
Provider written reasons for its
decision; and
(2) the Distribution Network Service
Provider may re-submit the
proposal with appropriate
amendments.
(e) The amendment, substitution or
revocation of a model standing offer
does not affect the validity or effect of:
(1) a connection offer made before the
amendment, substitution or
revocation takes effect; or
(2) a connection contract formed on
the basis of such an offer.
(f) The AER must deal expeditiously with
a proposal for the amendment,
substitution or revocation of a model
standing offer.
(g) If the AER, after making a distribution
determination, considers that an
existing model standing offer to provide
basic connection services or standard
connection services may be inconsistent
with the Distribution Network Service
Provider's distribution determination
(including the connection policy), the
AER may require the Distribution
Network Service Provider to submit a
proposal under paragraph (a) to bring
the model standing offer into
consistency with the distribution
determination.
-- 30 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
30
Authorised by the Chief Parliamentary Counsel
5A.B.7 Publication of model standing offers
A Distribution Network Service Provider
must publish, on its website, each of its
model standing offers to provide basic
connection services or standard connection
services.
Part C—Negotiated connection
5A.C.1 Negotiation of connection
(a) A connection applicant and a
Distribution Network Service Provider
may negotiate a connection contract
(a negotiated connection contract):
(1) where the connection service
sought by the connection
applicant is neither a basic
connection service nor a standard
connection service; or
(2) where the connection service
sought by the connection
applicant is a basic connection
service or a standard connection
service but the connection
applicant elects to negotiate the
terms and conditions on which the
connection service is to be
provided.
(b) The negotiations may, if the connection
applicant elects, extend to supply
services available from the Distribution
Network Service Provider.
(c) This Part sets out the requirements for
negotiation referred to in the NERL.
-- 31 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
31
Authorised by the Chief Parliamentary Counsel
(d) When reading this Part in the context of
the NERL:
(1) a reference to a connection
applicant in this Part corresponds
to a reference to a customer in the
NERL; and
(2) a reference to a Distribution
Network Service Provider in this
Part corresponds to a reference to
a distributor in the NERL; and
(3) this Part will be read subject to
any further adaptations and
modifications necessary to give
effect to the intendment of the
NERL.
(e) If, but for this paragraph, a contract
negotiable under this Part, or parts or
aspects of such a contract, would also
be negotiable under Chapter 6, this Part
applies to the exclusion of the relevant
provisions of Chapter 6.
5A.C.2 Process of negotiation
A Distribution Network Service Provider and
a connection applicant for a negotiated
connection contract must negotiate in
accordance with the negotiation framework
set out in clause 5A.C.3.
5A.C.3 Negotiation framework
(a) The following rules (collectively
described as the negotiation
framework) govern negotiations
between a Distribution Network Service
Provider and a connection applicant:
(1) each party must negotiate in good
faith.
-- 32 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
32
Authorised by the Chief Parliamentary Counsel
(2) the connection applicant must, at
the request of the Distribution
Network Service Provider, provide
the Distribution Network Service
Provider with information it
reasonably requires in order to
negotiate on an informed basis.
Note
The information might (for example)
include estimates of average and
maximum demand for electricity to be
supplied through the connection.
(3) the Distribution Network Service
Provider must provide the
connection applicant with
information the connection
applicant reasonably requires in
order to negotiate on an informed
basis including;
(i) an estimate of the amount to
be charged by the
Distribution Network Service
Provider for assessment of
the application and the
making of a connection offer
for a negotiated connection
contract; and
(ii) an estimate of connection
charges; and
(iii) a statement of the basis on
which connection charges
are calculated; and
-- 33 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
33
Authorised by the Chief Parliamentary Counsel
(iv) if the connection applicant
has elected to extend the
negotiations to supply
services— an estimate of any
applicable charges for supply
services and a statement of
the basis of their calculation.
Note
The Distribution Network Service
Provider might, according to the
circumstances of a particular case, need
to provide further information to ensure
the connection applicant is properly
informed – for example, information
about:
• technical and safety requirements;
• the types of connection that are
technically feasible;
• network capacity at the proposed
connection point;
• possible strategies to reduce the
cost of the connection.
(4) the Distribution Network Service
Provider may consult with other
users of the distribution network
who may be adversely affected by
the proposed new connection or
connection alteration.
(5) in assessing the application, the
Distribution Network Service
Provider must determine:
(i) the technical requirements
for the proposed new
connection or connection
alteration; and
-- 34 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
34
Authorised by the Chief Parliamentary Counsel
(ii) the extent and costs of any
necessary augmentation of
the distribution system; and
(iii) any consequent change in
charges for distribution use
of system services; and
(iv) any possible material effect
of the proposed new
connection or connection
alteration on the network
power transfer capability of
the distribution network to
which the new connection or
connection alteration is
proposed to be made and any
other distribution network
that might be affected by the
proposed new connection or
connection alteration.
(6) the Distribution Network Service
Provider must make reasonable
endeavours to make a connection
offer that complies with the
connection applicant's reasonable
requirements.
Example
Reasonable requirements as to the
location of the proposed connection point
or the level and standard of the
distribution network's power transfer
capability.
(7) the Distribution Network Service
Provider must comply with its
connection policy.
-- 35 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
35
Authorised by the Chief Parliamentary Counsel
(b) The following supplementary rules
apply:
(1) if a Distribution Network Service
Provider requires information
from a connection applicant in
addition to the information
provided in the application, a
request for the additional
information under
paragraph (a)(2) must
(if practicable) be made within
20 business days after the
Distribution Network Service
Provider receives the relevant
application;
(2) the Distribution Network Service
Provider must provide the
information required under
paragraph (a)(3) as soon as
practicable after the Distribution
Network Service Provider receives
the connection applicant's
application or, if the Distribution
Network Service Provider requests
additional information under
paragraph (a)(2), as soon as
practicable after the Distribution
Network Service Provider receives
the relevant information.
(c) Each party to the negotiations must
maintain the confidentiality of
confidential information disclosed by
the other party in the course of the
negotiations unless disclosure of the
information is authorised:
(1) by the party to whom the duty of
confidentiality is owed; or
-- 36 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
36
Authorised by the Chief Parliamentary Counsel
(2) under:
(i) the Law or the Rules; or
(ii) any other law.
5A.C.4 Fee to cover cost of negotiation
(a) A Distribution Network Service
Provider may charge a connection
applicant for a negotiated connection
contract a reasonable fee to cover
expenses directly and reasonably
incurred by the Distribution Network
Service Provider in assessing the
applicant's application and making a
connection offer.
(b) A fee charged under paragraph (a) is
recoverable as a debt (whether or not
the connection applicant accepts the
connection offer).
Part D—Application for
connection service
Division 1—Information
5A.D.1 Publication of information
(a) A Distribution Network Service
Provider must publish on its website
the following:
(1) an application form for a
new connection or a connection
alteration; and
-- 37 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
37
Authorised by the Chief Parliamentary Counsel
(2) a description of how an
application for a new connection
or a connection alteration is to be
made (including a statement of the
information required for the
application); and
(3) a description of the Distribution
Network Service Provider's basic
connection services and standard
connection services and the
classes (or subclasses) of retail
customer to which they apply.
If the Distribution Network
Service Provider does not provide
standard connection services for
all or some non-registered
embedded generators, a clear
statement to this effect must also
be included in the description; and
(4) an explanation of the connection
applicant's right to negotiate with
the Distribution Network Service
Provider for a negotiated
connection contract and a
description of the negotiation
process; and
(5) the requirements for an expedited
connection; and
(6) the basis for calculation of
connection charges; and
(7) information set out in clause
5.3A.3(b)(1)(vii), (2)-(7) as such
information relates to the
connection of embedded
generating units by a
non-registered embedded
generator.
-- 38 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
38
Authorised by the Chief Parliamentary Counsel
(b) To the extent a Distribution Network
Service Provider has provided the
information required under
paragraph (a)(7) by including that
information in its information pack
published under clause 5.3A.3(a)(3),
it will be taken to have complied with
paragraph (a)(7).
5A.D.1A Register of completed embedded
generation projects
(a) For the purposes of this
clause 5A.D.1A:
completed non-registered embedded
generation projects means all
embedded generating units, operated or
controlled by a non-registered
embedded generator that are connected
to the Distribution Network Service
Provider's network.
DAPR date has the same meaning as in
clause 5.13.2.
(b) In relation to completed non-registered
embedded generation projects, a
Distribution Network Service Provider
must establish and publish, on its
website, a register of the plant,
including but not limited to:
(1) technology of generating unit
(e.g. synchronous generating unit,
induction generator, photovoltaic
array, etc) and its make and
model;
(2) maximum power generation
capacity of all embedded
generating units comprised in the
relevant generating system;
-- 39 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
39
Authorised by the Chief Parliamentary Counsel
(3) contribution to fault levels;
(4) the size and rating of the relevant
transformer;
(5) a single line diagram of the
connection arrangement;
(6) protection systems and
communication systems;
(7) voltage control, power factor
control and/or reactive power
capability (where relevant); and
(8) details specific to the location of a
facility connected to the network
that are relevant to any of the
details in subparagraphs (1)-(7).
(c) The Distribution Network Service
Provider must not publish confidential
information as part of, or in connection
with, the register, unless disclosure of
the information is authorised:
(1) by the party to whom the duty of
confidentiality is owed; or
(2) under:
(i) the National Electricity Law
or the Rules; or
(ii) any other law.
(d) The Distribution Network Service
Provider must:
(1) by the DAPR date each year,
include in the register the details
contained in paragraph (b) for all
completed non-registered
embedded generation projects
since the date the register referred
-- 40 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
40
Authorised by the Chief Parliamentary Counsel
to in paragraph (b) is established;
and
(2) in the fifth year after the
establishment of the register, and
in each year thereafter, update the
register by the DAPR date with
details of all completed
non-registered embedded
generation projects in the 5 year
period preceding the DAPR date.
(e) To the extent a Distribution Network
Service Provider includes the
information required under
paragraphs (b) and (d) in its register
established under clause 5.4.5, it will be
taken to have complied with
paragraphs (b) and (d).
Division 2—Preliminary enquiry
5A.D.2 Preliminary enquiry
(a) A Distribution Network Service
Provider must, within 5 business days
after receiving an enquiry about a
connection service (or some other
period agreed between the Distribution
Network Service Provider and the
enquirer), provide the enquirer with the
information required to make an
informed application.
(b) The information must include:
(1) a description of the Distribution
Network Service Provider's basic
and standard connection services
and the terms and conditions of
the model standing offers to
-- 41 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
41
Authorised by the Chief Parliamentary Counsel
provide such services (including
possible costs); and
(2) a description of the process,
including a statement of the
information required, for
submission of a connection
application including an
application for an expedited
connection; and
(3) a statement of possible site
inspection charges; and
(4) a statement of a connection
applicant's right to negotiate the
terms of a connection contract and
a description of the relevant
process (including the types of
possible costs and expenses); and
(5) an indication of whether any
aspects of the proposed
connection are likely to be
contestable; and
(6) any additional information
reasonably required by the
enquirer.
(c) A Distribution Network Service
Provider that publishes any of the
above information on its website
complies with its obligation to disclose
information under this clause if it refers
the enquirer to the relevant part of the
website.
Exception:
If the enquirer asks for a written reply
to the enquiry or asks for specific
advice about the enquirer's particular
situation, the Distribution Network
-- 42 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
42
Authorised by the Chief Parliamentary Counsel
Service Provider must reply to the
enquiry as soon as reasonably
practicable and in writing if requested.
(d) If an enquiry is made to a Distribution
Network Service Provider about a
connection within the area of another
Distribution Network Service Provider,
the Distribution Network Service
Provider:
(1) must inform the enquirer of the
identity, and contact details, of the
responsible Distribution Network
Service Provider; and
(2) on doing so, is released from
further obligations in relation to
the enquiry.
Division 3—Applications
5A.D.3 Application process
(a) An application for a connection service
must be in the appropriate form
determined by the Distribution Network
Service Provider.
(b) An application for a connection service
may be made by:
(1) a retail customer for whom the
connection service is sought; or
(2) a retailer or other person acting on
behalf of a retail customer; or
(3) a real estate developer who seeks
connection services for premises
comprised in a real estate
development.
-- 43 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
43
Authorised by the Chief Parliamentary Counsel
(c) If an application for a connection
service has been made in error to the
wrong Distribution Network Service
Provider, that Distribution Network
Service Provider:
(1) must inform the connection
applicant of the identity, and
contact details, of the responsible
Distribution Network Service
Provider; and
(2) on doing so, is released from
further obligations in relation to
the application.
(d) If an application is incomplete in a
material respect, the Distribution
Network Service Provider must advise
the applicant of the deficiency and may
require the connection applicant to
complete the application and re-submit
it.
(e) If the Distribution Network Service
Provider reasonably requires additional
information to assess the application, it
may require the connection applicant to
provide the necessary information.
(f) The Distribution Network Service
Provider must, within 10 business days
after receipt of a complete application
for a connection service or if the
connection applicant is required to
provide additional information under
paragraph (e), within 10 business days
after receipt of the information,
(or some other period agreed between
the Distribution Network Service
Provider and the connection applicant):
-- 44 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
44
Authorised by the Chief Parliamentary Counsel
(1) subject to any statements
made on its website under
clause 5A.D.1(a)(3), advise the
connection applicant whether the
proposed connection service is a
basic connection service, a
standard connection service or
neither; and
(2) if;
(i) the connection service is
neither a basic connection
service nor a standard
connection service; or
(ii) the connection applicant
elects to have a negotiated
connection contract even
though the proposed
connection service is a basic
or standard connection
service;
advise the connection applicant of
the negotiated connection process
and of possible costs and expenses
related to the negotiations.
(g) A single application may relate to
multiple connection services of the
same or different kinds.
5A.D.4 Site inspection
If a Distribution Network Service Provider
reasonably needs to make a site inspection in
order to determine the nature of a connection
service sought by a connection applicant, the
Distribution Network Service Provider may
charge its reasonable expenses to the
connection applicant and recover those
expenses as a debt.
-- 45 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
45
Authorised by the Chief Parliamentary Counsel
Part E—Connection charges
5A.E.1 Connection charge principles
(a) This clause states the connection
charge principles.
(b) A retail customer (other than a
non-registered embedded generator or a
real estate developer) who applies for a
connection service for which an
augmentation is required cannot be
required to make a capital contribution
towards the cost of the augmentation
(insofar as it involves more than an
extension) if:
(1) the application is for a basic
connection service; or
(2) a relevant threshold set in the
Distribution Network Service
Provider's connection policy is not
exceeded.
Note
In general, the intention is to exclude deep
system augmentation charges for retail
customers.
(c) Subject to paragraph (b), in determining
connection charges in accordance with
its connection policy, a Distribution
Network Service Provider must apply
the following principles:
(1) if an extension to the distribution
network is necessary in order to
provide a connection service,
connection charges for the service
may include a reasonable capital
contribution towards the cost of
-- 46 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
46
Authorised by the Chief Parliamentary Counsel
the extension necessary to provide
the service;
(2) if augmentation of premises
connection assets at the retail
customer's connection point is
necessary in order to provide a
connection service, connection
charges for the service may
include a reasonable capital
contribution towards the cost of
the augmentation of premises
connection assets at the
connection point necessary to
provide the service;
(3) if augmentation of the distribution
system is necessary in order to
provide a standard connection
service, connection charges for
the service may include a
reasonable capital contribution
towards the cost of the
augmentation necessary to
provide the service;
(4) if augmentation of the distribution
system is necessary in order to
provide a connection service
under a negotiated connection
contract, connection charges for
the service may, subject to any
agreement to the contrary, include
a reasonable capital contribution
towards the cost of augmentation
of the distribution system to the
extent necessary to provide the
service and to any further extent
that a prudent service provider
would consider necessary to
-- 47 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
47
Authorised by the Chief Parliamentary Counsel
provide efficiently for forecast
load growth;
(5) despite subparagraphs (1) to (4) if
augmentation of the distribution
system is necessary in order to
provide, on the application of a
real estate developer, connection
services for premises comprised in
a real estate development,
connection charges for the
services may, subject to any
agreement to the contrary, include
a reasonable capital contribution
towards the cost of augmentation
of the distribution system to the
extent necessary to provide the
services and to any further extent
that a prudent service provider
would consider necessary to
provide efficiently for forecast
load growth;
(6) however, a capital contribution
may only be required in the
circumstances described in
subparagraphs (1) to (5) if
provision for the costs has not
already been made through
existing distribution use of system
charges or a tariff applicable to the
connection.
(d) If:
(1) a connection asset ceases, within
7 years after its construction or
installation, to be dedicated to the
exclusive use of the retail
customer occupying particular
premises; and
-- 48 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
48
Authorised by the Chief Parliamentary Counsel
(2) the retail customer is entitled, in
accordance with the connection
charge guidelines, to a refund of
connection charges;
the Distribution Network Service
Provider must make the refund, and
may recover the amount of the refund,
by way of a connection charge, from
the new users of the asset.
(e) For the purposes of paragraph (d), a
person is taken to be a new user of a
connection asset if the asset comes to
be used to provide a connection to that
person's premises
(f) For the purposes of this clause capital
contribution includes a prepayment or
financial guarantee.
5A.E.2 Itemised statement of connection charges
A connection offer must be accompanied by
a schedule containing an itemised statement
of connection costs including (so far as
relevant) the following:
(a) applicable connection charges;
(b) cost of network extension;
(c) details of upstream augmentation
required to provide the connection
service and associated cost;
(d) any other incidental costs and the basis
of their calculation including, if
relevant, costs of minor deviation from
the standard specification for a basic
connection service or a standard
connection service (as the case may
require).
-- 49 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
49
Authorised by the Chief Parliamentary Counsel
5A.E.3 Connection charge guidelines
(a) The AER must develop and publish
guidelines (connection charge
guidelines) for the development of
connection policies by Distribution
Network Service Providers.
(b) The purpose of the guidelines is to
ensure that connection charges:
(1) are reasonable, taking into account
the efficient costs of providing the
connection services arising from
the new connection or connection
alteration and the revenue a
prudent operator in the
circumstances of the relevant
Distribution Network Service
Provider would require to provide
those connection services; and
(2) provide, without undue
administrative cost, a user-pays
signal to reflect the efficient cost
of providing the connection
services; and
(3) limit cross-subsidisation of
connection costs between different
classes (or subclasses) of retail
customer; and
(4) if the connection services are
contestable – are competitively
neutral.
(c) The guidelines must:
(1) describe the method for
determining charges for premises
connection assets; and
-- 50 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
50
Authorised by the Chief Parliamentary Counsel
(2) describe the circumstances
(or how to determine the
circumstances) under which a
Distribution Network Service
Provider may receive a capital
contribution, prepayment or
financial guarantee from a retail
customer or real estate developer
for the provision of a connection
service; and
(3) describe how the amount of any
such capital contribution,
prepayment or financial guarantee
is to be determined; and
(4) establish principles for fixing a
threshold (based on capacity or
any other measure the AER thinks
fit) below which retail customers
(not being a non-registered
embedded generator or a real
estate developer) are exempt from
any requirement to pay connection
charges (or to give consideration
in the form of a capital
contribution, prepayment or
financial guarantee) for an
augmentation (other than an
extension) to the distribution
network necessary to make the
connection; and
(5) describe the methods for
calculating the augmentation
component for the connection
assets and, if the augmentation
consists of or includes an
extension, the extension
component of a connection
charge; and
-- 51 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
51
Authorised by the Chief Parliamentary Counsel
(6) describe the method for
calculating:
(i) the amount of a refund of
connection charges for a
connection asset when an
extension asset originally
installed to connect the
premises of a single retail
customer is used, within
7 years of its installation, to
connect other premises and
thus comes to be used for the
benefit of 2 or more retail
customers; and
(ii) the threshold below which
the refund is not payable;
and
(7) describe the treatment of
augmentation assets.
(d) The principles for establishing an
exemption under paragraph (c)(4) must
ensure that the exemption only operates
in the following circumstances:
(1) the connection is a low voltage
connection; and
(2) the connection would not
normally require augmentation of
the network beyond the extension
to the distribution network
necessary to make the connection;
and
-- 52 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
52
Authorised by the Chief Parliamentary Counsel
(3) the connection is not expected to
increase the load on the
distribution network beyond a
level the Distribution Network
Service Provider could reasonably
be expected to cope with in the
ordinary course of managing the
distribution network.
(e) In developing the guidelines, the AER
must have regard to:
(1) historical and geographical
differences between networks; and
(2) inter-jurisdictional differences
related to regulatory control
mechanisms, classification of
services and other relevant
matters; and
(3) the circumstances in which
connection services may be
provided by persons other than
Distribution Network Service
Providers (and are therefore
contestable).
(f) In developing guidelines dealing with
the method for calculating the amount
of a refund of connection charges paid
before a connection asset becomes a
shared asset, the AER must have regard
to:
(1) the Distribution Network Service
Provider's obligation to make the
refund; and
-- 53 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
53
Authorised by the Chief Parliamentary Counsel
(2) future projections of distribution
network expansion and usage and
any consequent effect on the
Distribution Network Service
Provider's capacity to finance the
acquisition of augmentation assets
out of increased revenue; and
(3) the fact that the Distribution
Network Service Provider's
obligation to make the refund will
expire after 7 years.
(g) In developing guidelines under this
clause, the AER must act in accordance
with the distribution consultation
procedures.
5A.E.4 Payment of connection charges
(a) Connection charges payable in respect
of a connection service must be paid to
the Distribution Network Service
Provider by the retail customer's
retailer unless:
(1) the retailer did not apply for the
connection service and the
Distribution Network Service
Provider has notified the retail
customer that the customer must
pay the connection charge
directly; or
(2) the retail customer asks to pay the
connection charge directly and the
Distribution Network Service
Provider agrees; or
-- 54 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
54
Authorised by the Chief Parliamentary Counsel
(3) the Distribution Network Service
Provider and the retailer agree
that the Distribution Network
Service Provider is to recover the
connection charge from the retail
customer.
(b) If the retail customer pays, or is
required to pay, a connection charge
directly to a Distribution Network
Service Provider under paragraph (a),
the Distribution Network Service
Provider must not recover that charge
from the retail customer's retailer.
(c) The Distribution Network Service
Provider must separately identify each
connection charge on the statement or
invoice to the retailer.
Note
Rule 25 of the National Energy Retail Rules
requires the listing of connection charges that
are passed through by a retailer to a retail
customer in the customer's bill.
Part F—Formation and integration
of connection contracts
Division 1—Offer and acceptance –
basic and standard connection services
5A.F.1 Distribution Network Service Provider's
response to application
(a) If the connection service sought by a
connection applicant is a basic
connection service or a standard
connection service (and the applicant
does not elect to apply for a negotiated
connection contract), the Distribution
-- 55 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
55
Authorised by the Chief Parliamentary Counsel
Network Service Provider must make a
connection offer to the applicant within:
(1) 10 business days after receiving a
properly completed application for
the service and the additional
information (if any) reasonably
required under clause 5A.D.3(e);
or
(2) some other period agreed between
the Distribution Network Service
Provider and the connection
applicant.
(b) The connection offer must be in
accordance with the relevant model
standing offer and must include:
(1) the date of the offer; and
(2) details of the connection service to
be provided; and
(3) a statement of the connection
charges payable by the connection
applicant.
5A.F.2 Acceptance of connection offer
(a) A connection offer to provide a basic
connection service or standard
connection service remains open for
acceptance for 45 business days from
the date of the offer and, if not accepted
within that period, lapses unless the
period for acceptance is extended by
agreement between the connection
applicant and the Distribution Network
Service Provider.
(b) This clause does not apply if the
connection application is for an
expedited connection.
-- 56 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
56
Authorised by the Chief Parliamentary Counsel
5A.F.3 Offer and acceptance—application for
expedited connection
(a) If:
(1) a connection applicant requests an
expedited connection in the
connection application; and
(2) the Distribution Network Service
Provider is satisfied that the
connection application is for a
basic connection service or
standard connection service that
falls within the terms of the
relevant model standing offer; and
(3) the connection applicant indicates
in the connection application that
a connection offer in terms of the
relevant model standing offer
would be acceptable to the
applicant,
the Distribution Network Service
Provider is taken to have made, and the
connection applicant is taken to have
accepted, a connection offer in terms of
the relevant model standing offer on the
date the Distribution Network Service
Provider receives the application.
(b) If a connection applicant applies for an
expedited connection but the
Distribution Network Service Provider
does not agree that an offer in terms of
any model standing offer is appropriate,
the Distribution Network Service
Provider must notify the connection
applicant accordingly and draw the
applicant's attention to the provisions of
-- 57 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
57
Authorised by the Chief Parliamentary Counsel
these Rules dealing with negotiated
connection.
Division 2—Offer and acceptance –
negotiated connection
5A.F.4 Negotiated connection offer
(a) A Distribution Network Service
Provider must use its best endeavours
to make a negotiated connection offer
to the connection applicant within
65 business days after the date of the
application for connection (but the time
taken by the applicant to provide
information reasonably sought by the
Distribution Network Service Provider
under clause 5A.C.3(a)(2) will not be
counted).
(b) A negotiated connection offer:
(1) must be in the form of an offer to
enter into a contract in specified
terms; and
(2) must comply with the minimum
requirements set out in
Schedule 5A.1.
(c) If the connection applicant elected to
extend the negotiations to supply
services, the connection offer must
contain terms and conditions relating to
the supply services.
(d) A negotiated connection offer must not
include a connection charge that is
inconsistent with the Distribution
Network Service Provider's connection
policy.
-- 58 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
58
Authorised by the Chief Parliamentary Counsel
(e) A negotiated connection offer remains
open for acceptance for 20 business
days from the date of the offer and then
lapses unless the period for acceptance
is extended by agreement between the
Distribution Network Service Provider
and the connection applicant.
Division 3—Formation of contract
5A.F.5 Acceptance of connection offer
(a) If a connection offer to provide a
connection service is accepted, the
terms and conditions of the connection
offer:
(1) become terms and conditions of a
connection contract formed
between the Distribution Network
Service Provider and the
connection applicant; and
(2) subject to rule 5A.F.6, are
enforceable accordingly.
(b) The Distribution Network Service
Provider must, at the request of a
connection applicant, provide a copy
of:
(1) the contract formed under
paragraph (a); or
(2) if that contract has been integrated
with, and forms part of, a
customer connection contract
arising under the NERL—the
integrated contract.
-- 59 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
59
Authorised by the Chief Parliamentary Counsel
Division 4—Contractual performance
5A.F.6 Carrying out connection work
(a) A Distribution Network Service
Provider must use its best endeavours
to ensure that connection work is
carried out within the applicable time
limits fixed by the relevant provisions
of the connection contract.
(b) However, a Distribution Network
Service Provider is not obliged to
commence or continue with connection
work if the connection applicant fails to
comply with conditions that are to be
complied with by the connection
applicant.
Examples
The connection applicant fails to pay
connection charges.
The connection applicant fails to comply with
technical or safety requirements.
The connection applicant fails to complete
work that is to be carried out on the connection
applicant's premises.
The connection applicant fails to comply with
the Distribution Network Service Provider's
reasonable request to allow the Distribution
Network Service Provider safe and unhindered
access to the applicant's premises.
5A.F.7 Retailer required for energisation where
new connection
A Distribution Network Service Provider is
not required to energise a new connection
unless a request to energise the new
connection is submitted by a retailer, or the
Distribution Network Service Provider is
otherwise satisfied that there is a relevant
-- 60 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
60
Authorised by the Chief Parliamentary Counsel
contract with a retailer in relation to the
premises.
Part G—Dispute resolution
between Distribution Network
Service Providers and customers
5A.G.1 Relevant disputes
(a) In this Part:
customer means:
(a) a retail customer; or
(b) a real estate developer.
relevant dispute means:
(1) a dispute between a
Distribution Network
Service Provider and a
customer about:
(i) the terms and
conditions on which a
basic connection
service or a standard
connection service is to
be provided; or
(ii) the proposed or actual
terms and conditions of
a negotiated connection
contract; or
(2) a dispute between a
Distribution Network Service
Provider and a customer
about connection charges.
-- 61 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
61
Authorised by the Chief Parliamentary Counsel
(b) A relevant dispute is an access dispute
for the purposes of section 2A of the
Law.
5A.G.2 Determination of dispute
(a) In determining a relevant dispute, the
AER must (so far as applicable) give
effect to:
(1) the relevant connection policy;
and
(2) a relevant model standing offer to
provide a basic or standard
connection service; and
(3) this Chapter and any other
applicable regulatory instrument.
(b) In determining a relevant dispute, the
AER may also:
(1) have regard to other matters the
AER considers relevant; and
(2) hear evidence or receive
submissions from the Distribution
Network Service Provider and the
customer; and
(3) if the dispute relates to a
negotiated connection contract –
have regard to the negotiation
framework set out in
clause 5A.C.3.
5A.G.3 Termination of proceedings
(a) If the AER considers that a relevant
dispute could be effectively resolved by
some means other than an access
determination, the AER may give the
parties to the dispute notice of the
-- 62 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
62
Authorised by the Chief Parliamentary Counsel
alternative means of resolving the
dispute.
Example
The AER might give such a notice if of the
opinion that a particular dispute could be dealt
with more efficiently, and with less expense, by
a jurisdictional ombudsman.
(b) The giving of such a notice is a
specified dispute termination
circumstance for the purposes of
section 131(3) of the Law.
Note
It follows that the AER may exercise its power
to terminate the dispute without making an
access determination (See section 131(1)(d) of
the Law).
SCHEDULE 5A.1—Minimum
content requirements for
connection contract
Part A—Connection offer not
involving embedded generation
(a) A connection offer must contain:
(1) a provision stating that a
connection contract will be
formed, and will come into
operation, on acceptance of the
connection offer; and
(2) details of the connection point, the
maximum capacity of the
connection, and the connection
assets required at the connection
point; and
-- 63 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
63
Authorised by the Chief Parliamentary Counsel
(3) details of the premises connection
assets and additional equipment to
be installed on the premises and
responsibility for undertaking the
work; and
(4) details of any distribution network
extension or other augmentation
required for the purposes of the
connection; and
(5) an undertaking to complete the
work required to establish the
connection within a specified time
frame; and
(6) a requirement that the retail
customer have appropriate
metering installed; and
(7) the relevant technical and safety
obligations to be met by the retail
customer relating to the
installation; and
(8) the retail customer's obligation to
allow access to the premises by
the Distribution Network Service
Provider's agents, contractors and
employees; and
(9) the retail customer's obligation to
accommodate on its premises, and
protect from harm, any equipment
necessary for the connection; and
(10) details of the retail customer's
monetary obligations including
billing arrangements and any
security to be provided by the
customer; and
-- 64 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
64
Authorised by the Chief Parliamentary Counsel
(11) details of the Distribution
Network Service Provider's
monetary obligations (if any) to
the retail customer; and
(12) a provision requiring the
Distribution Network Service
Provider to provide information
about the connection to the retail
customer; and
(13) provision for amendment of the
connection contract by agreement
between the Distribution Network
Service Provider and the retail
customer.
(b) A connection offer that relates to supply
services must also deal with:
(1) the Distribution Network Service
Provider's power to interrupt or
reduce the supply of electricity to
the connection point; and
(2) warranties and limitations on the
Distribution Network Service
Provider's liability; and
(3) disconnection and reconnection;
and
(4) reporting and correction of faults;
and
(5) dispute resolution; and
(6) ongoing customer obligations; and
(7) termination of the connection
contract.
-- 65 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
65
Authorised by the Chief Parliamentary Counsel
Part B—Connection offer involving
embedded generation
(a) A connection offer to a person who
operates, or proposes to operate,
an embedded generating unit
(the embedded generator) must
contain:
(1) a provision stating that a
connection contract will be
formed, and will come into
operation, on acceptance of the
connection offer; and
(2) details of the connection point, the
maximum capacity of the
connection to import and export
electricity, and the embedded
generator's installation required at
the connection point; and
(3) details of the premises connection
assets and additional equipment to
be installed on the premises and
responsibility for undertaking the
work; and
(4) details of any distribution network
extension or other augmentation
required for the purposes of the
connection; and
(5) an undertaking to complete the
work required to establish the
connection within a specified time
frame; and
(6) a requirement that the embedded
generator have appropriate
metering installed; and
-- 66 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
66
Authorised by the Chief Parliamentary Counsel
(7) the relevant technical and safety
obligations to be met by the
embedded generator relating to
the installation; and
(8) the embedded generator's
obligation to allow access to the
premises by the Distribution
Network Service Provider's
agents, contractors and
employees; and
(9) the embedded generator's
obligation to accommodate on its
premises, and protect from harm,
any equipment necessary for the
connection; and
(10) details of the embedded
generator's monetary obligations
including billing arrangements
and any security to be provided by
the embedded generator; and
(11) details of the Distribution
Network Service Provider's
monetary obligations (if any) to
the embedded generator; and
(12) a provision requiring the
Distribution Network Service
Provider to provide information
about the connection to the
embedded generator; and
(13) provision for amendment of the
connection contract by agreement
between the Distribution Network
Service Provider and the
embedded generator.
-- 67 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
67
Authorised by the Chief Parliamentary Counsel
(b) A connection contract that relates to
supply services must also deal with:
(1) the Distribution Network Service
Provider's power to interrupt or
reduce the supply of electricity to
the connection point; and
(2) warranties and limitations on the
Distribution Network Service
Provider's liability; and
(3) disconnection and reconnection;
and
(4) reporting and correction of faults;
and
(5) dispute resolution; and
(6) ongoing obligations of the
Distribution Network Service
Provider and the embedded
generator; and
(7) termination of the connection
contract.".
5 Clause 6.1.2—Structure of Chapter 6
5.1 After clause 6.1.2(b)(4) of the National
Electricity Rules insert—
"(4A) Part DA deals with the preparation of,
requirements for and approval of,
connection policies;".
6 Clause 6.2.1—Classification of
distribution services
6.1 At the foot of clause 6.2.1(a) of the National
Electricity Rules insert—
"Note
If the AER decides against classifying a distribution
service, the service is, subject to Chapter 5A, not
regulated under the Rules.".
-- 68 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
68
Authorised by the Chief Parliamentary Counsel
7 Clause 6.2.2—Classification of direct
control services as standard control
services or alternative control services
7.1 In clause 6.2.2(c)(5) of the National
Electricity Rules, for "customer" substitute
"person".
8 New Part DA inserted in Chapter 6
8.1 After Part D of Chapter 6 of the National
Electricity Rules insert—
"Part DA—Connection policies
6.7A Connection policy requirements
This Rule deals with the preparation of,
requirements for and approval of connection
policies.
6.7A.1 Preparation of, and requirements for,
connection policy
(a) A Distribution Network Service
Provider must prepare a document
(its proposed connection policy) setting
out the circumstances in which it may
require a retail customer or real estate
developer to pay a connection charge,
for the provision of a connection
service under Chapter 5A.
(b) The proposed connection policy:
(1) must be consistent with:
(i) the connection charge
principles; and
(ii) the connection charge
guidelines; and
-- 69 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
69
Authorised by the Chief Parliamentary Counsel
(2) must specify:
(i) the categories of persons that
may be required to pay a
connection charge and the
circumstances in which such
a requirement may be
imposed; and
(ii) the aspects of a connection
service for which a
connection charge may be
made; and
Example
The Distribution Network Service
Provider might (for example)
make separate connection charges
for the provision of a connection
asset and for making a necessary
extension to, or other
augmentation of, the distribution
network.
(iii) the basis on which
connection charges are
determined; and
(iv) the manner in which
connection charges are to be
paid (or equivalent
consideration is to be given);
and
Examples
The payment (or equivalent
consideration) might take the form
of a capital contribution,
prepayment or financial guarantee.
-- 70 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
70
Authorised by the Chief Parliamentary Counsel
(v) a threshold (based on
capacity or any other
measure identified in the
connection charge
guidelines) below which a
retail customer (not being a
non-registered embedded
generator or a real estate
developer) will not be liable
for a connection charge for
an augmentation other than
an extension.".
9 Clause 6.8.2—Submission of regulatory
proposal
9.1 After clause 6.8.2(c)(5) of the National
Electricity Rules insert—
"(5A) the proposed connection policy;".
10 Clause 6.12.1—Constituent decisions
10.1 For clause 6.12.1(17) of the National
Electricity Rules substitute—
"(17) a decision on the policies and
procedures for assigning retail
customers to tariff classes, or
reassigning retail customers from one
tariff class to another (including any
applicable restrictions);".
10.2 After clause 6.12.1(20) of the National
Electricity Rules insert—
"(21) a decision on the connection policy that
is to apply to the Distribution Network
Service Provider for the regulatory
control period (which may be the
connection policy as proposed by the
Distribution Network Service Provider,
some variant of it, or a policy
substituted by the AER).".
-- 71 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
71
Authorised by the Chief Parliamentary Counsel
11 Clause 6.12.3—Extent of AER's discretion
in making distribution determinations
11.1 After clause 6.12.3(h) of the National
Electricity Rules insert—
"(i) The AER must approve the proposed
connection policy if the AER is satisfied
that it adequately complies with the
requirements of Part DA.
(j) If the AER refuses to approve the
proposed connection policy, the
approved amended connection policy
must be:
(1) determined on the basis of the
current proposed connection
policy; and
(2) amended from that basis only to
the extent necessary to enable it to
be approved in accordance with
the Rules.
(k) The AER must approve a Distribution
Network Service Provider's proposed
tariff structure statement unless the
AER is reasonably satisfied that the
proposed tariff structure statement does
not comply with the pricing principles
for direct control services or other
applicable requirements of the Rules.
(l) If, in making a distribution
determination in relation to a
Distribution Network Service Provider,
the AER refuses to approve the
Distribution Network Service
Provider's proposed tariff structure
statement, the AER must include in that
distribution determination an amended
tariff structure statement which is:
-- 72 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
72
Authorised by the Chief Parliamentary Counsel
(1) determined on the basis of the
Distribution Network Service
Provider's proposed tariff
structure statement; and
(2) amended from that basis only to
the extent necessary to enable it to
be approved in accordance with
the Rules.".
12 Clause 6.18.3—Tariff classes
12.1 In clause 6.18.3(c) of the National Electricity
Rules, for "customers" (where twice
occurring) substitute "retail customers".
12.2 In clause 6.18.3(d)(1) of the National
Electricity Rules, for "customers" substitute
"retail customers".
13 Clause 6.18.4—Principles governing
assignment or re-assignment of retail
customers to tariff classes and assessment
and review of basis of charging
13.1 In the heading to clause 6.18.4 of the
National Electricity Rules, for "customers"
substitute "retail customers".
13.2 In clause 6.18.4(a) of the National Electricity
Rules, for "customers" (wherever occurring)
substitute "retail customers".
14 Clause 6.18.6—Side constraints on tariffs
for standard control services
14.1 In clause 6.18.6(d)(2) of the National
Electricity Rules, for "customers" substitute
"retail customers".
-- 73 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
73
Authorised by the Chief Parliamentary Counsel
15 Clause 6.18.7—Recovery of designated
pricing proposal charges
15.1 In clause 6.18.7(a) of the National Electricity
Rules, for "customers" substitute "retail
customers".
15.2 In clause 6.18.7(b) of the National Electricity
Rules, for "customers" substitute "retail
customers".
15.3 In clause 6.18.7(c)(2) of the National
Electricity Rules, for "customers" substitute
"retail customers".
16 Clause 6.19.2—Confidentiality of
distribution network pricing information
16.1 In clause 6.19.2(b) of the National Electricity
Rules, for "customer" substitute "retail
customer".
17 Insertion of definitions in Chapter 10
17.1 Insert the following definitions in
alphabetical order in Chapter 10 of the
National Electricity Rules—
"basic connection service
Has (in the context of Chapter 5A) the
meaning given in clause 5A.A.1.
basic micro EG connection service
Has (in the context of Chapter 5A) the
meaning given in clause 5A.A.1.
connection alteration
Has (in the context of Chapter 5A) the
meaning given in clause 5A.A.1.
-- 74 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
74
Authorised by the Chief Parliamentary Counsel
connection application
Has (in the context of Chapter 5A) the
meaning given in clause 5A.A.1.
connection charge
Has (in the context of Chapter 5A) the
meaning given in clause 5A.A.1.
connection charge guidelines
Has the meaning given in
clause 5A.D.3.
connection charge principles
Has the meaning given in
clause 5A.E.1.
connection contract
Has (in the context of Chapter 5A) the
meaning given in clause 5A.A.1.
connection offer
Has (in the context of Chapter 5A) the
meaning given in clause 5A.A.1.
connection policy
Has (in the context of Chapter 5A) the
meaning given in clause 5A.A.1.
customer connection service
Has (in the context of Chapter 6B) the
meaning given in clause 6B.A1.2.
energy laws
Has the meaning given in section 2(1)
of the NERL
energy ombudsman
Has the same meaning as in the NERL.
-- 75 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
75
Authorised by the Chief Parliamentary Counsel
enquiry
Has (in the context of Chapter 5A) the
meaning given in clause 5A.A.1
micro EG connection
Has (in the context of Chapter 5A) the
meaning given in clause 5A.A.1
micro embedded generator
Has (in the context of Chapter 5A) the
meaning given in clause 5A.A.1
model standing offer
Has (in the context of Chapter 5A) the
meaning given in clause 5A.A.1.
new connection
Has (in the context of Chapter 5A) the
meaning given in clause 5A.A.1
premises connection assets
Has (in the context of Chapter 5A) the
meaning given in clause 5A.A.1
real estate developer
Has (in the context of Chapter 5A) the
meaning given in clause 5A.A.1
real estate development
Has (in the context of Chapter 5A) the
meaning given in clause 5A.A.1
retail customer
Has the same meaning as in the
National Electricity Law.
Otherwise, a person to whom electricity
is sold by a retailer, and supplied in
respect of connection points, for the
premises of the person, and includes a
-- 76 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
76
Authorised by the Chief Parliamentary Counsel
person (or a person who is of a class of
persons) prescribed by these Rules for
the purposes of this definition.
Note:
In the context of Chapter 5A, the above
definition has been supplemented by a
definition specifically applicable to that
Chapter. See clause 5A.A.1.
retailer
Has the same meaning as in the
National Electricity Law.
Otherwise, a Customer who engages in
the activity of selling electricity to end
users.
standard connection service
Has (in the context of Chapter 5A) the
meaning given in clause 5A.A.1.
supply service
Has (in the context of Chapter 5A) the
meaning given in clause 5A.A.1".
17.2 In Chapter 10 of the National Electricity
Rules, at the foot of the definition of
confidential information, insert—
"Note:
In the context of Chapter 5A, the above definition has
been displaced by a definition specifically applicable
to that Chapter. See clause 5A.A.1.".
17.3 In Chapter 10 of the National Electricity
Rules, at the foot of the definition of
connect, connected, connection, insert—
"Note:
In the context of Chapter 5A, the above definition has
been displaced by a definition specifically applicable
to that Chapter. See clause 5A.A.1.".
-- 77 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
77
Authorised by the Chief Parliamentary Counsel
17.4 In Chapter 10 of the National Electricity
Rules, at the foot of the definition of
connection service, insert—
"Note:
In the context of Chapter 5A, the above definition has
been displaced by a definition specifically applicable
to that Chapter. See clause 5A.A.1.".
17.5 In Chapter 10 of the National Electricity
Rules, at the foot of the definition of
contestable, insert—
"Note:
In the context of Chapter 5A, the above definition has
been displaced by a definition specifically applicable
to that Chapter. See clause 5A.A.1.".
17.6 In Chapter 10 of the National Electricity
Rules, at the foot of the definition of
Embedded Generator, insert—
"Note:
In the context of Chapter 5A, the above definition has
been displaced by a definition specifically applicable
to that Chapter. See clause 5A.A.1.".
Schedule 3—Transitional
provisions for retail customer
connection arrangements
Section 16T
Part 1—Preliminary
1 Definitions
(1) In this Schedule—
applicable regulatory control period, for a
distribution company, means the
regulatory control period imposed
under the next distribution
-- 78 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
78
Authorised by the Chief Parliamentary Counsel
determination which applies to the
distribution company;
distribution company means any of the
following companies—
(a) Citipower Pty Ltd
(ACN 064 651 056);
(b) Jemena Electricity Networks (Vic)
Ltd (ACN 064 651 083);
(c) Powercor Australia Ltd
(ACN 064 651 109);
(d) AusNet Electricity Services
Pty Ltd (ACN 064 651 118);
(e) United Energy Distribution
Pty Limited (ACN 064 651 029);
next distribution determination, for a
distribution company, means the first
distribution determination made after
the relevant distribution determination
which applies to the distribution
company;
relevant distribution determination, for a
distribution company, means the
2016–2020 distribution determination
made by the AER under the National
Electricity Rules that applies to the
distribution company (as amended or
substituted from time to time);
relevant provisions means Chapter 5A and
Part DA of Chapter 6 of the National
Electricity Rules;
-- 79 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
79
Authorised by the Chief Parliamentary Counsel
specified date means a date specified by the
Minister under clause 2(1);
transition period, for a distribution
company, means the period—
(a) beginning on the day on which
section 6 of the National
Electricity (Victoria) Further
Amendment Act 2016 comes into
operation; and
(b) ending on the day on which the
applicable regulatory control
period for that distribution
company commences.
(2) Words and expressions used in the National
Electricity Rules have the same respective
meanings in this Schedule as they have in
those Rules.
2 Minister may specify date for purposes of
certain clauses
(1) The Minister, by notice published in the
Government Gazette, may specify a date for
the purposes of clause 4, 6, 7 or 8.
(2) To avoid doubt, the Minister may specify
more than one date under subclause (1) for
the purposes of clause 4, 6, 7 or 8, including
a date that replaces an earlier specified date.
3 Transitional operation of relevant
provisions
(1) During the transition period, the relevant
provisions operate subject to the exclusions,
qualifications and modifications prescribed
by this Schedule.
-- 80 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
80
Authorised by the Chief Parliamentary Counsel
(2) However, the relevant provisions operate
without the exclusions, qualifications and
modifications prescribed by this Schedule
insofar as they relate to a period beyond the
transition period.
Example
A distribution company which submits a regulatory
proposal for the regulatory control period that follows
the distribution company's transition period is bound
by the relevant provisions (without exclusion,
qualification or modification) in relation to the
regulatory proposal even though the proposal is
submitted during the transition period.
(3) A transaction commenced by or with a
distribution company during the transition
period may be continued and completed after
the transition period without regard to
changes to the rules governing the
transaction that take effect at the end of the
transition period.
4 Extended meaning of some terms
During the transition period—
(a) a basic connection service includes not
only a connection service for which a
model standing offer has been approved
by the AER (see paragraph (c) of the
definition in clause 5A.A.1 of the
National Electricity Rules) but also one
for which the AER's approval of a
model standing offer is not required;
and
(b) a standard connection service includes
not only a connection service for
which a model standing offer has
been approved by the AER (see the
definition in clause 5A.A.1 of the
National Electricity Rules) but also
-- 81 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
81
Authorised by the Chief Parliamentary Counsel
one for which the AER's approval of a
model standing offer is not required;
and
(c) a model standing offer includes a
document prepared and published by a
distribution company, without the
AER's approval, as a model standing
offer to have effect during the transition
period (but not beyond the specified
date).
Part 2—Exclusions, qualifications
and modifications
5 Connection policy
A document, prepared by a distribution
company and published on the distribution
company's Internet site, will (although not
approved by the AER) be taken to be the
distribution company's connection policy
if—
(a) it sets out the circumstances in which
connection charges are payable and the
basis for determining the amount of
such charges; and
(b) it is consistent with—
(i) the connection charge principles
and the connection charge
guidelines; and
(ii) legislation of Victoria that
regulates electricity in Victoria, or
any instrument made or issued
under or for the purposes of that
legislation; and
-- 82 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
82
Authorised by the Chief Parliamentary Counsel
(iii) the relevant distribution
determination for the distribution
company (if applicable).
6 Model standing offer (basic connection
services)
(1) A document, prepared by a distribution
company and published on the distribution
company's Internet site, will (although not
approved by the AER) be regarded as a
model standing offer to provide basic
connection services until the specified date if
it complies with the requirements of
clause 5A.B.2(b) of the National Electricity
Rules as to its terms and conditions.
(2) If, before the specified date, the AER
approves a model standing offer for the same
basic connection services, the approved
model standing offer supersedes the former
model standing offer.
(3) A distribution company's obligation to have
a model standing offer to provide basic
connection services (clause 5A.B.1 of the
National Electricity Rules) operates during
the transition period but the AER's approval
of the standing offer is not required until the
specified date.
7 Model standing offer (standard
connection services)
(1) A document, prepared by a distribution
company and published on the distribution
company's Internet site, will (although not
approved by the AER) be regarded as a
model standing offer to provide standard
connection services until the specified date if
it complies with the requirements of
-- 83 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
83
Authorised by the Chief Parliamentary Counsel
clause 5A.B.4(c) of the National Electricity
Rules as to its terms and conditions.
(2) If, before the specified date, the AER
approves a model standing offer for the same
standard connection services, the approved
model standing offer supersedes the former
model standing offer.
(3) A distribution company may submit for the
AER's approval a proposed model standing
offer to provide standard connection services
(clause 5A.B.4 of the National Electricity
Rules) before the specified date, but the
AER's approval of the model standing offer
is not required until the specified date.
8 Amendment of standing offers
Until the specified date, a distribution
company may amend a standing offer to
provide basic connection services or standard
connection services by publishing the
amendments and the amended text on its
Internet site. (This clause applies until
the specified date to the exclusion of
clause 5A.B.6 of the National Electricity
Rules).
Part 3—General provisions
9 Connection charges
A distribution company must comply with its
connection policy and any other applicable
regulatory obligation or requirement when
calculating or imposing a connection charge
for the transition period.
-- 84 of 87 --
Part 2—Amendments to the National Electricity (Victoria) Act 2005
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
84
Authorised by the Chief Parliamentary Counsel
10 References
A reference to any of the relevant provisions
in a legislative or other instrument will be
construed, during the transition period, as a
reference to the provision as modified by this
Schedule.
11 Authorisation of certain relevant
distribution determinations
(1) This clause applies if—
(a) the AER made a relevant distribution
determination under the Rules on or
after section 6 of the National
Electricity (Victoria) Further
Amendment Act 2016 was enacted,
but before the commencement of that
section; and
(b) the AER made that determination as if
the Rules had been amended by
Schedule 2.
(2) For the purposes of the National Electricity
(Victoria) Law and the Rules, the relevant
distribution determination (to the extent it
has been made as if the Rules under which
the determination was made were the Rules
as amended by Schedule 2)—
(a) is taken to be authorised to have been
made under the Rules; and
(b) has effect from that commencement
subject to that Law or Rules so
applying.'.
-- 85 of 87 --
Part 3—Repeal of amending Act
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
85
Authorised by the Chief Parliamentary Counsel
Part 3—Repeal of amending Act
7 Repeal of amending Act
This Act is repealed on 1 January 2018.
Note
The repeal of this Act does not affect the continuing operation of
the amendments made by it (see section 15(1) of the
Interpretation of Legislation Act 1984).
═══════════════
-- 86 of 87 --
Endnotes
National Electricity (Victoria) Further Amendment Act 2016
No. 24 of 2016
86
Authorised by the Chief Parliamentary Counsel
Endnotes
1 General information
See www.legislation.vic.gov.au for Victorian Bills, Acts and current
authorised versions of legislation and up-to-date legislative information.
† Minister's second reading speech—
Legislative Assembly: 9 December 2015
Legislative Council: 10 March 2016
The long title for the Bill for this Act was "A Bill for an Act to amend the
National Electricity (Victoria) Act 2005 to apply in Victoria certain
provisions of the National Electricity Law and to amend the National
Electricity Rules as in force in Victoria to implement certain retail
customer connection arrangements and for other purposes."
-- 87 of 87 --